Large-diameter bored piles and Large-hole drillings Applications

Similar documents
BUTE Department of Construction Management and Technology

ARCHITECTURAL TECHNOLGY 4 ADVANCED CONSTRUCTION TECHNOLOGY BASEMENT CONSTRUCTION YEAR 3 SEMESTER 1 AIDAN WALSH R Lecturer: Jim Cahill

STRUCTURES Excavation and backfill for structures should conform to the topic EXCAVATION AND BACKFILL.

Safe & Sound Bridge Terminology

Geotechnical Building Works (GBW) Submission Requirements

-SQA-SCOTTISH QUALIFICATIONS AUTHORITY HIGHER NATIONAL UNIT SPECIFICATION GENERAL INFORMATION

Tremie Concrete CM 420 CM 420 CM 420 CM 420. Temporary Structures. Tremie Concrete

ITEM # OSTERBERG CELL LOAD TESTING OF DRILLED SHAFT

TBM CROSSING OF STATIONS

Foundation Experts, LLC Specializes in Foundation Repair and Waterproofing

DESIGNING STRUCTURES IN EXPANSIVE CLAY

Building Pit Roche Building 1 Basel, Switzerland

Chapter. Restoration of Damaged Structures

Up-Down Construction Utilizing Steel Sheet Piles and Drilled Shaft Foundations

Milan M5 metro extension the construction of Lotto station

Emergency repair of Bridge B421

Eurocode 7 - Geotechnical design - Part 2 Ground investigation and testing

METHOD OF STATEMENT FOR STATIC LOADING TEST

Construction Technology 3

How To Retaining Wall Guide

SUPPLEMENTAL TECHNICAL SPECIFICATIONS BI-DIRECTIONAL STATIC LOAD TESTING OF DRILLED SHAFTS

PERMEABILITY TEST. To determine the coefficient of permeability of a soil using constant head method.

Chapter 9 Remedial Measures

SECTION SHEETING, SHORING AND BRACING

Stormwater/Wetland Pond Construction Inspection Checklist

Design, Testing and Automated Monitoring of ACIP Piles in Residual Soils

Comparison of Seismic Retrofitting Methods for Existing Foundations in Seismological Active Regions

INSITU TESTS! Shear Vanes! Shear Vanes! Shear Vane Test! Sensitive Soils! Insitu testing is used for two reasons:!

Construction sites are dewatered for the following purposes:

Pro-Lift Steel Pile Foundation Repair

PILE FOUNDATIONS FM 5-134

GOWANUS EXPRESSWAY TUNNEL PRIMER

Watershed Works Manual

Section Installation of pipe and casing for sanitary sewer by methods of augering.

TYPES OF PIERS USED IN NORTH AND EAST TEXAS RESIDENTIAL FOUNDATION REPAIR

FRANKIPILE. High Pile Loads Optimum Adaptation to Foundation Soil Low-noise Manufacturing Process

STANDARD AND SPECIFICATIONS FOR STORM DRAIN INLET PROTECTION

1.3.2 Method of construction and restoration of existing water service connections. This shall include:

CIVL451. Soil Exploration and Characterization

Section 2100-Trenching and Tunneling

Micropiles Reduce Costs and Schedule for Merchant RR Bridge Rehabilitation

Product Systems AQUAFIN-IC CEMENTITIOUS CRYSTALLINE PENETRATING WATERPROOFING. Waterproofing Specification

Slab Track Austria. System ÖBB-PORR elastically supported slab

CONSTANT HEAD AND FALLING HEAD PERMEABILITY TEST

PRESENT ISSUES FOR CENTRE DE LA MANCHE DISPOSAL FACILITY

Designed and Engineered to Perform

SAMPLE GUIDE SPECIFICATIONS FOR OSTERBERG CELL LOAD TESTING OF DEEP FOUNDATIONS

Foundations 65 5 FOUNDATIONS. by Richard Chylinski, FAIA and Timothy P. McCormick, P.E. Seismic Retrofit Training

Investigation of Foundation Failure. Step 1 - Data Collection. Investigation Steps

Contiguous Pile Wall as a Deep Excavation Supporting System

Estimation of Adjacent Building Settlement During Drilling of Urban Tunnels

SOME EXPERIENCE FROM THE SOFT GROUND TUNNELLING IN URBAN AREA

Chapter 3 Pre-Installation, Foundations and Piers

Attachment G-1: Pit Latrine Diagram. Fig E.1a: Pit Latrine. Fig E.1b: Plan View of Twin Pits

