OP CHECKLIST FOR PULL OUT TEST (SOIL NAIL)

Similar documents
METHOD OF STATEMENT FOR STATIC LOADING TEST

Method Statement for Static Load Testing (Compression) for Micropiles

Method Statement. Static Pile Load Test

SAMPLE GUIDE SPECIFICATIONS FOR OSTERBERG CELL LOAD TESTING OF DEEP FOUNDATIONS

ITEM # OSTERBERG CELL LOAD TESTING OF DRILLED SHAFT

SUPPLEMENTAL TECHNICAL SPECIFICATIONS BI-DIRECTIONAL STATIC LOAD TESTING OF DRILLED SHAFTS

Lymon C. Reese & Associates LCR&A Consulting Services Tests of Piles Under Axial Load

STATIC PILE LOAD TEST MANUAL. GEOTECHNICAL CONTROL PROCEDURE GCP-18 Revision #4

PILE TESTING SPECIFICATION

Step 11 Static Load Testing

Tex-421-A, Splitting Tensile Strength of Cylindrical Concrete Specimens

Page B-1 Hubbell Power Systems, Inc. All Rights Reserved Copyright 2014 LOAD TESTS

LOAD-CARRYING CAPACITY OF AXIALLY LOADED RODS GLUED-IN PERPENDICULAR TO THE GRAIN

MEASUREMENTS OF THRUST LOAD IN CABLE SYSTEMS SEMI-RIGIDLY INSTALLED IN DUCT / MANHOLE STRUCTURES

Standard Test Methods for Deep Foundations Under Static Axial Tensile Load 1

Precision Miniature Load Cell. Models 8431, 8432 with Overload Protection

Objectives. Experimentally determine the yield strength, tensile strength, and modules of elasticity and ductility of given materials.

CONTENTS 1. INTRODUCTION METHODOLOGY RESULTS & FINDINGS...9 APPENDIX

Butt Fusion Welding of HDPE Pipes Work Procedure

Physics 221 Experiment 5: Magnetic Fields

Research on the meaning of reinforcement ductility for a behavior of double-spans reinforced concrete beam.

HRA SULKY APPROVAL POLICY

SECTION SHEETING, SHORING AND BRACING

EDEXCEL NATIONAL CERTIFICATE/DIPLOMA MECHANICAL PRINCIPLES OUTCOME 2 ENGINEERING COMPONENTS TUTORIAL 1 STRUCTURAL MEMBERS

Quality Control and Quality Assurance Guide

Monitoring of Natural Hazards With the ImpactSentinel Alarming System An Intelligent Solution

INSTALLATION. General. Important Note. Design. Transport

Physics 41, Winter 1998 Lab 1 - The Current Balance. Theory

SECTION GUARDRAILS

Numerical modelling of shear connection between concrete slab and sheeting deck

ENGINEERING SCIENCE H1 OUTCOME 1 - TUTORIAL 3 BENDING MOMENTS EDEXCEL HNC/D ENGINEERING SCIENCE LEVEL 4 H1 FORMERLY UNIT 21718P

CONCRETE SEGMENTAL RETAINING WALL SYSTEM

Concrete 37 Compression machine accessories. ADR-Auto Console. Load Calibration Devices. Compression Machine Accessories

Hardened Concrete. Lecture No. 14

HORIZONTAL INSTALLATION

LABORATORY DETERMINATION OF CALIFORNIA BEARING RATIO

GOM Optical Measuring Techniques. Deformation Systems and Applications

Compression load testing straw bale walls. Peter Walker Dept. Architecture & Civil Engineering University of Bath Bath BA2 7AY.

Dr. Jesús Gómez, P.E. 36th Annual Conference on Deep Foundations, Boston, MA

Amendment to OPSS 415 (Nov 2008) Construction Specification for Pipeline and Utility Installation by Tunnelling

TECHNICAL NOTE Lining of Casings with SaniTite HP Pipe

PERFORMANCE TEST REPORT. Rendered to: FORMTECH ENTERPRISES, INC. SERIES/MODEL: Truline PRODUCT TYPE: PVC Seawall

Lessons 6 and 7 Foam Bridge Experiment- Forces and Stresses Lab

Force measurement. Forces VECTORIAL ISSUES ACTION ET RÉACTION ISOSTATISM

Forensic engineering of a bored pile wall

EDEXCEL NATIONAL CERTIFICATE/DIPLOMA MECHANICAL PRINCIPLES AND APPLICATIONS NQF LEVEL 3 OUTCOME 1 - LOADING SYSTEMS TUTORIAL 3 LOADED COMPONENTS

1997 Uniform Administrative Code Amendment for Earthen Material and Straw Bale Structures Tucson/Pima County, Arizona

MECHANICS OF SOLIDS - BEAMS TUTORIAL 1 STRESSES IN BEAMS DUE TO BENDING. On completion of this tutorial you should be able to do the following.

