ETC= (BAC EV) / CPI EAC= AC + ETC VAC= BAC EAC CV = EV AC

Similar documents
Earned Value Exercise. Su-Cheng Wu. MET AD 644: Project Risk, and Cost Management. Paul B. Cook, PhD PMP

Rules on using templates. MECH 896 Professional Development for MEng Students. Assignment #6A: Questions. Homework Discussion

INSE 6230 Total Quality Project Management

Earned Value Management (EVM) is a technique that is used to track the progress and status of a project and forecast its likely future performance.

Project Cost Management

Using Earned Value Management for Improving Processes. By Cynthia K. West

IST 302 : Project Cost Management

Earned Value Management Changes to the Glossary and Chapter 7 of the PMBOK Guide Third Edition.

Earned Value Management Tutorial Module 6: Metrics, Performance Measurements and Forecasting. Prepared by:

PROJECTS SCHEDULING AND COST CONTROLS

Earned Value. Valerie Colber, MBA, PMP, SCPM. Not for duplication nor distribution 1

Earned Value Formulae

Profesor: Francisco Javier Sanz Pérez. by fjspsv, PMP Test C07_01

A Gentle Introduction to Earned Value Management Systems

An introduction to Earned Value Analysis

Tracking Budgets and Schedules

Simple Earned Value (Using MS Project 2010)

Project Cost Management

Chapter 7. (PMBOK Guide)

AACE International Recommended Practice No. 86R 14

CVR/IT Consulting LLC

Earned Value Analysis Exercise

700 Analysis and Reporting

THE APPLICATION OF PERFORMANCE MEASUREMENT TECHNIQUE IN PROJECT MANAGEMENT : THE EARNED VALUE MANAGEMENT (EVM) APPROACH

How To Manage A Project

EARNED VALUE MANAGEMENT. CASE STUDY USING MICROSOFT PROJECT

Project Cost Management

Towards a Complete Earned Value Analysis. Sam Sharp and Peter Hall. Paper # 166

Earned Value Management Guidelines

COINS EVA Earned Value Analysis

PERFORMANCE AND QUALITY IN PROJECTS Project Management and Leadership 2016D, PhD, PMP

Brainstorm. What is Cost and Project Cost Management?

The Two Most Useful Earned Value Metrics: the CPI and the TCPI

Predicting progress on your project

PROJECT COST MANAGEMENT

Integration of Income Management and Cost Management: A Complementary for Financial Analysis of Projects. Abstract. Introduction

Introduction to earn value management in Civil Engineering

Adjust MS Project default settings to meet the needs of your project. Loading Analysis is an iterative process. Where are you overloaded?

Module 5 Cost Management PMP Exam Questions

GPMCEP GLOBAL PROJECT MANAGEMENT, LLC C O U R S E

Forecasting Project Schedule Completion by Using Earned Value Metrics

performance management system that is based on Earned Schedule Management.

Project Management: Tracking Progress and Earned Value with MS Project 2003

Managing Project Budgets with MS Project. Sonja Streuber, PMP, SSBB

technical tips and tricks

Assignment 2: Microsoft Project Toolset. Eric Palmer & Mahindra Bheodari. Kennesaw State University. IS 8100 Spring 2015

EVM.01. Earned Value Analysis Why it Doesn't Work

Earned Value Management and the Government Program Office. Blair Alan Knapp Jr. MSPM PMP

Procurement Management S# What? Formula Additional Notes CPPC CPFF CPAF CPIF T&M FPEPA FPAF FPIF FFP

How to Use EVM to Maintain Quality in an Agile Environment. A National Asset for National Missions 1

CPM -100: Principles of Project Management

Estimating Cost at Completion - Judgment & EV Information

Tracking Software Development Progress with Earned Value and Use Case Point

Appendix D Glossary Of Terms

IQPC IT Project Management Conference Sydney Recent Advances in Project Prediction Techniques

