San Gabriel Valley Grade Crossings Study and the Alameda Corridor East Construction Project Defining and Delivering a Program of Improvements



Similar documents
Goals & Objectives. Chapter 9. Transportation

Railway Crossing Information System

Leading the way in Quiet Zone Solutions. Implementing Quiet Zones to Address Train Horn Noise

Southern California International Gateway Project Description

CAPACITY AND LEVEL-OF-SERVICE CONCEPTS

5.0 FINANCIAL ANALYSIS AND COMPARISON OF ALTERNATIVES

1. REPORT CONTEXT Description of the development (include all of the following that are known at the time of the application):

An ITE Recommended Practice

Comment #1: Provide an interchange at Route 7 and Farm Market Road/White Gate Road. This was studied in the late 1990 s.

Appendix G.3 Crain & Associates, Peer Review

CHAPTER 11: PEDESTRIAN SIGNS AND SIGNALS

Seagull Intersection Layout. Island Point Road - A Case Study. Authors: John Harper, Wal Smart, Michael de Roos

Downtown Tampa Transportation Vision

Title: Integrating Management of Truck and Rail Systems in LA. INTERIM REPORT August 2015

Utah Transit Authority

4.5 TRANSPORTATION - YEAR 2025 TRAFFIC CONDITIONS WITH PROPOSED TIMP ESTIMATION OF TRIP REDUCTIONS WITH TIMP TRANSIT AND TDM PROGRAMS

The Top 50 Highway Projects to Support Economic Growth and Quality of Life in Alabama

Transportation Policy and Design Strategies. Freight Intensive. Level of Freight Presence

3.1 Historical Considerations

How To Improve Safety

Section ALTERNATIVES. 3. Alternatives

SAN DIEGO GAS & ELECTRIC COMPANY SOUTH BAY SUBSTATION RELOCATION PROJECT TRAFFIC MANAGEMENT PLAN SEPTEMBER 2014

CALIFORNIA AMERICAN WATER LOS ANGELES DISTRICT 2009 GENERAL RATE CASE CHAPTER: 1 INTRODUCTION AND SUMMARY OF APPLICATION

9988 REDWOOD AVENUE PROJECT TRAFFIC IMPACT ANALYSIS. April 24, 2015

4.0 Inventory of the Existing Rail System

Nashville Area MPO Regional Freight Study fast action projects

Chapter Forty-seven. RURAL TWO-LANE/MULTILANE STATE HIGHWAYS (New Construction/Reconstruction) BUREAU OF DESIGN AND ENVIRONMENT MANUAL

OM-13: Transportation Management and Operations

Southwest Light Rail Transit Minneapolis-St. Paul, Minnesota New Starts Project Development (Rating Assigned November 2014)

Median Bus Lane Design in Vancouver, BC: The #98 B-Line

IV. INDUSTRIAL TRACK DESIGN

Stop The stop sign, a red octagon with white lettering, means come to a full stop and be sure the way is clear before proceeding.

The Corporation of the TOWN OF MILTON

Wilmington to Newark Commuter Rail Improvement Project

SUMMARY OF CATEGORIES 2007 STATEWIDE PRESERVATION PROGRAM (SPP) _MAINTAIN IT_

Roadway Cost Per Centerline Mile Revised June 2014

Accident Analysis of Sheridan Road between Isabella Street and South Boulevard

CHAPTER 2 TRAFFIC SIGNS AND HIGHWAY MARKINGS

Surface Transportation Program (STP)

Advantages and Disadvantages of One Way Streets October 30, 2007

TRANSPORTATION IMPACT ANALYSIS PROCEDURES MANUAL

APPLICATION LAFAYETTE METROPOLITAN PLANNING ORGANIZATION (MPO) SURFACE TRANSPORTATION PROGRAM (STP) FUNDS TRANSPORTATION IMPROVEMENT PROGRAM (TIP)

Why build the Silvertown Tunnel?

