Quantity Take-off. Quantity Take-off



Similar documents
Quantity Takeoff. Dr. Ahmed Elyamany

CHAPTER 2 QUANTITY TAKE-OFF

L_All_Vocatinal_Ed_Construction. Sector: Construction. Sr. No Specialisation Page No 1 Construction and Building Technology 02.

RECOMMENDED MODEL AGREEMENTS BETWEEN HOUSING CONSUMERS AND HOME BUILDERS FOR THE CONSTRUCTION OF A HOME

PROJECT COST ESTIMATES & FEASIBILITIES

How to Estimate the Cost of Support of Excavation for Foundation Installation. CPE Candidate No May 15, 2013

Technical Notes 3B - Brick Masonry Section Properties May 1993

SECTION STORM DRAINAGE STRUCTURES. 1. Trench excavation, backfill, and compaction; Section

The unit costs are based on the trend line of the 3 low bids for the average quantity.

Repair and Remodeling Estimating Methods. 4th Edition. RSMeans

PROJECT TITLE : 2-STOREY RESIDENCE LOCATION : ALONG DAANG HARI,MOLINO.BACOOR,CAVITE OWNER : CUEVASVILLE REALTY

Elevating Your House. Introduction CHAPTER 5

ENGINEERED FOUNDATIONS. Department of Public Works Jeff Hill, PE

Materials. Estimating Steel. Players. Materials. Shop Drawings. Detailing Process. Standard shapes. Fabricated members, Built-up sections

Technical Assignment 2 TABLE OF CONTENTS

SECTION REMOVAL OR ABANDONMENT OF EXISTING UTILITIES AND UNDERGROUND STRUCTURES. 1. Trench excavation, backfill, and compaction; Section

Overview. Map of the Arabic Languagge. Some tips. Need to over-learn to reach a stage of unconscious competence. Recap Parts of Speech

TABLE OF CONTENTS. Manhole, Frame, and Cover Installation (includes Drop Manhole) Additional Manhole Depth

Facility Summary. Facility Condition Summary. Seattle School District David T. Denny International Infrastructure. Facility Components

FY08 SEWER POINT REPAIRS BID TABULATION

Requirements for Building Application Submission

TABLE OF CONTENTS. INTRODUCTION... 5 Advance Concrete... 5 Where to find information?... 6 INSTALLATION... 7 STARTING ADVANCE CONCRETE...

The Task. for. PERI Construction-Exercise 2003

Attachment G-1: Pit Latrine Diagram. Fig E.1a: Pit Latrine. Fig E.1b: Plan View of Twin Pits

After reading this lesson you will be able to: 12.3 IMPORTANCE OF ROOF 12.4 TYPES OF ROOF IN A HOUSE

Lighthouse Engineering, L.L.C.

Chapter 16. Mensuration of Cylinder

ICRC WORK SPECIFICATIONS IRAQ WATER AND HABITAT

AIR RELEASE, CLEANOUT, AND SEWER MANHOLES

State of Illinois Department Of Transportation CONSTRUCTION INSPECTOR S CHECKLIST FOR STORM SEWERS

HIGH LEVEL SEISMIC UPGRADE COST ESTIMATE FOR CENTRE BLOCK, PARLIAMENT HILL

HOUSE BUILDING DIGEST

SIMULATION PRE-INSTALLATION GUIDELINES CONTRACTOR REQUIREMENTS FOR ROOM PREPARATION

PLUMBING MAINTENANCE WORK FOR TOILETS IN HEAD OFFICE, SUPPLYCO ESTIMATE

VOLUME AND SURFACE AREAS OF SOLIDS

LAYING BLOCK AND BRICK

How to build a Pizza Oven in 4 days

CONSTRUCTION SUMMARY OF THE PEREIRA HOUSE AT MADOL, VERNA GOA.

