INTRODUCTION 5 COLLABORATION RIBBON 5 SELECT THE UPDATING METHOD 6 MAKE YOUR PROJECT COLLABORATIVE 8 PROCESSING RECEIVED TASK UPDATES 9
|
|
|
- Margery Cunningham
- 10 years ago
- Views:
Transcription
1
2 Contents Contents INTRODUCTION 5 COLLABORATION RIBBON 5 SELECT THE UPDATING METHOD 6 MAKE YOUR PROJECT COLLABORATIVE 8 PROCESSING RECEIVED TASK UPDATES 9 IMPORT UPDATES 12 CUSTOM TEXT FIELDS MAPPING 13 INTRODUCTION 15 CREATE PROJECT PLAN 15 MAKE PROJECT PLAN COLLABORATIVE 16 SELECT THE UPDATE METHOD 17 DISTRIBUTE THE PROJECT PLAN 18 INTRODUCTION 19 GETTING UPDATES - % COMPLETE 19 GETTING UPDATED ACTUAL WORK 21 Page 1
3 Contents Page 2
4 Chapter 1: Overview Chapter 1: Overview Team members who do not need to alter project plans use Seavus Project Viewer to view the tasks they have been assigned. But wouldn't it be better to know the progress status of each task in real time as well? Seavus Project Viewer is the only viewer for Microsoft Project that provides a collaborative environment for project teams without server installation. The process of sharing is very simple: The project manager creates a project plan in Microsoft Project and uploads it on a shared location Team members open the project plan with Seavus Project Viewer and report task progress or assignment progress (% Completed, % Work Complete or Actual Work). The project manager then opens the project plan and accepts or rejects submitted task updates. Create Project Update Task or Assignment Accept/Reject Page 3
5 Chapter 1: Overview With this very simple task update process, teams can easily introduce a collaborative project environment where they can: Get real-time project status Continually evaluate team's performance Build knowledge for future projects The project s categories that are available for updating are presented on the diagram below: Task Update Feature Assignment Update Task Update Custom Text Update Resource Usage view Task Usage view Gantt Chart views Gantt Chart views Assignment update Team Members can update the assignments in the project plan using the Resource Usage or Task Usage view. Project Manager will view this updates using the Get Updates functionality in Microsoft Project that is already developed, accept or reject them and the project plan will be updated. Task Update Team Members can update the assignments in the project plan using the Gantt Chart view and the fields that are prepared for this purpose. Project Manager will view this updates using the Show Updates in Gantt Chart functionality in the Gantt Chart tablet that will be developed. Page 4
6 Chapter 2: Task Update Toolbar in MS Project Chapter 2: Task Update Toolbar in MS Project In this section you will learn: Make project collaborative Receive project s updates Introduction In order to be able to use Task Update option in your Microsoft Project, you need to have installed the Seavus Add-in for Microsoft Project - Seavus Project Viewer Task Update options in the Seavus Add-in for Microsoft Project toolbar is an option available to the Project Managers that enables them to: Enable collaboration on the Project file (.mpp) they have created To receive task updates from the Team members on their assigned tasks Accept, Reject the received task updates and update the.mpp file by applying the changes The.MPP file that will be collaborative must be saved on shared folder, accessible by both Project Manager and Team members. Both parties should have read/write privileges on the shared folder. Collaboration ribbon The collaboration ribbon in Microsoft Project contains commands for converting the project file into collaboration one, receive the updates from the project s teams and choose the updating method. The following actions are available: Page 5
7 Chapter 2: Task Update Toolbar in MS Project Feature Make collaborative Get Updates Options Help Description Makes the project plan collaborative for the team members, in order updated of the tasks or assignments to be inserted. Receives the updated that are inserted for the tasks or assignments in the project plan by the team members and other project participant. Opens up a dialog with configuration options for the application. In this dialog you can specify the updating method, custom field mapping and the process of receiving updated. Opens up the Contents menu of the context help, which lets you to navigate the entire help through the available categories organized in hierarchy Select the Updating Method The first thins that should be done when working with is to choose the updating method. Since every company has its own policies regarding projects update, Task Update add-in contains the following update options: Update of % Complete Update of % Work Complete Update of Actual Work Update of Actual Start Update of Actual Finish Update of Actual Duration Map Custom fields Mapping the custom fields in Microsoft Project is necessary in order to choose which fields will be presenting the values that are reported in Seavus Project Viewer. The mapping process is performed in two cases: When starting to work with the Task Update method for first time (the custom fields are not defined); When the once defined fields have being put in use (containing data for the project plan). To map the field for presenting the reported values follow the next procedure: 1. Select the Options feature; Page 6
8 Chapter 2: Task Update Toolbar in MS Project 2. In the Mapping tab, select the radio button before the Project s field that is used for task reporting: a. In case you are working with the % Complete field, clicks the radio button in front of % Complete b. Select the Project s custom field that will present the Reported % Complete (type: Number) c. Select the Project s custom field that will present the Difference % Complete (type: Number) d. Select the Project s custom field that will present the Graphical Indicator (type: Text) 3. Click on the Ok button The look of the Map tab within the Options dialog is presented on Figure 1 Figure 1. Map tab in Options dialog Note: The same procedure is for % Work Complete, Actual Work, Actual Start, Actual Finish and Actual Duration fields. Page 7