Performance Measures for a Sustainable Transportation Network Pasadena s Approach Frederick C. Dock, Ellen Greenberg, Mark Yamarone

Connecticut s Bold Vision for a Transportation Future

2014 TRANSPORTATION SAFETY SUMMIT LOUISIANA STATE POLICE & LADOTD TIM INITIATIVE

Chapter 6. Intersections. 6 Intersections

ARIZONA-SONORA BORDER MASTER PLAN

How To Design A Crash Investigation Site

PART II SCHEDULE. Scope of Services. Special Terms and Conditions. Virginia Railway Express

Design and Implementation of Slot Left-Turn Lanes on the Manitoba Highway Network

Transportation Management Plan Template

21101 &?I I2 P 3: 2 I. kz COZY c:oi*;: iiss:en. DOCEET COEi1 f3.x..

City of Auburn Americans with Disabilities Act (ADA) Transition Plan for Curb Ramps, Sidewalks, and Pedestrian Signals ADA TRANSITION PLAN

South Carolina Multimodal Transportation Plan Vision, Goals, Objectives, and Performance Measures

Metropolitan Setting l

GTA Cordon Count Program

TRANSPORTATION ENGINEERING DESIGN STANDARDS. Adopted by City Council Ordinance

Guidelines. Work Zone Access and Egress

Q. What do you think the most important transportation issues are in this area with regard to east-west travel?

Economic Analysis Reports: Briefing. Transportation Finance Panel

S-11: Tacoma Link Extension to Tacoma Community College

Light Rail Transit in Calgary The First 25 Years

PRIORITIZATION PROCESSES

IDOT Chicago - St. Louis High-Speed Rail Program Management

Informational Workshop Public Meeting Kanawha Falls Bridge Project

TRANSPORTATION MODELLING IN CALGARY

Cost Reduction Opportunities

Transportation Management Center

Executive Summary. Literature/Community Review. Traffic Flows and Projections. Final Report Truck Route System for Miami-Dade County CORRADINO

BEST PRACTICE FOR TRAFFIC ENGINEERING DEVICES & OPERATIONS IN SCHOOL AREAS

Doing More with the Same: How the Trinity Railway Express Increased Service without Increasing Costs

ROUTE 178 CORRIDOR STUDY. Prepared For: KERN COG, CALTRANS, CITY OF BAKERSFIELD

88.1 Traffic Signals at Roundabouts 213

Executive Summary. Transportation Needs CHAPTER. Existing Conditions

Mercer County Multi-Modal Transportation Plan Year 2025 Travel Demand Model

AIR QUALITY TECHNICAL MEMORANDUM

TRANSPORTATION SERVICE STANDARDS ELEMENT GOALS, OBJECTIVES & POLICIES

Experts in Rail Maintenance and Infrastructure

WORK ZONE SAFETY & MOBILITY GUIDANCE DOCUMENT

EPA Technical Assistance for Sustainable Communities Building Blocks

Appendix 1 Washington State Department of Transportation (WSDOT)

Alternatives to the Circ Project Prioritization Methodology Prepared for Circ Task Force July 28, 2011

Rail Automation. What is ACSES? usa.siemens.com/rail-automation

Chapter Thirty-five ACCESS CONTROL/ ACCESS MANAGEMENT BUREAU OF DESIGN AND ENVIRONMENT MANUAL

FHWA Colorado Division Control of Access to the Interstate and its Right-of-Way February 2005

FHWA Minnesota Division Guidance for the Preparation of a FHWA INTERSTATE ACCESS REQUEST

Tier 1 Strategies. WV Route 14 Corridor Management Plan

Temporary Traffic Control for Building and Maintaining Single and Multi-Lane Roundabouts

FloridaNOTAllAboard RESOLUTION NO

DRAFT PLANNING THE OPENING OF A ROAD PROJECT GUIDELINE 1

IMPROVING TRUCK MOVEMENT IN URBAN INDUSTRIAL AREAS: APPLICATIONS OF GIS, ACCIDENT & FIELD DATA

Near Westside Neighborhood and University Avenue Corridor Transportation Study. Public Workshop #2. September 12 and 23, 2013

Definitions. For the purposes of this rule chapter the following definitions shall apply unless the context clearly shows otherwise:

