Chapter 5: Project Cost Management



Similar documents
Chapter 3: Project Cost Management

Chapter 7: Project Cost Management. Information Technology Project Management, Fourth Edition

Chapter 7: Project Cost Management. Munawar

Brainstorm. What is Cost and Project Cost Management?

Information Technology Project Management, Sixth Edition. Note: See the text itself for full citations. More courses at cie-wc.edu

How To Manage Project Cost Management

IST 302 : Project Cost Management

INSE 6230 Total Quality Project Management

Chapter 7. (PMBOK Guide)

PROJECT COST MANAGEMENT

Project Cost Management

Earned Value Management Changes to the Glossary and Chapter 7 of the PMBOK Guide Third Edition.

Unit 5: Cost Management (PMBOK Guide, Chapter 7)

Estimating Cost at Completion - Judgment & EV Information

Project Management for Scientists

Project Cost Management

Profesor: Francisco Javier Sanz Pérez. by fjspsv, PMP Test C07_01

pm4dev, 2008 management for development series Project Budget Management PROJECT MANAGEMENT FOR DEVELOPMENT ORGANIZATIONS

An introduction to Earned Value Analysis

Module 5 Cost Management PMP Exam Questions

How To Manage Project Cost Management

CPM -100: Principles of Project Management

Rules on using templates. MECH 896 Professional Development for MEng Students. Assignment #6A: Questions. Homework Discussion

Earned Value Formulae

Project Cost Management. Richard Boser

Earned Value and Agile Reporting

700 Analysis and Reporting

DESCRIPTION OF KNOWLEDGE, LITERATURE REVIEW AND INDUSTRY PRACTICES

How To Manage A Project

AACE International Recommended Practice No. 86R 14

EARNED VALUE MANAGEMENT. CASE STUDY USING MICROSOFT PROJECT

PMP Exam Preparation Answer Key

Procurement Management S# What? Formula Additional Notes CPPC CPFF CPAF CPIF T&M FPEPA FPAF FPIF FFP

Integration of Income Management and Cost Management: A Complementary for Financial Analysis of Projects. Abstract. Introduction

Project Cost Management

Predicting progress on your project

plans based on actual cost, schedule and technical progress of work [1, 9].

Using Earned Value Management for Improving Processes. By Cynthia K. West

Expert Reference Series of White Papers. Importance of Schedule and Cost Control

The Two Most Useful Earned Value Metrics: the CPI and the TCPI

IQPC IT Project Management Conference Sydney Recent Advances in Project Prediction Techniques

What is the Health of my Project?

10.1 Communications Planning 10.2 Information Distribution Figure Performance Reporting 10.1 Communications Planning 10.

Develop Project Charter. Develop Project Management Plan

Appendix D Glossary Of Terms

PROJECT COST MANAGEMENT

Earned Value Management (EVM) is a technique that is used to track the progress and status of a project and forecast its likely future performance.

Project Management Institute (PMBOK 2000) PMP Preparation Worksheet

Project Time Management

PERCEPTION. Tracking Progress & EAC

Agile and Earned Value. A white paper. October Author Stephen Jones, Sellafield Ltd

The 10 Knowledge Areas & ITTOs

Simple Earned Value (Using MS Project 2010)

Introduction to earn value management in Civil Engineering

THE PROJECT MANAGEMENT KNOWLEDGE AREAS

This EVMS Training Snippet sponsored by the Office of Acquisition and Project Management (OAPM) covers Firm Fixed Price (or FFP type) subcontracts.

專 案 管 理 實 務 嘉 義 縣 政 府 學 分 班 : 管 理 實 務 專 題 2006 中 正 大 學 企 管 系 助 理 教 授 周 瑞 生

Brillig Systems Making Projects Successful

Project Cost Management - 2 Days

Planning of Project Work (IS PM 6. Lecture, 2011 Spring)

DATA ITEM DESCRIPTION Title: Integrated Program Management Report (IPMR) Number: DI-MGMT Approval Date:

MTAT Software Economics. Lecture 6: Software Cost Estimation (part II)

PROJECT TRACKING and CONTROL

Lecture Slides for Managing and Leading Software Projects. Chapter 8: Measuring and Controlling Work Processes

