COATING & WRAPPING OF UNDERGROUND PIPING



Similar documents
SECTION CEMENT-MORTAR LINED AND COATED STEEL PIPE

CATHODIC PROTECTION SYSTEM DESIGN

A. The CONTRACTOR shall provide pipe coating, complete and in place, in accordance with the Contract Documents.

GENERAL RUBBER LINING PRINCIPLES

VC 104+ Rigid Grade / Rigid Grade Imagine VC 104 Rigid Grade Commercial Customised

Tractor Painting Tips

PIPING SYSTEM - ABRASIVE SLURRIES Engineering Standard Specification. 96 B. Riutta

BRIDGE FIELD PAINTING, REPAINTING, 412 AND PAINT RESIDUE CONTAINMENT. A. Field Painting, Bridge Repainting and Residue Containment:

SECTION HIGH DENSITY POLYETHYLENE (HDPE) PIPE AND FITTINGS FOR WATER DISTRIBUTION AND TRANSMISSION

Suggested Specifications: Steel Pipe for Water Transmission

White rust on galvanized and galvanized pre-painted steel. Technical Information

SECTION STORM DRAINAGE SYSTEM

SECTION DUCTILE-IRON PIPE AND FITTINGS

DIVISION 23 HEATING, COOLING, AIR CONDITIONING AND VENTILATION

SECTION 623 CONCRETE BONDING COMPOUND, EPOXY MORTAR AND EPOXY POLYMER CONCRETE OVERLAY SECTION CONCRETE BONDING COMPOUND.

POLYURETHANE LINING AND COATING ON PIPE RAW WATER

SECTION WATER STORAGE TANK PAINTING

Approved. Property Test/Standard Description. matt (0-35) Flash point ISO 3679 Method 1 27 C calculated IED (2010/75/EU) (calculated)

FIELD COATING OF STEEL PIPE AND FITTINGS INSTALLED UNDERGROUND AND IN SUBSURFACE STRUCTURES

Specification for Pipe Coating Repairs Offshore

PHOENIX Product Data Sheet (Updated on 14-Jan-2012)

Scotch-Weld TM. Epoxy Adhesive 1838 B/A Green 1838 B/A Tan 1838-L B/A Translucent. Technical Data February, Product Description

PAAM COMMERCIAL PRIVATE LIMITED

Electric Heat Tracing INSTALLATION PROCEDURES

DENSO WATERPROOFING SYSTEMS

CERTIFICATE NAME OF PRODUCT MANUFACTURER PRODUCT DESCRIPTION CERTIFICATION PROCEDURE. No VTT C Date of issue , Updated July 1, 2011

WATERPROOFING OF REINFORCED CONCRETE FLAT ROOF 12

INSTALLATION RECOMMENDATIONS. Outdoor Rubber Tiles

SECTION HIGH DENSITY POLYETHYLENE (HDPE) PIPE AND FITTINGS

Division 9. SignaFlor Pad and Pour Flooring System

STANDARD SPECIFICATION SECTION STEEL PIPE, FUSION-BONDED EPOXY LINED AND COATED

METHOD STATEMENT INSTALLATION OF INSULATING FLANGE KITS

NAPCA BULLETIN APPLICATION PROCEDURES FOR CONCRETE WEIGHT COATING APPLIED BY THE COMPRESSION METHOD TO STEEL PIPE

METAL ROOF RESTORATION SAMPLE DESIGN GUIDELINES

Reproduced with the permission of the American Welding Society (AWS), Miami, Florida - 09/15/ Stud Welding

SECTION POLYVINYL CHLORIDE (PVC) PIPE

RIW SHEETSEAL 226 BENEFITS APPLICATIONS APPLIED TO. CI/SfB TN6 L6813. November l Water and water vapour barrier. l Factory controlled thickness

Single-Phase AC Synchronous Generator

Pictorial Surface Preparation Standards For Painting Steel Surfaces

SPECIFICATIONS FOR BRIDGE CONSTRUCTION SECTION 16 BRIDGE DECK WATERPROOFING General Materials Equipment...

Rehabilitation of corroded pipelines and pipes with FibaRoll

Cavity Drain R20 is manufactured from1.0mm thick black high density polyethylene with studs approximately 20mm high.