SECTION 1 GENERAL REQUIREMENTS

Söderströmtunnel: immersion in downtown Stockholm, Sweden

CONTRACT SPECIFICATIONS - SEISMIC ISOLATION BEARINGS

PLM series Permanent load lifting magnets

Federation of Piling Specialists Testing Datasheet No 1

TABLE OF CONTENTS. Page 1

Field Application Note

FUTURE SLAB. PENETRATIONS and. DEMOLITION of POST-TENSIONED FLOORS

MECHANICAL PRINCIPLES HNC/D PRELIMINARY LEVEL TUTORIAL 1 BASIC STUDIES OF STRESS AND STRAIN

Prestressed Concrete I-Beam and TxGirder Haunch Design Guide

SFI SPECIFICATION 28.1 EFFECTIVE: SEPTEMBER 23, 2011 *

1 One Dimensional Horizontal Motion Position vs. time Velocity vs. time

Detailing of Reinforcment in Concrete Structures

HUS-V Screw anchor. HUS-V Screw anchor. Basic loading data (for a single anchor) Mean ultimate resistance

MECHANICS OF SOLIDS - BEAMS TUTORIAL 2 SHEAR FORCE AND BENDING MOMENTS IN BEAMS

Optimised Design for Soil Nailed Walls 1

LAB 24 Transpiration

Local Authority Building Control Technical Information Note 3 Driven and In-situ Piled Foundations

CONCRETE SEGMENTAL RETAINING WALL SYSTEM

STANDARD INSPECTION & TEST PLAN (ITP) FOR CIVIL WORKS :

Use of Strain Gauge Rosette to Investigate Stress concentration in Isotropic and Orthotropic Plate with Circular Hole

Pro-Lift Steel Pile Foundation Repair

A Simple Method of Gripping Prestressing Strands for Tension Tests

System. Stability. Security. Integrity. 150 Helical Anchor

June 2007 CHAPTER 7 - CULVERTS 7.0 CHAPTER 7 - CULVERTS 7.1 GENERAL

Full-Scale Load Testing of Steel Strutting System. For. Yongnam Holding Limited

CHAIN-LINK FENCES BID SPECIFICATIONS DESCRIPTION

ANALYSIS FOR BEHAVIOR AND ULTIMATE STRENGTH OF CONCRETE CORBELS WITH HYBRID REINFORCEMENT

Design of Steel Structures Prof. S.R.Satish Kumar and Prof. A.R.Santha Kumar. The design of any foundation consists of following two parts.

Acceptance Codes APPENDIX - A. Acceptance Criteria

ENGINEERING COUNCIL CERTIFICATE LEVEL

Code of Practice for the Manual Handling of Gas Cylinder and exchange of regulators

Experiment 2: Conservation of Momentum

4B The stiffness of the floor and roof diaphragms. 3. The relative flexural and shear stiffness of the shear walls and of connections.

IDEAL AND NON-IDEAL GASES

For Asset Management

APPENDIX A PRESSUREMETER TEST INTERPRETATION

FORCE ON A CURRENT IN A MAGNETIC FIELD

FLOORS REINFORCEMENT Shear Stud Connector for steel- concrete composite structures cold applied by pins

TECHNICAL SPECIFICATION SERIES 8000 PRECAST CONCRETE

PRODUCT SPECIFICATION

Chapter. Restoration of Damaged Structures

Design and Construction of Cantilevered Reinforced Concrete Structures

USE OF MICROPILES IN TEXAS BRIDGES. by John G. Delphia, P.E. TxDOT Bridge Division Geotechnical Branch

Lighthouse Engineering, L.L.C.

GUIDELINE FOR HAND HELD SHEAR VANE TEST

STATIC AND KINETIC FRICTION

COMPETENCY ANALYSIS PROFILE. Rodworker 452A. (All unshaded skill sets must be demonstrated/ completed) Lift equipment and materials

1.2 Advantages and Types of Prestressing

Ampere's Law. Introduction. times the current enclosed in that loop: Ampere's Law states that the line integral of B and dl over a closed path is 0

English version. Raised access floors

Transcription:

Page 1 of 5 WORK INSTRUCTIONS FOR ENGINEERS LST Compiled by : CCM Checked by : Approved by : LSS OP-3-74. CHECKLIST FOR PULL OUT TEST (SOIL NAIL)

