Bengt H. Fellenius THAILAND FOUNDATIONS FOR THE NEW INTERNATIONAL AIRPORT IN BANGKOK, THAILAND ASCE Seattle Section Geotechnical Group May 16, 29 1
FOUNDATIONS FOR THE NEW INTERNATIONAL AIRPORT IN BANGKOK, THAILAND Abstract Bengt H. Fellenius A presentation to the ASCE Seattle Section 29 Spring Seminar on Recent Developments and Case Histories in Deep Foundations. The Suvarnabhhumi airport, the new international airport in Bangkok, Thailand, covering an area of 8 Km by 4 Km (8, acres), is located in a former swamp, a flat marine delta about 3 Km outside Bangkok. The soil profile consists of a thin weathered crust on typical soft to stiff, compressible Bangkok clay deposited on a sand layer at a depth of about 25 m extending to about 47 m. Below the sand lies an about 1 m thick layer of hard silty clay followed by very dense sand to large depth. Most of the area is devoted to runways, roadways, and parking, which required extensive ground improvement to minimize settlement. The structures consist of several units sharing footprints: terminal building, conourse, trellis structure, parking garage, and elevated roadways. The structures are founded on three types of piles installed to the sand below the clay layer, 1, mm bored pile, 6 mm diameter bored piles, and 6 mm driven cylinder piles. The stress-bulbs from the various foundations overlap resulting in a complicated settlement analysis. A total of 25,+ piles were installed. The design of the airport started in 1995 and construction was completed in 25 at a total cost of close to us$3 billion. The lecture will present aspects of the soil improvement work, analysis of results from pile tests, and the design of the piled foundations for capacity, settlement, and downdrag. The main part of the presentation consists of information quoted from papers published in Geotechnical Engineering Special Issue, Vol.37, No. 3, December 26.
The New International Airport, Bangkok Thailand Foundation Design by TAMS/Earth Tech, NY with Dr. Bengt H. Fellenius as outside consultant The presentation is primarily based on papers published in the Special Issue of the Journal of South-East Asian Geotechnical Society, "Geotechnical Engineering", December, 26, as listed in the next slide. 2
Buttling, S. 26. Bored piles and bi-directional load tests. Special Issue of the Journal of South-East Asian Geotechnical Society, December 26, 37(3) 27-215. Cortlever, N.G., Visser, G.T, and dezwart, T.P., 26. Geotechnical History of the development of the Suvarnabhumi International Airport. Special Issue of the Journal of South-East Asian Geotechnical Society, December 26, 37(3) 189-194. Moh, Z.C. and Lin, P.C., 26. Geotechnical History of the development of the Suvarnabhumi International Airport. Special Issue of the Journal of South-East Asian Geotechnical Society, December 26, 37(3) 143-17. Seah, T.H., 26. Design and construction of ground improvement works at Suvarnabhumi International Airport. Special Issue of the Journal of South-East Asian Geotechnical Society, December 26, 37(3) 171-188. AND Fox, I., Du, M. and Buttling, S, 24. Deep Foundations For New International Airport Passenger Terminal Complex in Bangkok. Proceedings of the Fifth International Conference on Case Histories in Geotechnical Engineering, New York, April 13-14, Paper 1.22, 11 p.