A Review of Transit Technology Specifications

Ne w J e r s e y Tr a f f i c Co n g e s t i o n :

The Preservation of Local Truck Routes: A Primary Connection between Commerce and the Regional Freight Network

INDOT Long Range Plan

Truck Diversion Forecasts. DRAFT Executive Summary

Illinois Tollway: Development of Incident Management Based Performance Measures. Jeff Hochmuth, PE, PTOE Wilbur Smith Associates

Transcription:

San Gabriel Valley Grade Crossings Study and the Alameda Corridor East Construction Project Defining and Delivering a Program of Improvements By Brent D. Ogden Corporate Vice President Korve Engineering, Inc. 155 Grand Avenue, Suite 400 Oakland, CA, 94612 (510) 763-2929 tel (510) 451-4549 fax bogden@korve.com August 1, 2002 Word Count 5251 Revised November 14, 2002

Brent D. Ogden Page 1 Abstract The Alameda Corridor East (ACE) Project, which is presently developing in excess of $400-million in improvements including grade crossings reconstruction, track relocation and grade separations, began with the preparation of a comprehensive study of some 55 grade crossings in Los Angeles County along the Los Angeles Subdivision of the Union Pacific Railroad and the Alhambra Subdivision of the former Southern Pacific Railroad. This paper documents the techniques and insights used to identify the proposed program of improvements and provides a status of the project development efforts to date, including unique features of the program.

Brent D. Ogden Page 1 OVERVIEW The Alameda Corridor East (ACE) project has assembled nearly $400-million in funding for construction of Phase I improvements. This represents nearly 45% of the $900-million plus program identified in the initial study, which was completed in January of 1997. The ACE project is located in the San Gabriel Valley immediately east of downtown Los Angeles. The Valley is bisected by two major transcontinental main lines the Alhambra Subdivision (formerly part of the Southern Pacific Railroad network but now part of the Union Pacific system) is located to the north and the Los Angeles Subdivision of the Union Pacific Railroad is located to the south (see Figure 1.) The scope of the ACE project includes (see Figure 2): Up to 20 Grade Separations 38 Grade Crossing Safety Projects Up to 4 Grade Crossing Closures An ITS Demonstration Project Included in the candidate grade crossing closures are two crossings west of the City of Pomona, which may be eliminated by a diversion of the main line from the Alhambra Subdivision to the Los Angeles Subdivision in order to eliminate the need for a costly grade separation at a problematic grade crossing. The success of the ACE project has been a solid initial study backed up with strong local support from involved and friendly cities in the San Gabriel Valley and with aggressive project management by the ACE Construction Authority. This paper addresses some of the technical aspects of establishing the initial program and also provides information on status of accomplishments to date. PROGRAM INCEPTION GRADE CROSSING STUDY Cities in the San Gabriel Valley, members of the San Gabriel Valley Council of Governments (SGVCOG) were concerned about the impact of increasing levels of transcontinental train traffic resulting from expansive economic conditions at the Ports of Los Angeles and Long Beach. There are only three principal rail lines heading east out of Los Angeles and two of these lines bisect the San Gabriel Valley. At the same time, the Alameda Corridor Project was proceeding, which would grade separate and consolidate rail traffic between the Ports and downtown Los Angeles, facilitating train movements to the mouth of the Valley. SGVCOG commissioned a study of grade crossing impacts and potential mitigation. The study elements included: Field review of 55 grade crossings in Los Angeles County Development of up-to-date forecasts of future rail traffic levels Assembly of projected future highway traffic levels at the crossings Evaluation of the crossing gate blockage, vehicular delay and queuing at grade crossings Identification and evaluation of candidate improvements Development of a comprehensive, phased program of improvements In particular, the information developed on mobility impacts as presented below was instrumental in spurring the San Gabriel Valley Cities into action to pursue funding for grade separations and related grade crossings improvements. Rail Traffic The Grade Crossing Study identified the possibility of significantly increased levels of train traffic. Most heavily impacted was the City of Pomona, where the two main lines run immediately parallel to each other through the heart