9 Chapter 2: Task Update Toolbar in MS Project Make your project Collaborative First step that you need to do is to enable collaboration on your project file stored in shared folder. To do that, open your file with Microsoft Project that has previously installed Seavus Add-in for Microsoft Project with Task Update options and simply click on the Enable Collaboration icon in the toolbar in case for Microsoft Project 2007 or Make Collaborative feature in the Add-Ins ribbon in case for Microsoft Project 2010, as it is presented on Figure 2. Figure 2. Before making the project plan collaborative, project manager can select the updating method, i.e. which project categories will be updated: Tasks Assignments The updating method can be selected in the lower part of the Make Project Collaborative dialog, as it is presented on Figure 3. For that purpose, perform the following steps: 1. Select the project plan that will be 2. From the Collaborative column select the Yes for introducing the project plan into collaborative mode. 3. From the Reporting mode column select the Page 8
10 Chapter 2: Task Update Toolbar in MS Project Figure 3. Make project collaborative By enabling collaboration on your project file, your Team members that have installed Seavus Project Viewer with Task Update feature will be able to send updates about actual work they spent on the specific tasks or % Complete of the task. Constraints using the Make Project Collaborative feature During the process of making project collaborative, Microsoft Project will pop-up message for saving the project file(s). Do not use this saving process if you want to: 1. Change the Microsoft Project version when working with Master Project (example: Master project is created in Microsoft Project 2007 and you want to re-save in version When working with password protected files. Processing received Task Updates The Project Manager can view all newly received and untreated task updates from all Team members by clicking on the Get Updates icon in the toolbar menu for in case for Microsoft Project 2007/2003 or by clicking on the same action in the Add-Ins ribbon in case for Microsoft Project Page 9
11 Chapter 2: Task Update Toolbar in MS Project Receiving Assignment Updates The Project Manager has several filtering options to get only the assignment updates that meet the desired criteria. The project manager can filter by: Project name Task name Resource name The updates that will be accepted by the project manager, will be colored green, and those assignments that are rejected will be colored red. Figure 4. Get Assignment Updates window in MS Project Project manager can insert comments regarding the accepted and rejected assignments and these comments will be available for reading to the team members. Receiving Task Updates Updating the project plan can be done using one of the following techniques: Page 10
12 Chapter 2: Task Update Toolbar in MS Project Using the Get Updated dialog, or Directly to be inserted in the Gantt table, and inside the Gantt chart project manager will perform the necessary changes Receive Updates via dialog When working with the Task Update method, the Project Manager has several filtering options to get only the updates that meet the desired criteria. The project manager can filter by: Project name Task name The updates that will be accepted, will be colored green, and those assignments that are rejected will be colored red. The look of the Task Updating dialog is presented on Figure 5. Figure 5. Get Task Updates window in MS Project Page 11
13 Chapter 2: Task Update Toolbar in MS Project View Updates in Gantt table When working with the second technique, project manager will view 3 columns in the Entry table in the Gantt Chart: Reported field; Difference field; Graphical Indicators. Reported field contains the values that are reported by the team members using the Task Update feature in Seavus Project Viewer Reported field Difference gives numerical difference between the Reported value and the value from the project plan Graphical Indicators gives visual presentation of the difference between the Reported value and the value from the project plan After clicking on the Get Updated feature, the updates will be placed directly in the Gantt table. Import Updates Import Updates feature, located in the Import Updated tab from the Options windows, allows you to buy-pass the Get Update dialog and directly import in Gantt table. When the check-box in front of the feature is selected, the updated will be presented in the Get Updated dialog, where project manager can decide which updates will be accepted and which one will be rejected. The look of the Map tab within the Options dialog is presented on Figure 6 Page 12
14 Chapter 2: Task Update Toolbar in MS Project Figure 6. Import Updated tab Custom Text Fields Mapping Beside updating % Complete, % Work Complete, Actual Start, Actual Finish, Actual Work and Actual Duration, Project Manager can set three additional fields that can be used for communication with the working team. These fields, from Text type can contain any type of information that can be useful for the project manager to get the real overview of the project s progress. Project Manager can ask from the team members, beside the values for the % Complete for every task, to enter the status for the tasks that they are working on. The workflow for using the Custom Text fields together with updating task s progress in Gantt Chart view will be: 1. Project Manager wants to know the status and the % Completeness of project s tasks 2. From the Mapping tab, the % Complete radio button is selected and the following fields are mapped: a. Text 1 for Reported field Page 13
15 Chapter 2: Task Update Toolbar in MS Project b. Text 2 for Difference field c. Text 3 for Graphical indicator 3. From the Custom Text Fields Mapping tab, the following field is mapped: a. Text 4 for Status field 4. When opening the project plan into Seavus Project Viewer, Team members for % Complete will enter numbers, while in the Custom Text fields they will enter the status of the task. Example: On time, Late The look of the Map tab within the Options dialog is presented on Figure 7. Figure 7.Custom Text fields mapping tab Page 14
