Fast track to Sustainable Mobility. ETCS Implementation on HSL Zuid: Challenges and Technical Solutions Jörn Schlichting, Infraspeed, Siemens AG



Similar documents
HSL Zuid. Phase II Implementation Concept. Final Report. Study for alternative transport system on HSL Zuid

HS line TSI Conformity Certification and Safety Assessment

PPP in Practice High Speed Line Netherlands. Infraspeed Maintenance. Ruud Schellekens. Goal

3 RBC INTERFACE TO INTERLOCKINGS IN FINLAND

CTCS Chinese Train Control System

Hanzelijn Technical solution for the signalling system Ronald Doeleman, MIRSE 25 november 2011 TRANSPORT

Transrapid Project Shanghai

European Rail Traffic Management System (ERTMS) Complete Solutions for ETCS and GSM-R

Simis W electronic interlocking. Safe and economical.

Slab Track on the Dutch High Speed Line: Decision making criteria

The Dutch Railway System. Logistics & Railway Infrastructure Forum NL Indonesia April 30 th 2015

Certification Case: Locomotives for Corridor A (and more)

C a b l i n g s o l u t i o n s a t t h e c o r e o f R a i l w a y N e t w o r k s

Thameslink Desiro City & Signalling Press Trip April 20 to 21, 2015 Evolution in Motion. Siemens Mobility Division

BOMBARDIER INTERFLO*550 for ERTMS Regional

Signaling Programme. Signaling Programme - Laboratory Test Gitte Oberbossel

References: Fully automated metro lines worldwide

Complementary Tests: the key of the successful ERTMS deployment in Spain.

ERTMS for a competitive railway

User Manual Revision English

ERTMS deployment in Spain as a real demonstration of interoperability. Near future challenges

Banedanmark. TØF Jernbane i vækst. Signalprogrammet. Morten Søndergaard, Programme Director

White Paper European Railway Traffic Management System - ERTMS

Welkom. Dutch Track. IRSE Seminar: Delivering Business Performance. More Capacity, Less Complexity. Vincent Weeda 29 maart 2012

GO/GN3677. Guidance on Operational Criteria for the Provision of Lineside Telephony. Following GSM-R Introduction. Rail Industry Guidance Note

Investment projects on PKP Polish Railway Lines network

Trainguard Sirius CBTC

Banebranchen New line Copenhagen-Ringsted

Airport Rail Link is gathering speed. Wolfgang Rueprich, Project Manager Airport Rail Link, October 21, 2009

TECHNOLOGICAL MATURITY OF ERTMS ON THE READINESS OF ERTMS BASED SIGNALLING

Priority decision. High-Frequency Rail Transport Programme

Self-driving transport, On rails. SimTrans-IDA RISK Seminar June 6 th 2016

RATP safety approach for railway signalling systems

ERTMS/ETCS Configuration Management

Module M3. Managing incidents, floods and snow. GE/RT8000/M3 Rule Book. Issue 2. September 2015

Agenda. 1. The basis for the Danish Signalling Programme 2. Procurement Phase 3. Way ahead 4. Benefits

Network Statemen NETWORK STATEMENT. Annex A.1 Glossary. 1. Definitions

Railway Research and Technology in China Today

Plant automation and telecontrol in one system. SIMATIC PCS 7 TeleControl SIMATIC PCS 7. Answers for industry.

Remote Serial over IP Introduction on serial connections via IP/Ethernet

EIB/KNX IP Interface with Power over Ethernet (PoE)

Operating Concept and System Design of a Transrapid Maglev Line and a High-Speed Railway in the pan-european Corridor IV

The future is already here

PCS0100en Persy Control Services B.V. Netherlands

Choose certainty. Add value.

Alstom Transport supplier of Tram Systems in PPP schemes

Ein einheitliches Risikoakzeptanzkriterium für Technische Systeme

COMMISSION IMPLEMENTING DECISION. of XXX

INDIA S FIRST TETRA NETWORK by Delhi Metro Railway Corporation(DMRC)

INDUSTRIAL GATEWAYS VPN ROUTERS SERIAL DEVICE SERVERS

Digital input modules

IQ-C Action plan for rail freight corridor Rotterdam-Genoa

Portal Software GSM-PRO Run LED displays module activity Com LED displays activity on the GSM network GSM-PRO

VÝZKUMNÝ ÚSTAV ŽELEZNIČNÍ, a.s.

ACTION PLAN

Siemens AG Fieldbus solutions with the SIMATIC PCS 7 distributed control system. Brochure April 2010 SIMATIC PCS 7. Answers for industry.

