Contributing to Lowest Life Cycle Cost of High Speed. 15 th February 2011



Similar documents
LVT System for. AlpTransit Gotthard AG

Spatially Enabling an Asset Management Database

Embedded Rail Slab Track

How To Retaining Wall Guide

Track and Track Drainage Renewals Programme

RHEDA MRT The ballastless track for underground and surface commuter transit

SUPPLEMENTAL TECHNICAL SPECIFICATIONS BI-DIRECTIONAL STATIC LOAD TESTING OF DRILLED SHAFTS

IV. INDUSTRIAL TRACK DESIGN

INTERACTION BETWEEN MOVING VEHICLES AND RAILWAY TRACK AT HIGH SPEED

Installation PowerPoint for Grasscrete Formers

Selection of a Railway Track System by Best Value Analysis

HIGHWAYS DEPARTMENT GUIDANCE NOTES ON THE USE OF WATERPROOFING MEMBRANES ON CONCRETE BRIDGE DECKS

Assessment Of Whole Life Cost In Electrification. Matt Skinner, Functional Lead Analysis (Acting) 22 nd October 2013

The Gotthard Base Tunnel

Stormwater/Wetland Pond Construction Inspection Checklist

TECHNICAL SPECIFICATION SERIES 8000 PRECAST CONCRETE

SPECIFICATION FOR PIPE SUBSOIL DRAIN CONSTRUCTION

The Value of a Warehouse Floor Raising Flooring Standards around the Globe

SEDIMENT/STORMWATER MANAGEMENT BASIN CONSTRUCTION CHECKLIST

SnoTrace KSR Surface Snow and Ice Melting INSTALLATION PROCEDURES

Slab Track Austria. System ÖBB-PORR elastically supported slab

A new approach to rail asset management.

Inspection, Maintenance, and Repair of PaCT Canadian Pacific Rogers Pass Tunnels British Columbia, Canada

King Post Wall Information

SAMPLE GUIDE SPECIFICATIONS FOR OSTERBERG CELL LOAD TESTING OF DEEP FOUNDATIONS

Track Maintenance within an effective Asset Management Strategy Tailor Made proposal for UIC Middle East Region

Relevant parameters for a reference test track Deliverable D1.7

Investigation of Foundation Failure. Step 1 - Data Collection. Investigation Steps

M&EE Networking Group

TBM CROSSING OF STATIONS

Asset Management Policy March 2014

Life after 30! Innovative investigation and repair of the Overvaal railway tunnel. r a i l w a y s a n d h a r b o u r s PROJECT TEAM

INSTALLATION RECOMMENDATIONS. Outdoor Rubber Tiles

PRO. English COMPLETE PRECAST PLANT

Integrated Manhole Ladder System

Cable usage designation. Number of ducts required Number of spare ducts to be provided < > 11

METHOD OF STATEMENT FOR STATIC LOADING TEST

Technical Services. Product MM INCH Installation direction Seams treatment GTI CONNECT (interlocking)

Proposed Revision to Bridge Design & Drafting Manual

Cannon T4 Modular Data Centres. For Outside Deployment & Challenging Environments

Quality Assurance Concepts. Outline

The Follo Line Project

Hanson Building Products. precast basement solutions

CONCRETE SEGMENTAL RETAINING WALL SYSTEM

SECTION 55 PIPE FOR STORM DRAINS AND CULVERTS (FAA D-701)

Waterproofing System for Wastewater Tanks in Petrochemical Industries and Refineries

Amendment to OPSS 415 (Nov 2008) Construction Specification for Pipeline and Utility Installation by Tunnelling

ASSET MANAGEMENT GUIDE FOR PROJECT DESIGN FORMAT

Current opportunities of sprayed waterproofing membrane. Frank Clement Technical Manager Sprayable Membranes MEYCO Global Underground Construction

Construction of Quality Hot Mix Asphalt Pavements

Fixed Access Ladders. Table of Contents. 1. Legislative Requirements

Lesson 3. Portland Cement and Concrete

CCU Engineering Specifications. Section PRECAST CONCRETE PRODUCTS

DESIGN STANDARDS STRAY CURRENT MANAGEMENT

The minimum reinforcement for the stem wall is the placement of:

DASH KIT INSTALLATION

In-Track Repair of Concrete Ties. Deland Humpherys, Director Track Mtce

High-Speed Nondestructive Testing and Intelligent Construction Systems

Construction Specification for Concrete Curb and Concrete Curb and Gutter

Macetti Ing. Alessandro Via Marconi 12H Palosco (BG) Tel:

Lymon C. Reese & Associates LCR&A Consulting Services Tests of Piles Under Axial Load

The complete provider for. Gauging Products and Measurement Systems

CONCRETE SEGMENTAL RETAINING WALL SYSTEM

Asset Management Guide For Project Design Format

HS-Steel-Classic. Curing chambers for the concrete block industry in a proven steel version

STUDY TOUR TO CHINESE RAILWAY Presentation by Geetha Thoopal, Addl. Member (Finance), Ministry of Railways, Head of Delegation

Virginia Approach Spans

VEHICLE CROSSOVER INFORMATION PACK

Settlement of Precast Culverts Under High Fills; The Influence of Construction Sequence and Structural Effects of Longitudinal Strains

1 in 30 year 1 in 75 year 1 in 100 year 1 in 100 year plus climate change (+30%) 1 in 200 year

DESIGN CRITERIA AND OPERATIONAL LIMITS FOR AXIAL FLOW FANS OPERATED IN PARALLEL MODE

GRAVITY BASE FOUNDATIONS

RACKING AND ATTACHMENT CRITERIA FOR EFFECTIVE MEMBRANE ROOF SYSTEM INTEGRATION Public Version 1: July 9, 2012

Renishaw apply innovation TM. Calibrating 5-axis machines to improve part accuracy. 5Align

BARREL ALIGNMENT- A CRITICAL FACTOR IN REDUCING EXTRUDER WEAR

The ACR : Advanced Design Features for a Short Construction Schedule

Printed Polymer An alternative to the SMD assembly. Seite 1

Examining rails in detail. Rail inspection: Rail testing Rail measurement Welding monitoring and vehicle testing Consulting

WITH HIGH SPEED TO A SAFE EMERGENCY HANDLING - VIENNA - ST. PÖLTEN TUNNEL HIGH-SPEED LINE

How to build raised beds page

Big Data in Railroad Engineering

SHAFT CONSTRUCTION IN TORONTO USING SLURRY WALLS

September 1, 2003 CONCRETE MANUAL CONCRETE PAVEMENT REHABILITATION

Network Rail October 2007 Strategic Business Plan. Supporting document. Response to external efficiency studies

SECTION 4Aggegate Subbase

TECHNICAL NOTE Lining of Casings with SaniTite HP Pipe

State of Illinois Department Of Transportation CONSTRUCTION INSPECTOR S CHECKLIST FOR STORM SEWERS

4B The stiffness of the floor and roof diaphragms. 3. The relative flexural and shear stiffness of the shear walls and of connections.

Solid shape molding is not desired in injection molding due to following reasons.

How To Build A Luxury Apartment Complex In London

Bringing good things ahead

SikaProof A Technology

Bogie Overhaul. World-class facility producing high performance bogie overhaulss SERVING THE WORLD S RAILWAYS

Prestressed Concrete I-Beam and TxGirder Haunch Design Guide

Uniclass L L2123 EPIC J3413. CI/SfB (52.5) Heavy duty channel drainage system ACO S Range

BNAM 2008 BERGEN BYBANE NOISE REDUCTION BY TRACK DESIGN. Reykjavik, august Arild Brekke, Brekke & Strand akustikk as, Norway

How To Design A 3D Print In Metal

The Manitoba Water Services Board SECTION Standard Construction Specifications PIPE EXCAVATION, BEDDING AND BACKFILL Page 1 of 11

DESCRIPTION OF WORK:

SLACK PERFORMANCE KARTS

Transcription:

Contributing to Lowest Life Cycle Cost of High Speed 15 th February 2011

From a design, build and maintain perspective. Gottard Base Tunnel Railway Innotrack Project Emerging knowledge from HS1 and Channel Tunnel Experiences on UK mainline 2