16 Chapter 3: Example for making project plan collaborative Chapter 3: Example for making project plan collaborative In this section you will learn: How to make project plan collaborative Introduction In this chapter, the process of making project plan collaborative will be presented. Create Project plan First step in this example is to create project plan. In order, to better explain the key steps and the entire process of assign-update-approve, the project plan will be small plan with 15 tasks and 8 resources. The look of the example project plan is presented on the image below: Page 15
17 Chapter 3: Example for making project plan collaborative Figure 8. Project plan Make Project Plan collaborative The next step is to make the project plan collaborative, which can be done in several steps: 1. Go to the Add-ins ribbon in Microsoft Project and click on the Make Collaborative feature. 2. Click on the cell in the Collaborative column. The value will be changed from No into Yes. This means that team members can report updates for project s assignments or tasks. 3. Since team members will update % Complete of the assignments, the Reporting mode will be set as Task Report Page 16
18 Chapter 3: Example for making project plan collaborative 4. One the collaboration and reporting mode are set, you can click on the Ok button. Select the Update method Once the project plan is collaborative, the next step is to choose the update method. As mentioned in the beginning of this section, all team members will update % Complete of the tasks. The presented process is the same for any update method, no matter whether the project manager chooses to update % Complete or Actual Work of the tasks. The process is as follow: 1. In the Ad-ins ribbon click on the Options button. 2. In the Task Update Options select the Mapping tab 3. In the Map field section select the radio button in front of the appropriate updating method. In this example, the % Complete radio button will be selected. 4. In the Reported field drop-down list select the Microsoft Project s field that will contain updated from Seavus Project Viewer. In this example, the Text 1 will be selected. 5. In the Difference field drop-down list select the Microsoft Project s field that will contain updated from Seavus Project Viewer. In this example, the Text 2 will be selected. Page 17
19 Chapter 3: Example for making project plan collaborative 6. In the Graphical Indicator drop-down list select the Microsoft Project s field that will contain updated from Seavus Project Viewer. In this example, the Text 3 will be selected. Distribute the project plan After performing all these steps, you can place the project file on shared location where all team member have access. Common practice in the project management is to receive the updates at the end of the business day. Page 18
20 Chapter 4: Example for receiving updates Chapter 4: Example for receiving updates In this section you will learn: Make project collaborative Receive project s updates Introduction In order to receive the updates using the Task Update option in your Microsoft Project, your team members must insert updates for their tasks or assignments. The updates can be accepted or rejected, depends from the manager s opinion and the real status of the project tasks. Getting updates - % Complete Once the updates are inserted by the team members, project managers can upload the tasks or assignment progress and analyze the current status of the project. For that purpose, follow the next instructions: 1. Open the project plan that should be updated 2. From the Add-ins ribbon click on the Get Updates feature 3. In the newly opened dialog select which tasks updates will be accepted. a. In case project manager accepts the updates than the task will be colored green. b. In case the updated is rejected, then it will be colored red. Page 19
21 Chapter 4: Example for receiving updates 4. The accepted and rejected tasks are presented on the image below. 5. After accepting and rejecting the updates and hitting the Ok button, the application will display notification window, where the project manager has to approve the continuity of the information flow. Page 20
22 Chapter 4: Example for receiving updates After these steps, the project plan will be updated with the latest information from the team members, it can be undertaken for financial or scheduling analysis, while the updating cycle continues with the same processes that are described above. Note: The process of receiving task updates where team members updates % Work Complete, Actual Start, Actual Finish and Actual Duration is similar with the presented one. Getting updated Actual Work Getting updates for the Actual Work, is very similar to the process of updating the % Complete method. The only difference is in the Get Updates dialog. For that purpose, follow the next instructions: 1. Open the project plan that should be updated 2. From the Add-ins ribbon click on the Get Updates feature 3. In the newly opened dialog select which assignment updates will be accepted. a. In case project manager accepts the updates than the assignment will be colored green. b. In case the updated is rejected, then it will be colored red. The accepted and rejected tasks are presented on the image below. Page 21
23 Chapter 4: Example for receiving updates 4. After accepting and rejecting the updates and hitting the Ok button, the application will display notification window, where the project manager has to approve the continuity of the information flow. After these steps, the project plan will be updated with the latest information from the team members, it can be undertaken for financial or scheduling analysis, while the updating cycle continues with the same processes that are described above. Page 22
24 Chapter 4: Example for receiving updates Page 23
25 Chapter 4: Example for receiving updates Page 24
Microsoft SharePoint 2010 End User Quick Reference Card
Microsoft SharePoint 2010 End User Quick Reference Card Microsoft SharePoint 2010 brings together the people, documents, information, and ideas of the University into a customizable workspace where everyone
How to install and use the File Sharing Outlook Plugin
How to install and use the File Sharing Outlook Plugin Thank you for purchasing Green House Data File Sharing. This guide will show you how to install and configure the Outlook Plugin on your desktop.
1. Introduction. P2O is automatically loaded when you open Ms Project (2010 or 2013). The add-in can be found under the M5 Tools menu. 2.
