A Reliable Method of Pile Load Test on Cast-in-Situ Pile Group of Existing Building for Retrofitting

Similar documents
METHOD OF STATEMENT FOR STATIC LOADING TEST

Step 11 Static Load Testing

ANALYSIS FOR BEHAVIOR AND ULTIMATE STRENGTH OF CONCRETE CORBELS WITH HYBRID REINFORCEMENT

EFFECT OF GEOGRID REINFORCEMENT ON LOAD CARRYING CAPACITY OF A COARSE SAND BED

SAMPLE GUIDE SPECIFICATIONS FOR OSTERBERG CELL LOAD TESTING OF DEEP FOUNDATIONS

SEISMIC ANALYSIS AND RETROFITTING OF R.C.C STRUCTURE

SUPPLEMENTAL TECHNICAL SPECIFICATIONS BI-DIRECTIONAL STATIC LOAD TESTING OF DRILLED SHAFTS

Lymon C. Reese & Associates LCR&A Consulting Services Tests of Piles Under Axial Load

Miss S. S. Nibhorkar 1 1 M. E (Structure) Scholar,

Dead load (kentledge) A structure over the test pile. Ground anchorage either by tension piles or ground anchors. Bi-directional (Osterberg-cell)

STATIC PILE LOAD TEST MANUAL. GEOTECHNICAL CONTROL PROCEDURE GCP-18 Revision #4

ITEM # OSTERBERG CELL LOAD TESTING OF DRILLED SHAFT

Pent Up Load and Its Effect on Load Test Evaluation

USE OF MICROPILES IN TEXAS BRIDGES. by John G. Delphia, P.E. TxDOT Bridge Division Geotechnical Branch

Assistant Professor of Civil Engineering, University of Texas at Arlington

Draft Table of Contents. Building Code Requirements for Structural Concrete and Commentary ACI

FOUNDATION DESIGN. Instructional Materials Complementing FEMA 451, Design Examples

Page B-1 Hubbell Power Systems, Inc. All Rights Reserved Copyright 2014 LOAD TESTS

PRESENTATION ON REPAIR AND REHABILITATION OF BUILDINGS DAMAGED IN EARTHQUAKE. By H P Gupta & D K Gupta

Method Statement. Static Pile Load Test

DESIGN OF SLABS. 3) Based on support or boundary condition: Simply supported, Cantilever slab,

Geotechnical Investigation Reports and Foundation Recommendations - Scope for Improvement - Examples

DYNAMIC TESTING OF MICROPILES. COMPARISON OF STATIC AND DYNAMIC TEST RESULTS

ABSTRACT 1. INTRODUCTION 2. DESCRIPTION OF THE SEGMENTAL BEAM

The Impact of Market Demands on Residential Post-Tensioned Foundation Design: An Ethical Dilemma

Rehabilitation of Existing Foundation Building to Resist Lateral and Vertical Loads

METHODS FOR ACHIEVEMENT UNIFORM STRESSES DISTRIBUTION UNDER THE FOUNDATION

Optimum proportions for the design of suspension bridge

Method Statement for Static Load Testing (Compression) for Micropiles

Sisal Composite Ltd. Apparel 4 Ltd. JM Knit Ltd. Natun Para, Hemayetpur, Savar, Dhaka-1340 ( N, E)

Numerical modelling of shear connection between concrete slab and sheeting deck

METHOD STATEMENT HIGH STRIAN DYNAMIC TESTING OF PILE. Prepared by

Structural Audit of Buildings

The following sketches show the plans of the two cases of one-way slabs. The spanning direction in each case is shown by the double headed arrow.

STRUCTURES Excavation and backfill for structures should conform to the topic EXCAVATION AND BACKFILL.

