KINGSTONS HOUSE ENVISAGED BASEMENT CONSTRUCTION SEQUENCE

Similar documents
90 Brighton Road, Surbiton, Surrey

Local Authority Building Control Technical Information Note 3 Driven and In-situ Piled Foundations

BUILDING OVER OR NEAR WATER & SEWER MAINS POLICY

-SQA-SCOTTISH QUALIFICATIONS AUTHORITY HIGHER NATIONAL UNIT SPECIFICATION GENERAL INFORMATION

A Guide to Structural Waterproofing

Safe & Sound Bridge Terminology

STRUCTURES Excavation and backfill for structures should conform to the topic EXCAVATION AND BACKFILL.

IH-635 MANAGED LANES PROJECT, SEG. 3.2

Temporary Works. Jan Andresen BEng CEng MIStructE HM Specialist Inspector of Health and Safety. 12 October 2012

Asset Data Dictionary Definition Document Continuous Flight Auger Piles (CFA) Uniclass Classification

CITY OF VAUGHAN SCHEDULE O LOT GRADING DESIGN FOR RESIDENTIAL DEVELOPMENT

HIGHWAYS ASSET MANAGEMENT STRUCTURES TEAM GUIDANCE NOTE SMT/GN/03/10 TECHNICAL APPROVAL

CONTRACTORS INSURANCE SPECIFIC CONTRACT INSURANCE PROPOSAL

Eurocode 7 - Geotechnical design - Part 2 Ground investigation and testing

Permits to Dig / Permits to Excavate / Permits to work near underground services

CONTE NT DESIGN PROCESS. Appendix. 01 First Issue. 02 Revision A. 03 Revision B. 04 Co-ordination. 05 Panel Thicknesses. 06 Panel Surface Quality

Requirements for Building Application Submission

Demolition & Construction Management Plan

COPYRIGHT. Dincel Construction System Pty Ltd

Photo 2. View showing flour mill, machine shed, veranda and saw mill + storage shed.

CITY OF VINCENT CONSTRUCTION MANAGEMENT PLAN GUIDELINES

Piling Datasheets. Continuous flight auger (CFA) Driven Rotary

Geotechnical Building Works (GBW) Submission Requirements

Up-Down Construction Utilizing Steel Sheet Piles and Drilled Shaft Foundations

Re: Damages to Alaska Building from Legislative Information Office Construction

Tree Work on District of West Vancouver Property

CONTRACTORS COMBINED SUPPLEMENTARY PROPOSAL FORM THE RIGHT TOOL FOR THE JOB

ARCHITECTURAL TECHNOLGY 4 ADVANCED CONSTRUCTION TECHNOLOGY BASEMENT CONSTRUCTION YEAR 3 SEMESTER 1 AIDAN WALSH R Lecturer: Jim Cahill

SECTION SITE PREPARATION

Building over or close to a public sewer

Chapter 9 Remedial Measures

Appendix A Sub surface displacements around excavations Data presented in Xdisp sample file

LS 2540 SEWER LATERALS AND INSPECTION TEES

BUTE Department of Construction Management and Technology

GUIDANCE NOTES FOR DEVELOPMENTS OR ENGINEERING WORKS IN THE VICINITY OF SPT SUBWAY INFRASTRUCTURE JULY 2005

Challenging Skew: Higgins Road Steel I-Girder Bridge over I-90 OTEC October 27, 2015 Session 26

Design and Construction of Cantilevered Reinforced Concrete Structures

Uniform Construction Code (UCC) Manufactured Homes. Modular Homes. Building Permit Application Package

Ground-borne Vibrations and Ground Settlements Arising from Pile Driving and Similar Operations

Micropiles Reduce Costs and Schedule for Merchant RR Bridge Rehabilitation

Investigation of Foundation Failure. Step 1 - Data Collection. Investigation Steps

King Post Wall Information

Standard terms and conditions

EXCAVATION AND PILING NEAR SEWERS, STORMWATER DRAINS AND WATER MAINS

ENTRY FORM. DVASE 2013 Excellence in Structural Engineering Awards Program

Lighthouse Engineering, L.L.C.