1. Introduction Project 2 Outlook (P2O) will help Microsoft Project users to improve project communication by exporting MS Project tasks and information to MS Outlook Task or Appointments. Users don t
How To Use Ms Powerbook 2.5.2.2 On A Pc Or Mac Or Macbook 2 (Windows)
Overview 1 Content Overview Open a project file Create a new project plan Track progress View and print reports Share a project plan Conclusion 2 Overview With you can: create new/update project plan open
Outlook Profile Setup Guide Exchange 2010 Quick Start and Detailed Instructions
HOSTING Administrator Control Panel / Quick Reference Guide Page 1 of 9 Outlook Profile Setup Guide Exchange 2010 Quick Start and Detailed Instructions Exchange 2010 Outlook Profile Setup Page 2 of 9 Exchange
Excel 2013 What s New. Introduction. Modified Backstage View. Viewing the Backstage. Process Summary Introduction. Modified Backstage View
Excel 03 What s New Introduction Microsoft Excel 03 has undergone some slight user interface (UI) enhancements while still keeping a similar look and feel to Microsoft Excel 00. In this self-help document,
Laboratory 1 Initiating a Project
Laboratory 1 Initiating a Project Outline What is a project? What is project management? Initiating a project. Getting Starting with Project 2007? What Is a Project? A project is an activity that has a
Table of Contents. 1. Content Approval...1 EVALUATION COPY
Table of Contents Table of Contents 1. Content Approval...1 Enabling Content Approval...1 Content Approval Workflows...4 Exercise 1: Enabling and Using SharePoint Content Approval...9 Exercise 2: Enabling
IST 195 Lab 12 Introduction to Microsoft Project
IST 195 Lab 12 Introduction to Microsoft Project Microsoft Project is a project management software program developed and sold by Microsoft which is designed to assist project managers in developing plans,
Microsoft Project Server 2010 Project Manager s Guide for Project Web App
Microsoft Project Server 2010 Project Manager s Guide for Project Web App Copyright This document is provided as-is. Information and views expressed in this document, including URL and other Internet Web
Contents 1 Overview 2 Steps to run an Excel Add-In Setup: 3 Add-Ins 4 LOGIN 5 SEND SMS 5.1 Send Text or Flash Sms 5.2 Select Range 5.
Contents 1 Overview 2 Steps to run an Excel Add-In Setup: 3 Add-Ins 4 LOGIN 5 SEND SMS 5.1 Send Text or Flash Sms 5.2 Select Range 5.3 Selected Range Preview List 5.4 Scheduling of Messages 5.5 Scheduled
Learn how to create web enabled (browser) forms in InfoPath 2013 and publish them in SharePoint 2013. InfoPath 2013 Web Enabled (Browser) forms
Learn how to create web enabled (browser) forms in InfoPath 2013 and publish them in SharePoint 2013. InfoPath 2013 Web Enabled (Browser) forms InfoPath 2013 Web Enabled (Browser) forms Creating Web Enabled
UF Health SharePoint 2010 Introduction to Content Administration
UF Health SharePoint 2010 Introduction to Content Administration Email: [email protected] Web Page: http://training.health.ufl.edu Last Updated 2/7/2014 Introduction to SharePoint 2010 2.0 Hours
Lesson 6 - Managing Resources in a Project Plan
Lesson 6 - Managing Resources in a Project Plan Lesson Objectives In this lesson, you will manage resources in a project plan. You will: Create a resource calendar. Assign resources to tasks. Assign additional
Bradley University College of Liberal Arts and Sciences Department of Computer Sciences and Information Systems
Bradley University College of Liberal Arts and Sciences Department of Computer Sciences and Information Systems Computer Lab # 1 Time Management (with Microsoft Project 2007) Lab Manual (with master s
As your financial institution completes its system conversion, you
QuickBooks Business Accounting Software 2007 2009 for Windows Account Conversion Instructions Converting from Direct Connect to Web Connect As your financial institution completes its system conversion,
SharePoint Online Quick Reference
SharePoint Online Quick Reference www.messageops.com What is SharePoint? Microsoft SharePoint is a collaboration tool utilized by enterprises and small-medium businesses as a means for productivity solutions.
1. Click the Site Actions dropdown arrow and select Show Page Editing Toolbar. 2. Click Edit Page to begin changing the page layout
SharePoint Tools Create a Custom List Show Page Editing Tool Bar (If your Editing toolbar is not displaying) 1. Click the Site Actions dropdown arrow and select Show Page Editing Toolbar. 2. Click Edit
Project Management: Intermediate Microsoft Project 2010
Project Management: Intermediate Microsoft Project 2010 This document includes instructions for managing resources, updating project plans, and designing visual reports. Managing Resources in a Project
A. BACK UP YOUR CURRENT DATA. QuickBooks Business Accounting Software 2006 2009 for Windows Account Conversion Instructions
QuickBooks Business Accounting Software 2006 2009 for Windows Account Conversion Instructions As your financial institution completes its system conversion, you will need to modify your QuickBooks settings
MICROSOFT OUTLOOK 2011 READ, SEARCH AND PRINT E-MAILS
MICROSOFT OUTLOOK 2011 READ, SEARCH AND PRINT E-MAILS Lasted Edited: 2012-07-10 1 Find the Inbox... 3 Check for New Mail... 4 Manually check for new messages... 4 Change new incoming e-mail schedule options...
