Preparing a Simple Project Plan with MS Project



Similar documents
Using Microsoft Project 2000

MS Project Tutorial for Senior Design Using Microsoft Project to manage projects

Microsoft Project 2010

Project Management Dashboard Pro v5 Documentation

Microsoft Project From the WBS to a Complete Schedule Emanuele Della Valle, Lecturer: Dario Cerizza

Bradley University College of Liberal Arts and Sciences Department of Computer Sciences and Information Systems

Planning and Managing Projects with Microsoft Project Professional 2013

Laboratory 1 Initiating a Project

Using MS Project in Translation Projects Management

Lab 1 Introduction to Microsoft Project

Project Initiation and Revision Training Manual. Table of Contents

Microsoft Migrating to Word 2010 from Word 2003

KPN SMS mail. Send SMS as fast as !

Microsoft Project 2007 Level 2: Working with Resources and Managing a Project

IT Training. Microsoft Project. Vicky Samways, IT Training Information System Services Version 2.1

Microsoft Project 2007 Level 1: Creating Project Tasks

Introduction to Microsoft Project 2010

Appointment Schedule and Online Messaging Help Guide

Creating a New Project

Gantt Chart/Diagram Excel Template User Guide

How to use Microsoft Project? Basic Training to Help You during the BYI challenge

Microsoft Project 2013

Migrating to Excel 2010 from Excel Excel - Microsoft Office 1 of 1

Virto SharePoint Gantt Chart App for Office 365 Release User and Installation Guide

Staying Organized with the Outlook Journal

1. Introduction. P2O is automatically loaded when you open Ms Project (2010 or 2013). The add-in can be found under the M5 Tools menu. 2.

Nexsure Training Manual - Admin. Chapter 11

Getting Started with Excel Table of Contents

How To Use Ms Powerbook On A Pc Or Mac Or Macbook 2 (Windows)

How to test and debug an ASP.NET application

Beginning Microsoft Project

MS WORD 2007 (PC) Macros and Track Changes Please note the latest Macintosh version of MS Word does not have Macros.

OVERVIEW. Microsoft Project terms and definitions

Microsoft Outlook Introduction

Sheet Set Manager: Create a List of Sheets Instantly

WHAT S NEW IN MS EXCEL 2013

How schedule AccuTRConsole to run every hour

Scheduling Document Creation

Quick Start Guide. Highly customizable automated trading Automate your trades according to rules and models you create.

ABOUT THIS COURSE...3 ABOUT THIS MANUAL...4 EXCHANGING PROJECT PLAN DATA WITH OTHER APPLICATIONS...5

Microsoft PowerPoint 2010 Handout

Create task relationships by linking tasks. Switch task scheduling from manual to automatic. Set nonworking days for the project plan.

M-Files Gantt View. User Guide. App Version: Author: Joel Heinrich

Project Creation and Gantt Chart Design Using Microsoft Project. R. Baker. The University of Tampa

University of Sunderland. Microsoft Project. Basic Guide

If you re like most project managers, you juggle several projects at the same time.

Mail in Outlook Web App

Vodafone PC SMS (Software version 4.7.1) User Manual

MSP How to guide session 2 (Resources & Cost)

Microsoft PowerPoint Exercises 4

User Manual - Sales Lead Tracking Software

Project Management Quick Reference Guide for MS Project 2010

Microsoft Migrating to PowerPoint 2010 from PowerPoint 2003

Outlook . User Guide IS TRAINING CENTER. 833 Chestnut St, Suite 600. Philadelphia, PA

MICROSOFT OUTLOOK 2010 WORK WITH CONTACTS

BILL PAY. Frequently Asked Questions

Module A2 Item Activities, Gantt Chart and Utilization Sheet. A2.1 Project item activities A2.2 Gantt chart A2.3 Utilization sheet

Excel 2007 Basic knowledge

Task Card #2 SMART Board: Notebook

Every project requires communication and collaboration and usually a lot of

To reuse a template that you ve recently used, click Recent Templates, click the template that you want, and then click Create.