COINS EVA Earned Value Analysis

Project Cost Control: The Way it Works By R. Max Wideman

EVM.01. Earned Value Analysis Why it Doesn't Work

Earned Value Exercise. Su-Cheng Wu. MET AD 644: Project Risk, and Cost Management. Paul B. Cook, PhD PMP

Project Execution - PM Elements

PMP Exam Tips on Cost Management, Fourth Edition. Parallels between Cost and Time estimating:

Summary of GAO Cost Estimate Development Best Practices and GAO Cost Estimate Audit Criteria

Input, Output and Tools of all Processes

A DIFFERENT KIND OF PROJECT MANAGEMENT: AVOID SURPRISES

Tracking Budgets and Schedules

Project Integration Management

Earned Value Analysis of Construction Project at Rashtriya Sanskrit Sansthan, Bhopal Ankur Verma 1, K.K. Pathak 2, R K Dixit 2

Chapter 6. (PMBOK Guide)

L10: Budgeting and Cost Control. Olivier de Weck

EARNED VALUE MANAGEMENT SYSTEM AS A PROJECT MANAGEMENT TOOL FOR MAJOR MULTI-DISCIPLINARY PROJECTS

Appendix A of Project Management. Appendix Table of Contents REFERENCES...761

PROJECT MANAGEMENT PLAN TEMPLATE < PROJECT NAME >

Project Cost Management.

PMI Lexicon of Project Management Terms

Earned Value Management Tutorial Module 1: Introduction to Earned Value Management. Prepared by:

Cash flow is the life line of a business. Many start-up

Best Practices Statement Project Management. Best Practices for Managing State Information Technology Projects

PROJECT TIME MANAGEMENT. 1 Powered by POeT Solvers Limited

DICTIONARY OF INFORMATION TECHNOLOGY PROJECT MANAGEMENT

Systems Analysis and Design in a Changing World, Fifth Edition

Project Management Using Earned Value

Chapter 6: Project Time Management. King Fahd University of Petroleum & Minerals SWE 417: Software Project Management Semester: 072

Applied Software Project Management

PM in construction industry

A DIFFERENT KIND OF PROJECT MANAGEMENT

300 Scheduling and Budgeting

Accounting System. Page 1 of 9

Project Cost Management - 2 Days

Transcription:

Chapter 5: Project Cost Management 1

Learning Objectives Understand the importance of good project cost management Explain basic project cost management principles, concepts, and terms Describe how resource planning relates directly to project cost management Explain cost estimating using definitive, budgetary, and rough order of magnitude (ROM) estimates 2

Learning Objectives Understand the processes involved in cost budgeting and preparing a cost estimate for an information technology project Understand the benefits of earned value management and project portfolio management to assist in cost control Describe how software can assist in project cost management 3

The Importance of Project Cost Management IT projects have a poor track record for meeting cost goals Average cost overrun from 1995 CHAOS study was 189% of the original estimates; improved to 145% in the 2001 study In 1995, cancelled IT projects cost the U.S. over $81 billion 4

What Went Wrong? According to the San Francisco Chronicle front-page story, "Computer Bumbling Costs the State $1 Billion," the state of California had a series of expensive IT project failures in the late 1990s, costing taxpayers nearly $1 billion ironic that the state which leads in creation of computers is the state most behind in using computer technology to improve state services. The Internal Revenue Service (IRS) managed a series of project failures that cost taxpayers over $50 billion a year roughly as much money as the annual net profit of the entire computer industry. Connecticut General Life Insurance Co. sued PeopleSoft over an aborted installation of a finance system. 5

What is Cost and Project Cost Management? Cost is a resource sacrificed or foregone to achieve a specific objective or something given up in exchange Costs are usually measured in monetary units like dollars Project cost management includes the processes required to ensure that the project is completed within an approved budget 6

Project Cost Management Processes Resource planning: determining what resources and quantities of them should be used Cost estimating: developing an estimate of the costs and resources needed to complete a project Cost budgeting: allocating the overall cost estimate to individual work items to establish a baseline for measuring performance Cost control: controlling changes to the project budget 7

Basic Principles of Cost Management Most CEOs and boards know a lot more about finance than IT, so IT project managers must speak their language Profits are revenues minus expenses Life cycle costing is estimating the cost of a project plus the maintenance costs of the products it produces Cash flow analysis is determining the estimated annual costs and benefits for a project Benefits and costs can be tangible or intangible, direct or indirect Sunk cost should not be a criteria in project selection 8