Word 2010: Mail Merge to Email with Attachments
Word 2010: Mail Merge to Email with Attachments Table of Contents TO SEE THE SECTION FOR MACROS, YOU MUST TURN ON THE DEVELOPER TAB:... 2 SET REFERENCE IN VISUAL BASIC:... 2 CREATE THE MACRO TO USE WITHIN
SharePoint List Filter Favorites Installation Instruction
SharePoint List Filter Favorites Installation Instruction System Requirements Microsoft Windows SharePoint Services v3 or Microsoft Office SharePoint Server 2007. License Management Click link in Organize
Power Monitoring Expert 7.2
Power Monitoring Expert 7.2 PDF version of the Web Applications online help 7ENxx-00xx-00 07/2013 PDF version of the Web Applications online help Safety information Safety information Important information
Seavus Project Viewer Product Overview
Seavus Project Viewer Product Overview Seavus Project Viewer is the stand-alone, best enterprise, low-cost software for viewing Microsoft Project Plans. It reads the native.mpp file format and does not
Microsoft Outlook Tips & Tricks
Microsoft Outlook Tips & Tricks Columbia College Technology Services Table of Contents Creating an email signature Page 1 Handling attachments Page 1 Sending an attachment Opening an attachment Page 2
MS Project Tutorial for Senior Design Using Microsoft Project to manage projects
MS Project Tutorial for Senior Design Using Microsoft Project to manage projects Overview: Project management is an important part of the senior design process. For the most part, teams manage projects
BSDI Advanced Fitness & Wellness Software
BSDI Advanced Fitness & Wellness Software 6 Kellie Ct. Califon, NJ 07830 http://www.bsdi.cc SOFTWARE BACKUP/RESTORE INSTRUCTION SHEET This document will outline the steps necessary to take configure the
File Management Utility User Guide
File Management Utility User Guide Legal Notes Unauthorized reproduction of all or part of this guide is prohibited. The information in this guide is subject to change without notice. We cannot be held
Advanced Outlook Tutorials
Advanced Outlook Tutorials Filtering: Create a filter to send email directly to a specific folder from a certain sender: 1. Right click on the sender s email. 2. Choose Rules. 3. Click on Create Rule.
Module A2 Item Activities, Gantt Chart and Utilization Sheet
Module A2 Item Activities, Gantt Chart and Utilization Sheet A2.1 Project item activities A2.2 Gantt chart A2.3 Utilization sheet 1 Module 1. Project item activities, Gantt Chart & Utilization Sheet Contents...
Title: SharePoint Advanced Training
416 Agriculture Hall Michigan State University 517-355- 3776 http://support.anr.msu.edu [email protected] Title: SharePoint Advanced Training Document No. - 106 Revision Date - 10/2013 Revision No. -
INTERCALL ONLINE Administrator Invoices User Guide
INTERCALL ONLINE Administrator Invoices User Guide Access your invoices online, set up new billing accounts and view or edit existing billing accounts. With InterCall Online, also monitor and analyze your
ProperSync 1.3 User Manual. Rev 1.2
ProperSync 1.3 User Manual Rev 1.2 Contents Overview of ProperSync... 3 What is ProperSync... 3 What s new in ProperSync 1.3... 3 Getting Started... 4 Installing ProperSync... 4 Activating ProperSync...
Introduction to Microsoft Project 2010
Introduction to Microsoft Project 2010 This document provides an introduction in using Microsoft Project 2010. Microsoft Project is a project management application that contains a set of tools to help
Smart Sync. Computer Classroom Management Software. What is SMART Sync? Table of Contents
Smart Sync Computer Classroom Management Software What is SMART Sync? SMART Sync software helps instructors manage the computers in their classroom. SMART Sync keeps a student engaged and focused, and
Release Document Version: 1.4-2013-05-30. User Guide: SAP BusinessObjects Analysis, edition for Microsoft Office
Release Document Version: 1.4-2013-05-30 User Guide: SAP BusinessObjects Analysis, edition for Microsoft Office Table of Contents 1 About this guide....6 1.1 Who should read this guide?....6 1.2 User profiles....6
Intellect Platform - Tables and Templates Basic Document Management System - A101
Intellect Platform - Tables and Templates Basic Document Management System - A101 Interneer, Inc. 4/12/2010 Created by Erika Keresztyen 2 Tables and Templates - A101 - Basic Document Management System
Excel Reports User Guide
Excel Reports User Guide Copyright 2000-2006, E-Z Data, Inc. All Rights Reserved. No part of this documentation may be copied, reproduced, or translated in any form without the prior written consent of
User s Guide. Version 2.1
Content Management System User s Guide Version 2.1 Page 1 of 51 OVERVIEW CMS organizes all content in a tree hierarchy similar to folder structure in your computer. The structure is typically predefined
Working with Calendars
Working with Calendars Add an Appointment or Meeting to a Calendar You can add appointments and meetings to your calendar. Appointments are those items that you schedule only for yourself. For example,
UF Health SharePoint 2010 Document Libraries
UF Health SharePoint 2010 Document Libraries Email: [email protected] Web Page: http://training.health.ufl.edu Last Updated 2/7/2014 SharePoint 2010 Document Libraries 1.5 Hours 1.0 Shared Network
SENDING EMAILS & MESSAGES TO GROUPS
SENDING EMAILS & MESSAGES TO GROUPS Table of Contents What is the Difference between Emails and Selltis Messaging?... 3 Configuring your Email Settings... 4 Sending Emails to Groups Option A: Tasks...
