Prof. B V S Viswanadham, Department of Civil Engineering, IIT Bombay

Similar documents
Dimensional and Structural Data for Elliptical Pipes. PD 26 rev D 21/09/05

PUBLIC WORKS DESIGN, SPECIFICATIONS & PROCEDURES MANUAL LINEAR INFRASTRUCTURE

GEOTECHNICAL DESIGN MANUAL

State of Illinois Department Of Transportation CONSTRUCTION INSPECTOR S CHECKLIST FOR STORM SEWERS

SECTION 5: SANITARY SEWER SYSTEM DESIGN

Nebraska Department of Roads Drainage and Erosion Control Manual December 2011 Appendix C: Pipe Material Policy Page C-1 PIPE MATERIAL POLICY

ENGINEERING SCIENCE H1 OUTCOME 1 - TUTORIAL 3 BENDING MOMENTS EDEXCEL HNC/D ENGINEERING SCIENCE LEVEL 4 H1 FORMERLY UNIT 21718P

Chapter 9. Steady Flow in Open channels

METHODS FOR ACHIEVEMENT UNIFORM STRESSES DISTRIBUTION UNDER THE FOUNDATION

Oil and Gas Pipeline Design, Maintenance and Repair

DESCRIPTION OF STORMWATER STRUCTURAL CONTROLS IN MS4 PERMITS

MECHANICS OF SOLIDS - BEAMS TUTORIAL 2 SHEAR FORCE AND BENDING MOMENTS IN BEAMS

June 2007 CHAPTER 7 - CULVERTS 7.0 CHAPTER 7 - CULVERTS 7.1 GENERAL

ALLOWABLE LOADS ON A SINGLE PILE

SECTION 55 PIPE FOR STORM DRAINS AND CULVERTS (FAA D-701)

Estimation of Adjacent Building Settlement During Drilling of Urban Tunnels

APPLICATION PROCEDURES FOR PLACEMENT OF UNDERGROUND WATER AND SEWER PIPELINES IN THE VICINITY OF TRANSPORTATION FACILITIES UNDER THE

Liner system design for tailings impoundments and heap leach pads

REINFORCED CONCRETE. Reinforced Concrete Design. A Fundamental Approach - Fifth Edition. Walls are generally used to provide lateral support for:

Chapter 13 OPEN-CHANNEL FLOW

FIELD PERFORMANCE OF A CONCRETE PIPE CULVERT INSTALLED USING STANDARD INSTALLATIONS

DIVISION 2 - SEWERAGE AND DRAINAGE SECTION STORM DRAIN SYSTEMS PART 1 - GENERAL

APPLICATION PROCEDURES FOR PLACEMENT OF UNDERGROUND TELECOMMUNICATION CABLES IN THE VICINITY OF TRANSPORTATION FACILITIES

Investigation of Foundation Failure. Step 1 - Data Collection. Investigation Steps

Open Channel Flow. M. Siavashi. School of Mechanical Engineering Iran University of Science and Technology

IS THAT LINER THICK ENOUGH?

Eurocode 7 - Geotechnical design - Part 2 Ground investigation and testing

PDCA Driven-Pile Terms and Definitions

PVC PIPE PERFORMANCE FACTORS

SECTION EARTH MOVING

Final Report. Sacramento County Sanitation District No. 1. Engineering Sustainability of Piping Materials

Worked Example 2 (Version 1) Design of concrete cantilever retaining walls to resist earthquake loading for residential sites

INTRODUCTION TO SOIL MODULI. Jean-Louis BRIAUD 1

Module 7 (Lecture 24 to 28) RETAINING WALLS

APPENDIX G SETTLEMENT

6.0 Results of Risk Analyses

Comprehensive Design Example 2: Foundations for Bulk Storage Facility

When the fluid velocity is zero, called the hydrostatic condition, the pressure variation is due only to the weight of the fluid.