Life Cycle Cost High Value Locations Initial Cost Design for Construction Tunnel and Elevated Sections Track Longitudinal Construction and Support Aerodynamic/Tunnel Bore Dimensions Construction Logistics Plant and Just in Time Concrete Placement and Finishing Slipforming Ongoing Costs Key Assets Reliability Whole Life Cost - Design Rationale Ballasted Sections 3

Slab track construction in the Gotthard Base Tunnel Initial Cost Reduction and Logistical Challenge 4

The Gotthard Base Tunnel Longest Tunnel in the world North freight train loads up to 4000 tons/train 300 trains per day in each direction reduction of traveling time Zürich (CH) to Milano (I) less than 3 hours high speed trains up to 250 kmph Single tube bore tunnels for each track Tunnel length 57 km per tube Construction access only at North and South portals 5 5

Logistical conditions for the permanent way construction The finalized permanent track is the transport route Climatic conditions: up to 40 Celsius Multi work fronts in linear construction reduces material transport windows Transport windows only during change of shifts and in the night Materials to be moved for slab track construction: 228.000 m rails = 1.900 pieces of 120 m long rails 1.900 flash butt welds 380.000 pieces of LVT sleeper blocks 131.000 m3 Concrete 6

Logistical solutions for the permanent way construction (1) Highly mechanised and Standardised construction method to enable constant production quality and high work safety Special developed machineries : Rail laying and flash butt welding Sleeper transport wagons and sleeper distribution Special purpose machineries for the assembly of track panel (rail lifting, sleeper assembly, inclination assurance) Special developed support system for track fixation easy handling, light system, very high accuracy in track alignment Rail bounded mixing plant (The Concrete Train) Special concrete shuttle for transport in the tunnel Special concrete pouring machine and working platform 7

Construction Engineering Construction of a temporary track: Rail overlay of 100 m Length of ramp ca. 40 m Tunnel surface Rail pulling and flash butt welding 8

Construction Engineering Sleeper delivery and laying Driving direction of the sleeper train Construction of track panel 9

Track Assembly 10

11 11

Construction Engineering = The concreting process Working plattform Concrete paver Concrete shuttle Construction direction The machineries are moving electro hydraulically and are driving on rubber tyres 12

Achieved ongoing Performance Repetitive construction interval of 2160 m in a 20 day cycle (single access tunnel) Production capacity 220 m linear slab track in15h Exceptional Track Quality 13

Life Cycle Cost Non Ballasted Trackforms (Slabtrack) Experience to date initial cost 30% to 60% more expensive for slabtrack initial cost compared to ballasted. Production rates relatively slow (aligning in wet concrete or precast units). Ongoing maintenance costs less than ballast ( high loads static/dynamic). Improved LCC. Allows fixed relationship with Overhead Line (less adjustment and maintenance) 14

Opportunity Beyond Gotthard Specify trackform idealised for tunnel/elevated sections Access Constraints /Critical Path for Project adds Value Opportunities to be exploited; Automation of construction High Output Tunnel and Elevated Section Aerodynamic Interaction Reduced Depth of Construction Component Life Extended 15

Initial Cost Reduction High Productivity (low manpower technique) Slipforming 400metres/day Laser controlled alignment Separation of wet concrete from the final alignment process Continuous production cycle 4 man operation - 70% reduction Material costs (continuous support) Reduced loading 10% -15% Increase in space - Smaller tunnel or Reduced Aerodynamic Blockage Ratio 16

Whole Life Cost Reduced Increased Rail Life by up to 100% Lower cyclic loading due to continuous support. Use of harder rail to reduce wear (300-400 BHN) Vehicle interaction optimised with fully variable geometry and range of stiffness. Continuous support ease of automated inspection 17

2 nd Generation Slabtrack increasing value with tonnage 18 18

Ongoing Operational Saving with Comparable Initial Cost 19

High Speed Tunnel Discrete Loading Track laid in wet concrete Space lost in critical area Limit to productivity 20

Longitudinal Trackform designed for Tunnel/Elevated Sections High Productivity Mechanised Concrete Increased Free Space Designed interaction with Structure/Vehicle Emergency Access Included X X X 21

2 nd Generation Trackform for Tunnel / Elevated Track Form Longitudinal Construction/Optimised Logistics High productivity construction Integral Derailment protection Low construction depth Continuous Support Increase Rail Hardness Minimise Dead Load Aerodynamic / Blockage Ratio Smaller Tunnel? 22