Table 7-1. Cost of Software Defects When Defect is Detected Typical Cost of Correction User Requirements $100-$1,000 Coding/Unit Testing $1,000 or more System Testing $7,000 - $8,000 Acceptance Testing $1,000 - $100,000 After Implementation Up to millions of dollars It is important to spend money up-front on IT projects to avoid spending a lot more later. 9

Resource Planning The nature of the project and the organization will affect resource planning Some questions to consider: How difficult will it be to do specific tasks on the project? Is there anything unique in this project s scope statement that will affect resources? What is the organization s history in doing similar tasks? Does the organization have or can they acquire the people, equipment, and materials that are capable and available for performing the work? 10

Sample Headcount Information to Help Estimate Resource Costs A large percentage of the costs of many IT projects are human resource costs. 11

Cost Estimating An important output of project cost management is a cost estimate There are several types of cost estimates and tools and techniques to help create them It is also important to develop a cost management plan that describes how cost variances will be managed on the project 12

Table 7-3. Types of Cost Estimates Type of Estimate When Done Why Done How Accurate Rough Order of Magnitude (ROM) Very early in the project life cycle, often 3 5 years before project completion Provides rough ballpark of cost for selection decisions Budgetary Early, 1 2 years out Puts dollars in the budget plans 25%, +75% 10%, +25% Definitive Later in the project, < 1 year out Provides details for purchases, estimate actual costs 5%, +10% 13

Cost Estimation Tools and Techniques 3 basic tools and techniques for cost estimates: analogous or top-down: use the actual cost of a previous, similar project as the basis for the new estimate bottom-up: estimate individual work items and sum them to get a total estimate parametric: use project characteristics in a mathematical model to estimate costs 14

Constructive Cost Model (COCOMO) Barry Boehm helped develop the COCOMO models for estimating software development costs Parameters include source lines of code or function points COCOMO II is a computerized model available on the Web Boehm suggests that only parametric models do not suffer from the limits of human decisionmaking 15

Typical Problems with IT Cost Estimates Developing an estimate for a large software project is a complex task requiring a significant amount of effort. Remember that estimates are done at various stages of the project Many people doing estimates have little experience doing them. Try to provide training and mentoring People have a bias toward underestimation. Review estimates and ask important questions to make sure estimates are not biased Management wants a number for a bid, not a real estimate. Project managers must negotiate with project sponsors to create realistic cost estimates IT Project Management, Third Edition Chapter 7 16

Table 7-4. Business Systems Replacement Project Cost Estimate Overview IT Project Management, Third Edition Chapter 7 17

Table 7-5. Business Systems Replacement Project Cash Flow Analysis Costs Oracle/PM Software (List Price) FY95 ($000) FY96 ($000) FY97 ($000) 3 Year Total ($000) Future Annual Costs/Savings ($000) 992 500 0 1492 0 60% Discount (595) (595) Oracle Credits (397) 0 (397) Net Cash for Software 0 500 500 Software Maintenance 0 90 250 340 250 Hardware & Maintenance 0 270 270 540 270 Consulting &Training 205 320 0 525 0 Tax & Acquisition 0 150 80 230 50 Total Purchased Costs 205 1330 600 2135 570 Information Services & 500 1850 1200 3550 0 Technology (IS&T) Finance/Other Staff 200 990 580 1770 Total Costs 905 4170 2380 7455 570 Savings Mainframe (101) (483) (584) (597) Finance/Asset/PM (160) (1160) (1320) (2320) IS&T Support/Data Entry (88) (384) (472) (800) Interest 0 (25) (25) (103) Total Savings (349) (2052) (2401) (3820) Net Cost (Savings) 905 3821 328 5054 (3250) 8 Year Internal Rate of Return 35% IT Project Management, Third Edition Chapter 7 18

Cost Budgeting Cost budgeting involves allocating the project cost estimate to individual work items and providing a cost baseline For example, in the Business Systems Replacement project, there was a total purchased cost estimate for FY97 of $600,000 and another $1.2 million for Information Services and Technology These amounts were allocated to appropriate budgets as shown in Table 7-6 19