ASHULIA APPARELS LTD. Client Summary Report

Up-Down Construction Utilizing Steel Sheet Piles and Drilled Shaft Foundations

High Strain Dynamic Load Testing of Drilled Shafts

Hardened Concrete. Lecture No. 14

Current Status of Seismic Retrofitting Technology

In-situ Load Testing to Evaluate New Repair Techniques

SLAB DESIGN. Introduction ACI318 Code provides two design procedures for slab systems:

The advantages and disadvantages of dynamic load testing and statnamic load testing

PILE TESTING SPECIFICATION

DESIGN OF SLABS. Department of Structures and Materials Engineering Faculty of Civil and Environmental Engineering University Tun Hussein Onn Malaysia

Important Points: Timing: Timing Evaluation Methodology Example Immediate First announcement of building damage

Analysis and Repair of an Earthquake-Damaged High-rise Building in Santiago, Chile

Local Authority Building Control Technical Information Note 3 Driven and In-situ Piled Foundations

Seismic Isolation Retrofitting of Japanese Wooden Buildings

9.3 Two-way Slabs (Part I)

ADVANTAGES OF STEEL FIBRE REINFORCED CONCRETE IN INDUSTRIAL FLOORS

DESIGN OF PILES AND PILE GROUPS CONSIDERING CAPACITY, SETTLEMENT, AND NEGATIVE SKIN FRICTION

THE EFFECT OF IMPROVEMENT SURROUNDING SOIL ON BORED PILE FRICTION CAPACITY

Technical Notes 3B - Brick Masonry Section Properties May 1993

Numerical Analysis of the Moving Formwork Bracket Stress during Construction of a Curved Continuous Box Girder Bridge with Variable Width

MODELLING OF AN INFILL WALL FOR THE ANALYSIS OF A BUILDING FRAME SUBJECTED TO LATERAL FORCE

Seismic Risk Prioritization of RC Public Buildings

Foundations 65 5 FOUNDATIONS. by Richard Chylinski, FAIA and Timothy P. McCormick, P.E. Seismic Retrofit Training

FUTURE SLAB. PENETRATIONS and. DEMOLITION of POST-TENSIONED FLOORS

National Council of Examiners for Engineering and Surveying. Principles and Practice of Engineering Structural Examination

The Original Carbon Fiber Reinforced Polymer System

REHABILITATION OF THE FIGUEIRA DA FOZ BRIDGE

ALLOWABLE LOADS ON A SINGLE PILE

New construction Repairing failed or old foundations Retrofit foundations Permanent battered piers Machinery/equipment foundations

Wisconsin Building Products Evaluation

Safe & Sound Bridge Terminology

GEORGE J. CAMBOURAKIS, P.E., C. ENG. PRESIDENT & CHIEF STRUCTURAL ENGINEER

June 2007 CHAPTER 7 - CULVERTS 7.0 CHAPTER 7 - CULVERTS 7.1 GENERAL

Designed and Engineered to Perform

DEVELOPMENT AND APPLICATIONS OF TUNED/HYBRID MASS DAMPERS USING MULTI-STAGE RUBBER BEARINGS FOR VIBRATION CONTROL OF STRUCTURES

The International Workshop on Micropiles, 2007

Retrofitting By Means Of Post Tensioning. Khaled Nahlawi 1

Technical Assignment 2 TABLE OF CONTENTS

Fire and Concrete Structures

INSTALLATION. General. Important Note. Design. Transport

1.2 Advantages and Types of Prestressing

TARIFF CODE and updates standard

SECTION 1 GENERAL REQUIREMENTS

REPAIR AND RETROFIT OF BRIDGES DAMAGED BY THE 2010 CHILE MAULE EARTHQUAKE

SEISMIC RETROFITTING TECHNIQUE USING CARBON FIBERS FOR REINFORCED CONCRETE BUILDINGS

WORK SCOPE. Domains in which we work:

Detailing of Reinforcment in Concrete Structures

Federation of Piling Specialists Testing Datasheet No 1

Formwork for Concrete

Methods for Seismic Retrofitting of Structures

Chapter 3 DESIGN AND CONSTRUCTION FEATURES IMPORTANT TO SEISMIC PERFORMANCE

Seismic performance evaluation of an existing school building in Turkey

Re: Damages to Alaska Building from Legislative Information Office Construction

How To Model A Shallow Foundation

OPTIMAL DIAGRID ANGLE TO MINIMIZE DRIFT IN HIGH-RISE STEEL BUILDINGS SUBJECTED TO WIND LOADS

Joist. Reinforcement. Draft 12/7/02

Improvement in physical properties for ground treated with rapid impact compaction