3
4
Suvarnabhumi International Airport An 8 Km x 4 Km area close to the Gulf of Thailand 5
Basic Soil Parameters FILL Water Content, w n (%) 5 1 15 Density, ρ t (%) 1, 1,5 2, Vane Strength, τ u (KPa) 25 5 75 1 Very soft to Soft 5 5 5 Firm Depth (m) 1 Depth (m) 1 Depth (m) 1 τ u Stiff to Very Stiff 15 w P 3 w L 8-1 15 15 2 2 2 Data from: Fox, Du, and Buttling, (24), Buttling (26), Moh and Lin (26), Seah (26), Cortlever, Visser, and dezwart (26) 6
Compressibility Compression Ratio, CR..2.4.6.8 Virgin Modulus Number, m 5 1 15 2 Reloading Modulus Number, m r 5 1 15 5 5 5 Depth (m) 1 Depth (m) 1 Depth (m) 1 15 15 15 2 2 2 CR = C c /(1+ e ) m = ln1 (1 + e )/C c Red Lines show distribution for design Circles are data points 7
Comparison between the C c /e approach and the Janbu Modulus Number method.35 35 COMPRESSION INDEX, Cc.3.25.2.15.1.5..4.6.8 1. 1.2 VIRGIN MODULUS NUMBER, m 3 25 Do these values indicate a compressible soil, a medium compressible 5soil, or a non- compressible soil? 2 15 1 1.2 1..8.6.4 VOID RATIO, e VOID RATIO, e Data from a 2 m thick sedimentary deposit The C c -e approach (based on C c ) implies that the the compressibility varies by 3± %. However, the Janbu methods shows it to vary only by 1± %. The modulus number, m, ranges from 18 through 22; It would be unusual to find a clay with less variation. 8
Settlement of the Ground Surface Observed at Airport Site Regional settlement occurs at and around the airport area due to mining of ground water 1975 198 1985 199 1995 2 25 YEAR SETTLEMENT (mm) 1 2 3 4 5 6 7 Start of design work 9
Pumping (mining) of groundwater has reduced the pore pressures in the Bangkok delta resulting in significant regional settlement. In 1996, coinciding the beginning of the design process, pumping in the area was stopped. Pore pressure measurements indicate that the desired effect is being reached; the pore pressures are rising and the distribution may become hydrostatic in the future. Current and Future (long-term) Pore Pressure Distribution Pore Pressure (KPa) 1 2 3 4 5 Nearby Observations of Groundwater Table 5 1 YEAR 1975 198 1985 199 1995 2 25 21 Depth (m) 15 2 25 3 35 4 45 5 Short-Term (Current) Long-Term Depth to Graounwater Table (m) 1 2 3 4 5 6 7 Design Phase Construction Phase 1
The lowering of the groundwater table due to mining of water in the Bangkok delta is not unique. Below is a compilation of depth to the water table measured in the San Jacinto-Houston-Pasadena area in Texas. YEAR WATER DEPTH (m) 2 4 6 8 1 12 14 1925 1935 1945 1955 1965 1975 1985 1995 25 215 SHALLOW WELLS DEEP WELLS 132a- 14m 217-26m 216a- 39m 115-153m 29-159m 111-161m 51a-18m 912-26m 114a-261m 618-267m 66-31m 51b-365m 132b-442m 114b-48m 11
74 m 38 m 15 KPa 15 + 34 + 85 = 224-83 141 KPa 34 KPa 85 KPa -83 KPa 11 m SETTLEMENT (mm) (mm) 1936 1 1937 194 1945 1 195 196 1975 2 1 5 5 1 1 15 15 2 2 25 25 3 3 SETTLEMENT OF MONUMENT RELATIVE TO BENCHMARK LINEAR PLOT LOWER SCALE YEAR LOGARITHMIC PLOT UPPER SCALE 35 35 1936 1946 1956 1966 1976 1986 1996 26 4 YEAR 1936 1946 1956 1966 1976 1986 1996 26 12 Briaud et al. 27; Fellenius and Ochoa 28
Measured depths to water table and measured settlement of the Monument plus estimated settlement of the Monument had there been no drawdown of the water table. YEAR 1936 1937 194 1945 195 196 1975 2 1 1 1 SETTLEMENT (mm) 5 1 15 2 25 3 35 Monument only SETTLEMENT DEPTH TO WATER TABLE 25 5 75 1 DEPTH TO WATER TABLE (m) 4 125 13
And in the San Joaquin Valley in California: Approximate location of maximum subsidence in United States identified by research efforts of Joseph Poland (pictured).signs on pole show approximate altitude of land surface in 1925, 1955, and 1977. The pole is near benchmark S661 in the San Joaquin Valley southwest of Mendota, California, 1925 1955 1977 Subsidence at San Joaqu in Valley, California Devin Galloway and Francis S. Riley, U.S. Geological Survey 14
But back to Bangkok: Stress Profile Stress (KPa) 5 1 15 2 5 σ' c Depth (m) 1 15 2 Long-term σ' Short-term σ' Circles are preconsolidation data points Dashed green line shows distribution for design Short-term : Effective stress distribution at time of design Long-term : Effective stress distribution after groundwater table is raised 15
Concourses Main Terminal Acess Roads 16