Directive 2001/16 - Interoperability of the trans- European conventional rail system

The Shift to Wireless Data Communication

Broadband on Trains. Railway Solutions - Performance for a world in motion TM InnoTrans Berlin 25 September Nokia Solutions and Networks 2014

ERTMS/ETCS. Functional Requirements Specification FRS

Thales: World leader in signalling technology and the worldwide ETCS infrastructure leader with the most successful track record in the industry

User Manual Revision English

High speed railway principles

Voltage Regulator SPAU 341 C. Product Guide

SAT.VALID - A NEW DATA VALIDATION TOOL FOR COMMUNICATION BASED TRAIN CONTROL SYSTEMS (SUCH AS ETCS) SUMMARY 1 INTRODUCTION

siemens.com/mobility Trainguard LEU S21 Central trackside equipment component

Railway network. [and you drive??] PhD CE Jarosław Zwolski. 1. Railway network in Poland and in Europe. 2. Safety and traffic control

TX OPEN RS232/485 module

AGREEMENT REGARDING THE EXECUTIVE BOARD OF RAIL FREIGHT CORRIDOR RHINE-ALPINE

Chapter 2. Estimated Timetable. 2.1 Introduction. 2.2 Selected Timetable: Spoorboekje

Application Form Part A

Procurement & Contracting Division. Request for Information (RFI) Concerning Procurement of Electrified Rolling Stock ("Rolling Stock")

Voice over IP for small companies and offices. HiPath BizIP.

Cloud computing for maintenance of railway signalling systems

Fit for the European Rail Market Training Competence - Certification

ERTMS deployment challenges in a deregulated market. Björn Westerberg April 25, 2012

Lineside Signal Spacing and Speed Signage

Experience with taximeters with a look at the corresponding tables

Social Cost Benefit Analysis of implementation strategies for ERTMS in the Netherlands. Ministry of Transport, Public Works and Water Management

GSM-Railway Yesterday, Today and Tomorrow. Peter Tiberg May 2009

Rail Roughness Monitoring in the Netherlands

RAIL FREIGHT CORRIDOR 1 NSA WORKING GROUP GUIDELINE FOR CCS AUTHORISATION ON RAIL FREIGHT CORRIDOR 1

ATLAS. Proven Technology & Partnership For interoperability

Railway Business Strategy and R&D in Europe

Cisco - Configure the 1721 Router for VLANs Using a Switch Module (WIC-4ESW)

Dominic Taylor CEng MIET MIMechE MIRSE MCMI, Invensys Rail

Alert, inform, react Aastra Alarm Server

Permissible ambient temperature Operation Storage, transport

INTEROPERABILITY UNIT

Railway Simulation & Timetable Planning

Seoul Metro line 9 O&M Contract

BANGALORE METRO RAIL CORPORATION LIMITED

The Future of Transportation

Square D Model 6 Motor Control Centers

RAIL. Signalling at the St Pancras CTRL Terminal

T-05-S2. Rotary drive without spring return. Technical data sheet. Description. Technical data. Actuators

Measure 9: Updating the interoperability directives on high-speed and conventional railway networks First page:

Connectivity solutions for transport automation

Transcription:

Fast track to Sustainable Mobility ETCS Implementation on HSL Zuid: Challenges and Technical Solutions Jörn Schlichting, Infraspeed, Siemens AG 1

Signalling Overview Ca. 100 km high-speed line, ETCS level 2 and fallback level 1 Breda Belgium, France Amsterdam Rotterdam HSL-Zuid ca. 100 km Key Technical Data - Two double-track sections - Train speed (max. 300 km/h) - Min. signalled headway: 180 s Contract terms - Signature 05/2001 - Financial close 10/2001 - Certificate of Availability South 04/2006 (07/2006) - Certificate of Availability North 06/2006 (10/2006) Siemens: 2 Simis W interlockings, Siwes point controllers, balises, MSTT/LEU Thales: 2, cables, axle counters, point machines, Stopmerkborden Works: Engineering, installation, commissioning, documentation, maintenance training, approval, test 2

Contractual Structure INFRASPEED Holding Industrial shareholders Siemens Fluor Daniel NBM / BAM Dutch Government Ministry of Transport and Environment Concession contract The "IA" INFRASPEED HOLDING Institutional shareholders Charterhouse Innisfree EPC turnkey contract Concession company INFRASPEED BV Maintenance contract for 25 years EPC Consortium Maintenance BV Systems Siemens Trackwork/Civil works NBM Project management Fluor Daniel System design TS TK E/M system TS TK Traction power TS EL COM TS RA RC SIG TS RA MLI Mobirail Sie./KPN GSM-R & Tunnel radio NS RIB THALES Others 3

