Production systems Targets Ion sources Construction Tests validation Hanna Franberg-Delahaye SPIRAL 2 WEEK 2011 Page 1
Targets UC x Fusion évaporation targets Targets for light beams Sources ECR SIS Laser Febiad Test bench for the targets and ion sources Constructions of the units Hanna Franberg-Delahaye SPIRAL 2 WEEK 2011 Page 2
Experiment to characterize the release Ucx " Three new production methods have been used: " Carboreduction of UO2 targets " UO2 + 3C UC+ 2CO " Carboreduction of oxalate targets: " U(C2O4)2,2H2O+3C UC+4CO +2CO +2H2O " Fusion of carbon and uranium " U + C UC " Characterisation of the new materials " Chemical composition " density " porosity " Pores structure 26 MeV Deute rons P 1 P 2 γ P 1 γ P 2 FP " Release: γ " Irradiation " Off-line release measurements γ P 1 P 1 ov en P 2 γ FP P 2 Hanna Franberg-Delahaye SPIRAL 2 WEEK 2011 Page 3 3
Hanna Franberg-Delahaye SPIRAL 2 WEEK 2011 Page 4
Fusion évaporation targets " Turning target wheel 5000 tours / min " Febiad ion source type Vadis (tests foreseen in 2011) Hanna Franberg-Delahaye SPIRAL 2 WEEK 2011 Page 5
Developpements for light targets " Integration in the production module " Integration with the existing ion sources Hanna Franberg-Delahaye SPIRAL 2 WEEK 2011 Page 6
ION SOURCES Hanna Franberg-Delahaye SPIRAL 2 WEEK 2011 Page 7
Source ECR " Studies on the waveguide for the injection of the RF " Release times measurements connected to an oven. " Adaptation tests to a long extraction. Hanna Franberg-Delahaye SPIRAL 2 WEEK 2011 Page 8
Tests for the long extraction " Optimisation of the extractions of the production module and tests bench Hanna Franberg-Delahaye SPIRAL 2 WEEK 2011 Page 9
Source Ionisation surface Hanna Franberg-Delahaye SPIRAL 2 WEEK 2011 Page 10
Hanna Franberg-Delahaye SPIRAL 2 WEEK 2011 Page 11
Resonant Ionization Laser Ion Source " GISELE ANR project: first prototype of the SPIRAL2 RILIS (GANIL, IPNO) " TiSa System in collaboration with TRIUMF and the LARISSA group from Mainz University " Off line laser room fully equiped at GANIL (restricted area, filtered air and stabilized temp ± 1 C) 3 TiSa Cavities running Up to 3.5W of InfraRed beams produced This work is supported by the French Research National Agency (ANR) under contract n ANR-08- BLAN-0116-01 Hanna Franberg-Delahaye SPIRAL 2 WEEK 2011 Page 12
GISELE Schedule in 2011-2012 " Laser beam transport in the Hall D: May 2011 " Installation of the IPNO source prototype in the banc 2 " 1 st Off line experiment for Ga + production: June 2011 " Ionization efficiencies measurements " Ionization scheme developments 2011-2012 Hanna Franberg-Delahaye SPIRAL 2 WEEK 2011 Page 13
Laser beam transport for SPIRAL2 " Preliminary design review: 25th November 2010 SEGULA Hanna Franberg-Delahaye SPIRAL 2 WEEK 2011 Page 14
" A large variety or positioning of the TIS units inside the production module. Lentille Einzel Delay window Source 105 mm N- converter Position 105 Source Lentille Einzel Target 305 mm n- converter 40 mm Position 305 Delay window Hanna Franberg-Delahaye SPIRAL 2 WEEK 2011 Page 15
Off line tests prior to mounting in the production module - Container : Compatable with the connector system for the TIS unit Confinement for test under vaccum - Beam extraction: Compatible with all TIS units Validation of functionning of the TIS unit: heating connectors effiencies Hanna Franberg-Delahaye SPIRAL 2 WEEK 2011 Page 16
Validation and tests of each parts of the TIS units " Mounting of the different ion sources " Validations of the material used " Validation of the ion sources depending on the ion source " Mounting of target oven " Validation of materials " Tests of " Mounting of target oven and ion source on the support plate and with the connectors for the production module Hanna Franberg-Delahaye SPIRAL 2 WEEK 2011 Page 17
Construction tests - irradiation - waste Hanna Franberg-Delahaye SPIRAL 2 WEEK 2011 Page 18
Forseen for 2011 " SAC Janv./Fév. 2011: Recomendations for the firsts beams. Priorities in the developpement of targets and ionsources. " Uranium targets: " Construction of the target laboratory at IPNO " Irradiation and analysis of release from the different uranium carbide samples at temperatures of 1600ºC (irradiated dec 2010) et 2000ºC " Construction of a PARRNe size target and on-line expriment. " Fusion évaporation target " Tests with a VD ion source " Ion Sources " Extraction studies of all sources " Ionization efficiencies measurements " New Surface ion source prototype " Laser beam transport in the Hall D " First laser ionised beams at GANIL " Tests with a new Febiad IRENA version at IPNO " Installation of test bench for test of the target oven at GANIL " Off-line test bench: detailled study of the TIS unit transfert. Hanna Franberg-Delahaye SPIRAL 2 WEEK 2011 Page 19
Thank you for your attention IN COLLABORATION WITH IPNO, CENBG, LNL, GANIL Hanna Franberg-Delahaye SPIRAL 2 WEEK 2011 Page 20
Assemblage de l ensemble fourtube transfert - source et raccordement au plateau de connexion. Vérification de l étanchéité des circuits de refroidissements et tests mécaniques ok Diagnostiques sur banc réparations mineures envisageables Pb Prévoir contrôle SPR de l ensemble Transfert- mise en place sur le banc de réception (accostage au container test sous confinement car résidu de poussières) -dégazage du four et de la source -qualification de la source avec four chaud ok Pb Retrait de l ensemble du container test sous atmo. neutre, chargement de la cible dans le four (opération réalisée dans BAG)- mise en place de l ECS dans container test sous atmo.neutre Mise en place dans container test Retrait du container Retour de l ECS (non contaminé) en labo de montage Retrait de l ECS du container sous atmo. Neutre Retrait de la cible du four en BAG Contrôle SPR de l ensemble Pb -dégazage de la cible -qualification de la source avec cible chaude et identification des polluants ok -optimisation de l électrode d extraction Retrait de l ECS du container test sous atmo. neutre - transfert de l ECS vers la cellule SAS supérieur Mise en production de l ECS F.LEMAGNEN 19/11/2010 Hanna Franberg-Delahaye SPIRAL 2 WEEK 2011 Page 21
Hanna Franberg-Delahaye SPIRAL 2 WEEK 2011 Page 22