First a few words on the soil improvement work Measured and Calculated Settlement at center line of for a 3. m Embankment during 2 days. No drains, i.e., incomplete consolidation. HEIGHT (m) SETTLEMENT (mm) -4-3 3. -2 2. -1 1. 1 2 3 4 5 6 Construction Period Full Height = 3. m Calculated Immediate Settlement Measured Total Settlement 4 m 1 m Calculated Consolidation Settlement Calculated Total Settlement 4 8 12 16 2 24 DAYS 17
Settlement at center line of a 3.6m Embankment on Wick Drains Wick Drains Installed 2 days FINAL HEIGHT OF FILL For reference, the curve of the 3.m "undrained" embankment SETTLEMENT (mm) 1. m DESIGN CURVE FOR THIS SURCHARGE (75 KPa) AVERAGE MEASURED SETTLEMENT 18
Settlement and Horizontal Movement for the 3.6 m Embankment Settlement was monitored in center and at embankment sides and horizontal movement was monitored near sides of embankment WICK DRAINS TO 1 m DEPTH WICK DRAINS TO 1 m DEPTH 1. m WICK DRAIN 2. m Time from start to end of surcharge placement = 9 months Observation time after end of surcharge placement = 11 months 19
Horizontal Movement versus Settlement at Different Test Locations HORIZONTAL MOVEMENT (cm) SETTLEMENT (cm) 2
The Problem Lateral spreading Settlement with risk for downdrag Piles 21
22
These photos of the bridge foundations illustrate a common problem affecting maintenance ($$$!), as well as, on occasions, being one compromising safety. 23
The problem is not limited to bridge foundations 24
Consolidation Coefficient, c v (m 2 /s) S E T T L E M E N T (m) Settlement after 4 months as a function of the Consolidation Coefficient and Drain Spacing Consolidation Coefficient, c v (m 2 /s) t = T v H c Degree of Consolidation after 4 months as a function of the Consolidation Coefficient and Drain Spacing v 2 C O N S O L I D A T I O N (%) 25
6 mm Bored Piles 6 mm Driven Closed-toe 1, mm Bored Piles Cylinder Piles 6 mm Bored Piles 1, mm Bored Piles The clay is soft and normally consolidated with a modulus number smaller than 1. All foundations the trellis roof, terminal buildings, concourse, walkways, etc. are placed on piles. The stress-bulbs from the various foundations will overlap each other s areas resulting in a complicated settlement analysis. 26
TYPICAL FOOTPRINT LAYOUT OF TRELLIS AND BUILDING FOUNDATIONS Additional features, such as Embankments, Aprons, Concourse foundations, Area Fills, etc. adversely affect the piles and the piled foundations. FOOTPRINTS OF PILE CAPS FOR TERMINAL BUILDING NEAR TRELLIS ROOF TRELLIS ROOF PILE CAP The stress interference between the foundations is significant and must be considered in the design analyses Horizontal soil movement ("lateral spreading") toward piles can be critical 27
To minimize lateral spreading toward adjacent foundations, some embankments were "supported" on soil-cement columns. For others, vacuum surcharge was employed together with fill surcharge. Vacuum surcharge will cause the perimeter soil to move inward. Combining vacuum and fill surcharge can minimize the horizontal soil movement. Vacuum surcharge can theoretically reach a stress of 1 KPa, but in practice, the maximum stress is about 6 KPa, equivalent to a fill height of about 3 m. The final design employed a vacuum surcharge (considered to be effective at 6 KPa) combined with an about 3 m surcharge fill (= 56 KPa) and a.9 m c/c triangular drain spacing. The target time for 6 % consolidation was 4 months at which time the extra surcharge was removed to bring the degree of consolidation to about 85 %. 28
29
6, 5, STATIC LOADING TEST 6 mm, 35 m Long Bored Pile 5 LOAD (KN) 1, 2, 3, 4, 5, 6, LOAD (KN) 4, 3, 2, DEPTH (m) 1 15 2 25 1, 3 5 1 15 2 25 3 MOVEMENT (mm) 35 4 3
Bi-directional Static Loading Test, "O-cell" test 1, mm Pile Stage 1 Lower Cell activated Upper cell closed Stage 2 Lower Cell open Upper Cell activated Stage 2 Lower Cell closed Upper Cell activated Data from Fox, I., Du, M. and Buttling,S. (24) Buttling, S. (26) 31
O-Cell tests Downward movements during test phases 1, 2, and 3 LOAD (KN) 2, 4, 6, 8, 1, MOVEMENT (mm) 25 5 75 1 125 P1 P2 P3 1 2 3 15 175 Active Cell Inactive, Open Cell Inactive, Closed Cell Concern was expressed that the toe resistance (Phase 1) was 3, KN and the shaft resistance for the lower segment was 5, KN (Phase 2), while in Phase 3 the combined shaft and toe resistances were only 6, KN. Should not the Phase 3 resistance be 8, KN rather than 6, KN (i.e., the sum of the values 5, KN and 3,)? 32