Program COLANY Stone Columns Settlement Analysis. User Manual

LOAD TESTING OF SOME NEW BRIDGES IN LATVIA

Time- Cost Benefit Analysis for Anchor Type Foundation in Transmission Towers

The Strength of Concrete

Rigid and Braced Frames

ENGINEERED FOUNDATIONS. Department of Public Works Jeff Hill, PE

Seismic Risk Evaluation of a Building Stock and Retrofit Prioritization

Transcription:

July 2014, Volume 8, No. 7 (Serial No. 80), pp. 881-887 Journal of Civil Engineering and Architecture, ISSN 1934-7359, USA D DAVID PUBLISHING A Reliable Method of Pile Load Test on Cast-in-Situ Pile Group of Existing Building for Retrofitting Upal Mohammad Towfiqul Quadir Department of Civil Engineering, Military Institute of Science and Technology, Dhaka 1206, Bangladesh Abstract: Following the foundation failure of a building, with an aim of economical solution to strengthen other existing buildings of the same project, a new arrangement was implemented experimentally to test the adequacy of load bearing capacity of a few selected cast-in-situ RCC (reinforced cement concrete) pile groups without demolishing the existing buildings. In this test, the column bottom of an existing building was removed by the help of scaffolding and after that a frame system consisting tension piles and hollow beam was constructed over the pile cap of the to be tested pile group. The load was tested by the help of hydraulic jack system and the constructed frame system. This paper contains the detailed plan, arrangement and method of the test with illustrations. The deflection and loading data analysis is also included which was performed to determine the outcome of the test. Through this test method the appropriate assessment of capacity of pile group of existing building could be done successfully and in result the structure could be saved by only super structure retrofitting. Key words: Cast-in-situ, pile, load test, load bearing capacity, retrofitting. 1. Introduction Pile load tests are performed to find out if the pile have a certain least capacity or not [1]. In modern days, pile load tests are being performed by various methods such as conventional method, quick load test method or a modern static load test method such as self-balanced load test method [2, 3]. Even artificial neural networks are being used to predict the pile bearing capacity [4]. In modern era, some researches have also been performed on the degree of reliability on the conceptual frameworks to find out the pile capacity [5]. Usually, pile load tests are performed to find out the ultimate load bearing capacity and skin friction considering the residual stresses inside the pile [6]. Normally the pile load tests are performed on the piles before constructing the super structure. That is why all the methods available for pile load tests are usually for piles without a structure over them. One of the methods to test the load bearing capacity of the piles of an Corresponding author: Upal Mohammad Towfiqul Quadir, M.Sc., research field: structural engineering. E-mail: towfiq@ce.mist.ac.bd. existing structure was planned and applied in a retrofitting project in Dhaka which is discussed in this paper. The structure of a building of Dhalpur Cleaners Colonies project of DCC (Dhaka City Corporation) collapsed. The building was five storied residential building and was less than ten years old. The soil condition in that area was medium stiff which is why the buildings where constructed with pile foundation. DCC decided to strengthen the remaining existing buildings of the same project. But as the primary cause of the structural failure was found to be the load baring capability failure of the foundation, some experts advised reconstruction of the structures from foundation level. But as it would be a matter of huge budget for same project, DCC desperately looked for an alternative economical solution. Then a structural consultant company named Shaheedullah and New Associates Ltd. who were experienced in these types of structural solutions for over twenty years, came forward offering an experimental but promising solution. In their solution, they planned to test the load

