Scheduling Maintenance for Infiltration Basins and Trenches



Similar documents
PRIVATE TREATMENT CONTROL BMP OPERATION AND MAINTENANCE VERIFICATION FORM BIORETENTION FACILITIES, VEGETATED SWALES & HIGHER RATE BIOFILTERS

DESCRIPTION OF STORMWATER STRUCTURAL CONTROLS IN MS4 PERMITS

Minimizes sediment and debris from entering storm drains that lead to waterways and watercourses.

Outlet stabilization structure

Stormwater Ponds. c ıty of a bı le ne st or m wat e r utı lıty dıv ısı on

Storm Drain Inlet Protection

SUSTAINABLE URBAN DRAINAGE SYSTEMS

SE-10 STORM DRAIN INLET PROTECTION. Objectives

Maintaining water sensitive urban design elements

Operation & Maintenance Document Templates

GREEN ROOFS. Location. Design SMALL COMMERCIAL GUIDE CITY OF ATLANTA, GEORGIA DEPARTMENT OF WATERSHED MANAGEMENT

Property Care White Papers. Site Drainage: Monitor and Maintain

Storm Drain Inlet Protection

Seattle Public Utilities. Natural Drainage Systems (NDS) Maintenance Manual

City of Des Moines Stormwater Structural Control Maintenance Guidelines

4.3 Cisterns and Rain Barrels

Operations and Maintenance Plan The Residences at Johnson Farm 189 Landham Road Sudbury, Massachusetts. Submitted to: Town of Sudbury

Post Construction Stormwater Management Inspection & Maintenance PROGRAM MANUAL

Guidelines for. Permeable Pavement

Compost-Based Stormwater Best Management Practices Using Compost to Improve Stormwater Management and Erosion Control On Roadsides

APPROVAL AMENDMENT HISTORY

Interlocking Concrete Pavement Institute (ICPI) Model Stormwater Ordinance for Permeable Interlocking Concrete Pavements August 2010

Tree Pits Operation & Maintenance Guide

BMP #: Dry Wells / French Drains

P-23 - DEVELOPMENT OF DELAWARE DEPARTMENT OF TRANSPORTATION STORMWATER BEST MANAGEMENT PRACTICE INSPECTION PROGRAM

Chapter 3 CULVERTS. Description. Importance to Maintenance & Water Quality. Culvert Profile

COMBINED SEWER OVERFLOW OPERATIONAL AND MAINTENANCE PLAN SUMMARY

City of Shelbyville Site Inspection Checklist

Index. protection. excavated drop inlet protection (Temporary) Block and gravel inlet Protection (Temporary)

3.4 DRAINAGE PLAN Characteristics of Existing Drainages Master Drainage System. Section 3: Development Plan BUTTERFIELD SPECIFIC PLAN

STORM WATER MANAGEMENT PLAN (SWMP)

Use of Green Roofs to Meet New Development Runoff Requirements. Greg Davis Nov. 8, 2007

Standard Operating Procedures Storm Drain System Maintenance

CLIFTY CREEK PLANT MADISON, INDIANA

Preventing Storm Water Pollution: What We Can Do

City of Green Bay Department of Public Works Engineering Department

ADS Water Quality Units

Chapter 2 Stormwater Pollution Prevention Plan (SWPPP) for Park Operations

Travel Time. Computation of travel time and time of concentration. Factors affecting time of concentration. Surface roughness

Land Disturbance, Erosion Control and Stormwater Management Checklist. Walworth County Land Conservation Department

Flash Flood Science. Chapter 2. What Is in This Chapter? Flash Flood Processes

Gettysburg Adams Chamber of Commerce Storm Water Management

Type of Sewer Systems. Solomon Seyoum

10/4/ slide sample of Presentation. Key Principles to Current Stormwater Management

Detention Ponds. Detention Ponds. Detention Ponds. Detention Ponds. Detention Ponds. Detention Ponds. CIVL 1112 Detention Ponds - Part 1 1/12

Source Water Protection Practices Bulletin Managing Sanitary Sewer Overflows and Combined Sewer Overflows to Prevent Contamination of Drinking Water

A perforated conduit such as pipe, tubing or tile installed beneath the ground to intercept and convey ground water. or structures.

RIPRAP From Massachusetts Erosion and Sediment Control Guidelines for Urban and Suburban Areas

CONSTRUCTION STORMWATER POLLUTION PREVENTION PLAN TEMPLATE

STANDARD INSPECTION FORM GENERAL PERMIT FOR STORMWATER ASSOCIATED WITH CONSTRUCTION ACTIVITY

Construction Site Inspection. Inspecting to Keep You in Compliance

BMP 6.4.6: Dry Well / Seepage Pit

POLLUTION PREVENTION FACT SHEETS: CATCH BASINS. Description

Homeowner s Guide to Maintaining a Sewage Treatment System

PROPRIETARY WATER QUALITY PRODUCTS AND THE METROPOLITAN ST. LOUIS SEWER DISTRICT S STORMWATER MANAGEMENT PROGRAM

CITY UTILITIES DESIGN STANDARDS MANUAL

Best Management Practice Fact Sheet 7: Permeable Pavement

Improper storage of fuel on construction sites will increase the risk of water pollution that may occur as a result of leaks or spills.