Downward toe movements are best plotted per sequence of testing. Particularly when considering toe resistance, one must evaluate the load-movement response in comparing Phase 1 + Phase 2 to Phase 3 (i.e., P2 shaft below cell plus P1 toe). DOWNWARD MOVEMENT MOVEMENT (mm) (mm) 25 5 75 1 125 15 175 LOAD (KN) 2, 4, 6, 8, 1, P1 P2 P3 P3 P1 and P2 data combined 1 2 3 Active Cell Inactive, Open Cell Inactive, Closed Cell 33
Load Distributions 5 Load (KN) 2, 4, 6, Stage 1 5 Load (KN) 2, 4, 6, Stage 2 1 1 15 15 Depth (m) 2 25 Depth (m) 2 25 62 mm Downward Movement 3 3 35 4 45 11 mm toe Movement 35 4 45 Stage 3 Max Load 34
5 Load (KN) 2, 4, 6, Stage 3 Load (KN) 2, 4, 6, 8, 1, 12, 5 Stage 1 Stage 2 Stage 3 1 1 15 15 Depth (m) 2 25 Depth (m) 2 25 3 3 35 35? 4 45 48 mm Downward Movement 4 45? 35
The test data settlement data as well as pile test data were applied to the design of the piled foundations employing the Unified Design Method. 36
The Unified Design Method is a three-step approach 1. The dead plus live load must be smaller than the pile capacity divided by an appropriate factor of safety. The drag load is not included when designing against the bearing capacity. [The capacity of the pile toe should be defined from a movement criterion]. 2. The dead load plus the drag load must be smaller than the structural strength divided with a appropriate factor of safety. [The live load must not be included because live load and drag load cannot coexist]. 3. The settlement of the pile (pile group) must be smaller than a limiting value. The live load and drag load are not included in this analysis. [The value(s) of acceptable settlement often governs a piled foundation design]. 37
Construing the Neutral Plane and Determining the Allowable Load 38
A repeat: Distribution of unit shaft shear and of load and resistance SHAFT SHEAR LOAD Settling Soil DEPTH ( ) (+) DEPTH Non- Settling Soil 39
The Unified Method (typical example) LOAD and RESISTANCE (KN) 5 1, 1,5 2, 2,5 3, SETTLEMENT (mm) SETTLEMENT OF PILE HEAD 1 2 3 4 5 6 7 8 DEAD LOAD 5 1 PILE "CAPACITY" 5 1 15 15 DEPTH (m) 2 25 DRAGLOAD DEPTH (m) 2 25 NEUTRAL PLANE 3 3 35 35 4 TOE RESISTANCE * ) 4 TOE MOVEMENT THAT MOBILIZES THE TOE RESISTANCE 45 45 * ) Portion of the toe resistance will have developed from the driving 1
Force and settlement (downdrag) interactive design. The unified pile design for capacity, drag load, settlement, and downdrag 5 Q d LOAD (KN) 2, 4, 6, Silt Sand Pile Cap Settlement SETTLEMENT (mm) 5 1 15 2 5 DEPTH (m) 1 15 2 Clay DEPTH (m) 1 15 2 Soil Settlement O-cell O-cell 25 Till 25 3 Pile toe load in the load distribution diagram must match the toe load induced by the toe movement (penetration), which match is achieved by a trialand-error procedure. TOE LOAD (KN) 3 1, 2, 3, 4, 5 1 PILE TOE PENETRATION (mm) q-z relation 41
Applied to the Bangkok Airport case Several static loading tests on instrumented piles were performed to establish the load-transfer conditions at the site at the time of the testing, i.e., short-term conditions. Effective stress analysis of the test results for the current pore pressures established the coefficients applicable to the long-term conditions after water tables had stabilized. A total of 25,4+ piles were installed. 42
Example of calculated resistance distribution for 6 mm diameter bored pile installed to a 3 m embedment depth. Short-Term Long-Term Q d = 1,4 KN F s = 2. on longterm capacity F s = 2. R ULT = 2,87 KN Q d = 1,4 KN F s = 2. R ULT = 2,8 KN 1 1 DEPTH (m) 2 Q n = 77 KN DEPTH (m) 2 Q n = 5 KN Clay Sand 3 1, 2, 3, LOAD (KN) The extensive testing and the conservative assumption on future pore pressures allowed an F s of 2.. The structural strength of the pile is more than adequate for the load at the neutral plane: Q d + Q n 1,5 KN. 3 1, 2, 3, LOAD (KN) 43
The settlements for the piled foundations were calculated to: Construction Long-term Total Trellis Roof Pylons 2 mm 9 mm 11 mm Terminal Building 3 15 45 Concourse 35 2 55 * * * 44
Contour lines of settlement of ground surface and pile caps near a trellis roof pile cap 45
46