882 A Reliable Method of Pile Load Test on Cast-in-Situ Pile Group of Existing Building for Retrofitting bearing capacity of a critical pile group of the existing building structure by the help of hydraulic jack constructing a set of tension pile and hollow beam system around the to-be-tested cast in situ pile group. As there is an existing structure over the pile cap, they suggested the removal of column bottom by the help of scaffolding. And for the placement of boring equipment for the construction of friction pile which falls inside the floor area, they suggested removal of the portion of slabs which are directly over the to-be-constructed friction piles location. 2. Description 2.1 Preparation At first, a most critical pile group at a most convenient location where the friction piles could be constructed and which carried greater load than other pile groups was selected for testing. The plan view of the pile cap of the selected pile group is shown in Fig. 1. Four friction piles of 45 cm diameter were planned to be constructed around the selected pile group of which one friction pile fell inside the floor area. So as the first step of the process, an area of around 10 m 2 of all the five slabs were removed at the place where the friction pile was planned to be constructed. Four 45 cm diameter friction piles of 18 m, 19.5 m and 21 m length were constructed around the pile group. Different lengths were chosen due to different friction capacity of soil in the respective locations. After that, the ground floor segment of the column was replaced by some angular support as scaffolding. The column bottom was demolished after that. A cross shaped steel box frame was placed over the pile cap for proper distribution of load while testing. After that a hollow steel beam system containing three hollow beams was constructed over the pile cap connecting the friction piles as support. The steel made hollow beams were welded to the extended reinforcements of the friction pile. At first 0.75 cm thickness was chosen for the hollow steel beams as per local availability of the steel plates and the highest load to be applied. A hydraulic pump jack was placed between the hollow steel beam arrangement and the cross shaped steel box frame on the pile cap. To resist failure due to shear force, some angular bars were welded to the steel beams at the portion where the hydraulic jack was placed. A precision strain dial gauge with magnetic base was used to determine the deflection. The jack pump system had a capacity of applying 300 t and the strain dial gauge to monitor pile settlement had maximum run of 50 mm with a sensitivity of 0.01 mm. The information of the to-be-tested pile group is shown in Table 1. As per the designated engineer of DCC, the design load for the group pile was 86 t which was derived from the calculated column load of the design data of that building which data was used at the time of that building s construction. ASTM(1989) specifies a test load of 1.5 times the design load for individual service piles. So it was decided that a test load of 129 t should be applied to the service group pile. 2.2 Testing (First Phase) It was planned to apply the test load of 129 t in six approximately equal increments. The elevation and parts of the whole arrangement is shown in Figs. 2 and 3. While applying the load, in one of the initial loading stages, it was found that one of the beam of the steel hollow beam system failed due to the failure of one of the friction piles. The test was stopped for this reason and corrective measures were started to be planned. 2.3 Testing (Second Phase) As one of the friction pile failed in the first phase and also the hollow beam, a new set of friction piles were constructed and a new arrangement of steel hollow beam was introduced. The elevation and all the details of the new arrangement are shown in Figs. 4-11. The Table 1 Physical and technical descriptions of the service group pile [7]. Service group No. of piles Pile diameter Pile length pile No. in the group (mm) (m) 1 5 450 12.5

A Reliable Method of Pile Load Test on Cast-in-Situ Pile Group of Existing Building for Retrofitting 883 1,500 5 cast in situ piles of 450 mm diameter and 12.5 m height 400 1,500 350 350 400 400 350 350 400 Fig. 1 Plan view of pile cap of the to-be-tested pile group. Fig. 2 Elevation of first arrangement. thickness of the steel plates of the hollow beams were increased to 1.5 cm to be on the safe side. Like the first phase, it was again planned to apply a test load of 129 t (1.5 time the design loads) in six approximately equal increment. The hydraulic jack was placed between the steel hollow beam system and the cross shaped steel box placed over the pile cap. The plan of both arrangements are shown in Fig. 12. Then the load was