RAUFOSS EXPLOSIVE COMPRESSION FITTINGS

3 Scotch-Weld TM. Urethane Adhesives 3532 B/A 3535 B/A 3549 B/A. Technical Data January, 2010

PRODUCT DATA SHEET DESCRIPTION:

SIGMACOVER 280. PRODUCT DATA SHEET December 10, 2014 (Revision of March 1, 2014) DESCRIPTION

Inspections Standard Operating Procedure 5 Aboveground Storage Tanks

SURFACE PREPARATION STANDARDS

BLACK JACK ALL WEATHER ROOF COATING

SECTION 560 COATING NEW STRUCTURAL STEEL

WIRE, TERMINAL AND CONNECTOR REPAIR CONDUCTORS

SECTION 15 AIR RELEASE VALVE ASSEMBLIES General

Mechanical Installation

WATERPROOFING FOR CONCRETE STRUCTURES

CORROSION ENGINEERING RESIN-BASED POLYMER CONCRETES AND GROUTS

IHSS-N1 WELDED HONEYCOMB CORE SPECIFICATION. Generated: Sergiy Papyshev Engineering. Approved: Don Prysi Manufacturing. Approved: Merzuk Ramic Quality


Pipe Protection Tape System

3M Scotchkote Urethane Coating 165HB

The Contractor shall furnish and install all shielded power cable suitable for use on this project.

Construction. SikaProof A-08 Edge, A-12 Edge. Fully bonded FPO sheet membrane in L-shape for the SikaProof A waterproofing system. Product Description

Double Coated Urethane Foam Tapes

FIRESTOPPING & SMOKE SEALS

Property Test/Standard Description. gloss (70-85) Flash point ISO 3679 Method F (100 C) calculated VOC-US/Hong Kong. US EPA method 24 (tested)

DC MOTOR ANALYSIS & TROUBLESHOOTING

SSPC-SP 6/NACE NO. 3

Crystal Clear Sealant

SC2000 CEMENT BONDING PROCEDURES

NATIONAL INSTITUTE OF BIOLOGICALS

CABLE TRENCH INSTALLATION GUIDE

PTFE Teflon Glass Fabric Grades & Material Data Sheets

Field Welding Inspection Guide

Section 2100-Trenching and Tunneling

This will also provide you with the knowledge to insure long life for your Investment

DIVISION 4300 STORM DRAINAGE

3 Scotch-Weld TM. Urethane Adhesives 3532 B/A 3535 B/A 3549 B/A. Technical Data March, 2002

Approved. Property Test/Standard Description. matt (0-35) Flash point ISO 3679 Method 1 28 C calculated VOC-US/Hong Kong. US EPA method 24 (tested)

Specifications. Preformed Metal Wall and Roof Panels. Alcoa Cladding Systems Manufacturing Plant 100 Industrial Boulevard Eastman, Georgia 31023

KNOW YOUR OPTIONS: 69 KV XLPE POWER CABLE

A. Shop Drawing submittals shall include, but not be limited to, the following:

SCHEDULE ' A' TECHNICAL SPECIFICATION FOR 11/22/33KV H.T.XLPE POWER CABLE FOR DISTRIBUTION NETWORK IN MAHARASHTRA (SPECIFICATION NO.

Weatherproofing Kit for Connectors and Antennas

KNOW YOUR OPTIONS: 230 KV POWER CABLES

Document Library TS Data Sheet M Windo-Weld Super Fast Urethane. Data Sheet. Public

Waterproofing System for Wastewater Tanks in Petrochemical Industries and Refineries

NEW ELECTRICAL SUBSTATION Building 300 SECTION ETHYLENE-PROPYLENE-DIENE-MONOMER ROOFING WORK

GAS INSTALLERS MANUAL CINERGY AND SUBSIDIARY COMPANIES CUSTOMER PROCEDURE FOR INSTALLING 3", 4", 6", AND 8" IPS PLASTIC GAS SERVICE PIPING

Construction. 3-part thixotropic epoxy patching mortar. Product Description. Tests

APPENDIX C MOISTURE GUIDELINES & MOISTURE TESTING

Phone: FAX: website: GUIDE TO INSULATION FASTENING

Vinyl Composition Tile Installation System

Section kv Power Cables

SECTION FIRE HYDRANTS

SIGMACOVER 300. PRODUCT DATA SHEET December 12, 2014 (Revision of November 1, 2013) DESCRIPTION

