Microsoft Project 2013



Similar documents
Introduction to Microsoft Project 2010

Planning and Managing Projects with Microsoft Project Professional 2013

Microsoft Project 2013 Guide to Task and Resource Planning

MS Project Tutorial for Senior Design Using Microsoft Project to manage projects

Using Microsoft Project 2000

Computer Training Centre University College Cork

Project Management: Intermediate Microsoft Project 2010

Microsoft Project 2007 Level 1: Creating Project Tasks

Planning and Managing Projects with Microsoft Project Professional 2013

Project Quick Reference. The Assignment Equation. EPM Architects

Create task relationships by linking tasks. Switch task scheduling from manual to automatic. Set nonworking days for the project plan.

Excel Pivot Tables. Blue Pecan Computer Training Ltd - Onsite Training Provider :: :: info@bluepecan.co.

How to use Microsoft Project? Basic Training to Help You during the BYI challenge

Creating a New Project

Microsoft Access 2010 handout

I N FO RM A T I O N T EC H N O L O G Y S ERV I C ES M I C ROSOFT PROJ EC T T A S K M A N A GEM EN T LEARNING GUIDE

Produced by Flinders University Centre for Educational ICT. PivotTables Excel 2010

1 Start a new project

Beginning Microsoft Project

Project Management Quick Reference Guide for MS Project 2010

Microsoft Access 2010 Part 1: Introduction to Access

T12. Excel and Microsoft Project. Introduction LEARNING OUTCOMES

Microsoft Project From the WBS to a Complete Schedule Emanuele Della Valle, Lecturer: Dario Cerizza

Planning and Managing Projects with Microsoft Project Professional 2013

OVERVIEW. Microsoft Project terms and definitions

Lesson 6 - Managing Resources in a Project Plan

Access Tutorial 1 Creating a Database

How To Use Ms Powerbook On A Pc Or Mac Or Macbook 2 (Windows)

Sample Table. Columns. Column 1 Column 2 Column 3 Row 1 Cell 1 Cell 2 Cell 3 Row 2 Cell 4 Cell 5 Cell 6 Row 3 Cell 7 Cell 8 Cell 9.

Microsoft Project 2007 Level 2: Working with Resources and Managing a Project

Microsoft Excel 2013: Macro to apply Custom Margins, Titles, Gridlines, Autofit Width & Add Macro to Quick Access Toolbar & How to Delete a Macro.

Microsoft Excel 2010 Part 3: Advanced Excel

Hands on Microsoft Project (Part I) From a WBS to a Complete Schedule Emanuele Della Valle, Lecturer: Dario Cerizza

Microsoft Project 2010

Lab 1 Introduction to Microsoft Project

Creating tables of contents and figures in Word 2013

Microsoft Office PowerPoint Identify components of the PowerPoint window. Tutorial 1 Creating a Presentation

Microsoft Excel 2013: Using a Data Entry Form

Pivot Tables & Pivot Charts

Introduction to Word 2007

ABOUT THIS COURSE...3 ABOUT THIS MANUAL...4 EXCHANGING PROJECT PLAN DATA WITH OTHER APPLICATIONS...5

About the Tutorial. Audience. Prerequisites. Disclaimer & Copyright. MS Project 2013

Word 2010: Mail Merge to with Attachments

Microsoft Office PowerPoint Creating a new presentation from a design template. Creating a new presentation from a design template

Getting Started with Access 2007

PowerPoint 2013: Basic Skills

Virto SharePoint Gantt Chart App for Office 365 Release User and Installation Guide

University of Sunderland. Microsoft Project. Basic Guide

Using MS Project in Translation Projects Management

Migrating to Excel 2010 from Excel Excel - Microsoft Office 1 of 1

Microsoft Migrating to Word 2010 from Word 2003

In this session, we will explain some of the basics of word processing. 1. Start Microsoft Word 11. Edit the Document cut & move

Excel 2003 PivotTables Summarizing, Analyzing, and Presenting Your Data

Bradley University College of Liberal Arts and Sciences Department of Computer Sciences and Information Systems

How To Manage A Project In Project Management Central

Introduction To Microsoft Office PowerPoint Bob Booth July 2008 AP-PPT5

Excel 2007 Basic knowledge

Computer Training Centre University College Cork. Excel 2013 Pivot Tables

Handout: Word 2010 Tips and Shortcuts

Microsoft PowerPoint 2010

CREATING EXCEL PIVOT TABLES AND PIVOT CHARTS FOR LIBRARY QUESTIONNAIRE RESULTS

Create Charts in Excel

Basic Pivot Tables. To begin your pivot table, choose Data, Pivot Table and Pivot Chart Report. 1 of 18

3. Locate the different selections of Styles from the Home Tab, Styles Group

Microsoft Outlook 2013 Part 1: Introduction to Outlook

In this example, Mrs. Smith is looking to create graphs that represent the ethnic diversity of the 24 students in her 4 th grade class.