Brent D. Ogden Page 2 of the downtown. Existing train levels of about 67 trains per day observed in 1994 were projected to exceed 109 trains per day by Year 2010. Consolidation The Southern California Association of Governments in the 1995 Regional Rail Consolidation Study has studied rail consolidation over the years for Southern California, most recently. Given the fact that much of the mileage in the San Gabriel Valley is single track with passing sidings, in reality, a minimum of three tracks would be needed to consolidate operations along one of the two San Gabriel corridors. Development of a three-track railway within the existing rights-of-way would be difficult and costly given the presence of supplemental industry sidings and the need to make grades conform at the edge of the right-of-way. Substantial investment in additional bridges over water features, most notably the Rio Hondo Bridge east of Montebello, makes this approach very costly. As a result, the Grade Crossing Study and the ACE Project are proceeding with the expectation that there will continue to be two principal rail lines through the Valley for the foreseeable future. Highway Traffic Highway traffic levels are also expected to climb in the San Gabriel Valley. The Valley is the heart of regional distribution for Southern California, with major rail intermodal yards, extensive warehousing and truck terminal operations, a large cargo operation at Ontario Airport, and with the Ports to the southwest. Residential development is continuing to take place and additional suburban employment centers are developing. As a result, aggregate growth between 1994 and 2020 is expected to increase by 15 to 60% or more. AssessmentofImpacts In order to assess the impact of combined traffic increases both on the rail mode as well as the highway mode, a comprehensive, rational impact assessment process was utilized to evaluate the following four key operational parameters for each grade crossing: Crossing Gate Blockage Time The total amount of gate down time due to rail operations including warning time prior to activation of the grade crossing gear, the time to lower the crossing gates, the train passage time required for the train to cross the roadway centerline, plus the clearance time required for the train the cross the roadway right-of-way and the lag time for the gates to raise after the train has departed the island circuit controlling the crossing gates. Vehicular Delay The impact on vehicular traffic flow due to the number and type of cars and trucks approaching the crossing, the delay while stopped and the delays encountered during deceleration and acceleration. Crossing Spillback Queue vs. Available Storage The crossing spillback queue is the queue which develops from the lowered crossing gate; if this queue extends back to an upstream principal intersection, traffic disruption to both cross-street traffic as well as parallel roadway traffic may result Crossing Influence Zone Queue vs. Available Storage The influence zone queue is the queue of vehicles from and nearest signalized intersection towards the grade crossing. In accordance with the Millennium Edition of the Manual of Uniform Traffic Control Devices, engineering study is recommended to determine whether the influence zone extends beyond the nominal 200 foot criteria formerly used as a rule of thumb In the event the grade crossing falls within the influence zone, pre-emption or other countermeasures should be considered even if the signal is located beyond the nominal 200 foot distance indicated in the MUTCD. The approach to be taken for estimating grade crossing mobility impacts needed to reflect a balance between two concerns: (1) From the perspective of the local communities, it was important to identify as much of the impact as possible to demonstrate the need for mitigation as well as to provide local officials with documentation needed to seek funding for possible improvements; (2) On the other hand, it was critical that the study should avoid worst case type of analyses which could be challenged, either by the rail operators or by independent reviewers.