Safe & Sound Bridge Terminology

PUBLIC WORKS DESIGN, SPECIFICATIONS & PROCEDURES MANUAL LINEAR INFRASTRUCTURE

DRAINAGE PART 5 HA 40/01 DETERMINATION OF PIPE AND BEDDING COMBINATIONS FOR DRAINAGE WORKS SUMMARY

ENCE 4610 Foundation Analysis and Design

NCHRP. Web-Only Document 190: Structural Design of Culvert Joints. I.D. Moore D. Becerril García Queen s University Kingston, Ontario

Gas Meter Clearances and Service Installation Requirements

Structural Axial, Shear and Bending Moments

Module 5 (Lectures 17 to 19) MAT FOUNDATIONS

Gas Meter Clearances and Service Installation Requirements

PILE FOUNDATIONS FM 5-134

720 Contour Grading. General. References. Resources. Definitions

Embankment Consolidation

SLAB DESIGN. Introduction ACI318 Code provides two design procedures for slab systems:

1997 Uniform Administrative Code Amendment for Earthen Material and Straw Bale Structures Tucson/Pima County, Arizona

Open channel flow Basic principle

H 300 DESIGN LOADS AND DISTRIBUTION OF LOADS

The Pipe/Soil Structure Actions and Interactions

CONCRETE PIPE AND PORTAL CULVERT HANDBOOK P.I.P.E.S

OPEN-CHANNEL FLOW. Free surface. P atm

SIERRA LAKES COUNTY WATER DISTRICT P.O. Box 1039, Soda Springs, CA (7300 Short Road, Serene Lakes)

DAMAGE TO FOUNDATIONS FROM EXPANSIVE SOILS

STRUCTURES Excavation and backfill for structures should conform to the topic EXCAVATION AND BACKFILL.

Figure CPT Equipment

SUPPLEMENTAL TECHNICAL SPECIFICATIONS BI-DIRECTIONAL STATIC LOAD TESTING OF DRILLED SHAFTS

CHAPTER 9 FEM MODELING OF SOIL-SHEET PILE WALL INTERACTION

Impacts of Tunnelling on Ground and Groundwater and Control Measures Part 1: Estimation Methods

Module 2. Analysis of Statically Indeterminate Structures by the Matrix Force Method. Version 2 CE IIT, Kharagpur

SAMPLE GUIDE SPECIFICATIONS FOR OSTERBERG CELL LOAD TESTING OF DEEP FOUNDATIONS

Foundation Experts, LLC Specializes in Foundation Repair and Waterproofing

Pipes and Fittings for Gravity Sewer Mains. SewerMAX

Benchmarking Multi-Dimensional Large Strain Consolidation Analyses D. Priestley 1, M.D. Fredlund 2 and D. van Zyl 3

3. Contractor shall ensure that all permits are obtained prior to any construction. Contractor shall be responsible for all utility fees.

Repair or Replacement - Band-Aids vs. Surgery

Specialised Data Specifications

Module 7: Hydraulic Design of Sewers and Storm Water Drains. Lecture 7 : Hydraulic Design of Sewers and Storm Water Drains

Indiana State Department of Health Construction Guidelines for Gravity and Flood-Dose Trench Onsite Systems

OSU Extension FACT SHEET

TECHNICAL NOTE Lining of Casings with SaniTite HP Pipe

Chapter 4 SUBSURFACE INVESTIGATION GUIDELINES

Seismic Analysis and Design of Steel Liquid Storage Tanks

DIVISION OF WATER QUALITY CONSTRUCTION GRANTS & LOANS SECTION FAST TRACK AUDIT CHECKLIST

EFFECT OF GEOGRID REINFORCEMENT ON LOAD CARRYING CAPACITY OF A COARSE SAND BED

DIRECTIONAL DRILLING

Drained and Undrained Conditions. Undrained and Drained Shear Strength

Collapse of Underground Storm Water Detention System

SEISMIC UPGRADE OF OAK STREET BRIDGE WITH GFRP

Settlement of Precast Culverts Under High Fills; The Influence of Construction Sequence and Structural Effects of Longitudinal Strains