Macros in Word & Excel

Maximizing the Use of Slide Masters to Make Global Changes in PowerPoint

Working with sections in Word

Excel basics. Before you begin. What you'll learn. Requirements. Estimated time to complete:

ELECTRO-MECHANICAL PROJECT MANAGEMENT

Microsoft Word 2011: Create a Table of Contents

Excel Using Pivot Tables

Microsoft Office PowerPoint 2013

Laboratory 1 Initiating a Project

WHAT S NEW IN MS EXCEL 2013

Everyday Excel Stuff Excel Day Planner Organizer Reference Guide

Microsoft Outlook 2010 Part 1: Introduction to Outlook

Excel 2013 What s New. Introduction. Modified Backstage View. Viewing the Backstage. Process Summary Introduction. Modified Backstage View

Project 2010 Introduction

Microsoft PowerPoint Tutorial

INTRODUCTION 5 COLLABORATION RIBBON 5 SELECT THE UPDATING METHOD 6 MAKE YOUR PROJECT COLLABORATIVE 8 PROCESSING RECEIVED TASK UPDATES 9

Microsoft Office 2010

Access Tutorial 1 Creating a Database. Microsoft Office 2013 Enhanced

Asta Powerproject GETTING STARTED WITH ASTA POWERPROJECT VERSION 14. astapowerproject.com. Asta Powerproject: The power behind successful projects

Instructions for Formatting MLA Style Papers in Microsoft Word 2010

FastTrack Schedule 10. Tutorials Manual. Copyright 2010, AEC Software, Inc. All rights reserved.

Instructions for Creating an Outlook Distribution List from an Excel File

INTRODUCTION TO MICROSOFT PROJECT 2007 CONTENTS

Advanced Presentation Features and Animation

ONBASE OUTLOOK CLIENT GUIDE for 2010 and 2013

Project Management Dashboard Pro v5 Documentation

Microsoft Outlook 2010 Managing Disk Quotas

Instructions for Formatting APA Style Papers in Microsoft Word 2010

Project planning with MindGenius

PEMBINA TRAILS SCHOOL DIVISION. Information Technology Department

Presentations and PowerPoint

Create a PivotTable or PivotChart report

Appendix A: Brief Guide to Microsoft Project 2010

Create a New Database in Access 2010

Transcription:

CALIFORNIA STATE UNIVERSITY, LOS ANGELES INFORMATION TECHNOLOGY SERVICES Microsoft Project 2013 Summer 2014, Version 1.0 Table of Contents Introduction...2 Overview of the User Interface...2 Creating a New Project...3 Working with Tasks...3 Creating a Manually Scheduled Task...3 Creating an Automatically Scheduled Task...4 Linking Tasks...4 Creating a Summary Task...5 Updating Task Progress...5 Working with Resources...6 Adding a Work Resource...6 Changing a Resource s Work Hours...7 Assigning a Resource to a Task...7 Scheduling...8 Changing a Project s Work Hours...8 Setting a Scheduling Constraint...10 Assigning Multiple Resources to a Task...10 Creating a Work Exception...11 For additional handouts, visit http://www.calstatela.edu/handouts. For video tutorials, visit http://www.youtube.com/mycsula.

Introduction Microsoft Project 2013 is a project management program that is designed to assist managers to more effectively manage their projects. It gives users greater power over their projects by allowing them to simplify such things as defining work resources, assigning tasks to workers, visualizing a project, and managing a budget. This handout covers the essentials of Project 2013. It provides a brief overview of the user interface and covers creating and linking tasks, adding resources and assigning them to tasks, and scheduling. This handout uses the planning and development of a website as a project example. Overview of the User Interface Like the other Microsoft Office 2013 applications, Project 2013 incorporates the Ribbon, Quick Access toolbar, Backstage view, and context-sensitive menus and toolbars. These all make working with Project 2013 more familiar and intuitive. The default view in Project 2013 is the Gantt Chart view (see Figure 1). It has two main areas: the task table (left side of the view) and the timescale (right side of the view). The task table lists the project tasks and their accompanying information. The timescale displays task bars that correspond to the tasks listed in the task table. The task bars show the duration of each task, from their planned start date to their planned finish date, over time. You can move the separator bar between the timescale and the task table to the left or right to display more of either area. The timeline provides a graphical view of a project along a single left-right axis. Figure 1 Project 2013 Program Window Microsoft Project 2013 2