Contractual Conditions and Challenges The HSL Zuid Contract (PPP) covers the infrastructure. The State is the Contracting & Developing Party, ProRail has been involved at a later time. In parallel there is a contract between the State and the High Speed Alliance (HSA), today NS-Highspeed, for the rolling stock. The TSI definition of trackside assembly defines a larger scope than what has been contracted to Infraspeed. Additional need to clarify the Real Configuration Tests (RCT) and the Safety Qualification Tests (SQT) etc. The HSL Zuid contract is mainly a functional contract. Technical specifications and details have been clarified after the contract had been signed. Originally the contract only required ETCS Level 2. Due to the very strict performance regime Infraspeed decided to additionally implement ETCS Level 1 as fallback level. 4

Baseline, Rules and Regulations ETCS and high-speed lines require dedicated operating rules. At the beginning of the project, operational procedures and rule books for ETCS and operation above 160 km/h were not available. Operational scenarios had to be created. Originally Unisig TSI 2.0.0 was ordered. During the project, it had to be changed to 2.2.2 and finally after CoA to 2.3.0 (2.2.2 plus selected CRs, Subset 108). 2.3.0 OBU definition received as a baseline to determine the impact on the infrastructure. Compliance with the rolling stock according to the definitions set up by the corridor countries. 5

Planning Challenges The HSL Zuid is the first border crossing ETCS project (first application of the TSI for border crossing, also for the Notified Bodies). Need to efficiently synchronise processes and all involved parties. The stations (Schipol airport, Rotterdam, Breda) are not included in the project. The connections were located at in total five heavily traffic-loaded areas (RAS). Possessions had to be required and managed. The main challenge has been timing rather than the technical changes. 2.3.0 update had to be squeezed into the customer s time frame with the target of producing no or little impact on the overall program executed by the State/HSA. Dependencies between rolling stock and infrastructure activities (access to site, compliance, test programme) had to be considered. 6

Border Crossing Challenges Unisig TSI 2.0.0 as well as 2.2.2 did not define the - hand-over at a technical border between two countries in enough detail. However, the ETCS L2-L2 border crossing at 300 km/h was a contractual requirement in both contracts. Several proposals had been made (e. g. wait until 2.3.0, Gateway, L1-L1 300 km/h connection as an interim solution). The States decided for the Gateway. During the past period of having no real - link across the border, the seamless L2-L1 solution was an auxiliary measure, which can be regarded as a best-practice example for preventing trains being stopped until the real - connection can be provided. Consequently, ETCS L1 is a useful measure to keep the performance and availability level high in case of a non-available ETCS L2. 7

Approval, Conformity, EC Declaration Whenever decisions are made in favour of a new technology, it is recommended also to consider the changes for operating staff. This applies to rules as well as to the approval process, especially in the case of the ERTMS process of reaching the position to release the EC Declaration of Conformity. The European process of achieving conformity and authorisation is not always and everywhere commonly seen and partly depends on interpretation. Contractual needs, standard definitions and reality may conflict with each other. Example: EC declarations are not defined for interim versions but might be needed for operational purposes. Way out: pragmatic and commonly target-oriented approach of all parties involved (customer, supplier, notified body, safety assessor, etc.). 8

Thank you for your attention. 9

BACKUP 10

Line Overview Amsterdam Schiphol Airport Key Technical Data - Two double-track sections - Train speed (max. 300 km/h) - Min. signalled headway: 180 s - Max. capacity: 20 train sets per h/d (800 passengers each) 16,000 passengers per hour/direction - Grades max. 2.5% - Curves (300 kph) min. 4,000 m radius Key Requirements - Performance (RAMS) - Validation & verification and safety case according to Cenelec (EN 50126 to EN 50129) - Interoperability according to the TSI Contract terms - Signature 05/2001 - Financial close 10/2001 - Certificate of Availability South 04/2006 (07/2006) - Certificate of Availability North 06/2006 (10/2006) RA RANDSTAD SECTION 43 km BR BRABANT SECTION 45 km London Ringvaart Aqueduct Groene Hart Tunnel Bleiswijk Viaduct Bergschenhoek Cutting Rotterdam Noordrand Tunnel Rotterdam Oude Maas Tunnel Mook Hoek Cutting Dordtsche Kil Tunnel Hollandsch Diep Bridge Breda Galder Cutting Dutch/Belgian border Brussels Paris 11

Structural Breakdown, Hardware Overview Project Level Level 0 Infraspeed EPC consortium Maintenance(IMC) Level 1 E&M Siemens Track & civils BAM- NBM Level 2 Traction power Siemens Communication system Siemens SIG SIG subsystem System Siemens/Alc. Ancillary equipment Siemens/TBN Route protection Train protection Power supply Level 3 Route protection Siemens Route protection Thales Train protection Siemens Train protection Thales Interlocking and interface Point machines Balises Level 4 Signal modules (MSTT/LEU) Vicos MMI Axle counters Outdoor cables TBE MMI Only for test purposes Siemens' part Key switches Block markers Alcatel's part Siwes 12