SECTION REMOVAL OR ABANDONMENT OF EXISTING UTILITIES AND UNDERGROUND STRUCTURES. 1. Trench excavation, backfill, and compaction; Section

DESIGN-BUILD SUPPORT OF EXCAVATION FOR BLOCK 76. Rick Deschamps and Tom Hurley, Nicholson Construction, Pittsburgh, PA USA

Table 4.9 Storm Drain Inlet Protetion Applicable for

SPECIFICATION FOR DYNAMIC CONSOLIDATION / DYNAMIC REPLACEMENT

EXCAVATION AND PILING NEAR SEWERS, STORMWATER DRAINS AND WATER MAINS

Sewer network renovation using glass-fiber reinforced (GRP) pipe liners

DUDERSTADT FOUNDATION & CONSTRUCTION, LLC.

Geotechnical Investigation Reports and Foundation Recommendations - Scope for Improvement - Examples

SHAFT CONSTRUCTION IN TORONTO USING SLURRY WALLS

COMPENDIUM OF INDIAN STANDARDS ON SOIL ENGINEERING PART 2

National Council of Examiners for Engineering and Surveying. Principles and Practice of Engineering Structural Examination

SCHEMATIC AND PROJECT BUDGET APPROVAL EAST CAMPUS NURSING EDUCATION AND CLASSROOM

Moving Small Mountains Vesuvius Dam Rehab

June 2007 CHAPTER 7 - CULVERTS 7.0 CHAPTER 7 - CULVERTS 7.1 GENERAL

RAM JACK INTRODUCTION

SEDIMENT/STORMWATER MANAGEMENT BASIN CONSTRUCTION CHECKLIST

Waterproofing System for Wastewater Tanks in Petrochemical Industries and Refineries

How To Use A Water Source Heat Pump

New construction Repairing failed or old foundations Retrofit foundations Permanent battered piers Machinery/equipment foundations

8 EXTRA LIGHT GRC SANDWICH ELEMENTS FOR ROOFING IN INDUSTRIAL BUILDINGS

USE OF MICROPILES IN TEXAS BRIDGES. by John G. Delphia, P.E. TxDOT Bridge Division Geotechnical Branch

The Manitoba Water Services Board SECTION Standard Construction Specifications PIPE EXCAVATION, BEDDING AND BACKFILL Page 1 of 11

DIRECTIONAL DRILLING

High Strain Dynamic Load Testing of Drilled Shafts

50AI01oe 02/15. Labko GRP cesspools. Instructions for installation, operation and maintenance

Indiana State Department of Health Construction Guidelines for Gravity and Flood-Dose Trench Onsite Systems

Tunnelling & Underground. Specialists

GEORGE J. CAMBOURAKIS, P.E., C. ENG. PRESIDENT & CHIEF STRUCTURAL ENGINEER

Mark Cramer Inspection Services, Inc.

STRUCTURAL CONCEPT FOR LIGHT GAUGE STEEL FRAME SYSTEM

Membrane for tunnels and underground construction

REPAIR AND STRENGTHENING OF HISTORICAL CONCRETE BRIDGE OVER VENTA RIVER IN LATVIA

COSMOS 2012: Earthquakes in Action COSMOS 2012

HIGH PERFORMANCE PRE-APPLIED SYSTEM FOR BLIND SIDE & BELOW GRADE WATERPROOFING APPLICATIONS

Appendix E Construction Methods

GENERAL SPECIFICATION FOR CIVIL ENGINEERING WORKS SECTION 13 WORK FOR ELECTRICAL AND MECHANICAL INSTALLATIONS

SECTION GRAVITY SANITARY SEWERS

TECHNICAL SPECIFICATION SERIES 8000 PRECAST CONCRETE

High Capacity Helical Piles Limited Access Projects

TECHNICAL NOTE Lining of Casings with SaniTite HP Pipe

BUILDING OVER OR NEAR WATER & SEWER MAINS POLICY

Types of Retaining Walls - Gravity walls - Pre-cast crib walls - Gabion walls - Reinforced concrete walls - Sheet pile walls - MS walls (mechanically