Creating a New Project When creating a new project, you can start with the default blank project, or you can base your new project on an existing project or template. To create a new project: 1. Click the Start button, click All Programs, click Microsoft Office 2013, and then click Project 2013. The Start screen appears (see Figure 2). 2. In the right pane, click Blank Project. A new, blank project opens in the program window in the Gantt Chart view. NOTE: You can create a new blank project at any time by clicking the File tab on the Ribbon, clicking New in the left pane, and then clicking Blank Project in the right pane. Figure 2 Project 2013 Start Screen Working with Tasks Most projects begin with a list of the tasks that need to be completed. Once you create your task list, you can then define the relationships between the tasks. Tasks can be automatically or manually scheduled, depending on the needs of the project and the information currently available. At any point during a project, you can change a task from manual scheduling to automatic scheduling, or vice versa. Creating a Manually Scheduled Task By default, all new tasks in Project 2013 are set for manual scheduling. With manual scheduling, you can fully control the task s duration, start date, and finish date. The duration can be entered in minutes (m), hours (h), days (d), weeks (w), or months (mo). Manually scheduled tasks are marked with the pushpin icon in the Task Mode field. Microsoft Project 2013 3

To create a manually scheduled task: 1. In the first row of the task table, enter Website Ideas and Mockups in the Task Name field (see Figure 3). 2. Enter 1w in the Duration field. This sets the duration of the task to one week. 3. Enter Monday in the Start field. Project 2013 automatically calculates the finish date using the given information and fills in the Finish field. Also, a task bar appears in the timescale (on the same row as the task) showing the task s time frame. Figure 3 Manually Scheduled Task in the Task Table Creating an Automatically Scheduled Task With automatically scheduled tasks, you can have Project 2013 calculate dates and durations. Automatically scheduled tasks are marked with the Gantt bar icon in the Task Mode field. To create an automatically scheduled task: 1. In the second row of the task table, enter Preparation & Planning in the Task Name field (see Figure 4). 2. Click in the Task Mode field, click the down arrow that appears, and then click Auto Scheduled. By default, Project 2013 assigns the task an estimated duration of one day and automatically fills in the Duration, Start, and Finish fields. Also, a task bar appears in the timescale showing the task s time frame. 3. To change the duration of the task to two days, enter 2d in the Duration field. Project 2013 recalculates the finish date and updates the Finish field. Figure 4 Automatically Scheduled Task in the Task Table Linking Tasks When you link tasks, you create a relationship between them called a task dependency. Project 2013 supports four types of task dependencies. By default, Project 2013 creates finish-to-start links, which means the first task needs to finish before the second task can start. To link tasks: 1. In the third row of the task table, create a new manually scheduled task named Website Draft #1 and set the duration to two weeks by typing 2w in the Duration field. Leave the Start and Finish fields empty. 2. In the Task Name column, click to select the first task, and then hold down the Ctrl key and click to select the remaining two tasks. NOTE: The order in which the tasks are selected is important. It defines the order in which the tasks are linked. 3. On the Task tab of the Ribbon, in the Schedule group, click the Link the Selected Tasks button. Project 2013 fills in the Start and Finish fields of the Website Draft #1 task and links the three tasks by adding link lines between the task bars in the timescale. Microsoft Project 2013 4