884 A Reliable Method of Pile Load Test on Cast-in-Situ Pile Group of Existing Building for Retrofitting started to be applied by the help of hand pump connected to the hydraulic jack. The current loading stage after each increment of load was maintained until the rate of settlement was not greater than 0.25 mm/h or 2 h had elapsed whichever occurred first. After that the next load increment was applied. This procedure has been followed for all increments of load. When the load was raised to 132.46 t, it was found that the pile group was able to sustain this load. At that point, to be more assured about the load baring capacity of the pile group, it was decided to raise the load to a magnitude of 150.5 t (1.75 times the design load). As per the decision the load was raised to 152.29 t, consequently. It was observed that the pile group was able to sustain the load of 152.29 t. The total settlement at the test load of 152.29 t was found to be 13.85 mm. After that, the test load was then released with four step decrement. The elastic rebound of the pile due to unloading was measured by keeping the strain dial gauges attached to a pile. By this the final net settlement of the service group pile was found to be 10.67 mm. Fig. 3 Parts of first arrangement. Steel hollow beams New arrangement Cross shaped steel box Fig. 4 Elevation of second arrangement. Pile cap of the to-be-tested pile group

A Reliable Method of Pile Load Test on Cast-in-Situ Pile Group of Existing Building for Retrofitting 885 Fig. 8 Strain dial gauge. Fig. 5 Parts of second arrangement (1). Fig. 9 Hand pump and gauge of hydraulic jack. Fig. 6 Parts of second arrangement (2). Fig. 10 Parts of second arrangement (4). Fig. 7 Parts of second arrangement (3). Fig. 11 Parts of second arrangement (5).

886 A Reliable Method of Pile Load Test on Cast-in-Situ Pile Group of Existing Building for Retrofitting Fig. 12 Plan of both arrangements. Friction piles of first arrangement is indicated by Spoilt [8]. 3. Results and Discussion The load settlement time curve and load settlement curve for the test are shown in Figs. 13 and 14, respectively. According to the test, the maximum settlement was found to be 13.85 mm which is lower than the maximum allowable settlement of 25 mm according to ACI code. So from this test, it was clear that the building foundation was capable to sustain the design load unlike the foundation of the building that already collapsed. Through this experimental method, many buildings of the same project of which the foundation was capable were saved from demolition of the whole structure, which economically contributed a lot by saving a huge budget of the government of a developing country as Bangladesh.

A Reliable Method of Pile Load Test on Cast-in-Situ Pile Group of Existing Building for Retrofitting 887 Fig. 14 Load-settlement curve of the tested pile group [7]. References Fig. 13 Load-time-settlement curves of the tested pile group [7]. 4. Conclusions The main purpose of this experiment was to determine the load bearing capacity of a service pile group of an existing building which was successfully done. Later on, after this test, the building super structures of DCC were strengthened as per necessity as the problem was found not to be in the sub structure/foundation. This experimental method opened various scopes of future research as well, such as reconstruction of reinforced concrete columns after removal due to retrofitting works, easier method to test the load bearing capacity of an existing building, using constructed friction piles as part of the foundation of an existing structure. [1] B.H. Fellenius, The analysis of results from routine pile load tests, Ground Engineering13 (6) (1980) 19-31. [2] F.M. Fuller, H.E. Hoy, Pile load tests including quick-load test method, conventional methods and interpretations, Highway Research Records 333 (1970) 74-86. [3] G. Weiming, D. Guoliang, J. Yongsheng, X. Guoya, Theory and practice of self-balanced loading test for pile bearing capacity, Journal of Building Structures 1 (2002) 82-88. [4] M.F. Randolph, Science and empiricism in pile foundation design, Géotechnique 53 (10) (2003) 847-875. [5] M. Lee, J.H. Lee, Prediction of pile bearing capacity using artificial neural networks, Elsevier 18 (3) (1996) 189-200. [6] R.D. Rieke, J.C. Crowser, Interpretation of pile load test considering residual stresses, Journal of Geotechnical Engineering 113 (4) (1987) 320-334. [7] Report on Results of Pile Load Test on Cast-in-Situ Service Group Pile for the Strengthening of Existing Cleaner Colony Buildings at Dhalpur (Building-A) of Dhaka City Corporation, Department of Civil Engineering, Bureau of Research, Testing and Consultants (BRTC), Bangladesh University of Engineering and Technology (BUET), 00574/09-10/CE, 2010. [8] Work Details Archive, Dhaka City Corporation, Dhaka, Bangladesh, 2010.