CHAPTER 7 - STEEL REINFORCEMENT

Similar documents
PRE INSTALLATION MANUAL

SPECIAL INSPECTION AND TESTING AGREEMENT INTERNATIONAL BUILDING CODE

Embedded Parts Introduction - Anchors

Welded Fabric. The CARES Guide to Reinforcing Steels Part 5. Installation of welded fabric on a major contract. 1.0 Introduction

Draft Table of Contents. Building Code Requirements for Structural Concrete and Commentary ACI

Measuring the Condition of Prestressed Concrete Cylinder Pipe

SERIES NG 1800 STRUCTURAL STEELWORK

How To Write A Recipe Card

METHOD OF STATEMENT FOR STATIC LOADING TEST

PTS HELICAL PIERS INSTALLATION SPECIFICATIONS NOTICE

SAFETY FENCES, SAFETY BARRIERS AND PEDESTRIAN GUARDRAILS

COATING & WRAPPING OF UNDERGROUND PIPING

SECTION 623 CONCRETE BONDING COMPOUND, EPOXY MORTAR AND EPOXY POLYMER CONCRETE OVERLAY SECTION CONCRETE BONDING COMPOUND.

Chapter. Restoration of Damaged Structures

SECTION CEMENT-MORTAR LINED AND COATED STEEL PIPE

NDT Procedure for Liquid Penetrant Inspection

Fabrication of Reinforcement

No allowance will be made for classification of different types of material encountered.

Hardened Concrete. Lecture No. 14

Mechanical Installation

Q&A Session for Advanced Ball Screws 102: Troubleshooting for Design Engineers

Design and Construction of Cantilevered Reinforced Concrete Structures

NDT Procedure for Liquid Penetrant Inspection TRINITY NDT. An ISO 9001:2008 Certified Company

Concrete structures for nuclear facilities

738-B-297 POLYMERIC CONCRETE BRIDGE DECK OVERLAY. (Adopted )

TECHNICAL SPECIFICATION SERIES 8000 PRECAST CONCRETE

Wire Damage on Ships Cranes

CATHODIC PROTECTION SYSTEM DESIGN

Structural Failures Cost Lives and Time

SECTION CAST-IN-PLACE CONCRETE

BENTLEY ELEMENTS COLLECTION LVT

OTTAWA CIVIC CENTRE & NORTH SIDE STANDS LANSDOWNE PARK FRANK CLAIR STADIUM STRUCTURAL ADEQUACY REPORT 2007

Diameter. Swift Lift Round Recess Plug. Note: The diameter of the narrow recess plug is the same as the diameter of the round recess plug.

Reproduced with the permission of the American Welding Society (AWS), Miami, Florida - 09/15/ Stud Welding

CRASH RAIL INSTALLATION HEIGHT

MATERIALS DIVISION MEMORANDUM

VC 104+ Rigid Grade / Rigid Grade Imagine VC 104 Rigid Grade Commercial Customised

CATHODIC PROTECTION OF REINFORCED CONCRETE STRUCTURES

INSTRUCTIONS FOR USE

North American Stainless

Section 8.1 Volume I QUALITY ASSURANCE PROGRAM OF PRECAST PRESTRESSED CONCRETE PRODUCTS

FUTURE SLAB. PENETRATIONS and. DEMOLITION of POST-TENSIONED FLOORS

Fiberglass Rebar (GFRP Rebar)

STANDARD INSPECTION & TEST PLAN (ITP) FOR CIVIL WORKS :

Field Damage Inspection and Static Load Test Analysis of Jiamusi Highway Prestressed Concrete Bridge in China

1 Barlines Rebar Detailing Standards in the Philippines

NAPCA BULLETIN APPLICATION PROCEDURES FOR CONCRETE WEIGHT COATING APPLIED BY THE COMPRESSION METHOD TO STEEL PIPE

Tensile Testing Laboratory

Acceptance Codes APPENDIX - A. Acceptance Criteria

C. Section TESTING LABORATORY SERVICE.

North American Stainless

Detailing of Reinforcment in Concrete Structures

Photographs: Acceptable, Unacceptable, and Unacceptably Repaired Precast Concrete Products

Field Welding Inspection Guide

HIGH PERFORMANCE PRE-APPLIED SYSTEM FOR BLIND SIDE & BELOW GRADE WATERPROOFING APPLICATIONS

FIVE STAR PRODUCTS, INC. (800)