EXAMPLE 1 DESIGN OF CANTILEVERED WALL, GRANULAR SOIL

Appendix A Sub surface displacements around excavations Data presented in Xdisp sample file

Design and Construction of Cantilevered Reinforced Concrete Structures

Trenching and Excavation Safety

Type of Sewer Systems. Solomon Seyoum

SEISMIC DESIGN. Various building codes consider the following categories for the analysis and design for earthquake loading:

EN Eurocode 7. Section 10 Hydraulic Failure Section 11 Overall Stability Section 12 Embankments. Trevor L.L. Orr Trinity College Dublin Ireland

Underground Installation of PE Piping

Technical Notes 3B - Brick Masonry Section Properties May 1993

There is no water, surface tension cracks, nor other environmental conditions present that reduce the stability of the excavation.

Fluid Mechanics: Static s Kinematics Dynamics Fluid

Geotechnical Building Works (GBW) Submission Requirements

SECTION GRAVITY SANITARY SEWERS

Pipeline design. concrete for life

BUTE Department of Construction Management and Technology

Transcription:

37

Module 6: Lecture -2: Buried Structures

Content in this module: Load on Pipes, Marston s load theory for rigid and flexible pipes, Trench and Projection conditions, minimum cover, Pipe floatation and Liquefaction.

Materials transported through buried pipes Crude and refined petroleum, Fuels - such as oil, natural gas and biofuels Waste products in a fluid sate slurry and industrial wastes. including sewage, Water used for drinking or irrigation In some cases, hydrogen gas, and highly toxic ammonia have been transported.

Buried pipelines Pipes that are buried underground are required to sustain other loads besides the internal fluid pressure. That is, they must support the soil overburden, groundwater, loads applied at the ground surface (like vehicular traffic) and forces induced by seismic motion in seismic prone zones.

Buried pipelines Buried pipes are, therefore, structures as well as conduits for conveying fluid. Special design procedures are required to be adopted while designing buried pipelines, to ensure that both the functions are simultaneously fulfilled.

Significance of Buried pipelines As the pipelines are buried, more land space can be utilized for construction above the ground. Buried pipelines ensure minimum number of bends/crossing along the length of the pipe, as they can pass in a relatively straight manner below the ground. This, in turn ensures minimum losses due to bending and joints.

Significance of Buried pipelines As the pipes are placed below the ground, they are relatively safe from sabotage point of view. Moreover, buried pipelines are a necessity in case of pipelines carrying sewage, oil or hazardous end-products of complex industrial processes in order to prevent contamination to the surrounding environment.

Functions of buried pipe lines Hydraulic: Designed to carry fluids produced by public water systems, sewers, drainage facilities, and many industrial processes. Structural: Designed to carry the weight of the ground and any load acting on it.

Various classes of conduits installation (Spangler & Handy, 1973) Buried pipes are divided into two main categories: ditch conduits (trench conduits) and projecting conduits (embakment conduits) Pipe is installed in a narrow trench (generally, trench width 2 d) in undisturbed soil, then backfilled to natural ground surface level. Examples of this type of conduit are sewers, drains, water mains, gas mains, and buried oil pipelines. Backfill Ditch conduit d H

Various classes of conduits installation (Spangler & Handy, 1973) Projecting conduits are further divided into two groups: Positive and Negative Projecting conduits. A positive projecting conduit is a conduit or pipe installed in shallow bedding with the top of the pipe cross-section projecting above the natural ground surface. Highway and railroad culverts are often installed in this way. H Positive projecting conduit

Various classes of conduits installation (Spangler & Handy, 1973) A negative projecting conduit is a conduit installed in a relatively narrow and shallow ditch with the top of the conduit below the natural ground surface; the ditch is then backfilled with loose soil and an embankment is constructed. Compacted soil Effective in reducing the load on the conduit, especially if the backfill above the conduit is loose soil. Negative projective conduit