Pune, MH, India. 2 P.G. Student, Imperial College of Engineering & Research, Wagholi, Pune, MH, India. wit.vaishnavi@gmail.com

earned value management

LEADING EDGE FORUM CSC PAPERS 2012 EARNED SCHEDULE: FROM EMERGING PRACTICE TO PRACTICAL APPLICATION

Earned Value Management Tutorial Module 8: Reporting. Prepared by:

QUALITY AND PERFORMANCE IN PROJECTS. Project Management and Leadership 2015D, PhD, PMP

L10: Budgeting and Cost Control. Olivier de Weck

Project Management. ZEUS Student Seminar on 14 th November 2003 by Riko Wichmann. Riko Wichmann, MPY Zeus Student Seminar - PM,

Chapter 7: Project Cost Management. Munawar

PMI Lexicon of Project Management Terms

Unit 5: Cost Management (PMBOK Guide, Chapter 7)

Agile Project Management Controls

Project Control with ProTrack

Selftestengine..PMI-SP.270 questions PMI-SP. PMI Scheduling Professional

PROJECT MONITORING AND CONTROL USING BURNDOWN CHARTS

Using Earned Value Management Concepts to Improve Commercial Project Performance

Create Stoplight charts using Milestones Professional

SoaDssPm: A new Service-Oriented Architecture of the decision support system for the Project Management.

PMP PREP QUICK STUDY GUIDE BY THE PERSIMMON GROUP

Expert Reference Series of White Papers. Importance of Schedule and Cost Control

pm4dev, 2008 management for development series Project Budget Management PROJECT MANAGEMENT FOR DEVELOPMENT ORGANIZATIONS

Application of Earned Value Management System on an Infrastructure Project: A Malaysian Case Study

FERMI RESEARCH ALLIANCE PROCEDURES PROJECT MANAGEMENT. Head, Office of Project Management Oversight

Metrics for Agile Projects:

PMP Exam Preparation Answer Key

Information Technology Project Management, Sixth Edition. Note: See the text itself for full citations. More courses at cie-wc.edu

Earned Value and Agile Reporting

DCMA DCMA-EA PAM October 2012

Certification Exam Objectives: PK0-003

Earned Value Management

Applied Project Management ( APM )

Earned Value Management System Description

Project Cost Management. Richard Boser

Project Management Institute (PMBOK 2000) PMP Preparation Worksheet

Guided Process across Project Management; Preliminary phase: Contract Preparation

Basic Concepts of Earned Value Management (EVM)

Abstract. Earned Value Management Basics

Towards a Multi-Dimensional Framework for Assessing the Value of. Software Projects

Project Management Using Earned Value

The To Complete Performance Index

What is the Health of my Project?

Earned Value Reports from PMPlan Enterprise

Is Poor Project Management a Crime?

Lecture Slides for Managing and Leading Software Projects. Chapter 8: Measuring and Controlling Work Processes

Earned value method as a tool for project control

Transcription:

Forecasting Costs (ETC, EAC, VAC) Now that we know where our project stands, it is time to look ahead and answer some questions about the future of our project, such as: If things continue as they have been going, what will be our final project cost? How much will this vary from our current project budget? What type of performance do we need to have in order to be within our project budget by the end of the project? Estimate to Complete (ETC) Since we have calculated CPI, we can figure out what the cost to complete the remaining work on our project will be if our performance on the rest of the project is the same is we have experienced so far. In other words, what the remaining work will cost if our current CPI holds. This is known as the Estimate to complete (ETC) and it is calculated as: Estimate cost At Completion (EAC) ETC= (BAC EV) / CPI Now that we have an estimate of what it will cost to complete the work, we can add that to our costs so far to provide an estimate of what our total cost will be when we complete the project: Variance At Completion EAC= AC + ETC Variance at Completion is just the difference between what we had budgeted (the BAC) and the current estimate at completion (EAC). VAC= BAC EAC Watch the following video for an overview and example of how these forecasting tools are used. Cost Variance (CV) Cost Variance (CV) is the first of two basic variances that we can calculate once we have collected EV, PV and AC. Negative = over budget CV = EV AC positive= under budget 1 P a g e https://ca.linkedin.com/in/pedramshz Pedramshz@gmail.com Earn Value Report Management