James M. Pleasants Company

T A B L E T 1 T E S T S A N D I N S P E C T I O N C A B L E P C U T A N D P C U T - A

SECTION SANITARY SEWER AND STORM DRAIN SYSTEMS

NCCER Progress Blvd., Alachua, FL Tel: (888) Task Number Item Date(s) Recorded By

Transcription:

CONSTRUCTION STANDARD SPECIFICATION DOCUMENT NO :SEC-PJ-000-SPC-PI-008 TOTAL PAGES : 8 Page 1 of 8

CONTENTS 1. SCOPE 2. DEFINITION 3. CODES AND STANDARDS 4. MATERIALS Page 2 of 8

1. SCOPE This specification describes the materials, applications, handling, installation and testing procedures For external coating and wrapping over Carbon Steel piping to be laid under ground for protection against corrosion. 1.1 All buried Carbon Steel and Galvanized pipes, valves, fittings etc., shall be externally double wrapped. Double wrapping of pipe shall be achieved by overlapping the wrap by a minimum of 55%. 1.2 All conflicts between the requirements of this standard, purchase order or data sheets shall be referred to contractor for clarification before commencement of site operations. 2. DEFINITION OWNER : CONTRACTOR : Engineering Company 3. CODES AND STANDARDS 3.1 The following standard should be the latest edition. BS 2782 Method of Testing for Plastics. EN 12068 Cathodic protection. External organic coatings for the corrosion protection of buried. ASTM American Society for Testing of Materials. D-1000 Standard Specification for Method of Testing Sensitive Adhesive Coated Tapes. D-1004 Standard Specification for Test Method for Initial Tear Resistance. D-638 Standard Test Method for Tensile Properties of Plastics. G-14 Test Method for Impact Resistance of Pipeline Coating. G-8 Test Methods for Cathodic Disbonding of Pipeline Coating. G-62 Standard Test Method for Holiday Detection in Pipeline coatings. 4. MATERIALS Polyethylene wrapping material shall be used in cold applied tape system. 4.1 POLYETHYLENE WRAPPING MATERIAL All materials shall be furnished from the same manufacturer and consist of the followings: a) Laminated polyethylene (low-density), backed self-adhesive, rubberized, bitumastic compound tape. a.1) Polyethylene inner wrap: Thickness should be minimum 0.305 mm (0.012"), with self-adhesive compound thickness 0.203 mm (0.008") minimum. Interleaf in rolls supplied shall be double sided release coated paper or polymer preferably with extra width for roll protection. Final thickness should be defined as per vendor data. Page 3 of 8

Characteristics of tape: - Elongation : 250% - Tensile strength : 7 N/mm2 - Tear resistance : 8 kg/cm - Dielectric strength : 40 Kvolt/mm 6 - Insulation strength : 1 x 10 Ohm/mm - Impact resistance : 3.2 Joules - Adhesion to steel (With primer) : 2.6 N/mm - Adhesion to self : 0.5 N/mm - Temperature range : -5~ C to 90~ C a.2) Polyethylene outer wrap : Thickness should be minimum 0.229 mm (0.009") with 0.102 mm (0.004") self-adhesive compound. Polyethylene to be White or Silver-Grey light reflecting. Final thickness should be defined as per vendor data. Characteristics of tape: - Elongation : Min 200% - Dielectric strength : Min. 10 KVolt 12 - Insulation resistance : 1x10 Ohm/in b) Bitumen solution type primer, fast drying (3 to 10 minutes). c) Molding Putty A compatible molding putty to the supplied tape shall be provided for applying around fittings and flanges, etc., supplied in packs as per manufacturers standard. 4.2 STORAGE a) All materials shall be stored in a covered warehouse in a location as cool as possible and protected from the ingress of dirt, dust, moisture, etc. b) Any coating materials show evidence of deterioration due to weathering or damage due to mishandling while are in the custody contractor, shall be replaced by the contractor at his expense. c) Any materials, which have been rejected for any reason, shall be removed from the site. 4.3 SURFACE PREPARATION 4.3.1 Surface shall be completely free from rust, mill scale, grease, weld spatter, weld slag, dirt, dust, oil and any other foreign matter and to be dry at time of application. 4.3.2 Oil and grease shall be removed using an approved solvent. White spirit and paint thinners are suitable solvents. Kerosene shall not be used. Page 4 of 8