Getting Started The Windows SharePoint Services Window

Table of Contents User Guide... 1 Welcome... 4 Front End Life Blue... 5 General Navigation... 5 Menu Bar... 5 Continuous Scroll... 5 Hyperlinks...

Managing Your Desktop with Exposé, Spaces, and Other Tools

Hands on Microsoft Project (Part I) From a WBS to a Complete Schedule Emanuele Della Valle, Lecturer: Dario Cerizza

Managing Projects. With. MinuteMan Project Management Software

Setting up a basic database in Access 2003

Inventory Manager. Getting started Usage and general How-To

Symantec Enterprise Vault

Section 4. Mastering Folders

Managing Agile Projects in TestTrack GUIDE

Creating and Using Forms in SharePoint

To launch the Microsoft Excel program, locate the Microsoft Excel icon, and double click.

Open Workbench. User Guide. v2.0.00

Aras Corporation Aras Corporation. All rights reserved. Notice of Rights. Notice of Liability

Creating trouble-free numbering in Microsoft Word

Macros in Word & Excel

Explore commands on the ribbon Each ribbon has groups, and each group has a set of related commands.

Microsoft Excel 2013: Macro to apply Custom Margins, Titles, Gridlines, Autofit Width & Add Macro to Quick Access Toolbar & How to Delete a Macro.

What's New in ADP Reporting?

Revealing the Secrets of Microsoft Project

User Guide for TeamDirection Dashboard

Search help. More on Office.com: images templates. Here are some basic tasks that you can do in Microsoft Excel 2010.

Excel 2010: Create your first spreadsheet

Excel macros made easy

RemoteWare Software Manager

Produced by Flinders University Centre for Educational ICT. PivotTables Excel 2010

Microsoft Project Activity

Virto SharePoint Gantt Chart Web Part for SharePoint 2013 Release User and Installation Guide

Excel 2003 PivotTables Summarizing, Analyzing, and Presenting Your Data

Resource Allocation in MS Project

Dreamweaver and Fireworks MX Integration Brian Hogan

Outlook 2010 Essentials Power Point Slides Corporate Training Materials

INTRODUCTION 5 COLLABORATION RIBBON 5 SELECT THE UPDATING METHOD 6 MAKE YOUR PROJECT COLLABORATIVE 8 PROCESSING RECEIVED TASK UPDATES 9

EditAble CRM Grid. For Microsoft Dynamics CRM. How To Guide. Trial Configuration: Opportunity View EditAble CRM Grid Scenario

IST 195 Lab 12 Introduction to Microsoft Project

Using Excel As A Database

Toad for Data Analysts, Tips n Tricks

Mastering Mail Merge. 2 Parts to a Mail Merge. Mail Merge Mailings Ribbon. Mailings Create Envelopes or Labels

I N FO RM A T I O N T EC H N O L O G Y S ERV I C ES M I C ROSOFT PROJ EC T T A S K M A N A GEM EN T LEARNING GUIDE

Transcription:

Background Preparing a Simple Project Plan with MS Project Part 1: Preliminary set-up MS-Project is the most widely used software product for project planning and control. It s both flexible and powerful, but it s also overcomplicated, and it lacks a few important features. This document shows a way of making the best of this interesting and sometime frustrating product for preparing a simple and straightforward project plan. After you install the product and launch it, you ll see this screen: The left side is for specifying tasks. The right side will become a Gantt chart showing the project schedule. Setting up to plan a project The default screen above is ill-suited for preparing a project plan. The columns Start and Finish for an individual task can t be known until we decide when the project itself will begin, and MS- Project will then compute those data based on the estimated durations and predecessor relationships. To save space on the form we need to get rid of those columns; one way is to right-click the column hearing and then select Hide Column. Then we need a place to specify essential Predecessor task information. Using either the mouse or keyboard shortcuts select Insert Column from the menu. You ll then see a list of dozens of fields, COMP 477/388, Summer, 2010 1 of 7 Planning with MS-Project