OCC Netherlands Belgium Signalling System Project RAS RAS Hoofdorp (SIMIS C) RAS Rotterdam (SIMIS C) Breda (SIMIS C) NMBS IL S Approx. 22 km Approx. 10 km Approx. 46 km Approx. 47 km Amsterdam Schiphol Rotterdam Breda Belgium Key: Man-machine interface Maintenance point Cross-over Quantities 100 Stopmerkborden with overrun light Central interlocking Lineside interlocking container Branch Maintenance yard (sidings) 72 Stopmerkborden without overrun light 134 transparent balises 135 fixed balises 140 axle counter devices Uninterruptible power supply Passenger station 28 points with up to 9 point machines 13

Signalling System Computer Configuration VPT + KEV CE Rotterdam Central PIA MMI S+D MMI S+D MMI S+D MMI S+D GSM R IIC / OMC IIC / OMC GSM R Electronic housing Electronic housing Electronic housing Electronic housing Electronic housing Electronic housing Electronic housing Electronic housing Electronic housing 14

System Configuration SIG Subsystem Operation (OCC) Diagnose Central VPT+ KEV CE KEV CE EBP NMBS Area Route Protection Operation & Display S & D Axlecounter LAN MMI VICOS OC111 LAN VPT+ TCP/ IP LAN VPT+ PIA 1 PIA 2 Network- Analyser Network- Analyser S & D Block Interface TCP/ IP und UDP LAN STW 1 2 LAN Central Management S & D VICOS Service & Diagnose IBS-PC Testsystem Network- Analyser LAN STW Signalling SIMIS W and Tools Recorder (BMR) IL- Bus Application HSL Zuid Configurationdata MMI LAN Train Protection ETCS LEVEL 2 Radio Interlocking Container Cabling Grounding RAS-HSL Block Interface Signal Axlecounter Staff Protection Power Supply Status TTI (Simatic) Flood Doors Water Barriers Drainage Control MSTT MA Marker I/O Elements SIWES Points LEU Fixed Balise Switchable Balise (Transparent) TRAIN ETCS LEVEL 1 EMC Power Supply 15

European Process to Achieve Conformity and Authorisation Process of declaration of conformity of constituents Process of EC verification of subsystems and national authorisation to put them into service Trackside assembly National authority Balise OBU Onboard assembly Verification of the National Parts Authorisation for putting subsystems into service Notified body Assessment of conformity Certificate of conformity of the constituent EC verification procedure Technical record Certificate of conformity of the subsystem Manufacturer Operating company Application for assessment of conformity Declaration of conformity Goal Systems integration Application for EC verification procedure Implementation of constituents at the assembly EC declaration of verification Application for verification of the national parts (non-etcs) Level of products launching Level of customer projects 16

Signalling System Input for Signalling Design Operational Scenarios, Example of Entrance from Hoofdorp RAS Area ATB Operation L1 Operation L2 Operation GSM-R Announcement Position Report L1 MA GSM-R Position Report GSM-R L2 MA L2 MA GSM-R Position Report Announcement Balise group Transition to L1 L2 Transition Announcement Transition to L2 1105A HR472 HR447 HR258 1106 HSL 1111-1 1111-2 1:34,7. 1:15 Route to Leiden 1:34,7. VC463 L1T 1131B 1133A-1 1133A-2 AL2 L2T 8 1132 HSL HR472 HR447 HR358 270 91 194 712 451 119 268 623 406 1431 9815 ETCS Balise group 17855 Announcement Balise group L1T ETCS L1 Transition Balise Group AL2 ETCS L2 Announcement Balise group L2T ETCS Level 2 Transition Balise Group Km Kilometer Mark Balise group 18125 18216 18410 19122 19573 19692 ATB Supervision L1 Movement Authority L2 Movement Authority Normal Travelling Direction Drawing not at scale Distances in meters Vmax: 130km/h km marks (in meters) VC: Voltage Changeover Hoofddorp 19960 47176 Shl-Ldn: 19972 HSL: 47164 HSL 46553 46147 44716 35845 Vmax: 160km/h Vmax: 300km/h 17

Signalling System Input for Signalling Design Operational Scenarios, Example of Interface to NMBS Traffic control centre VPT + Traffic control interface Traffic control centre NMBS VPT + interface server Route request Line status Radio block centre Interlocking Block interface Interlocking Routes locked Route request Radio block centre Movement authority and track description Train position and status Control of field elements Element status Gateway Control of field elements Element status Movement authority and track description Train position and status ATC ATC HSL Zuid SIG scope Belgium 18