4. To see the advantage of automatically scheduled tasks, change the duration of the Website Ideas and Mockups task to 2 wks instead of 1 wk. In the timescale, notice that the start date of the automatically scheduled task, Preparation & Planning, was automatically adjusted. The start date of the manually scheduled task, Website Draft #1, was not automatically adjusted and will need to be adjusted manually (see Figure 5). 5. Change the duration of the Website Ideas and Mockups task back to 1 wk. Figure 5 Linked Tasks in the Timescale Creating a Summary Task When organizing the tasks for a project, you can group tasks that share characteristics or that will be completed in the same time frame under a summary task. By default, the summary tasks are bold and outdented, and the subtasks are indented beneath them. To create a summary task: 1. In the Task Name column, drag to select all three tasks. 2. On the Task tab of the Ribbon, in the Insert group, click the Insert Summary Task button. Project 2013 inserts the new summary task above the three tasks, fills in the Task Name field with the text <New Summary Task>, and turns the three tasks below it into subtasks. 3. Enter Website Upgrade in the Task Name field of the summary task (see Figure 6). Figure 6 Summary Task with Three Subtasks Updating Task Progress One of the simplest methods of tracking task progress is to specify a percentage of completion. You can enter a value between 0% (for a task that has not started) and 100% (for a task that is finished). To update a task s percentage of completion: 1. In the Task Name column, double-click the Website Ideas and Mockups task. The Task Information dialog box opens. 2. On the General tab, in the Percent complete box, enter 70% (see Figure 7). Microsoft Project 2013 5

Figure 7 Task Information Dialog Box 3. Click the OK button. In the timescale, a progress bar is added within the Website Ideas and Mockups task bar to show progress on the task (see Figure 8). Figure 8 Task Bar with Progress Bar NOTE: You can quickly set tasks to 0%, 25%, 50%, 75%, or 100% complete by selecting the tasks in the task table, and then clicking the corresponding buttons in the Schedule group on the Task tab of the Ribbon (see Figure 9). Figure 9 Schedule Group on the Task Tab Working with Resources Resources are typically people assigned to tasks in a project. They can also include anything that is used to complete a project, such as materials or cost. Adding a Work Resource By adding resources to your project, you make them available to assign to tasks within your project. To add a work resource: 1. On the View tab of the Ribbon, in the Resource Views group, click the Resource Sheet button to switch to the Resource Sheet view. 2. In the first row, enter John Smith in the Resource Name field (see Figure 10). 3. Make sure that the Type field is set to Work. Microsoft Project 2013 6

4. Enter JS in the Initials field. 5. Enter Programmer in the Group field. 6. Enter 30 in the Std. Rate field. This sets the hourly rate for that worker to $30. Figure 10 Work Resource in the Resource Sheet View Changing a Resource s Work Hours By default, a resource s work hours are set to the project s work hours. You can change a resource s work hours to reflect his or her actual work schedule. To change a resource s work hours: 1. In the Resource Name column, double-click the John Smith resource. The Resource Information dialog box opens. 2. On the General tab, click the Change Working Time button. The Change Working Time dialog box opens. 3. Click the Work Weeks tab in the lower section of the dialog box. 4. In the Name column, double-click the [Default] work week. The Details for '[Default]' dialog box opens (see Figure 11). 5. In the Select day(s) box, select Monday through Friday by clicking Monday, holding down the Shift key, and then clicking Friday. 6. Select the Set day(s) to these specific working times option. 7. Change the From time in the first row to 7:00 AM and the To time in the second row to 4:00 PM. 8. Click the OK button in each dialog box to apply the changes. Figure 11 Details for '[Default]' Dialog Box Assigning a Resource to a Task After you add resources to your project, the next step is to assign them to tasks within your project. Microsoft Project 2013 7

To assign a resource to a task: 1. On the View tab of the Ribbon, in the Task Views group, click the Gantt Chart button to switch to the Gantt Chart view. 2. In the task table, click in the Resource Names field of the Website Ideas and Mockups task, click the down arrow that appears, and then select the check box next to John Smith to assign him to the task (see Figure 12). NOTE: If the Resource Names column is not displayed, use the scroll bar at the bottom of the task table, or move the separator bar between the timescale and the task table to display it. Figure 12 Assigning a Resource 3. A red person icon appears in the Indicators field (in the first column) of the Website Ideas and Mockups task to indicate that the resource is overallocated. To resolve the overallocation, temporarily change the Task Mode from Manually Scheduled to Auto Scheduled, and then change it back to Manually Scheduled (see Figure 13). Figure 13 Changing the Task Mode NOTE: Overallocations are Project s way of letting you know that a resource cannot complete a task in the allotted time. In this case, however, Project simply wants to extend the project duration to Monday morning. Scheduling Scheduling is a key part of project management. Project 2013 includes several scheduling enhancements that give you greater control over your schedule. Changing a Project s Work Hours By default, a project s work hours are set to Monday through Friday, 8:00 a.m. to 5:00 p.m., with an hour off for lunch between 12:00 p.m. and 1:00 p.m. each day. A new resource s work hours are initially based on the project s work hours. You can change the project s work hours to reflect the general working days and hours of your project. Microsoft Project 2013 8