Page 2 of 5 CHECKED BY. CHECKLIST ITEMS G&P ENGINEER 1.0 NAIL INFORMATION 1.1 Type of pull-out test: Preliminary (Verification test)/working (Proof test)* * delete wherever not applicable Nail ID/Location: Length: m (minimum 3m of bonded length) Design Test Load: kn Load Cycle: cycles 2.0 INFORMATION PRIOR TO TESTING AT SITE 2.1 2.2 2.3 2.4 2.5 2.6 2.7 Is pull out test to be carried out at least 72 hours after grouting of the soil nail or achieve minimum 20N/mm 2? At least six (6) numbers of cube samples to be prepared for the 7 days and 28 days compression test. Is the cube result (i.e 7 days) submitted to G&P for review? Is the nail installation record(s) reviewed and approved by the consultant? Are the typical contents of the pull-out test report and loading schedule (sequence) made known to the contractor? Calibration certificates of the following measuring devices: a) Pressure Gauge (Hydraulic Jack) - Serial : The capacity shall be at least 1.2 to 2.0 times maximum test load. b) Load Cell - Serial : c) Dial Gauges-Serial : 1) 2) 3) 4) d) Data logger (if any) - Serial : Is the date of calibration of the above measuring devices not exceeding six (6) months? The description and layout/cross section of test setup shall be submitted for Engineer s approval prior to testing at site. Is the pressure gauge and load cell capable of loading up to the required test loads at site? Confirm with the contractor first before carrying out at site (sometimes it cannot due to setting-up and slope condition issue) 3.0 SLOPE CONDITION PRIOR TO TESTING 3.1 Localised uneven slope profile shall be trimmed when necessary. 3.2 3.3 3.4 To prevent excessive disturbance to the existing slope, large scale slope trimming is prohibited. If test nail is at higher ground and requiring staging, sufficient bracing and strutting shall be fixed to ensure that the staging is rigid and safe prior to pull-out testing and during monitoring works. The bearing capacity of the subsoil at the slope is adequate for pull-out test? (Check if it will subside if load increases gradually when load to the required test load).

Page 3 of 5 4.0 TESTING SETUP 4.1 Seating base for the pull-out test is a) steel plate b) shotcrete surface c) concrete pad * * delete wherever not applicable Dimension of the seating base: L ( ) X B ( ) X H ( ) 4.2 4.4 4.5 Independent Reference Beam (IRB) [distance, rigid, IRB legs shall be firmly installed, not too close to the soil nail position (minimum distance 1.0m away from the nail position and/or outside the seating base)]. compressible material between the hydraulic jack and the soil nail head. The seating preparation for the hydraulic jack (pressure gauge) shall be directly contacted on the seating base. Independently support and centre the jack over the nail bar so that the bar does not carry the weight of the testing equipment. The contact face should be even and perpendicular to the soil nail position. 4.6 4.7 4.8 4.9 Visually align the dial gauges to be parallel with the axis of test nail. Sometimes, alignment load (<5% of design test load) is required to align the testing apparatus. Dial gauges should be set to zero after the alignment load has been applied. Check whether the soil nail is in contact with the abovementioned seating base. (please refer to Figures below) Are the adopted pressure gauge, load cell, dial gauges, datalogger (if any) similar with the submitted calibration certificates to the consultant? Check the serial no of the measuring devices prior to start monitoring. Check and record the seating of the dial gauges and the direction of the dial gauges readings during loading and unloading. This is to confirm the reading corresponding to tensile or compression nail movement. This is important when corrections are necessary during results interpretation. 5.0 DURING LOAD SEQUENCE, MONITORING AND RECORDING 5.1 Did testing follow loading sequence and its holding period? 5.2 5.3 5.4 Take and record readings before and after load increment/decrement and record all necessary info. Actual readings of load cell and pressure gauge shall be recorded, not the calculated values from the loading schedule. Refer to Soil Nail Field Record Sheet. Check the following critical movement: a) For preliminary pull-out test, 0.8 times steel characteristic strength: b) For working pull-out test, creep test (1.5 times working load): The load during the creep test shall be maintained within 2% of the intended load by use of the load cell. For creep test, is the nail movement more than 1mm within the holding periods of 1 to 10 minutes? If yes, extend to total of 60 minutes and monitor the movement and check whether more than 2mm in total. Measure nail movement at 1,2,3,5,6,10,20,30,50 and 60 minutes during creep test.

Page 4 of 5 6.0 REPORT PREPARATION 6.1 The following information to be included in the report submission: a) Introduction b) Methodology c) Description of Apparatus d) Test Procedure (with setting up sketch) e) Table of the Load Increment / Cycle f) Summary of Test Results g) Graphs [Applied Load (kn) vs Deflection (mm) and Applied Load (kn) vs Time (min)] h) Pull out Test Field Record Form (with verification by Site Supervising Staff) i) Detail Results of Pull Out Test j) Datalogger Output (with verification by Site Supervising Staff) k) Copies of Calibration Certificates l) Actual photos at site drawing showing the setting-up and arrangement of the apparatus/instrument adopted for the pullout test. 7.0 MISCELLANEOUS Ensure the following are provided at site: - Stop watch and clock - Field recording form - Loading Sequence - Bubble level - Additional dial gauges - Digital camera te: The abovementioned practice should be prohibited as it will produce false result.

Page 5 of 5 Annulus and seating plate shall be larger than grout diameter te: Option A is adopted when the nail is fully grouted. te: Option B is highly recommended.