Hunter College school of Social Work Thesis Proposal

Important Points: Timing: Timing Evaluation Methodology Example Immediate First announcement of building damage

POST FOUNDATION REPAIR PERFORMANCE RESIDENTIAL AND OTHER LOW-RISE BUILDINGS ON EXPANSIVE SOILS. The Repair Committee of

Local Authority Building Control Technical Information Note 3 Driven and In-situ Piled Foundations

Transcription:

Large-diameter bored piles and Large-hole drillings Applications Bilfinger Spezialtiefbau GmbH Goldsteinstrasse 114 D-60528 Frankfurt Phone: +49 69 6688-345 Fax: +49 69 6688-277 Email: info.spezialtiefbau@bilfinger.com www.foundation-engineering.bilfinger.com

Large-diameter bored piles and large-hole drillings In-situ concrete piles with diameters of 0.3 m up to 3.0 m are referred to as large-diameter bored piles. For their construction hollow spaces are made in the soil by means of drilling equipment. Depending on soil conditions the excavation is carried out under the protection of a casing or without casing. Subsequently the drilling holes are filled with concrete; according to static requirements a rebar cage is placed before concreting. Large-diameter bored piles have a broad scope of application: They are used as foundation elements for carrying vertical building loads foundation elements for retaining walls temporary building pit walls components of the final structure protection against uplift and for taking up tension loads slope security and energy piles Large-hole drillings are applied for the construction of large-diameter bored piles the construction of a soldier wall with lagging the construction of wells removing obstacles in planned retaining wall or diaphragm wall lines underground demolition of structures under groundwater soil replacement in order to improve the soil and soil replacement in order to remediate contamination Bored pile wall underground parking Goetheplatz, Frankfurt Obstacle drillings Europakai, Hamburg

Large-diameter bored piles as foundation elements for carrying vertical building loads If the building ground for a spread foundation is not stable enough large diameter bored piles, which can transfer heavy building loads into deeper and more sustainable soil layers, are placed as foundation elements. The transfer of the loads into the soil takes place via end-bearing under the pile bottom and via skin friction along the shaft area. The centering and transfer of the building loads into the piles usually takes place via pile caps, pile cap beams, pile cap grids and via a continuous concrete slab. Measures to reduce settlements resp. to increase the pile load bearing capacity With pile foundations next to built-up areas sensitive to settlement the adjacent settlements must be minimized by the deformation of the piles. The same applies if the settlement difference of adjacent foundations is restricted. On the other hand the measures to increase the load bearing capacity can reduce the pile diameter and / or the pile length. a) Increasing the pile diameter and / or increasing the pile length With the increase of the pile diameter the point pressure is reduced quadratically and the shaft friction raises linear to the increase. The settlements can be reduced. Excavated large-diameter piles with shaft grouting Pile base underreaming device System Hartfuss 1050-2500 mm

b) Shaft grouting With shaft grouting, the shaft friction is increased by additional selective injections into the pile shaft area. For this purpose a thin plastic tube with valve is attached to the rebar cage for each injection point. When the pile concrete starts hardening the concrete cover of the valves is blasted with water high pressure and subsequently injected with cement slurry. On blasting the concrete cover of the rebar cage is partially shifted against the soil. The gap is cured by cement slurry, so that the concrete steel is secured against corrosion. Neubau Silo 3, Ruedersdorfer Zement, piles d = 180 cm Rebar cage with additional injection tubes Pressure bag for base grouting c) Pile base grouting During pile base grouting a pressure bag, a pressure bubble or a pressure box at the bottom of the rebar cage is injected with cement slurry by an injection tube after construction of the piles. This measure extends the pile base injection facility and therefore causes a preload of the soil under the pile base (anticipation of the settlement) before the building load is placed. d) Additional shaft grouting For the rehabilitation of bored piles with a non-sufficient load bearing capacity it is possible to carry out injection drillings around the piles and to inject grout. This corresponds to a pile cross-section enlargement and increases the load bearing capacity. e) Pile base enlargement For mainly base bearing piles a pile base enlargement for increasing the load bearing capacity can be recommended. Rebar cage with shaft grouting tubes