Opportunity of a 2 nd Generation Trackform for Tunnels/Elevated Sections Initial cost reduction of 300-600 per metre compared to traditional top down construction. 1000 per metre saving on tunnel or aerodynamic benefit (10% plus free space) Whole life cost 25% better than ballasted track plus availability Value of whole life benefit increases with load/speed/access constraints. 23

Maximising the Opportunity for lower LCC of Ballasted Sections Design Principles and Rationale Whole Life Cost Models New materials and technology 24

Whole Life Costs Key Assets Ballasted Trackform Switches and Crossings High Value - Reliability Access Requirements Dynamic Forces Transitions Bridges/Structures Track Stiffness Dynamic Forces Rail Expansion Joints (facilitating optimised viaduct structure) Access constraints Curves and Geometry Transitions Ballast Migration OLE Interactions 25

Resolving Differences of Design Rational Structures 100 years Life 30 years without significant maintenance and inspection Current Performance Key Track Assets on Ballast 25 years life? Ongoing interventions from 7 years or less Intense Inspection regimes Repeated Access to Track Compromise of Track Component Design 26

High Value Locations Performance Criticality, Reliability and Maintenance Cost Tunnels Elevated Sections Transitions to Structures S&C High Speed Curves Define as Key Asset Structures!! 27

Enhanced Key Asset Design Rational Design life 40 years plus for ballast structure Sleeper / Ballast / Bearer Support tuned to reduce dynamic loads i.e. managed stiffness Zero intervention below sleeper / bearer for up to 20 years Reduce then eliminate tamping (currently as high as annually) 28

Why the difference from current practice? Adequate performance but reaching limit. New technology not proven over time. Improvements in current maintenance equipment. Requires LCC model to be accepted/proven over time. Elimination of cause of degradation not fully researched Good at managing the ongoing failure cycle of ballast 29

What is required? Eliminate differential settlement of bearer / sleeper support Minimise Ballast Attrition Tuned vertical track stiffness through the key locations Ballast Mobility controlled. 30

Possible Tools of the New Design Approach Sleeper / Bearer Pads Top Ballast Attrition Vertical Stiffness Ballast Polyurethane Injection Differential Settlement Bottom / Top Ballast Attrition Vertical Stiffness 31

How using proven technology? Bearer Pads Variable Properties and thickness Extensive development Polyurethane Injection Flexible layer to minimise differential settlement Varied depth and polyurethane properties Designed transition stiffness 32

Polyurethane Ballast Reinforcement It penetrates to a depth controlled by how quickly it reacts Curing time is very quick takes only seconds Ballast remains free draining as it doesn t fill all the voids Ballast is robustly locked in a cage of polymer 33 33

Adopting Proven Technology Polyurethane (PU) Other Infrastructure Fit and Forget Confidence in new materials and design. 34

Tamp Free S&C Phase 1 Bottom Ballast Polyurethane Enhanced Top ballast free Adjust/ Stone blow/tamp Bearer Pads reduce attrition of Top ballast 35

Tamp Free S&C Phase 2 Bottom Ballast Polyurethane Enhanced Top ballast - Treated All adjustment above the bearer 36

LCC cost Benefit from Initial Installation DB AG assessment of Treatment in ICE lines. Crossing only treatment initial cost 24,000 break even on a Discounted Cash Flow basis within ten years with significant operational benefit. Complete Switch and Crossing including transition 72,000 If designed into construction significantly less achieved for multiple sites. Benefit to other components and reliability not included. Consistent with HS1 experience 37

Definition of new design rationale for Key Assets. Whole Life cost of asset maintenance. Operational benefit of reliability. Operational benefit of reduced access. Decrease in track/vehicle forces and alignment tolerances benefit. Consider change to Three Tier design principles making use of emerging technology. Structures - 100years life Key Asset Ballast Structures -40years life General Ballasted Track 38

For UK to Secure a Leading Position Integrated Slabtrack Railway System Design for Tunnels with fully developed production cycle. Early involvement of contractor to realise benefits of Design for Construction and LCC improvements Ballasted Track new design standards for key assets consistent with automated inspection and low maintenance. 39