Various classes of conduits installation (Spangler & Handy, 1973) Special case, similar to negative embankment condition, but more favorable from standpoint of load reduction on pipe, used in very deep installations. Difficult to achieve for largediameter pipes. This type of construction is called imperfectditch conduit or induced-trench conduit. Not recommended for wet areas Imperfect ditch conduit

Active arching (Flexible pipes) Active arching occurs when the structure is more compressible than the surrounding soil. If the structure deforms uniformly on plane above and below pipe, the stresses on it tend to be lower toward the edges due to mobilized shear stresses in the soil. Stress distribution across plane above and below pipe

Passive arching (rigid pipes) In passive arching, the soil is more compressible than the structure. As a result, the soil undergoes large displacements, mobilizing shear stresses which increase the total pressure on the structure while decreasing the pressure on the adjacent ground. Assuming the structural deformations are uniform, the stresses are highest at the edges and lowest at the centerline. Stress distribution across plane above and below pipe

Effect of soil settlement on flexible and rigid pipes Actual load on the pipe is less than the load of the central prism due to the direction in which the shearing stresses Actual load on the pipe is more than the load of the central prism due to the direction in which the shearing stresses Flexible pipe Rigid pipe

Arching effect in underground conduits Flexible pipes Rigid pipes

Example problem: What is the maximum load on a very rigid pipe in a ditch excavated in sand? The pipe outside diameter (OD) is 0.45 m, the trench width is 1 m, the depth of burial is 2.5 m, and the soil unit weight is 18.4 kn/m 3. Solution: Determine C d

Variation of C d with z/b for different values of Kµ For wet sand, K = 0.33 and µ = 0.5 Kµ = 0.165 z/b = H/B = 2.5/1 = 2.5 For H/B = 2.5 & Kµ = 0.165 C d = 1.4 W = C d γb 2 = 1.4 x 18.4 x (1) 2 = 25.76 kn/m

Marston load theory (Embankment conditions) In conjunction with positive projecting conduits, Marston determined the existence of a horizontal plane above the pipe where the shearing forces are zero. This plane is called the plane of equal settlement. Above this plane, the interior and exterior prisms of soil settle equally. The condition where the plane of equal settlement is real (it is located within the embankment) is called an incomplete projection or an incomplete ditch condition. If the plane of equal settlement is imaginary (the shear forces extend all the way to the top of the embankment), it is called a complete ditch or complete projection condition.

Positive projecting conduit In Case I, the ground at the sides of the pipe settles more than the top of the pipe. In Case II, the top of the pipe settles more than the soil at the sides of the pipe. Case I was called the projection condition by Marston and is characterized by a positive settlement ratio r sd The shear forces are downward and cause a greater load on the buried pipe for Case I. Case II is called the ditch condition and is characterized by a negative settlement ratio r sd. The shear forces are directed upward in this case and result in a reduced load on the pipe.

Embankment conditions Not all pipes are installed in ditches (trenches); therefore, it is necessary to treat the problem of pipes buried in embankments. An embankment is where the top of the pipe above the natural ground. This type of installation is defined as positive projecting conduit. Case I H > H e S f +d c < S m +S g Incomplete Projection condition

Ditch condition Case II is called the ditch condition and is characterized by a negative settlement ratio r sd. The shear forces are directed upward in this case and result in a reduced load on the pipe. Case II H > H e S f +d c > S m +S g Incomplete ditch condition After Spangler and Handy(1982)

Positive projecting conduit Where: Critical plane settlement = S m (strain in side soil) +S g (ground settlement). Settlement of the top of the pipe = S f (conduit settlement) + d c (vertical pipe deflection). s m = compression of soil at sides of pipe; s g = settlement of natural ground surface at sides of pipe; s f = settlement of foundation underneath pipe; d c = deflection of the top of pipe. In conjunction with positive projecting conduits, Marston determined the existence of a horizontal plane above the pipe where the shearing forces are zero. This plane is called the plane of equal settlement. Above this plane, the interior and exterior prisms of soil settle equally.