Brent D. Ogden Page 3 Accordingly, the analysis used estimated train speeds based upon the allowable track speed. This resulted in a conservative assessment of impact due to the fact that train speeds may be slower than allowable. Manual adjustments were made to reflect additional gate blockages at locations where industry switching was known to occur on a regular basis. This approach proved key to the ultimate success of the program the Southern California Association of Governments (SCAG) staff conducted a detailed independent review of the methodology and results before agreeing with SGVCOG that the projected impacts were not inflated and that the improvements program warranted SCAG support for funding. The vehicular delays were developed using the following equation: D=Tg 2 * q / (120 * (1 q/d)) Where: D = Delay (vehicle-hours) Tg = Gate Blockage Time (minutes) q = Vehicle Arrival Rate (vehicles/minute) d = Vehicle Departure Rate (vehicle/minute) Using the maximum crossing blocking times computed for ordinary train movements (e.g. excluding parked trains or switching), the queuing was computed using the following equation: N=q * T Where: N = Number of Vehicles in Queue q = Vehicle Arrival Rate (vehicles/minute) T = Tg Gate Blockage Time (minutes) for Gate Spillback Queue Tr Red Signal Time (minutes) for Influence Zone Queue As noted above, for the gate spillback queue, the crossing blocking time was evaluated and for the influence zone queue, the estimated average red time at the downstream traffic signal was evaluated. 1 The queues were then compared to the available storage lengths with appropriate adjustments for the number of lanes to determine whether the projected queue would exceed the available storage. Field review was used to identify other factors contributing to queuing, such as adverse impacts from more highly-congested traffic signals further downstream. Projected Impacts The impact assessment was conducted for all grade crossings along the Alhambra and Los Angeles Subdivisions in Los Angeles County as well as a portion of San Bernardino County between the Los Angeles County line and the point west of Ontario Airport where the two mains diverge. There are 66 grade crossings at some 55 different cross streets due to the fact that the mains from both subdivisions have shared crossings in Pomona, Montclair and Ontario the location where the two rail main lines diverge at Ontario Airport. The projected impacts of the increases in rail and highway traffic indicated very large increases in mobility impacts could be expected as a result of higher levels of traffic and train movements: Crossing Blocking (Table 1) Whereas 68% of the grade crossings would be in the low impact category with the remaining 32% in the moderate blocking time category in 1994, by the Year 2020 conditions would be reversed with nearly 20% of the crossings in the very high category and additional 29% in the high category. 1 The influence zone equation is a simplified form of Webster s equation valid for low to moderate levels of congestion; it assumes random arrivals, which is correct for most of the San Gabriel Valley grade crossings.

Brent D. Ogden Page 4 Vehicular Delay (Table 2) Whereas more than 90% of the crossings studied were evaluated in the low delay category for existing conditions, by Year 2020, about 26% of the crossings would be operating with high vehicular delay levels, 29% in the moderate category and only 45% remaining in the low category. Aggregate Delay An aggregate measure of delay was also developed for the entire corridor. This metric indicated that 621 daily vehicle-hours of delay under existing conditions would increase about 300% to nearly 1,800 vehicle-hours of delay by Year 2020. Gate Queue Spillback With significant increases in traffic predicted, crossing gate spillback queues exceeding storage identified at 24 locations in 1994 and was projected to increase to 26 locations by Year 2020. Given these results, additional analysis was conducted to capture secondary delay and air quality impacts to traffic passing through traffic signals, which were found to be impacted by gate queue spillback. 2 Influence Zone Queue Possible queuing from adjacent traffic signals back across the railroad tracks was zone storage concerns were identified at 18 of the 55 study cross streets for 1994, and forecast projected to increase to 22 locations by Year 2020. Similarly, crossing gate spillback queues exceeding storage were estimated at 24 locations in 1994 and were projected to increase to 26 locations by Year 2020. Overall Philosophy The mobility impacts noted above provided a basis for consideration of grade separation at many of the grade crossings, particularly at arterial roadways in the study area. Since all of the grade crossings were already equipped with automatic gates, the philosophy of the program was to grade separate locations where the greatest mobility impacts were predicted and to improve the safety of the remaining at-grade crossings based upon state-of-the-art considerations for traffic control and safety treatments. It should be noted that review of the accident data did not reveal any pattern of accidents which would warrant grade separation strictly on the basis of safety, in fact, the 55 grade crossings had relatively low levels of accidents compared to other crossings in California. Grade Separations As noted, mobility considerations were the principal factor. A literature search was conducted to identify criteria for grade separation, which indicated a variety of considerations for grade separation but few standards. The literature search identified the following considerations: Safety The California Public Utilities Commission regulations indicate safety as the key criterion for grade separation, to be accomplished wherever practicable in the event significant safety concerns cannot be addressed by other means. However, the crash data assembled for the San Gabriel Valley grade crossings showed relatively low crash rates with very few and infrequent fatalities at the crossings. Economic Classic cost-benefit analysis could be conducted to evaluate the value of the vehicle-hours of delay eliminated with grade separation vs. the cost of a separation. However, at this point in the study, no conceptual designs were available to indicate the possible cost of separation. Mobility Some of the sources reviewed indicated a rule of thumb of 40 to 50 vehicle hours of delay per day as being a threshold for separation. A technical committee of the Institute of Transportation Engineers has prepared an Informational Report for light rail transit grade crossings, which has criteria for identifying conditions under which at-grade operation is inadvisable due to traffic impact. 3 2 Modifications were made to the software used to identify mobility impacts to take into account the following types of secondary impacts: (1) Parallel roadway through traffic impacted by queues traffic turning into the grade crossing that would lock up a shared lane or overflow from a turn bay, and (2) Approaching cross street turning traffic impacted by the queue approaching the grade crossing that would lock up a shared lane or overflow from a turn bay. 3 Refer to the ITE Committee 6A-42, Light Rail Transit Grade Separation Guidelines, March 1992.