SECTION 36 - CAST-IN-PLACE CONCRETE PIPE (CIPCP) TABLE OF CONTENTS

1.054/1.541 Mechanics and Design of Concrete Structures (3-0-9) Outline 1 Introduction / Design Criteria for Reinforced Concrete Structures

CORROSION ENGINEERING RESIN-BASED POLYMER CONCRETES AND GROUTS

It's large enough to handle most welding job shop projects, yet small enough to make it a worth while home-workshop tool

Bearing Failure: Causes and Cures

SAMPLE TEST QUESTIONS MOTOR VEHICLE BODY REPAIRER- ITA WEBSITE

North American Stainless

European Technical Approval ETA-09/0169

Waterstops play a critical role in the integrity of concrete

OVERVIEW OF TMH19: DRAFT STANDARD FOR THE VISUAL ASSESSMENT OF ROAD STRUCTURES

Basics of Reinforced Concrete Design

SURFACE PREPARATION STANDARDS

WARNING! Failure to follow these inspection procedures can cause personal injury and property damage.

bout your HOUSE before you start Repairing And Replacing Materials Exterior Walls

Strengthening of Large Storage Tank Foundation Walls in an Aggressive Environment by External Post-tensioning. May 7th 2013: Dominique Deschamps

Fatigue Performance Evaluation of Forged Steel versus Ductile Cast Iron Crankshaft: A Comparative Study (EXECUTIVE SUMMARY)

SECTION HIGH DENSITY POLYETHYLENE (HDPE) PIPE AND FITTINGS FOR WATER DISTRIBUTION AND TRANSMISSION

GENERAL SPECIFICATION FOR CIVIL ENGINEERING WORKS SECTION 13 WORK FOR ELECTRICAL AND MECHANICAL INSTALLATIONS

Safe Operating Procedure

Operations and Instruction Manual Might Swivel - Part # Concrete and Steel Anchorage Connector ANSI Z ,000 lbs / 44kn

COMPETENCY ANALYSIS PROFILE. Rodworker 452A. (All unshaded skill sets must be demonstrated/ completed) Lift equipment and materials

2001/069. Decks, stairways,gangways and their associated handrails OFFSHORE TECHNOLOGY REPORT HSE

Current opportunities of sprayed waterproofing membrane. Frank Clement Technical Manager Sprayable Membranes MEYCO Global Underground Construction

DMS REINFORCED CONCRETE PIPE AND MACHINE-MADE PRECAST CONCRETE BOX CULVERT FABRICATION AND PLANT QUALIFICATION

WATERPROOFING FOR CONCRETE STRUCTURES

SECTION PRECAST CONCRETE STRUCTURES

Product Name: Beamer 2000

NRDCA 400 GUIDELINE FOR FIELD APPLICATION of LIGHTWEIGHT INSULATING CONCRETE REROOFING/RECOVER SYSTEMS

Rehabilitation of an Aging Concrete Reservoir Adit Tower

~iffiui ~ Bridge Condition Survey. Inspection Date: 21 May 2003 District: San Angelo County: Tom Green Highway:

Site Auditing for Building Works. This practice note provides details of the strategy on auditing building works by the Buildings Department (BD).

ROLLING BEARING FAILURES

ROLLED STAINLESS STEEL PLATES, SECTIONS AND BARS

Guide Specification Precast Concrete Products

PIPING SYSTEM - ABRASIVE SLURRIES Engineering Standard Specification. 96 B. Riutta

SECTION 18 - CAST IN PLACE HIGH PERFORMANCE CONCRETE (HPC)

[BARLINES MANUAL OF STANDARD PRACTICE (PHILS)] Chapter One METRIC (SI), PNS BAR SIZES STANDARDS AND OTHER CRITERION

1.3.2 Method of construction and restoration of existing water service connections. This shall include:

JIS G3472 Electric Resistance Welded Carbon Steel Tubes for Automobile Structural Purposes

1.2 Advantages and Types of Prestressing

How To Repair A Steel Pier With A Watertight Frame

Attenuation: Bending Loss

GENERAL PROPERTIES //////////////////////////////////////////////////////

Transcription:

CHAPTER 7 - STEEL REINFORCEMENT DS Temple 7.1 SCOPE This section covers the inspection of steel reinforcement to be used in the works as per the applicable chapter of the Specifications. It also covers the special attention which must be given by the engineer s monitoring staff to material requirements, placing, fixing, cover and supports, coupling and welding of reinforcement. 7.2 MATERIALS The monitoring staff should ensure that the contractor submits a certificate of compliance for each type and batch of steel reinforcement used on the works. 7.3 INSPECTION The monitoring staff should take cognizance of the following in the inspections of the reinforcement. 7.3.1 Storage of Materials The reinforcement delivered to site should be stored neatly in a location specially prepared for this purpose. Reinforcement should be stored on a platform off the ground to prevent corrosion and contamination due to deleterious matter (mud, grease, oil, paint, loose rust, etc). If the reinforcement is to be stored for a long period of time or where stored in a marine environment (within 10km of sea) the reinforcement piles should be covered. 7.3.2 Condition of Reinforcement Photo 7.1: Very poor storage of reinforcement The condition of the reinforcement should preferably be checked in the storage yard before delivery to the point of use. The reinforcement should be clean and free of all deleterious matter and cleaned by means of water jetting, degreasing or other method if required as the presence of the above will have an adverse effect on the bond of reinforcement to concrete. Steel Reinforcement 7-1

Photo 7.2: Corroded reinforcement It is very important that reinforcement is not corroded to the point that pitting of the bars is evident. Pitting is a potential flaw which under cyclic loading can reduce the life of the structure significantly. If pitting of steel is greater than that permitted by SANS 920, the reinforcement should be rejected or further guidance sought from the engineer. 7.3.3 Bending Dimensions Photo 7.3: Reinforcement damage during demolition Bending dimensions of reinforcement should be frequently checked to ensure that the bars will fit into the formwork and provide enough cover. The inside radius of bends is very important to ensure that the bars were not overstressed during bending. Monitoring staff should have suitable templates for checking radius available on site. Steel Reinforcement 7-2

The minimum radii of bends are: High Tensile Steel = 3 Bar diameters Mild Steel = 2 Bar diameters WARNING Do not allow the use of heating to bend reinforcement. 7.3.4 Placing and Fixing Placing and fixing of reinforcement into the forms for the structure is one of the most important aspects of the construction of a structure. Special care should be taken by the monitoring staff to ensure that the reinforcement is placed and fixed in accordance with the design by verifying the following: (a) Type of steel (R or Y) (b) (c) (d) (e) (f) (g) (h) (i) (j) Diameter of bar Bar mark Spacing of bars Concrete cover (refer to item 7.3.5 below) Laps as per drawing (refer to designer if in doubt) Grouping of bars to create space for placing and vibrating concrete. All reinforcement should be adequately tied together and properly supported to ensure that the reinforcement does not displace and move in position during the concreting process as this will affect the cover to bars and the effective functioning of the concrete member. Adequacy of stools and clips provided (need for stools where not provided). Where bars are detailed to project out of a member (such as parapet anchors) they must be accurately placed and held in position. General neatness of the fixed reinforcement in the forms is always an indication of the accuracy of the placing and fixing and the contractor should be required to carry out corrective actions until the cages of reinforcement are fixed properly. 7.3.5 Cover and Supports WARNING Lack of cover on parapet anchors/starter bars results in loss of durability, pop outs and corrosion of reinforcement The minimum cover requirements are usually given on the drawings and/or in the project specifications. When checking the placing and fixing of reinforcement the monitoring staff must pay special attention to ensure that the specified cover to reinforcement is achieved. Cover has the most significant effect on the long term durability of reinforced concrete and therefore of the structure. Excess cover should be avoided as micro cracking due to bending stress can result in the growth and development of cracks and resulting corrosion of reinforcement or member loss due to spalling. The correct cover is required to ensure that reinforced concrete members meet their specified design requirements. Steel Reinforcement 7-3

Photo 7.4: Insufficient cover to reinforcement cage in forms Photo 7.5: Correct cover blocks in place In order to ensure that the reinforcement does not move during concreting the Specifications give specific requirements for the types and specifications of spacer blocks and stools and these requirements should be strictly adhered to. Photo 7.6 (a) & (b): Reinforcement corroding due to lack of cover Steel Reinforcement 7-4