Amendment to OPSS 415 (Nov 2008) Construction Specification for Pipeline and Utility Installation by Tunnelling

APPLICATION FOR DEMOLITION & RIGHT-OF OF-WAY PERMIT

SECTION 15 FLOODPLAIN MANAGEMENT

Uncovered Decks & Porches

Guide to Carrying Out Engineering Works within Road Structure Safety Zone and Engineering Activity on Land adjoining Public Streets

How to Estimate the Cost of Support of Excavation for Foundation Installation. CPE Candidate No May 15, 2013

NCMA TEK CONCRETE MASONRY FOUNDATION WALL DETAILS. TEK 5-3A Details (2003)

HOUSE BUILDING DIGEST

FLOOD DAMAGE PREVENTION ORDINANCE

APPLICATION PROCEDURES FOR PLACEMENT OF UNDERGROUND WATER AND SEWER PIPELINES IN THE VICINITY OF TRANSPORTATION FACILITIES UNDER THE

Building Permit Application Packet. BUILDING CODES Adopted by La Plata County For Enforcement In The Unincorporated Areas Of La Plata County

Greater Dublin Strategic Drainage Study Regional Drainage Policies - Volume 2 New Development

March 19, Ms. Jean McDonald CAP Management th Street, Suite 1010 Denver, Colorado 80202

DESIGNING STRUCTURES IN EXPANSIVE CLAY

Building Condition Assessment: West Lexington Street Baltimore, Maryland

Federation of Piling Specialists July 2010

DEMOLITION PERMIT CHECKLIST* B.H.M.C. Section

USE OF MICROPILES IN TEXAS BRIDGES. by John G. Delphia, P.E. TxDOT Bridge Division Geotechnical Branch

720 Contour Grading. General. References. Resources. Definitions

Westminster City Council s Residential Basement Report Prepared for Westminster City Council July 2013

Transmission Foundations Case History : Helical piles Hydro One Networks Inc.

Elevating Your House. Introduction CHAPTER 5

When is a Permit Required? What Types of Permits are Required? The most common types of projects that require permits are:

Foundation Experts, LLC Specializes in Foundation Repair and Waterproofing

Civil Engineering and Architecture (CEA) Detailed Outline

Exterior Elevated Elements Inspection Guidelines

CONCRETE FLOOR SLAB & CASTING BED CONSTRUCTION

SIKA AT WORK THE KAENG KRACHAN ELEPHANT HOUSE AT ZURICH ZOO

How To Build A Luxury Apartment Complex In London

Excavation Procedure. MIDGA Reviewed: 07/29/14 Effective: 06/20/09 Supersedes: Original Preparer: Owner: Approver: Safety Safety Safety

Outlet stabilization structure

6 RETROFITTING POST & PIER HOUSES

September September Consulting Structural and Civil Engineers. 100 St John Street London EC1M 4EH. akt-uk.com

IALN / FAO: The Planning Department The Royal Borough of Windsor and Maidenhead Town Hall, St. Ives Road Maidenhead SL6 1RF

Milan M5 metro extension the construction of Lotto station

Federation of Piling Specialists

Settlement of Precast Culverts Under High Fills; The Influence of Construction Sequence and Structural Effects of Longitudinal Strains

Interim Advice Note 105/08 Implementation of Construction (Design and Management) 2007 And the withdrawal of SD 10/05 and SD 11/05

STANDARD AND SPECIFICATIONS FOR STORM DRAIN INLET PROTECTION

Series 600: Earthworks

Property Inspection. 83A Ascot Avenue North New Brighton Christchurch STRUCTURAL REPORT

Chapter 3 Pre-Installation, Foundations and Piers

COMMONLY USED RESIDENTIAL BUILDING CODES

Sample Drawing Package for One and Two Family Dwelling Applications

University Arms Hotel, Cambridge

Gas Meter Clearances and Service Installation Requirements

Quality Control and Quality Assurance Guide

GUIDELINES FOR DESIGNERS BUILDING AND CONSTRUCTION WORKS WITHIN PROXIMITY TO CORPORATION SERVICES

Supplier ID: Local Office: GLASGOW 69 Buchanan Street Glasgow G1 3HL

Chapter 5.4. Waterproofing of basements and other below ground structures

Designed and Engineered to Perform

CITY OF YORBA LINDA P.O. BOX CALIFORNIA

Residential Building Permits

The information and materials contained in this disc are provided as is and as available.