To change a project s work hours: 1. On the Project tab of the Ribbon, in the Properties group, click the Change Working Time button. The Change Working Time dialog box opens. 2. Click the Work Weeks tab in the lower section of the dialog box. 3. In the Name column, double-click the [Default] work week. The Details for '[Default]' dialog box opens (see Figure 14). 4. In the Select day(s) box, select Monday through Friday by clicking Monday, holding down the Shift key, and then clicking Friday. 5. Select the Set day(s) to these specific working times option. 6. Change the From time in the first row to 7:00 AM and the To time in the second row to 4:00 PM. 7. Click the OK button. Figure 14 Details for '[Default]' Dialog Box 8. In the Change Working Time dialog box, click the Options button. The Project Options dialog box opens, displaying the Schedule options. 9. In the right pane, change the Default start time to 7:00 AM and the Default end time to 4:00 PM (see Figure 15). 10. Click the OK button in each dialog box to apply the changes. Figure 15 Schedule Options Microsoft Project 2013 9

Setting a Scheduling Constraint A constraint is a restriction set on the start or finish date of a task. There are several types of constraints that can be placed on a task. To set a scheduling constraint: 1. Make sure that the Gantt Chart view is displayed. 2. On the Task tab of the Ribbon, in the Properties group, click the Display Task Details button. The Task Details Form view displays below the Gantt Chart view. 3. In the Gantt Chart view, in the Task Name column of the task table, click to select the Website Draft #1 task. 4. In the Task Details Form view, deselect the Manually Scheduled check box. This changes the task from Manually Scheduled to Auto Scheduled which is required for setting scheduling constraints. 5. In the Constraint section, select Start No Earlier Than from the Constraint list (see Figure 16). Figure 16 Constraint List 6. Set the Date to one day after its original start date. 7. Click the OK button. The start and finish dates of the Website Draft #1 task are updated in the task table. NOTE: After setting the constraint, if you change the start date to an earlier date, a warning will be issued. Assigning Multiple Resources to a Task A task can be assigned to multiple resources to reduce the amount of time needed to complete the task. To assign multiple resources to a task: 1. First, add another work resource. On the View tab of the Ribbon, in the Resource Views group, click the Resource Sheet button to switch to the Resource Sheet view. 2. In the second row, enter James Wilson in the Resource Name field. 3. Make sure that the Type field is set to Work. 4. Enter JW in the Initials field. 5. Enter Manager in the Group field. 6. Enter 40 in the Std. Rate field. This sets the hourly rate for that worker to $40. 7. Next, on the View tab of the Ribbon, in the Task Views group, click the Gantt Chart button to switch to the Gantt Chart view. Microsoft Project 2013 10

8. In the Task Name column of the task table, click to select the Website Draft #1 task. 9. On the Resource tab of the Ribbon, in the Assignments group, click the Assign Resources button. The Assign Resources dialog box opens. 10. In the Resource Name column, click to select the James Wilson resource, and then click the Assign button. 11. Click to select the John Smith resource, and then click the Assign button (see Figure 17). 12. Click the Close button. Figure 17 Assigned Work Resources 13. Click the exclamation icon that appears to the left of the Website Draft #1 cell and select the Reduce duration but keep the same amount of work. option as the reason for assigning two resources to the task (see Figure 18). Figure 18 Reducing Task Duration NOTE: A task must be set to Auto Scheduled to enable this option. Creating a Work Exception In the event that a person is unable to make it to work, you can create an exception to remove that day from the person s work hours. To create a work exception: 1. In the Gantt Chart view, make a note of the week during which the Website Draft #1 task is scheduled. 2. On the View tab of the Ribbon, in the Resource Views group, click the Resource Sheet button to switch to the Resource Sheet view. 3. In the Resource Name column, double-click the John Smith resource. The Resource Information dialog box opens. 4. On the General tab, click the Change Working Time button. The Change Working Time dialog box opens. 5. On the Exceptions tab, enter Sick in the first row of the Name column. 6. Set the Start date to the Tuesday of the week that the Website Draft #1 task is scheduled. 7. Click the OK button in each dialog box. Microsoft Project 2013 11

8. On the View tab of the Ribbon, in the Task Views group, click the Gantt Chart button to switch to the Gantt Chart view. Notice that the task has been extended to the next working day so that it can be completed since one of the two resources assigned to the task is going to miss a day. Microsoft Project 2013 12