Brent D. Ogden Page 5 As a result of the research, it was decided to use the rule of thumb vehicle hours of delay criteria in conjunction with the ITE criteria, modified to take into account the much longer duration of gate blockage associated with mainline freight railroad operation (as opposed to frequent, short, LRT gate activations): 1. Total Vehicular Delay Exceeding 40 Vehicle Hours 2. Combination of Gate Blockage Time and Traffic Density (see table): Rail Operations Roadway Traffic Level Hourly Gate Blockage (mins) Hourly Volume (veh/lane) V/C Ratio Level of Service 15 575.85 D 14 610.9 D/E 13 640.95 E 12 675 1.0 E/F The author of this paper supports additional research to develop unified and effective planning-level criteria for selecting grade separation candidates. Regardless of the issues involved in selecting criteria, the participating SGVCOG cities readily accepted the identified program of grade separation improvements and gave their full support to the study. Programmatic Considerations As a practical consequence, the physical configuration of the roadways and rail in the vicinity of the grade crossing influenced the ultimate selection of grade separation locations; for example, at locations where the only apparent solution was to lower or raise the track, several nearby grade crossings would need to be treated as a unit. Finally, efforts were made to assure a reasonable geographic distribution of improvements and investments throughout the San Gabriel Valley. In some cases this meant trade-offs between isolated near-term separations at selected key locations with potential long-term track relocation projects specified for the future. The overall principles used to develop the program may be summarized as follows: Given the considerations described above, it is recommended that a framework for development of a program be utilized. The attributes of this framework are as follows: 1. Candidate projects were screened using the threshold criteria described in this paper to develop short lists of improvements for further consideration. 2. A high priority, near term improvement group later called the Jump Start Safety project will consist of a set of low-cost baseline safety improvements which will be implemented from end to end in the study area. 3. Higher capital cost projects such as grade separations, roadway widening and realignments were evaluated for relative benefit under existing versus future conditions in order determine whether such projects should be considered near or long term in nature. 4. Efforts were made to define and implement lower cost/near term solutions at locations where high cost options may ultimately be needed, especially for those locations where the projected needs are long term.

Brent D. Ogden Page 6 5. Projects were grouped into geographic units based upon similar conditions and sub-regional traffic flow and rail operations zones. The benefits to crossings within these units will be considered in relationship to each other to avoid piecemeal solutions. 6. Funding was sought for the entire program of improvements. At the same time, efforts were made to obtain funding from a variety of sources, and any projects, which are capable of obtaining funding regardless of the program, will be implemented with such separate funding. Application of these principles lead to the development of the following $950-million improvements program indicated on the following page:

Brent D. Ogden Page 7 PROGRAM OF IMPROVEMENTS Description JUMP START Item Cost (Millions) Corridor Safety Upgrade 30 Traffic Signal Control Measures 31 NEAR TERM Total Cost (Millions) Subtotal: JUMP START 61 Roadway Widening (9 locations) 36 Fairway Drive/UP, LA County, Roadway Underpass 31 Nogales Street/UP, LA County, Roadway Underpass 24 Ramona Boulevard/SP, El Monte, Roadway Underpass 14 Temple Avenue/SP, Pomona, Roadway Underpass 36 Fullerton Road - Fairway Drive/SP, Industry, Elevated Track 123 7 th Avenue/UP, Industry, Roadway Underpass 0 (funded) INTERMEDIATE Subtotal: NEAR TERM 264 Roadway Widening (5 locations) 20 Baldwin Avenue/SP, El Monte, Roadway Underpass 24 East End Avenue/SP/UP, Pomona, Roadway Underpass 28 Montebello Boulevard/UP, Montebello, Depressed Track 55 Ramona St-San Gabriel Bl/SP, San Gabriel, Depressed Track 198 LONG TERM Subtotal: INTERMEDIATE 325 Roadway Widening (3 locations) 12 Brea Canyon Road/UP, Industry, Roadway Underpass 27 Reservoir Street/SP/UP, Pomona, Roadway Underpass 29 Rose Hills Road/UP, Industry, Roadway Underpass 17 Turnbull Canyon Road/UP, Industry, Roadway Underpass 23 Valley Boulevard/SP, Los Angeles, Roadway Overhead 38 Vineland Ave-California Ave/SP, Industry, Elevated Track 154 Subtotal: LONG TERM 300 GRAND TOTAL 950

Brent D. Ogden Page 8 IMPLEMENTATION PROCESS Extensive efforts were undertaken to fund the program. This included obtaining consensus from the 26 member cities in the SGVCOG to pursue outside funding for the program and initiation of efforts to assemble funding commitments. Short-term accomplishments lead to the assembly of nearly $400-million in funding for the program. SGVCOG formed a wholly owned subsidiary, the Alameda Corridor East (ACE) Construction Authority, to manage the program. The ACE Construction Authority initiated efforts to refine and deliver the program. One of the first activities was to refine the Jump Start Safety category of improvements. A design criterion was developed to guide the selection of safety improvements for those crossings, which were to remain at grade. Diagnostic field reviews were accomplished involving the California Public Utilities Commission (CPUC), the Union Pacific Railroad (which at the time of the formation of the ACE Project had taken over the former Southern Pacific main line), and involved local transportation and public works officials. Jump Start Safety Program The ACE Jump Start Safety design criteria included the following key considerations: 1. Provide Consistent Treatment for Similar Conditions Applicable to all standard devices as required under MUTCD 2. Verify Length of Influence Zone To define appropriate pre-emption requirements; utilize active signing and pre-signals or queue cutters to control predicted or observed queuing across grade crossings 3. Constant Warning Time Upgrade grade crossing predictors to provide constant warning time to minimize likelihood of gate drive-around events and increase motorist respect for grade crossing control activations 4. Supplemental Lanes / Roadway Widening Where possible, widen crossing areas and/or provide supplemental lanes to control traffic near grade crossings 5. Medians Where possible, provide medians, preferably raised, to reduce gate drive-around activity 6. Four Quadrant Gates At locations where switching and gate drive-around activity has been observed, provide four quadrant gates to preclude gate drive around (applicable to crossings in City of Pomona) 7. Pedestrian Accommodation The Union Pacific Railroad installed additional grade crossing panels to provide a pedestrian walkway across the crossings and ACE constructed sidewalk connections at numerous locations where pedestrian activity levels were significant Traffic Signalization Measures The other element of the Jump Start program consisted of an advanced traffic control system. Designated as the Intelligent Roadway/Rail Interface System (IR/RIS), the improvements are being developed as part of a Demonstration Program in the City of Pomona. Pomona was selected due to the fact that it has a grid street system with three existing grade separations, two programmed future grade separations, and five streets to remain at grade for the foreseeable future. The IR/RIS Demonstration Project includes the following provisions: Remote Wayside Detection Magnetometers buried alongside the track as far as five miles (8 km) from Pomona will provide five minutes or more advance notice of the speed and location of approaching trains Train Predictor Software The wayside detection units are connected by spread spectrum radio to a control center which analyzes the approaching train data to determine predicted occupancy of the Pomona grade crossings