4.3.3 Blast cleaning shall not be conducted when the temperature of the surfaces is less than 3~ C above dew point of the surrounding air or when the relative humidity of the air is greater than 85%. 4.3.4 The coat of primer shall be given as soon as practicable and before detrimental corrosion or recontamination occurs. The cleaned surface shall never be left unprotected over night. Mechanical cleaning machines shall not employ knives or other tools, which may produce notches or gauges on the pipe surface. 4.3.5 Blast cleaning machines shall be maintained in correct adjustment and replacement tools shall be available throughout the cleaning process. 4.3.6 The cleaning method employed shall not result in thinning of the pipe wall beyond the limits of the pipe specification. Wire brush (surface according to ST2) is accepted. 4.3.7 Cleaning shall be carried out immediately before application of the priming coat and shall be to the satisfaction of OWNER. If the outside of the pipe becomes contaminated with any foreign matter, OWNER shall have the right to call for relearning before the priming coat is applied. 4.4 APPLICATION OF PRIMER 4.4.1 The clean and dry prepared surface shall be primed with one thin continuous coat of the primer and allowed to dry completely. 4.4.2 Coating and wrapping shall not be started until that section of line has been tested and accepted. 4.4.3 The primer shall be suitable for brush or spray application and still form at thin uniform coating with an approximate 40 micrometer dry film thickness according to vendor s instruction. 4.5 APPLICATION OF WRAPPING 4.5.1 Clean and dry primed surface shall be shaped up at pipe fittings and flanges, using the cold applied bitumen based molding putty packed into crevices around bolts, etc., to provide an even contour suitable for wrapping. Unequal tees shall receive a 45~ fillet at the branch inter section. 4.5.2 The total, clean, dry prepared surface shall be spirally wrapped with the laminated tape with 55% overlap using sufficient tension to ensure complete conformability. Any bulges formed at covers may be removed by splicing the tape in site and repress ring. 4.5.3 End laps between adjoining rolls of the wrap or between pipe sections shall be a minimum of 150 cm. 4.5.4 When the wrapping shall be performed "AT SHOP" or "AT SITE" (when it is necessary to stock the wrapped pipes), an outer wrap shall be spirally wound over a clean dry inner wrap with a 55% or 50 mm minimum overlap using sufficient tension to ensure complete conformity. No bulges shall be permitted. Page 5 of 8

4.5.5 Roll widths of wrapping tapes to be used shall be conform to the table below: TAPE WIDTH PIPES BENDS TEES FLANGES (MM) 150 Up to 3" Up to 8" Up to 12" All 100 4" to 8" 10" to 24" 14" and above - 150 10" to 16" 28" and above - - 225 18" and above - - - a) Flanges and tees shall receive molding putty as per 3.5.1; Cross bandaging technique shall be used in accordance with manufacturer s instruction. b) Tees shall be machine-wrap only, otherwise 150 mm tape shall be used. 4.5.6 At the wind and weather line (pipe risers), Pipe wrap shall be applied with 55% overlap completely. 4.6 WRAPPING OF BURIED FLANGES, VALVES AND OTHER FITTINGS 4.6.1 The approved tape shall protect buried flanges, valves and fittings, plus primer and putty supplied by the tape manufacturer. 4.6.2 All exposed metal surfaces of the object to be protected and existing protective coating at each extremity to be cleaned by blasting or wire brushing as appropriate so that the metal surfaces are free of all rust, weld spatter, mill scale, dirt, dust, lime wash and other deleterious matter. 4.6.3 The clean, dry prepared surface to be brush primed with one thin continuous coat of quick drying primer and allowed to dry completely. 4.6.4 Where necessary the dry cleaned, primed surfaces to be shaped up using cold-applied molding putty supplied by the tape manufacturer packed into crevices, around bolts etc. to provide an even contour suitable for wrapping. 4.7 HANDLING OF COATED PIPE 4.7.1 All coated pipes shall be handled in such a way that the coating does not suffer damage. Coated pipe shall be handled at all times with wide non-abrading slings or belts, or other equipment designed to prevent damage to the coating. All skids used to support coated pipe shall be padded. 4.7.2 If the pipeline protective coating suffers damage between the coating and laying operations, the Contractor shall replace or repair the coating to the satisfaction of the OWNER 4.7.3 Coating materials shall be handled in such a way that the materials do not suffer damage. 4.7.4 Pipe shall normally be lowered into the trench immediately after the coating and wrapping has been approved. Where coated and wrapped pipe is supported on padded skids, their number shall be sufficient to ensure that no damage will be caused to the coating and wrapping. Page 6 of 8