Microsoft Outlook 2010. Reference Guide for Lotus Notes Users
Microsoft Outlook 2010 Reference Guide for Lotus Notes Users ContentsWelcome to Office Outlook 2010... 2 Mail... 3 Viewing Messages... 4 Working with Messages... 7 Responding to Messages... 11 Organizing
Scheduling Document Creation
Scheduling Document Creation What is a Schedule in epm? Schedules The epm Schedule application is an integral part of the Portfolio Management suite of applications. Start and end dates for each summary
State of Indiana Content Management System. Training Manual Version 2.0. Developed by
State of Indiana Content Management System Training Manual Version 2.0 Developed by Table of Contents Getting Started... 4 Logging In... 5 RedDot Menu... 6 Selecting a Project... 7 Start Page... 8 Creating
Editor Manual for SharePoint Version 1. 21 December 2005
Editor Manual for SharePoint Version 1 21 December 2005 ii Table of Contents PREFACE... 1 WORKFLOW... 2 USER ROLES... 3 MANAGING DOCUMENT... 4 UPLOADING DOCUMENTS... 4 NEW DOCUMENT... 6 EDIT IN DATASHEET...
Advanced Outlook 2010 Training Manual
Advanced Outlook 2010 Training Manual 1 2 Contents Using the Calendar... 5 Creating Additional Calendars... 5 Viewing Calendars Side-by-Side or Overlaid... 7 Printing option for the Calendar... 9 Adding
Windows XP Exchange Client Installation Instructions
WINDOWS XP with Outlook 2003 or Outlook 2007 1. Click the Start button and select Control Panel: 2. If your control panel looks like this: Click Switch to Classic View. 3. Double click Mail. 4. Click show
Unified Reporting Tool: Troubleshooting Guide
Unified Reporting Tool: Troubleshooting Guide This appendix identifies procedures and best practices for the most frequently-encountered challenges and questions regarding the 2015 Unified THIRA/SPR Reporting
Teacher References archived classes and resources
Archived Classes At the end of each school year, the past year s academic classes are archived, meaning they re still kept in finalsite, but are put in an inactive state and are not accessible by students.
Implementing Mission Control in Microsoft Outlook 2010
Implementing Mission Control in Microsoft Outlook 2010 How to Setup the Calendar of Occasions, Not Doing Now List, Never Doing Now List, Agendas and the Vivid Display In Outlook 2010 Handout Version 3
Department of Information Technology. Microsoft Outlook 2013. Outlook 101 Basic Functions
Department of Information Technology Microsoft Outlook 2013 Outlook 101 Basic Functions August 2013 Outlook 101_Basic Functions070713.doc Outlook 101: Basic Functions Page 2 Table of Contents Table of
Updating Your Applied Account
For Applied System Administrators Updating Your Applied Account, Assigning Chubb Codes, Configuring Users, Activating New Users To start using Transformation Station to conduct Chubb policy inquiries directly
Creating a Patch Management Dashboard with IT Analytics Hands-On Lab
Creating a Patch Management Dashboard with IT Analytics Hands-On Lab Description This lab provides a hands-on overview of the IT Analytics Solution. Students will learn how to browse cubes and configure
Affiliated Provider Billing/Coding
Affiliated Provider Billing/Coding ED BILLING USING FIRSTNET Table of Contents Affiliated Provider ED Billing...2 icentra FirstNet...2 Accessing FirstNet...2 To access FirstNet:...2 Checking In as a Provider...2
Module One: Getting Started... 6. Opening Outlook... 6. Setting Up Outlook for the First Time... 7. Understanding the Interface...
2 CONTENTS Module One: Getting Started... 6 Opening Outlook... 6 Setting Up Outlook for the First Time... 7 Understanding the Interface...12 Using Backstage View...14 Viewing Your Inbox...15 Closing Outlook...17
Module A2 Item Activities, Gantt Chart and Utilization Sheet. A2.1 Project item activities A2.2 Gantt chart A2.3 Utilization sheet
Module A2 Item Activities, Gantt Chart and Utilization Sheet A2.1 Project item activities A2.2 Gantt chart A2.3 Utilization sheet 1 Assistance PSA: Advanced Functionalities Welcome to the Advanced Functionalities
How To Create A Powerpoint Intelligence Report In A Pivot Table In A Powerpoints.Com
Sage 500 ERP Intelligence Reporting Getting Started Guide 27.11.2012 Table of Contents 1.0 Getting started 3 2.0 Managing your reports 10 3.0 Defining report properties 18 4.0 Creating a simple PivotTable
EXCEL 2007. Using Excel for Data Query & Management. Information Technology. MS Office Excel 2007 Users Guide. IT Training & Development
Information Technology MS Office Excel 2007 Users Guide EXCEL 2007 Using Excel for Data Query & Management IT Training & Development (818) 677-1700 [email protected] http://www.csun.edu/training TABLE
Viewing and Troubleshooting Perfmon Logs
CHAPTER 7 To view perfmon logs, you can download the logs or view them locally. This chapter contains information on the following topics: Viewing Perfmon Log Files, page 7-1 Working with Troubleshooting
Outlook Tips & Tricks. Training For Current & New Employees
Outlook Tips & Tricks Training For Current & New Employees The workshop will help build the necessary skills needed to begin using Microsoft Outlook 2010. The participant will learn how to create e-mail
Corporate Telephony Toolbar User Guide
Corporate Telephony Toolbar User Guide 1 Table of Contents 1 Introduction...6 1.1 About Corporate Telephony Toolbar... 6 1.2 About This Guide... 6 1.3 Accessing The Toolbar... 6 1.4 First Time Login...