Primary columns for top-down construction The top-down construction method was first applied for underground railway construction. In these constructions the covers (concrete slabs) were used to maintain the traffic on the building site and to ensure a continuous working flow, as excavations and construction, under the cover. Moreover the covers were used for the bracing of building pits. In recent years the top-down construction method has been applied more often for bracing large building pits. The construction period for building construction sites can be reduced by this technology as after completion of the top or cover slab (ground level slab) simultaneous upwards and downwards construction is possible. Before construction of the top slab the bearings or supports must be provided. Usually the slabs rest at the building pit edge on the building pit boundary wall and on primary columns within the building pit. For the construction of the primary columns drillings are carried out up to the required maximum depth and concreted up to the planned final building pit bottom slab. Elements of steel profiles or precast concrete elements are integrated in the borehole with the exact required position and level. The remaining ring space within the drilling is filled with appropriate material. Construction of a primary column FrankfurtHochVier, Frankfurt Primary columns underground parking Goetheplatz, Frankfurt Primary columns FrankfurtHochVier, Frankfurt

Large-diameter bored piles as foundation elements for retaining walls Building pits for the construction of foundations for spread founded retaining walls are sometimes very elaborate. Frequently due to adjacent building structures there is not sufficient space available for the construction of the spread foundation elements. To solve this problem laterally soil supported large-diameter bored piles for the foundation of retaining walls are recommended. Bored pile walls Bored pile walls are executed as single, contiguous or secant pile walls. In the case of the secant bored pile wall every second, third or fourth pile is reinforced as supporting secondary pile, the primary piles in between are without reinforcement. In the case of the single and contiguous pile wall all piles are supporting and thus reinforced. The interspaces of the single bored pile wall are generally closed by shotcrete laggings, which can be drained. Bored pile walls as temporary building pit walls Bored pile walls are used as temporary building pit walls for the construction of building pits. Because of the high stiffness, compared to soldier walls with lagging or sheet pile walls, it is called a building pit wall with low deformation. Bored pile walls are chosen when in the area of the building pit construction buildings or other structures are to be protected against settlements. Bored pile wall types Building pit piling Domberg Freising, Freising Building pit with contiguous pile wall,coburg

Secant bored pile walls are used for "watertight building pits and apart from their function as building pit walls also used as impermeable walls. Therefore they must reach up to an artificial impermeable bottom slab or they should be socketed in a natural impermeable layer. Impermeable walls of secant large-diameter piles have been executed by Bilfinger Spezialtiefbau GmbH as seepage barriers against seepage water contaminated with heavy metals and micro-elements. As sealing material a cement-free, very solid sealing compound was used, fully developed by Bilfinger Spezialtiefbau GmbH. The upper 1 to 2 m of bored pile walls are often designed as walls with inserted beam support. In the case of pile construction this depth is executed as empty drilling and in the reinforced piles in the pile cap area steal beams are built in, which end at the ground surface. During excavation between the vertical beams a horizontal lagging of wood or shotcrete is carried out. This sheeting can be dismounted more easily for later activities like underground facilities. Bored pile walls, which are to be passed through by a tunnel boring machine (TBM), so called "spectacle walls are reinforced with a glass fibre reinforcement in the passage area (so called soft-eye construction). This reinforcement material is so brittle and easy to cut through that no damage to the TBM is to be expected. Rebar cage with glass fibre reinforcement for spectacle wall Building pit with contiguous bored pile wall Building pit with secant bored pile wall with inserted beams

In many cases for "watertight building pits a groundwater communication under the bottom slab must take place again after completion of the structure. To this end Bilfinger Spezialtiefbau GmbH developed and applied successfully the "Essener Dichtlamelle (sealing membrane) for the underground railway, lot 25 in Essen as a replacement for partial freezing. Every 10th pile was executed as sealing membrane under the excavation bottom level. During the building period this membrane was sealed and after completion of the structure reopened by a tube set in concrete over the membrane. Bored pile walls as components of the final structure Bored pile walls are not only used as temporary building pit walls but also as components of the final structure or as final independent structures. In underground railway or underground parking construction a watertight concrete cover wall is generally carried out on the inside of the bored pile wall. During the construction period the pile wall has to transfer the earth and water pressure loads, but after completion only earth load - the water load is carried by the concrete wall. In Munich at several underground stations the secant bored pile wall is a component of the final structure as a visual supporting element. Essener Dichtlamelle Secant bored pile wall as component of the final construction, underground railway Munich contiguous pile wall as component of the final structure, slope securing Beuersberger Strasse, Wolfratshausen