Transcription:

Intended for J Document type Kingstons House Envisaged Basement Construction Sequence Date August, 2015 KINGSTONS HOUSE ENVISAGED BASEMENT CONSTRUCTION SEQUENCE

KINGSTONS HOUSE ENVISAGED BASEMENT CONSTRUCTION SEQUENCE Revision 01 Date 14/08/2015 Made by Grace Richardson Checked by Chris Papanastasiou Ref Kingstons House Envisaged Basement Construction Sequence Ramboll 240 Blackfriars Road SE1 8NW T +44 (0)20 7632 5291 www.ramboll.co.uk

CONTENTS 1. INTRODUCTION 1 2. METHOD OF CONSTRUCTION 1 3. FURTHER CONSIDERATIONS 1 3.1 Soil Conditions 1 3.2 Network Rail Asset Protection 2 3.3 Existing Building Foundations 3 APPENDICES Appendix 1 Sketches Outlining Envisaged Basement Construction Sequence Appendix 2 Outline Risk Assessment

1 of 3 1. INTRODUCTION The proposed development is situated on the corner of Station Road and Coombe Road in Kingston upon Thames. The site is not within a conservation area and none of the existing buildings currently on the site are statutory or locally listed. It is proposed to demolish the existing building to make way for a new mixed use development that will include a new purpose built two form early primary school and 25 residential units. This Report summarises a possible construction sequence for the basement construction at Kingstons House. The content of the Report is for the exclusive use of J and should not be used in whole or in part by any third parties without the express permission of Ramboll UK in writing. It should not be relied upon exclusively for decision making purposes and should be read in conjunction with all other relevant reports and drawings submitted as part of the planning application. The following information was provided by the architect to inform this Report: Architecture Initiative, Proposed Plans evels -1 & -2, Drawing No. KH-100 Rev D; Architecture Initiative, Proposed Plans evel 0, Drawing No. KH-101 Rev E; and Architecture Initiative, Proposed Section, Drawing No. KH-202 Rev A. An outline risk assessment highlighting the key design risks at this stage has been included in Appendix B. 2. METHOD OF CONSTRUCTION Reference should be made to the Ramboll sketch numbers 162556sk001 and 162556sk002 in Appendix A for an indicative construction sequence for the proposed basement. A piled wall such as a secant wall is the recommended form of construction for the basement with a reinforced concrete capping beam. This will allow for construction in most soil types and it will also provide a temporary barrier to groundwater during construction if the ground water levels are above formation level. A secant piled wall has vertical load bearing capacity which will allow the superstructure to be constructed directly above the capping beam. A concrete liner wall is likely to be required to meet the waterproofing requirements for a Grade 3 habitable basement. In the temporary condition, props will be required to support the wall until the ground and basement floor slabs have been constructed. In the permanent state the floor slabs will prop the piled wall. 3. FURTHER CONSIDERATIONS 3.1 Soil Conditions The site geology and associated soil design parameters will greatly influence the design of the piled wall in both the temporary and permanent condition. A full site investigation will need to be undertaken including a representative number of boreholes across the site to understand the soil strata and ground water levels. This information can then be used to inform the design and determine the lengths and diameters of piles required as well as the number of props and their locations in the temporary state. Wall and adjacent ground movement predictions can then be made.

2 of 3 3.2 Network Rail Asset Protection Given the close proximity of the South West Trains railway line to the development, we would recommend early engagement with Network Rail to ensure that their requirements are incorporated into the scheme. The first stage of the formal ageement process with Network Rail is a Form A. This includes a summary of the analysis undertaken to justify the negligible impact on the rail tracks. Following this, if Network Rail do not believe that the works are sufficiently far from their assets, they may require further submission under Forms B & C. Since the proposed scheme is adjacent to the bottom of the slope that the rail lines sit on, the following analyses will likely be required to satisfy the Network Rail requirements regardless of the level of the basement: Slope stability analysis; Ground movement assessment of rails and other key Network Rail assets; Condition surveys before and after construction; and The above may include a requirement for monitoring before construction begins, during construction and for a certain time after construction has finished. The current scheme includes a basement which extends into both the track and slope support zones. Usually, the Network Rail guidelines advise that if a new structure is proposed within a 3:2 slope that starts 2.75m from the edge of the closest rail track or below a notional extension of an embankment then analysis will have to be carried out to demonstrate that the development will not affect the operation of the railway. Figure 1 shows an indicative line of influence from the rail tracks and the slope. New development (Kingstons House) South West Trains railway line ocation of Network Rail fence unknown ~ 2.75m 2 ine of influence of slope 3 ine of influence of rail tracks Figure 1: Indicative line of influence from Network Rail lines During construction the following should also be considered: Tower cranes cannot over-sail Network Rail land. Tower cranes will have to be overdesigned by 25% as will working platforms for mobile plant. Mobile cranes cannot work towards the railway if working within a collapse radius of the Network Rail boundary. Piling rigs must be perpendicular to the railway. A façade glare assessment may be required. Design and Method Statement submissions will be required for any element of temporary or permanent works that has potential to affect the railway.