SECTION 55 PIPE FOR STORM DRAINS AND CULVERTS (FAA D-701)

FY11 Sanitary Sewer Main Rehab and Point Repair Bid Tabulation

Construction Laborer Dies after Falling off Collapsed Precast Concrete Floor Slab

QS 004 DEPARTMENT OF PUBLIC WORKS REPUBLIC OF SOUTH AFRICA BUILDING COST DATABASE

King Post Wall Information

Geotechnical Building Works (GBW) Submission Requirements

MHD BRIDGE SECTION WEIGHTED AVERAGE UNIT PRICES GUIDELINES FOR THE USE OF THE WEIGHTED AVERAGE UNIT PRICE TABULATION SHEETS

School Construction Authority Architecture & Engineering

Important Points: Timing: Timing Evaluation Methodology Example Immediate First announcement of building damage

COPYRIGHT. Dincel Construction System Pty Ltd

Excerpts from the Canadian National Building Code (NBC)

SAMPLE SCHEDULE OF VALUES APPLICATION & CERTIFICATE FOR PAYMENT

BUILDING OVER OR NEAR WATER & SEWER MAINS POLICY

High Strain Dynamic Load Testing of Drilled Shafts

Knock Down Rebuild. Building Process Building process - knock down rebuild 1

Project : CONSTRUCTION OF BUILDING(including electrical and plumbing works) FOR NATIONAL CENTRE FOR SUSTAINABLE COASTAL MANAGEMENT,CHENNAI

WORK SCOPE. Domains in which we work:

THE DEVELOPMENT OF DESIGN METHODS FOR REINFORCED AND UNREINFORCED MASONRY BASEMENT WALLS J.J. ROBERTS

When is a Permit Required? What Types of Permits are Required? The most common types of projects that require permits are:

Special Use Commercial Properties

Cost Guide MARKET SUMMARY OVERVIEW REPAIRS AND MAINTENANCE ELECTRICAL ROOFING & ROOF DRAINAGE (UP TO TWO STOREYS; FIXED TO EXISTING ROOF FRAME)

CONSOLIDATED EDISON CO. OF NEW YORK, INC. 4 IRVING PLACE NEW YORK, NY DISTRIBUTION ENGINEERING DEPARTMENT SUBSTATION & EQUIPMENT SECTION

If stepping is required, step at 180mm as seen in this picture.

The minimum reinforcement for the stem wall is the placement of:

Section 600 Incidental Construction

4. ANCHOR BOLTS AND STRAPS a. ½" anchor bolts shall be embedded 7" into concrete a maximum of 6' on center and 12" from corners and ends of plates.

SECTION TABLE OF CONTENTS. H Proposed Material, Product or Equipment Substitution Request

PROJECT SUMMARY. Scope of work details: (If phased construction, please see plan submittal guidelines.)

Seattle Public Schools Building Excellence IV Projects Under Construction

Gas Meter Clearances and Service Installation Requirements

2. What building projects are exempted? (permit not required)

Residential Deck Safety, Construction, and Repair

Residential Prototype III. Multi-Story. The Multi-Story. Your connection to ideas + answers. Prepared by: AISC Steel Solutions Center

Design and Build of Passenger Terminal Building North Extension At Macau International Airport (RFQ-198) Section 6 Bill of Quantities

SUCF PROJECT COST REPORTING GUIDE

Louisiana Administrative Code Title 51 Part XIII. Sewage Disposal

City of Treasure Island FEMA Cost Breakdown Worksheet For Substantial Improvement / Damage

TAX APPRAISAL DISTRICT OF BELL COUNTY STORES & COMMERCIAL IMPROVEMENT CLASSIFICATION GUIDE

LITITZ MUTUAL INSURANCE COMPANY 2 North Broad Street Lititz, Pennsylvania - MAIN OFFICE -

DIVISION 2 - SEWERAGE AND DRAINAGE SECTION STORM DRAIN SYSTEMS PART 1 - GENERAL

Buildings Construction Procurement Strategy

SEDIMENT/STORMWATER MANAGEMENT BASIN CONSTRUCTION CHECKLIST

Gas Meter Clearances and Service Installation Requirements

Detailing of Reinforcment in Concrete Structures

NAHB PRODUCT DEFINITION

EAST LYME HIGH SCHOOL

Baton Rouge Foundation Repair

CONTRACT PRICE ADJUSTMENT PROVISIONS (CPAP)

ARCHITECTURAL TECHNOLGY 4 ADVANCED CONSTRUCTION TECHNOLOGY BASEMENT CONSTRUCTION YEAR 3 SEMESTER 1 AIDAN WALSH R Lecturer: Jim Cahill

VOLUME V GUIDELINES FOR DESIGN CONSULTANT TABLE OF CONTENTS APPENDIX B: MASTER CONSTRUCTION SPECIFICATIONS AND PREPARATION GUIDE, DIVISIONS 0-10