Schedule Variance (SV) Schedule Variance (SV) is the second of two basic variances that we can calculate once we have collected EV, PV and AC. SV = EV PV Negative = work schedule to be complete at this time is not done Positive= work NOT YET schedule to be complete at this time has been done Cost Performance Index (CPI) While CV gave us a dollar amount that we are over or under budget at a particular point in time, Cost Performance Index (CPI) gives us an indicator of our overall performance to date and a good idea of how we are trending in regards to cost performance. CPI is calculated as follows: CPI = EV/AC CPI < 1 CPI = 1 CPI > 1 the cost of completing the work is higher than planned. the cost of completing the work is right on plan. the cost of completing the work is less than planned. While SV gave us a dollar amount to indicate how well we are doing at turning dollars into completed activities on schedule, Schedule Performance Index (SPI) gives us an indicator of our overall schedule performance to date, and a good idea of how we are trending in regards to schedule performance. However, please remember that there are some limitations on using money to measure schedule. Those limitations apply to SPI as well as SV. To know whether a project is 2 P a g e https://ca.linkedin.com/in/pedramshz Pedramshz@gmail.com Earn Value Report Management

really behind or ahead of schedule we will look at our planned start and finish dates, milestones, etc. SPI is calculated as follows: SPI = EV/PV SPI < 1 we are behind schedule. SPI = 1 we are on schedule. SPI > 1 we are ahead schedule. Percent Complete Index Budget (PCIB) The percentage of work that is complete based on baseline budget. We can use this if we trust our initial project baseline. We can use our inputs for the EVM to calculate PCIB: PCIB = EV / BAC Percent Complete Index Cost (PCIC) The percentage of work that is complete based on our actual costs so far and a revised estimate of the project costs (EAC re). This index is used if we have to revise the baseline due to changes in scope, if we are using rolling wave planning, or for some other reason where we don t trust out baseline costs. PCIC= AC/EAC re 3 P a g e https://ca.linkedin.com/in/pedramshz Pedramshz@gmail.com Earn Value Report Management

Planned Value Cost (PV) The Schedule % Complete specifies how much of the activity's baseline duration has been completed so far. Budget at Completion is computed from the baseline. When an activity has assignments, the Planned Value Cost is calculated as the Budget At Completion * (Data date of current project - baseline Assignment start date) / (baseline Assignment start date) for each of the assignments and then summed to the activity level. PV = BAC x Schedule % Complete Example: EV=$4134 x 50% = $2,067 4 P a g e https://ca.linkedin.com/in/pedramshz Pedramshz@gmail.com Earn Value Report Management

Over Budget Behind Schedule 5 P a g e https://ca.linkedin.com/in/pedramshz Pedramshz@gmail.com Earn Value Report Management

Planned Value (PV) is the authorized budget assigned to work to be accomplished for an activity or WBS component Total Planned Value for the project is known as Budget at Completion (BAC). Earned Value = % of completed work x BAC PCIB = 50% Schedule % complete =62.26% SV = EV PV= -$507 CV = EV AC=-$933 SPI = EV/PV = 0.80 CPI = EV/AC = 0.69 ETC= (BAC-EV)/CPI ETC= ($4,134-$2,067)/0.69 = $2,996 EAC= AC+ ETC = $3,000+$2,996 = $5,996 Estimate cost At Completion =$5,996 6 P a g e https://ca.linkedin.com/in/pedramshz Pedramshz@gmail.com Earn Value Report Management

If our baseline is inaccurate, or if we have reason to believe that CPI will not remain the same, ETC, EAC, and VAC may be based on Revised Estimates (sometimes referred to as ETC re, EAC re, and VAC re respectively). 7 P a g e https://ca.linkedin.com/in/pedramshz Pedramshz@gmail.com Earn Value Report Management

TCPI < 1: More Budget than Work Left TCPI = 1: Right amount of remaining Budget for remaining work. TCPI > 1: More Work than Budget Left 8 P a g e https://ca.linkedin.com/in/pedramshz Pedramshz@gmail.com Earn Value Report Management