Special attention should be given to the cover blocks and their mix design. Samples of cover blocks should be submitted by the contractor to the engineer for approval before the work commences. Care should be taken to ensure that the cover blocks are made in such a way that they integrate with the parent concrete. Only concrete cover blocks as specified in the Specifications may be used. Photo 7.7: Failure of member due to too much cover Photo 7.8: Corroded reinforcement resulting in loss of concrete Stools are not necessarily detailed on the drawings. They must be robust enough to perform well under concreting and other superimposed construction loads. The engineer has the authority to order the contractor to add additional stools to ensure the reinforcement is fixed securely and does not swivel or move during concreting. The provision of concrete cover to reinforcement stools should be checked. WARNING A wide range of plastic cover blocks are available but owing to problems associated with their use, are not permitted by a number of road authorities. If permitted they should only be used with great caution and subject to successful trials and ongoing monitoring. This is necessary as many are prone to bending or buckling under load and are sometimes clearly visible on the finished concrete surface. Steel Reinforcement 7-5

Approved cover meters will generally be provided on site. Where specified in the project specifications, cover to reinforcement should be confirmed after casting of the concrete by the use of electromagnetic cover meters. If the cover is substandard the engineer may instruct the contractor to remove and reconstruct the concrete member or agree to acceptable remedial measures with the employer. 7.3.6 Laps and Joints Laps, joints and splices should be placed as indicated on the drawings. As a general rule the lap length should not be less than 45 times the diameter of the smaller bar at the splice or lap. The lap positions should only be moved when the casting sizes are such that the contractor makes a specific request to do so. In all such cases any of these changes should be referred to the designer. It is good practice for laps and splices to be staggered as indicated on the drawings. This facilitates better placing of concrete and improved stress distribution in the concrete section, but may not be preferred by the Contactor in terms of casting construction joints. 7.3.7 Welding The welding of reinforcement is generally not permitted for high tensile steel as heating hot rolled bars causes brittle fracturing of the reinforcement. In the case of cold worked deformed bars, heating causes the reinforcement to revert to mild steel as it loses the effects of strain hardening. Welding may be permitted on mild steel in very specific cases, which should be referred by the monitoring staff to the engineer. Where welding of reinforcement is specified on the drawing the monitoring staff should ensure that the welding is carried out strictly in accordance with the Specifications and that specialized testing is carried out as required. 7.3.8 Mechanical Couplers Mechanical couplers may be specified where concrete members are coupled together due to staged construction processes, or where space restrictions do not permit normal laps and splices. The contractor should submit to the monitoring staff (for approval by the engineer) all the test certificates for the proposed proprietary products as required in the Specifications. 7.3.9 Conformance with Project Specifications The monitoring staff must check the Project Specifications for specific requirements related to types of reinforcement to be used, specific cover, cover block types, etc, and should ensure the compliance thereof for the duration of the contract. 7.4 STEEL REINFORCEMENT- CONSTRUCTION MONITORING CHECK LIST The monitoring staff should use the Steel Reinforcement - Construction Monitoring Check List as far as possible to ensure the quality of the installation of steel reinforcement. Steel Reinforcement 7-6

INDEX TO APPENDICES 7A - STEEL REINFORCEMENT Steel Reinforcement 7-7

CONSTRUCTION MONITORING CHECKLIST APPENDIX 7A STEEL REINFORCEMENT CHECK LIST PROJECT NO. / NAME:... INSPECTOR S NAME(S):... STRUCTURE:... ELEMENT:... ACTIVITY AND DETAILS APPROVAL Y/N N/A Comment SIGNED DATE 1. GENERAL 1.1 Storage of reinforcement 1.2 Condition of reinforcement 1.3 Bending dimensions 2. PLACING AND FIXING 2.1 Type of steel (R or Y) 2.2 Diameter of bars 2.3 Bar marks 2.4 Spacing / Number of bars 2.5 Concrete cover (general) 2.6 Laps (alternating) 2.7 Grouping of bars (clearances) 2.8 Fixing ties adequate 2.9 Spacers 2.11 Stools in place 2.12 Projecting anchor bars 2.13 Cleanliness of reinforcement 3. COVER AND SUPPORTS 3.1 Minimum cover as per drawing 3.2 Spacer block type 3.3 Spacer block positions 3.4 Spacer block spacing / Number provided 3.5 Stool spacing / Number provided 3.6 Stool fixity 4. SPECIAL REQUIREMENTS 4.1 Welding procedure approved 4.2 Welding quality 4.3 Mechanical couplers 4.4 Coupler type approved 4.5 Installed correctly 4.6 Other special requirements Steel Reinforcement 7-8