3 of 3 3.3 Existing Building Foundations The type and location of any existing foundations from the building that currently sits on the site are unknown. A full site survey will be required to understand the implications that this may have on the construction sequence. It should be noted that if there are existing foundations in the location of proposed piles, these will either have to be removed or piled through which have time and cost implications. The contractor should decide the preferred strategy if this is required.

1-1 APPENDIX 1 SKETCHES OUTINING ENVISAGED BASEMENT CONSTRUCTION SEQUENCE

Temporary propping KINGSTON HOUSE ENVISAGED BASEMENT CONSTRUCTION SEQUENCE STAGE 1 INVESTIGATIONS TO BE CARRIED OUT TO OCATE ANY EXISTING FOUNDATIONS PRIOR TO PIING AND EXCAVATION. IF THERE ARE EXISTING FOUNDATIONS IN THE PIING OCATIONS, CONTRACTOR TO DECIDE IF THE EXISTING FOUNDATIONS SHOUD BE REMOVED PRIOR TO PIING. PIING ASSUMED TO BE CARRIED OUT FROM GROUND EVE CONSTRUCT CAPPING BEAM 1 A A Indicative location of existing building. A full site investigation should be carried out to understand any clashes with the new and existing foundations. Any clashes may affect the speed of construction. Contractor to decide if existing foundations should be dug out or piled through. Indicative piled wall and capping beam over STAGE 2 EXCAVATUE TO JUST BEOW CAPPING BEAM INSTA FYING SHORES/TEMPORARY WORKS EXCAVATE TO BASEMENT FORMATION EVE 2 B B Temporary propping may be in the form of flying shores SECTION A-A SECTION B-B Capping beam constructed before excavation Indicative piled wall General Notes: 1. Sketches are schematic only and not to scale. 2. Sketches show envisaged sequence of construction. 3. Sketches should be read in conjunction with relevant design philosophy reports and architectural information. 4. Final construction sequence to be developed by the contractor. 5. All temporary works shown is indicative only. The contractor will be responsible for the design, erection and maintenance of all of the temporary works. Project Title Kingstons House Project N 1620000556 Sketch N 162556sk001 Title Basement Construction Sequence Scale NTS Eng: Rev: Date: Checked GR 02 14/08/15 CP

KINGSTON HOUSE ENVISAGED BASEMENT CONSTRUCTION SEQUENCE STAGE 3 INSTA INTERMEDIATE PROPPING IF REQUIRED EXCAVATION COMPETED 3 STAGE 4 REMAINING FOUNDATIONS CONSTRUCTED WHERE REQUIRED. BASEMENT SAB AND CONCRETE SUBSTRUCTURE, CONSTRUCTED. INER WA INSTAED TO ENSURE WATERTIGHTNESS. PROPS REMOVED ONY ONCE GROUND FOOR SAB HAS REACHED SUFFICIENT STRENGTH. 4 STAGE 5 SUPERSTRUCTURE FRAME CONSTRUCTED 5 Superstructure frame Props dismantled and removed once ground floor slab has reached sufficient strength iner wall for water tightness Additional props may be required Allow for temporary openings in slab for removal of props Substructure frame Given the space constraints, it may be difficult to fit a rig in for the internal foundations. One possibility is to pile these at the Stage 1 from ground level. The piles can then be broken down during excavation. This will mean that temporary heave forces have to be accounted for in the pile design. If the piles are bored rather than CFA then the bores above formation could be filled with gravels rather than concrete and the steel cages hung at final cut off level to avoid breaking down the piles over the entire basement depth. General Notes: 1. Sketches are schematic only and not to scale. 2. Sketches show envisaged sequence of construction. 3. Sketches should be read in conjunction with relevant design philosophy reports and architectural information. 4. Final construction sequence to be developed by the contractor. 5. All temporary works shown is indicative only. The contractor will be responsible for the design, erection and maintenance of all of the temporary works. Project Title Kingstons House Project N 1620000556 Sketch N 162556sk002 Title Basement Construction Sequence Scale NTS Eng: Rev: Date: Checked GR 02 14/08/15 CP