Holz Choices & Specifications

WILDCAT CANYON ROAD SPECIFICATION NO SLIDE REPAIR BIDDER'S PROPOSAL (continued)

Aluminium systems profile selection

GEORGE J. CAMBOURAKIS, P.E., C. ENG. PRESIDENT & CHIEF STRUCTURAL ENGINEER

CHAPTER 5 ESTIMATING WORK ITEMS COSTS, IDIRECT COSTS, MARKUP AND CONTRACT PRICING

TYPICAL ESTIMATE OF A RAINWATER COLLECTION UNIT (110 mm / 150 mm dia PVC Pipelines)

STRUCTURAL CONCEPT FOR LIGHT GAUGE STEEL FRAME SYSTEM

BILL OF QUANTITY FOR THE WORK OF "REPAIRING OF CIVIL & PLUMBING WORKS INSIDE AND OUTSIDE OF THE WORKSHOP"

BUILDING PERMIT SPECIFICATIONS

MEMORANDUM. General: Foundation:

Transcription:

Quantity Take-off Required Information for Cost Estimate Detailed drawings Specifications Available site data Available resource data (labor, material & equipment) Government regulations Applicable owner requirements 07/11/2013 Emad Elbeltagi 2 1

Contract Documents Contract agreement General conditions Special conditions Bills of quantities Drawings Specifications Plans Others (Change orders, Warranty,..) 07/11/2013 Emad Elbeltagi 3 Quantity takeoff is necessary to perform a cost estimate The quantity of material in a project can be accurately determined from the drawing the estimator must make a complete and thorough job analysis The unit cost of different materials should be obtained from material suppliers Cost of delivery and wastage should be included The material quantity takeoff is extremely important for cost estimating 07/11/2013 Emad Elbeltagi 4 2

: Why? Owner perspective: Initial (preliminary) estimate of the project costs at the different stages of the project Preparing the BOQ as a requirement of the contract documents Estimating the work done for issuing the contractor payments 07/11/2013 Emad Elbeltagi 5 : Why? Contractor perspective: Pricing different work items Identifying the needed resources (Labor, Equipment, etc.) Project schedule Preparing invoices for work done Subcontractors payments Review and control of crews production rates 07/11/2013 Emad Elbeltagi 6 3

Quantity Surveying Table 07/11/2013 Emad Elbeltagi 7 Table 07/11/2013 Emad Elbeltagi 8 4

Bill of Quantity: Sample 07/11/2013 Emad Elbeltagi 10 5

Bill of Quantity: Sample 07/11/2013 Emad Elbeltagi 11 Priced Bill of Quantity: Sample 07/11/2013 Emad Elbeltagi 12 6

وزج ف ل ن اص و ا Statement for payment 07/11/2013 Emad Elbeltagi 14 7

Word order Items in takeoff sheets are organized in the same construction sequence Order of items in the same chapter: Items estimated in cubic meter (m 3 ) Items estimated in square meter (m 2 ) Items estimated in linear meter (m) Items estimated in numbers (unit) Items estimated in weight (ton) Items estimated in lump Sum (L.S.) Volume of some shapes A 1 =Top Area A=Bottom Area h ( 1 1 ) 1 Volume =. h A + A + A. A 3 r 1 h r 1 Volume =. r. h r + r + r. r 2 2 2 ( 1 1 ) Volume = Area of Base Height 1 Volume = Area of Base Height 3 07/11/2013 Emad Elbeltagi 16 8

Units of Measurements Each (numbers): Piles, doors, Windows, Precast concrete, etc. Length (meter): Windows sills, Pipes, Skirts, stair steps, etc. Area (Square meter): Flooring, painting, plastering, Brick walls (12 cm or less), etc. Volume (Cubic meter): Brick walls (>12 cm thick), Excavation, Backfilling, Reinforced Concrete, etc. Weight (Ton): Metallic works, Reinforcement steel, etc. Lump Sum: Some electrical and plumbing works, Manholes, etc. Effort (Man-day): Renting of equipment or labor, etc. 07/11/2013 Emad Elbeltagi 17 Measuring units Cubic meter (m 3 ) Used for items such as: Excavation Filling Concrete Masonry Square meter (m 2 ) Used for items such as: Masonry Plastering Flooring Painting 9