Positive projecting conduit The condition where the plane of equal settlement is real (it is located within the embankment) is called an incomplete projection or an incomplete ditch condition. If the plane of equal settlement is imaginary (the shear forces extend all the way to the top of the embankment), it is called a completeditch or complete projection condition. Marston s load equation for positive projecting (embankment) conduits is given by: For complete condition

Positive projecting conduit The minus signs are for the complete ditch, and the plus signs are for the complete projection condition. For incomplete condition: where the minus signs are for the incomplete ditch and the plus signs are for the incomplete projection condition. And H e is the height of the plane of equal settlement. At H = H e, the incomplete case becomes complete case.

Positive projecting conduit C c is a function of the ratio of height of cover to pipe diameter (H/B c ), the product of the settlement ratio (r sd ) and projection ratio (p), Rankine s constant (K), and the coefficient of friction (µ). The value of the product Kµ is generally taken as 0.19 for the projection condition and 0.13 for the ditch condition.

Four conditions classified according to Spangler Complete projection condition: The top of the conduit settles less than the critical plane and the height of the embankment is less than the theoretical height of equal settlement. Incomplete projection condition: The top of the conduit settles less than the critical plane and the height of the embankment is greater than the height of equal settlement. Complete ditch condition: The top of the conduit settles more than the critical plane and the height of the embankment is less than the height of equal settlement. Incomplete ditch condition: The top of the conduit settles more than the critical plane and the height of the embankment is more than the height of equal settlement.

Complete projection condition H < H e Incomplete projection condition H > H e S f +d c < S m +S g S f +d c < S m +S g

Diagram for coefficient C c for positive projecting conduits r sd p = 0, C c = H/B c After Spangler and Handy(1982)

The settlement ratio r sd is difficult, if not impossible, to determine even empirically from direct observations. Note that when r sd p = 0, C c = H/B c and W c =γ HB c. This is the prism load (i.e., the weight of the prism of soil over the top of the pipe). When r sd = 0, the plane at the top of the pipe called the critical plane settles the same amount as the top of the conduit

Design values of settlement ratio After Spangler and Handy(1982) When a pipe is installed in a narrow, shallow trench with the top of the pipe level with the adjacent natural ground, the projection ratio p is zero. The distance from the top of the structure to the natural ground surface is represented by pb c

Load transfer pattern in flexible and rigid pipes As the loading increases, the vertical diameter decreases and the horizontal diameter increases.

Typical failure modes for flexible pipes After Spangler and Handy(1982)

For flexible pipes, Moser proposed the following formula (American Water Works Association manual) to calculate load on pipes: W W = γ B d h h D Pipe Trench with a flexible pipe

Importance of proper bedding on buried pipe Width of trench Width of trench Load on the pipe Undisturbed soil Load on the pipe Undisturbed soil P1 P1 Improper bedding Proper bedding (After NYSDOT Geotechnical design manual) The area of contact between the The area of contact between the pipe and soil is small so stress is pipe and soil is large so stress is more and may damage the pipe. less.

Importance of proper bedding on buried pipe Cracks Soil bed Load is concentrated and creating cracks Load is uniformly distributed Soil bed (After NYSDOT Geotechnical design manual)

1. External Loads Types of load on pipe lines A. Dead load or overburden pressure B. Live Loads C. Seismic Loads 2. Internal Loads A. Internal Pressure and Vacuum B. Pipe and associated contents

1.A. Dead load or overburden pressure This is the pressure due to weight of the soil and water above the pipe. The pressure increases with depth of the pipe, i.e. dead load for (P1<P2<P3<P4). Ground surface P1 P2 P3 P4

1.B. Live load This is the static or dynamic load acting on the ground above the pipe and transmitted to the pipe through the soil. Vehicles, trains, aircrafts etc are the source of such loads. Magnitude of such loads get reduced as the depth of embedment is increased.