most of which you ll never need for planning and controlling a single project. Fortunately, they re alphabetized, so you can find and select Predecessors. What s still missing? The estimated quantities of the specified resources and the task deliverables specification. We don t have a simple way of entering that information on the above form, so for now we ll leave the form like this: You ll want to adjust the widths of the columns, but that s easy to do at any time. Note that there s also no task identifier column. MS-Project will assign them automatically in the form of sequential numbers. The tasks will get renumbered from time to time as the plan evolves, so the identifiers have no permanent significance and shouldn t be referred to in other documents. Entering a project plan Now we can start to enter a project plan. Let s enter a couple of tasks: COMP 477/388, Summer, 2010 2 of 7 Planning with MS-Project

Whoops! MS-Project is assigning definite start and end dates to our tasks. But we re just preparing a plan and don t yet know when (or if) the project will actually begin. We just want the Gantt chart to show time relative to the project start. Erase the tasks and right-click the row containing the dates. That opens a menu from which we select Timescale, which in turn brings up a dialog box: Look over the long list of Label options, just dozens of ways of displaying time. (MS-Project is sometimes criticized for paying more attention to formatting and display than to actual project planning and control.) Week1, Week2...(from start) seems appropriate. Now our data-entry form looks like this: COMP 477/388, Summer, 2010 3 of 7 Planning with MS-Project

Are we now ready to start entering tasks on our plan? No, there s still a problem. Although the Gantt chart will display dates relative to the start of the project, MS-Project will still assign specific dates internally! We need to do one more thing: On the first line, enter a dummy Begin milestone, a task with 0 duration. We ll specify Begin (task #1) as predecessor of every task that really has no predecessor. Then when we know the actual date on which the project will start, we can enter it as the start date for Begin, and the whole project plan will get adjusted to the actual calendar. So here s the way the form should look before we start entering tasks: Now we ll enter our project plan. Specifying a task Suppose we ve just agreed to investigate the need and potential benefits of a new computer application system. The sponsoring user has authorized funds for a preliminary study phase. We know that we re going to have to interview people in the user organization to determine what they think they need. So we ll start by identifying those people: Now there are still three essential things missing from the above task specification: COMP 477/388, Summer, 2010 4 of 7 Planning with MS-Project

Specification of the deliverable(s) to be produced. The quantity of the Analyst resource required Any contingencies That information won t fit on this form, but we can easily enter it. Right click on the task name and select Task Information from the menu. You ll then see this: This General tab contains no useful information, 1 but the Notes and Resources tabs 2 will allow us to complete the task specification. Let s agree to specify the task deliverables 3 in the Notes area: 1 In fact the dates are misleading 2 For the sake of simplicity we won t try to use the Custom Fields facility, but you may want to investigate it for your projects. 3 In the list of field names under Insert Column you ll find several that refer to deliverables, but they don t support simple specification of the results of a task. Under the Collaborate menu, you ll see Manage Deliverables, but that s concerned with communication among multiple projects, and it s unavailable in the standard version of MS-Project.. COMP 477/388, Summer, 2010 5 of 7 Planning with MS-Project

If there are contingencies to specify, we can put them in the Notes section, too. Finally, we need to quantify the resources. We ve already specified that the task will be assign to an Analyst and we ve estimate that he or she will need 3 days to compile the information, but we haven t specified how much of those 3 days will be spent on this task. Assuming normal delays waiting for phone calls or E- mail to be returned, it seems reasonable that the Analyst will spend about ¼ of his or her time on this task during those 3 days: Note that MS-Project has misunderstood our original Duration specification as a manpower estimate, altering the duration to 12 days! That s all right; just re-enter the correct duration: It may seem that we had to go to a huge amount of trouble to specify a simple task, but now that it s done the information is easy to see and easy to modify. COMP 477/388, Summer, 2010 6 of 7 Planning with MS-Project

Note that the Notes field is now shown as an icon in the leftmost column, and we can quickly navigate to it by clicking the icon. Now that we ve set up MS-Project, in part 2 we ll enter our project plan. COMP 477/388, Summer, 2010 7 of 7 Planning with MS-Project