Large diameter piles against uplift and for transferring tension loads Large-diameter piles are often used as foundation elements for alternating loads (pressure and tension). These alternating loads occur due to the system on cantilevering hall or stadium roofs. In the case of pile foundation of high-rise buildings tension loads from uplift can appear during the construction period, if the dewatering for the building pit is turned off, the building pit is flooded and the weight of the building is not yet sufficient due to the degree of completion. In the final state these piles support like pressure piles. Large-diameter piles as slope securing Large-diameter piles are applied for slope securing in different versions. The stability is increased by active elements like: bored pile walls as retaining walls bored pile walls as supporting shear walls bored piles for dowelling A further possibility for securing slopes against sliding exist in the construction of deep drain trenches. To this end large-diameter secant, tangential or contiguous drillings are carried out vertically to the main gradient of the slope, on the bottom slab, a bottom drain tube is installed for the effluent overflow and the drillings are filled with filter material. Securing of slopes against slides by deep drain trenches Construction tension pile Hennes-Weisweiler-Stadion, Moenchengladbach Large-diameter piles as foundation element for retaining walls as slope securing retaining wall Horrem

Large-diameter piles as energy piles For new structures the regenerative usage of energy is growing incrementally. The heat of the earth close to the surface as part of the geothermal energy, is used for the climate control of buildings. The substratum is suited as a store for heat and cold, the required quantities depend on the time of day and year. By using necessary static building parts (no additional parts required) such as in-situ piles of the foundation or building pit piles as energy piles the investment costs for the usage of energy can be kept low. Heat exchanging pipes fixed to the rebar cage are installed in the in-situ piles. In these pipes a heat transfer medium flows for the temperature balance between the earth store and the interior rooms. In recent years Bilfinger Spezialtiefbau GmbH has executed the pile foundations as energy piles for the highrise buildings in Frankfurt Main Tower, Gallileo and Mainforum, for the building project FrankfurtHochVier, for the building project Rheinauhafen in Cologne as well as for the underground lot 2/1 in Vienna. Principle of an energy pile View in a rebar cage for an energy pile View in a rebar cage for an energy pile

Large-diameter drillings Large-diameter piles are executed for the construction of all sorts of piles, for the construction of soldier walls with lagging and of wells for dewatering. Obstacle drillings For the removal of obstacle drillings in diaphragm and sheet pile wall alignments, which lay very deep beneath the groundwater, Bilfinger Spezialtiefbau GmbH carries out replacement drillings and even drills solid reinforced concrete using the wash over method with self-developed rock augers. Subsequently the drilling is filled. Large-diameter drillings for underground demolition of concrete and reinforced concrete structures in the groundwater The demolition of concrete and reinforced concrete structures in the building ground under the groundwater level, if the ground water cannot be lowered, generally requires a "watertight building pit with impermeable walls and impermeable slab. Bilfinger Spezialtiefbau GmbH has developed the patented method of demolition by wash-over drilling method with cased borings and executed this method for the building project "Traffic facilities in the central area of Berlin, site clearing lot A, B and C. These lots comprised the underground demolition of an underground tunnel, a test caisson and a middle wall foundation of reinforced concrete surrounded by steel sheet pile retaining walls. After completion of the drilling it is filled and the filling material is compacted after the casing is pulled out. Site clearing traffic area in the central area of Berlin Drilling material for underground demolition of concrete and reinforced concrete in groundwater Obstacle drillings d = 120 cm in planned sheet pile retaining wall alignment Europakai Hamburg

Replacement drilling to improve the building ground For large areas of soil replacement of deeper non-load bearing soil layers, also in the groundwater, secant replacement drillings are appropriate. Excavation of the building pit, securing of the building pit and any dewatering which may be required are now unnecessary. The drillings are drilled up to the maximum depth and filled with suitable material. This filling becomes compacted after the drilling pipe is pulled out. Replacement drillings for removing the contamination Simultaneously with the soil rehabilitation using secant replacement drillings, contaminated soil is substituted by soil free from contaminants. According to the contamination degree a "blackwhite-plant has to be erected and the work is carried out under full protection. Replacement drillings gasworks Karlsruhe Reconstruction gasworks Freiburg Site plan secant drillings for soil replacement