Measuring units Linear meter (m) Used for items such as: Oil pipe lines Sewage water pipe lines Canals Number (unit) Used for items such as: Electric outlets Doors and windows Sanitary fixtures Measuring units Lump sum(l.s.) Used for items such as: Manholes Lifts Item is subcontracted when the contractor does not have enough experience to construct it or there is an item which has a small quantities of many work items, such as manholes. 10

Preparation for quantity take-off Check the availability of drawings Check the axis and dimensions Check building levels and link it to structural drawings. Check doors and windows model numbers Check ground water levels Preparation for quantity take-off Check architectural against structural drawings Check foundation design and foundation levels Check construction members dimension and reinforcement. Review the contract conditions and specifications 11

2 Work items 1 Storage Each Ton Ton 2 م TILES m 3 95 % 75 % 07/11/2013 Emad Elbeltagi 23 Earth Works Backfilling Excavation Earth works Soil Transportation Leveling 07/11/2013 Emad Elbeltagi 24 12

Excavation (Cubic meter) Quantities are calculated based on the dimensions of the foundation in plans. Prices differ based on the soil type, deep of excavation, ground water level, site location, shoring system, Equipment used, etc. 2m GWT 0.5 m 0.5 m 0.5 m Wet soil (0.5 m) 2 m 2 m 1 m Dry soil (2 m) 07/11/2013 Emad Elbeltagi 25 Excavation Volume = 1 15.6 1.8 Contractor Owner Depth of exc. Actual Engineering Length Width = smell width 07/11/2013 Emad Elbeltagi 26 13

Backfilling (Cubic meter) Backfilling = Excavation volume of all works inside the excavated pit (footings, smells, column necks, brickwork, etc.) + amount above GL (or amount below GL) Ground level (GL) Above Ground level Below 07/11/2013 Emad Elbeltagi 27 Leveling and Soil Transportation Leveling: Area (m 2 ) if thickness less than 30 cm Volume (m 3 ) if thickness more than 30 cm Transportation: Transported soil = vol. of exc. vol. of backfilling + additional soil at site Add swelling factor based on the soil type: 5% sandy soil. 15% clayey soil and 25% for demolition material. (owner or contractor) 07/11/2013 Emad Elbeltagi 28 14

Earth Works: Example 07/11/2013 Emad Elbeltagi 29 Plain concrete Quantity of P.C footing = No. of footings for a specific model * length * width * depth Total quantity of P.C footings = summation of P.C footing models 15

Ground beams Quantity of ground beam = No. of ground beams for a specific model * length * width * depth Total quantity of ground beams = summation of ground beam models Concrete Works Measured exactly, deduct all openings except spaces required for reinforcement, piping and pre-stressed concrete cables. Plain concrete (PC): m 2 if thickness <20 cm m 3 if thickness 20 cm Average thickness (thickness) should be mentioned Reinforced concrete (RC): All RC elements measured by volume (m 3 ) except hollow block slabs measured by area (m 2 ). Domes, cylindrical roofs and shells measured by area in the horizontal projection. P.C. 20 cm P.C. <20 cm 07/11/2013 Emad Elbeltagi 32 16

Columns Quantity of columns = No. of columns for a specific model * length * width * height Total quantity of columns = summation of columns models Slabs Solid slabs: Quantity of slab = length * width * thickness Flat slab: Quantity of slab = length * width * thickness Beams: Quantity of beam = length * width * height 17

stairs Quantity of stairs = inclined length * width * height + stair section area * stair width * No. of stairs Brickworks Measurement m 2 if thickness <25 cm m 3 if thickness 25cm Deduct all openings Deduct half the area (volume) of arches Deduct all Concrete elements Facades are measured by area Separate item for each brick type slab top level Ground beam top level Beam bottom level slab top level Beam bottom level Wall height Wall height Ground level 07/11/2013 Emad Elbeltagi 36 18

Plastering Internal Engineering measurement by area (m 2 ) All openings are deducted All openings sides are added Inclined slabs are calculated based on their horizontal projection External Measured by area (m 2 ) Deduct half the area of the openings 4 m 2 Openings with areas <4 m 2 are kept without deduction Cantilever slabs < 1 m projection not added Add half the area of cantilever slabs 1 m 07/11/2013 Emad Elbeltagi 37 Example 5.6m ع 1 ك 2 ع 1 15cm 7ɸ10/m 4.8m ك 1 7ɸ12/m ك 1 A A ع 1 ك 2 ع 1 19