Create an Excel BI report and share on SharePoint 2013
2013 Create an Excel BI report and share on SharePoint 2013 Hands-On Lab Lab Manual This document is provided as-is. Information and views expressed in this document, including URL and other Internet Web
Microsoft Office System Tip Sheet
Experience the 2007 Microsoft Office System The 2007 Microsoft Office system includes programs, servers, services, and solutions designed to work together to help you succeed. New features in the 2007
Microsoft Office System Tip Sheet
The 2007 Microsoft Office System The 2007 Microsoft Office system is a complete set of desktop and server software that can help streamline the way you and your people do business. This latest release
Adobe Acrobat 9 Pro Accessibility Guide: Creating Accessible PDF from Microsoft Word
Adobe Acrobat 9 Pro Accessibility Guide: Creating Accessible PDF from Microsoft Word Adobe, the Adobe logo, Acrobat, Acrobat Connect, the Adobe PDF logo, Creative Suite, LiveCycle, and Reader are either
Email Basics. a. Click the arrow to the right of the Options button, and then click Bcc.
Email Basics Add CC or BCC You can display the Bcc box in all new messages that you compose. In a new message, do one of the following: 1. If Microsoft Word is your e-mail editor a. Click the arrow to
Editing your Website User Guide
User Guide Adding content to your Website To add or replace content on your website you will need to log in to your Content Management System (Joomla) using your username and password. If you do not already
Managing Documents in the Citrix XenApp Remote Desktop
Introduction Managing Documents in the Citrix XenApp Remote Desktop What is a Citrix XenApp Remote Desktop? It is a virtualized instance of MS Windows with only enough software to run TAS in a controlled
Working with SQL Server Integration Services
SQL Server Integration Services (SSIS) is a set of tools that let you transfer data to and from SQL Server 2005. In this lab, you ll work with the SQL Server Business Intelligence Development Studio to
MS Outlook 2002/2003. V1.0 BullsEye Telecom Email
IMAP Settings Manual Our application allows you to access your email in many different ways. For those of you who do not wish to use the Webmail interface, you may also manage your email and custom folder
Export the address book from the Blackberry handheld to MS Outlook 2003, using the synchronize utility in Blackberry Desktop Manager.
Export the address book from the Blackberry handheld to MS Outlook 2003, using the synchronize utility in Blackberry Desktop Manager. Revised 2/25/07 Creating a New Contacts Folder in Outlook Open Outlook
User Guide. Opening secure email from the State of Oregon Viewing birth certificate edits reports in MS Excel
User Guide Opening secure email from the State of Oregon Viewing birth certificate edits reports in MS Excel Birth Certifier Edition Last Revised: August, 0 PUBLIC HEALTH DIVISION Center for Public Health
Microsoft Access 2010 handout
Microsoft Access 2010 handout Access 2010 is a relational database program you can use to create and manage large quantities of data. You can use Access to manage anything from a home inventory to a giant
Workflow Notifications
Workflow One of the components of workflow in PeopleSoft/NUFinancials is the ability to send email notifying users when there is an item in their Approval Inbox. Depending upon the number of emails received,
Microsoft Project 2013
CALIFORNIA STATE UNIVERSITY, LOS ANGELES INFORMATION TECHNOLOGY SERVICES Microsoft Project 2013 Summer 2014, Version 1.0 Table of Contents Introduction...2 Overview of the User Interface...2 Creating a
Setting up Sharp MX-Color Imagers for Inbound Fax Routing to Email or Network Folder
Setting up Sharp MX-Color Imagers for Inbound Fax Routing to Email or Network Folder MX-2300, MX-2600, MX-2700, MX-3100, MX-3501, MX-4501, MX-5500, MX-6200, MX-6201, MX-7000, MX-7001, *MX-M850, *MX-M950,
Custom Reporting System User Guide
Citibank Custom Reporting System User Guide April 2012 Version 8.1.1 Transaction Services Citibank Custom Reporting System User Guide Table of Contents Table of Contents User Guide Overview...2 Subscribe
OmniTouch 8400 Instant Communications Suite. My Instant Communicator for Microsoft Outlook User guide. Release 6.7
OmniTouch 8400 Instant Communications Suite My Instant Communicator for Microsoft Outlook User guide Release 6.7 8AL 90243USAD ed01 Sept 2012 Table of contents 1 MY INSTANT COMMUNICATOR FOR MICROSOFT OUTLOOK...