Brent D. Ogden Page 9 Dynamic Message Signs Roadway message signs will alert motorists to impending grade crossing delays; in the event switching activity, slow moving long trains, or parked trains are detected, detours will be advised Traffic Responsive Signal Control Software Traffic responsive software will implement alternative traffic management strategies depending upon the circumstance; capabilities will include modification of background traffic signal timing plans as well as responding to modified traffic conditions due to diverted traffic. Grade Separation Projects ACE has continued to refine the grade separation projects. Examples include: A costly multiple-crossing concept along Valley Boulevard in the City of Industry has been refined to provide a single separation at the most heavily-traveled crossing with closure of an adjacent crossing, resulting in reduced cost and accelerated project delivery. A difficult and costly grade separation at Temple Avenue near California Polytechnic University, Pomona, has been reconfigured as a main line track relocation, which will result in closure of two crossings and construction of additional multi-track main line. This project will also allow Union Pacific to shunt trains to and from the Chino Branch line with reduced impact to the remaining at grade crossings in Pomona. CURRENT STATUS Since its inception, ACE has the following accomplishments to its credit: Secured $395 million in Federal, State and local funding Initiated master and standard form agreements with UPRR Obtained cooperative agreements with 12 different agencies 4 grade separations and 1 train diversion in final design August, 2002 groundbreaking for first separation 31 safety projects under design 7 safety projects out to construction IR/RIS in design with two equipment contracts awarded Examples of completed Jump Start improvements include the pre signal at the Fairway / Valley Boulevard / Alhambra Subdivision grade crossing (see Figure 3), the reconstruction of the Walnut Grove grade crossing to provide sidewalks and median channelization (see Figure 4). Figure 5 shows the design concept plan for four quadrant gates at the Hamilton Avenue / North First Street grade crossing, a three-track crossing of both the Alhambra and Los Angeles Subdivisions. Figure 6 shows the conceptual architecture for the IR/RIS system.

Brent D. Ogden Page 1 LIST OF FIGURES AND TABLES Figure 1 ACE Project Vicinity Figure2 ACEProjects Figure 3 Pre Signal Fairway Drive at Valley Boulevard / Alhambra Subdivision Figure 4 Walnut Grove Grade Crossing Sidewalk and Median Improvements Figure 5 Four-Quadrant Gate Design Concept Plan Hamilton at First Street, Pomona Figure 6 Intelligent Roadway / Rail Interface System (IR/RIS) Conceptual Architecture Table 1 Daily Crossing Blocking Delay Number of Crossings by Delay Level Table 2 Daily Total Vehicle Delay Number of Crossings by Delay Level

Brent D. Ogden Page 1 Figure 1 ACE Project Vicinity

Brent D. Ogden Page 2 Figure 2 ACE Projects

Brent D. Ogden Page 3 Figure 3 Pre Signal Fairway Drive at Valley Boulevard / Alhambra Subdivision

Brent D. Ogden Page 4 Figure 4 Walnut Grove Grade Crossing Sidewalk and Median Improvements

Brent D. Ogden Page 5 Figure 5 Four Quadrant Gate Design Concept Plan Hamilton at First Street, Pomona

Brent D. Ogden Page 6 Figure 6 Intelligent Roadway / Rail Interface System (IR/RIS) Conceptual Architecture

Brent D. Ogden Page 7 Table 1 Daily Crossing Blocking Delay Number of Crossings by Delay Level Year Low Moderate High Very High 1994 45 21 0 0 68% 32% 0% 0% 2010 17 28 12 9 26% 42% 18% 14% 2020 12 22 19 13 18% 33% 29% 20% Scale: Low 0 to 5% blockage; Moderate 5% to 7.5% blockage; High 7.5% to 10% blockage; and Very High more than 10% blockage

Brent D. Ogden Page 8 Table 2 Daily Total Vehicle Delay Number of Crossings by Delay Level Year Low Moderate High 1994 61 92% 2010 41 62% 2020 30 45% 4 6% 18 27% 19 29% 1 2% 7 11% 17 26% Scale: Low up to 20 vehicle-hours of delay; Moderate 20 to 40 vehicle-hours of delay; High more than 40 vehicle hours of delay