Table 7-6. Business Systems Replacement Project Budget Estimates for FY97 and Explanations Budget Category Estimated Costs Explanation Headcount (FTE) 13 Included are 9 programmer/analysts, 2 database analysts, 2 infrastructure technicians. Compensation $1,008,500 Calculated by employee change notices (ECNs) and assumed a 4% pay increase in June. Overload support was planned at $10,000. Consultant/Purchased Services $424,500 Expected consulting needs in support of the Project Accounting and Cascade implementation efforts; maintenance expenses associated with the Hewlett- Packard (HP) computing platforms; maintenance expenses associated with the software purchased in support of the BSR project. Travel $25,000 Incidental travel expenses incurred in support of the BSR project, most associated with attendance of user conferences and off-site training. Depreciation $91,000 Included is the per head share of workstation depreciation, the Cascade HP platform depreciation, and the depreciation expense associated with capitalized software purchases. Rents/Leases $98,000 Expenses associated with the Mach1 computing platforms. Other Supplies and Expenses Total Costs $1,800,000 $153,000 Incidental expenses associated with things such as training, reward and recognition, long distance phone charges, miscellaneous office supplies. 20

Cost Control Project cost control includes monitoring cost performance ensuring that only appropriate project changes are included in a revised cost baseline informing project stakeholders of authorized changes to the project that will affect costs Earned value management is an important tool for cost control 21

Earned Value Management (EVM) EVM is a project performance measurement technique that integrates scope, time, and cost data Given a baseline (original plan plus approved changes), you can determine how well the project is meeting its goals You must enter actual information periodically to use EVM. Figure 7-1 shows a sample form for collecting information 22

Figure 7-1. Cost Control Input Form for Business Systems Replacement Project WBS#: 6.8.1.2 Description: Design Interface Process - Customer Information Assignments Revision: Forecast Hours per day Effort (in hours) Calculated Revision Date: Responsible: SMC Role: PA Availability: 6 Optimistic: 20 Most Likely: 30 Plan Effort: Involved: Role: Availability: Pessimistic: 40 Involved: Role: Availability: Plan Duration : Involved: Role: Availability: Delay (Days): 30 Hrs 5 Days Description Develop an operational process design for the Customer Information interface from the Invoicing System to Oracle Receivables. This task will accept as input the business/functional requirements developed during the tactical analysis phase and produce as output a physical operational design, which provides the specifications, required for code development. Results / Deliverables Process Design Document - Technical - Operation/Physical DFD - Process Specifications - Interface Data Map Predecessors (WBS#): Assumptions - All business rules and issues will be resolved prior to this task. - The ERD & data model for Oracle Receivables & any Oracle extension required will be completed and available prior to this task. - The ERD for the Invoicing System will be completed and available prior to this task. - Few iterations of the review/modify cycle will be required. - Primarily a documentation task. 4.7 Dependencies Successors (WBS#): 23

Earned Value Management Terms The planned value (PV), formerly called the budgeted cost of work scheduled (BCWS), also called the budget, is that portion of the approved total cost estimate planned to be spent on an activity during a given period Actual cost (AC), formerly called actual cost of work performed (ACWP), is the total of direct and indirect costs incurred in accomplishing work on an activity during a given period The earned value (EV), formerly called the budgeted cost of work performed (BCWP), is an estimate of the value of the physical work actually completed 24

Earned Value Calculations 25

Earned Value Formulas 26

Rules of Thumb for Earned Value Numbers Negative numbers for cost and schedule variance indicate problems in those areas. The project is costing more than planned or taking longer than planned CPI and SPI less than 100% indicate problems 27

Figure 7-2. Earned Value Calculations for a One-Year Project After Five Months 28

Earned Value Chart 29

Project Portfolio Management Many organizations collect and control an entire suite of projects or investments as one set of interrelated activities in a portfolio Five levels for project portfolio management Put all your projects in one database Prioritize the projects in your database Divide your projects into two or three budgets based on type of investment Automate the repository Apply modern portfolio theory, including risk-return tools that map project risk on a curve 30

Using Software to Assist in Cost Management Spreadsheets are a common tool for resource planning, cost estimating, cost budgeting, and cost control Many companies use more sophisticated and centralized financial applications software for cost information Project management software has many costrelated features 31

Sample Enterprise Project Management Screen 32