4.7.5 All coated and wrapped pipes which have been supported in any manner on padded skids, or lowering devices, shall be subjected to closed inspection to see that the coating is undamaged before the pipe reaches the bottom of the trench. Backfilling shall be carried out immediately after the pipeline is lowered into the trench but Contractor shall first obtain the approval by OWNER. If any backfilling is carried out without this approval, OWNER will have the right to require the Contractor to remove the backfill for examination of the coating and wrapping. 4.8 TESTS ON NEW MATERIALS Manufacturers shall conform to the following tests or OWNER approved equivalent tests, in writing. OWNER reserves the right to have any production sample tested subsequently to ensure that the material conforms to these specifications. 4.8.1 Tensile strength and elongation at break tests shall be carried out according to BS 2782,D638 or EN12068. 4.8.2 Tear resistance test shall be carried out according ASTM D1004. Laboratory conditions may alternatively be 20~C ± 2~C and 65 ± 2% relative humidity. 4.8.3 Adhesion testing shall be carried out according to ASTM D 1000 or EN 12068. 4.8.4 Impact resistance tests shall be carried out according to ASTM G-14. 4.8.5 Dielectric strength test shall be carried out according to BS 2782 or ASTM D1000. 4.8.6 Cathodic disbonding test shall be carried out according to ASTM G-8 or EN12068. 4.9 INSPECTION AND TESTING OF COMPLETED WORK 4.9.1 All coating shall be subjected to 100% visual inspection and 100% inspection with an electrical holiday detector according to ASTM G62 before being lowered into the trench. 4.9.2 Prior to back filling, all wrapped pipe shall be holiday tested using an approved holiday tester set at 5KV per mm of tape thickness to a maximum of 15KV. 4.9.3 Visual inspection shall ensure that the coating is continuous, that the overlap is correctly maintained and that there are no wrinkles in the tape. 4.9.4 The holiday detector shall be used to check that there is a continuous coating over the pipe surface, particular attention being given to bends and to areas where the tape has been spliced or repaired. NOTE: It is not intended that the holiday detector should be used to reveal pin holes and minor faults in the inner tape wrap. Such defects would not normally show up on the holiday detector with the specified coating system, unless the voltage was set at a level, so high, that it would be likely to damage the coating. 4.9.5 The holiday detector shall be of an approved type and the operating voltage and setting shall be determined by a method approved by OWNER. Page 7 of 8

4.9.6 The holiday detector settings shall be checked at least twice per day, while it is in use. 4.9.7 The holiday detector shall be operated strictly in accordance with the manufacturer's instructions at all times. 4.9.8 At no time, shall the holiday detector be permitted to remain stationary around a coated pipeline with the operating voltage switched on. 4.9.9 All defects, whether discovered visually or by means of the holiday detector, shall be clearly and indelibly marked. 4.9.10 To ensure continuity between the brushes or rings, a short circuit test shall be carried out at regular intervals to determine the efficiency. If brushes are used, these must be cleaned every day. 4.10 REPAIRS OF COATINGS 4.10.1 All defects in the coating shall be made good immediately after their detection. 4.10.2 The Contractor shall be responsible for the complete cost, including cost of materials, of making good all defects caused by incorrect storage, handling, application, erection and testing of the protective coating or caused by incorrect construction of the pipeline. 4.10.3 In the event of numerous defects in the coating, OWNER shall have the right to order the whole coating to be stripped, the pipe cleaned and another coating provided, applied and tested in accordance with this specification at the Contractor's expense. 4.10.4 Holiday or localized defects in the inner tape wrap shall be repaired by the following procedure: a) Strip off outer wrap from affected area, after ensuring that completed coating on either side is properly secured to prevent the outer wrap from unraveling. b) Strip off inner wrap and primer from the affected area and thoroughly clean the pipe surface. c) Reprime in accordance with this specification. d) Apply patch of inner wrap not smaller than 150 mm x 150 mm (6" x 6"). e) Test for continuity of repaired inner wrap with holiday detector before replacing outer wrap. f) Replace outer wrap and secure firmly. 4.10.5 Tears, abrasion or other coating defects shall be repaired as directed by contractor. Page 8 of 8