Example # 'دل و ات 6ɸ8/m ا-طء ار 4ɸ16+ 'وي 2ɸ16 2.5 م 0.3m x 0.5m طع ارات ك 1 ك, 2 طع ا"ود ع 1 0.3m x 0.3m ار#ع ا"ود ع 1 3.0m طع ات 0.3m x 0.5m ا)وا'د ا&% 1m x 1m x 0.4m وب ا 0 رض اط.("(% 1.2 m Section A-A ا)وا'د ا"د(% 1.6m x 1.6m x 0.3m Example It is required to estimate the quantities of the following jobs: (ت ار) Excavation Plain Concrete Footings (ر اواد اد) (ر اواد ا) Reinforced Concrete Footings (ر ات) Ground Beams concrete (ت اردم) Backfilling (ر ادة) Columns concrete (ر ا ط ورات اف) Slab and beams Concrete دد!" ا ط ( Reinforcement Slab and beams (ورات اف 20

Example: Excavation 1.6 m 4.8 m 1.2 m 1.6 m.15 m 5.6 m.15 m 5.3 1.6 m 0.8 m 3.7 m Example: Excavation No. Item Unit Number Length Width Depth Total 1 Excavation m3 4 1.6 1.6 1.2 12.288 2 3.7 0.3 0.5 1.11 2 2.9 0.3 0.5 0.87 21

Example: PC footings No. Item Unit Number Length Width Depth Total 2 PC Concrete m3 4 1.6 1.6 0.3 3.072 1.6 m 0.3 m 1.6 m Example: RC footings No. Item Unit Number Length Width Depth Total 3 RC Concrete m3 4 1 1 0.4 1.6 1.0 m 0.4 m 1.0 m 22

Example: ground beams No. Item Unit Number Length Width Depth Total 4 Ground Beams m3 2 5.3 0.3 0.5 1.59 2 4.5 0.3 0.5 1.35 4.8 m 4.5 m 0.5 m 0.3 m 0.15 m 5.6 m 0.15 m 0.3 m 5.3 Example: Backfilling No. Item Unit Number Length Width Depth Subtotal Total 1 Excavation m3 14.27 2 PC Concrete m3 3.07 3 RC Concrete m3 1.60 4 Ground Beams m3 2.94 Total Concrete m3 7.61 5 Filling m3 6.66 23

Example: Columns No. Item Unit Number Length Width Depth Total 6 Columns Concrete m3 4 0.3 0.3 3 1.08 3.0 m 3.0 m ا 3 'دة 3.0 m Example: Slabs and beams No. Item Unit Number Length Width Depth Total 7 Slab & Beams m3 2 5.3 0.3 0.5 1.59 2 4.5 0.3 0.5 1.35 1 5 4.2 0.15 3.15 4.2 m 5.0 m 15 cm 4.8 m 4.5 m 0.15 m 0.5 m 0.3 m 0.15 m 5.6 m 5.3 0.15 m 24

Example: Summary sheet No. Item Unit Number Length Width Depth Total 1 Excavation m3 14.27 2 PC Concrete m3 3.07 3 RC Concrete m3 1.60 4 Ground Beams m3 2.94 5 Filling m3 6.66 6 Columns Concrete m3 1.08 7 Slab & Beams m3 6.09 Total Concrete 14.78 Example: Reinforcement 30cm 0.3m x 0.5m 4ɸ16+ 'وي 2ɸ16 طع ارات ك 1 ك, 2 # 'دل و ات 6ɸ8/m ا-طء ار 2.5 م 2.5cm 25cm 2.5cm 7ɸ10/m 7ɸ12/m 50cm 45cm 25

Example: Reinforcement Unit No. of Length Total Unit Total (kg) bars length Weight Weight 16 upper (beams) 4 4.8 19.2 1.63 31.296 4 5.6 22.4 1.63 36.512 16 lower (beams) 8 4.8 38.4 1.63 62.592 8 5.6 44.8 1.63 73.024 10 long (Slab) 34 5.6 190.4 0.63 119.952 12 short (Slab) 40 4.8 192 0.92 176.640 8 stirrup (beams) 60 1.55 93 0.41 38.130 51 1.55 79.05 0.41 32.411 Total Steel 570.557 26