Table of Contents. I. Using ical... pg. 1. Calendar views and formats..pg. 1 Navigating the calendar.pg. 3 Searching the calendar..pg.
ical Manual Table of Contents I. Using ical... pg. 1 Calendar views and formats..pg. 1 Navigating the calendar.pg. 3 Searching the calendar..pg. 4 II. Administering the Calendar. pg. 5 Display options.pg.
NETWRIX EVENT LOG MANAGER
NETWRIX EVENT LOG MANAGER ADMINISTRATOR S GUIDE Product Version: 4.0 July/2012. Legal Notice The information in this publication is furnished for information use only, and does not constitute a commitment
SHAREPOINT 2010 FOUNDATION FOR END USERS
SHAREPOINT 2010 FOUNDATION FOR END USERS WWP Training Limited Page i SharePoint Foundation 2010 for End Users Fundamentals of SharePoint... 6 Accessing SharePoint Foundation 2010... 6 Logging in to your
MS WORD 2007 (PC) Macros and Track Changes Please note the latest Macintosh version of MS Word does not have Macros.
MS WORD 2007 (PC) Macros and Track Changes Please note the latest Macintosh version of MS Word does not have Macros. Record a macro 1. On the Developer tab, in the Code group, click Record Macro. 2. In
WebSphere Business Monitor V7.0 Business space dashboards
Copyright IBM Corporation 2010 All rights reserved IBM WEBSPHERE BUSINESS MONITOR 7.0 LAB EXERCISE WebSphere Business Monitor V7.0 What this exercise is about... 2 Lab requirements... 2 What you should
Microsoft Excel 2013: Using a Data Entry Form
Microsoft Excel 2013: Using a Data Entry Form Using Excel's built in data entry form is a quick and easy way to enter data into an Excel database. Using the form allows you to: start a new database table
AvePoint Tags 1.1 for Microsoft Dynamics CRM. Installation and Configuration Guide
AvePoint Tags 1.1 for Microsoft Dynamics CRM Installation and Configuration Guide Revision G Issued August 2014 Table of Contents About AvePoint Tags for Microsoft Dynamics CRM... 3 Required Permissions...
Orientation Course - Lab Manual
Orientation Course - Lab Manual Using the Virtual Managed Workplace site for the lab exercises Your instructor will provide the following information before the first lab exercise begins: Your numerical
How to use Microsoft Project? Basic Training to Help You during the BYI challenge
How to use Microsoft Project? Basic Training to Help You during the BYI challenge Table of Contents I. Main Concepts 1. Overview of Microsoft Project 2. Explanation of the main concepts II. How to : Create
Seavus Group 2013. All rights reserved www.seavusprojectviewer.com
Table of Contents: I Microsoft Office 2013 Style... 1 II Microsoft SharePoint Integration... 1 II.1 Connect to the EPM environment... 2 II.2 Import project plans... 2 II.3 Import Master project plans...
OVERVIEW. Microsoft Project terms and definitions
PROJECT 2003 DISCLAIMER: This reference guide is meant for experienced Microsoft Project users. It provides a list of quick tips and shortcuts for familiar features. This guide does NOT replace training
What is My Teamwork? What s new in this release? MY TEAMWORK 5.0 QUICK START GUIDE
MY TEAMWORK 5.0 QUICK START GUIDE What is My Teamwork? My Teamwork is a converged communications solution that combines presence-aware instant messaging with the ability to make phone calls, conference
Exchange 2003 Mailboxes
Exchange 2003 Mailboxes Microsoft will stop supporting Exchange 2003 mailboxes in 2014 as it comes to the end of it s life. To maintain our levels of support and performance of all our customers, we will
Google Drive Create, Share and Edit Documents Online
Revision 3 (1-31-2014) Google Drive Create, Share and Edit Documents Online With Google Drive, you can easily create, share, and edit documents online. Here are a few specific things you can do: Convert
Chapter 15: Forms. User Guide. 1 P a g e
User Guide Chapter 15 Forms Engine 1 P a g e Table of Contents Introduction... 3 Form Building Basics... 4 1) About Form Templates... 4 2) About Form Instances... 4 Key Information... 4 Accessing the Form
Legal Notes. Regarding Trademarks. 2011 KYOCERA MITA Corporation
Legal Notes Unauthorized reproduction of all or part of this guide is prohibited. The information in this guide is subject to change without notice. We cannot be held liable for any problems arising from
Redtail Integration. Establishing the Redtail Connection. 1. From the Applications dropdown, choose Setup.
In this user guide, we will demonstrate how to integrate your Redtail service into the emoney platform. This will allow the Advisor to import and link clients currently in Redtail into emoney. Establishing
Protus Virtual Fax Send Fax Plug-in Installation and User Guide
Protus Virtual Fax Send Fax Plug-in Installation and User Guide Virtual Fax Send Fax Plug-in The Virtual Fax Send Fax Plug-in is an add-in for Microsoft Outlook that places a Send Fax button on the toolbar,