2-2 APPENDIX 2 OUTINE RISK ASSESSMENT

RISK ASSESSMENT (PP12.4) job title KINGSTONS HOUSE 1620000556 file ref. Stage / Section of works BASEMENT CONSTRUCTION METHOD Rev 1-04/06/2015 PD/PM approval The list of risks below is not intended as an exhaustive list. Hazards have been identified where they are project specific and as such hazards that a competent contractor would be expected to identify have not been listed. Design item giving rise to risk² Consequence of item giving rise to risk Residual risks - risks that cannot be designed out or those remaining Action to mitigate/reduce risk Action By Status 7 following risk assessment Activity /Element Item Cat¹ Nº P 1 A site specific Ground Investigation has not been undertaken. Delays due to unforeseen ground conditions; cost and programme implications. Impacting on foundation solution. P 2 The groundwater levels on site are unknown at present. Impact of Excessive and/or differential water uplift. potential dewatering/groundwater control measures of adjacent Delays due to unforeseen ground conditions; cost and structures/services. programme implications. Cost and program implications should remedial water retention measures be required. Impacting on foundation solution. Extensive dewatering measures may be required. P 3 South West Train railway lines. The new development is adjacent to the bottom of the sope that the rail lines sit on and also cuts through the expected line of influence of the rail tracks. Delays due to lengthy approval process with Network Rail. Network Rail may believe that the development will affect their assts and therefore ask for changes to the proposal or reject the proposal altogether. The close proximity of the rail tracks will dictate the construction methodology including type and location of piling rig and tower cranes. The close proximity will also affect the permanent design including the façade access and maintenance strategy, and possibly the building geometry. P/C 4 The location of all the existing services in the vicinity of the site is not known. Risk of damaging services beneath/surrounding the site during site investigation and construction works. Health and safety implications of unexpected service strike during excavation. iability through damage. Removal/re-routing of services will have cost and programme implications. P 5 Undiscovered buried obstructions and existing piles Increased costs due to hold up in construction program and increased costs for removing buried obstructions. Carry out a Ground Investigation to confirm the ground conditions Carry out a Ground Investigation to confirm the ground water level. Any excavation that extends below the groundwater level will require dewatering. Basement walls for levels that extend below the groundwater table will have to be formed by interconnecting embedded concrete or steel piles if required. Early engagement with Network Rail is advised to ensure that their requirements are incorporated into the scheme. A detailed immpact assessment should be carried out for both the slope stability and any additional impact on the rail tracks. Design and method statement submissions will be required for any element of temporary o parmanent works that has the potential to affect the railway. Desk study should be carried out to visually identify the locations of any services on or surrounding the site if the building footprint will extend close to service routes. Contractor to carry out survey prior to works to confirm location of services. Programme to ensure that all services at the sites are located, isolated and disconnected at meter where applicable before commencement of any works. Identification of requirements and scope of works issued to the health and safety site manager. ocation of existing piles to be investigated NR may not approve the scheme. Risk of damaging existing services Risk present until works complete. Client/ Engineer/ Contractor Client/ Engineer/ Contractor Client/ Engineer/ Contractor Client/ Engineer/ Contractor Client/ Engineer/ Contractor P 6 Existing public sewers potentially crossing the development site If public sewerage crosses the site then no build zones may be enforced around them or they may need to be diverted. Diversion agreements will need to be in place with Thames Water before any works can be undertaken. CCTV survey undertaken to confirm the exact location of all sewerage crossing the site. Public sewer diversions may be required. Client P 7 Basement waterproofing. Different waterproofing strategies have different build-up requirements, potential impact on basement size and construction. Structural engineer to assist Architect with waterproofing strategy where integral to the basement structure e.g. waterproof concrete admixture. Design Team / Client 1 (C) CDM / (P) Project / (E) Environmental ² Hazard consideration - harm to human health, construction, cost, project developments, breach of legislation/regulations or the natural environment 7 ive/close ramboll uk PP12.4 Designers Risk Assessment Rev 02/10 Risk Assessment for Basement Construction.xlsx Page 1 of 1