APPENDIX F. RESIDENTIAL WATER QUALITY PLAN: ALLOWABLE BMP OPTIONS

Homeowner s Guide to Drainage

Local Road Assessment and Improvement Drainage Manual

COLORADO DEPARTMENT OF TRANSPORTATION STORMWATER FIELD INSPECTION REPORT - ACTIVE CONSTRUCTION

A HOMEOWNERS GUIDE ON-SITE SEWAGE MANAGEMENT SYSTEMS

Anglian Water Services Limited. Sustainable drainage systems (SUDS) adoption manual

Retention/Irrigation. Design Considerations. Soil for Infiltration Area Required Slope Environmental Side-effects

SITE-SPECIFIC BEST MANAGEMENT PRACTICES (BMP) PLAN REVIEW CHECKLIST

ENVIRONMENTAL CODE OF PRACTICE FOR CONCRETE BATCH PLANT & ROCK WASHING OPERATIONS

Total Suspended Solids: The Hows & Whys of Controlling Runoff Pollution

SECTION 5. Sediment Control Measures

WSUD maintenance guidelines. A guide for asset managers

Mosquito Control Guidelines

Storm Drain Inlet Protection for Construction Sites (1060)

Operations and Maintenance

City of Paso Robles Community Development Department Construction Site Storm Water Quality Requirements

First in Service First in Safety

Vegetative Filter Strips

SITE-SPECIFIC BEST MANAGEMENT PRACTICES (SSBMP) PLAN/STORM WATER POLLUTION PREVENTION PLAN (SWPPP) REVIEW CHECKLIST

WETLAND RESTORATION PROGRAM WATER ACT APPROVAL ADMINISTRATIVE GUIDE

Stormwater Design Guidelines Frequently Asked Questions:


piles of debris that accumulate after a rain such as leaves, trash, twigs, etc., water stains on fences and buildings, or salts extruded on bricks,

DISTRICT OF COLUMBIA WATER AND SEWER AUTHORITY. a guide to PREVENTING SEWER BACKUPS AND FLOODING

Low Impact Development Checklist

Sustainable Drainage Systems (SUDS) A guide for developers

Town of Elkton & Cecil Soil Conservation District Checklist for Joint Agency Review Stormwater Management / Erosion and Sediment Control

Block and Gravel Inlet Protection (BIP)

Maine Department of Environmental Protection Program Guidance On Combined Sewer Overflow Facility Plans

POLLUTION PREVENTION FACT SHEET: AUTOMOBILE MAINTENANCE

PROCEDURE. See: Great Lakes Coastal Wetlands (

A Developer s Guide: Watershed-Wise Development

Massachusetts Department of Environmental Protection Bureau of Resource Protection - Wetlands Program Checklist for Stormwater Report

CHAPTER 15 MUNICIPAL SEPARATE STORM SEWER SYSTEM PROGRAM REQUIREMENTS

Extreme Wet Weather in Brookfield. How to Keep Your Basement Dry During Heavy Rains and Floods

Activity Yes No N/A Notes

STORMWATER POLLUTION PREVENTION PLAN TEMPLATE. 1.0 SITE DESCRIPTION 1.1 Project Name and Location Date

Improper storage of potential pollutants will increase the risk of water pollution that may occur because of spills.

Photo Credit: Geoff Brosseau

Pervious Concrete Pavement Maintenance and Operations Guide

Post Construction and Redevelopment Inspection Manual

OPERATIONS AND MAINTENANCE GUIDELINES. CDS Stormwater Treatment Unit

Transcription:

Visual Inspection for Infiltration Practices Visual inspection is a rapid assessment procedure for qualitatively evaluating the functionality of a stormwater best management practice (BMP). Visual inspections use a set of criteria that, under certain circumstances (described in chapter 3), determine if the stormwater BMP is malfunctioning. Detailed instructions for visual inspection of infiltration practices are included below and reproduced in appendix B, part 2, which can be easily printed out and taken to the field. Scheduling Maintenance for Infiltration Basins and Trenches The following section provides discussion about each question answered on the field data sheet above. 1)Has visual inspection been conducted on this location before? It is important to determine whether this location has been previously assessed so that assessment efforts are cost effective (i.e., neither duplicated nor wasted). If previous assessment has occurred, the current assessment should verify that actions suggested by the previous assessment were completed and are effective. 2)Has it rained within the last 48 hours at this location? Many infiltration practices are designed to drain the design storm volume (i.e., water quality volume, maximum storage volume) within 48 hours (Minnesota Stormwater Steering Committee 2005). Assessing a infiltration practice within 48 hours of a rainfall event may provide additional assessment clues than assessment during a long dry period. Additionally, rainfall within the last 48 hours at a location will alter how answers to other questions in this assessment are interpreted. 3)Does this infiltration basin or trench utilize any pretreatment practices upstream? If any pretreatment practices exist they should also be inspected and maintained on a regular basis. 4)Access Access to the areas upstream and downstream of the site as well as the site itself is needed in order to properly assess the practice. This is true regardless of the level of assessment applied. 5b)Are any of the inlet structures clogged? Inlet structures should be free of any debris, sediment, vegetation, and other obstructions so that stormwater runoff can easily enter the infiltration practice. If an inlet structure is even partially clogged, suspended solids may be deposited in the upstream conveyance system, or upstream areas may flood because the conveyance systems are limited by such obstructions. Any obstructions should be removed immediately to ensure proper operation of the infiltration practice. 5c)Are any of the inlet structures askew or misaligned? Misaligned inlet structures often allow stormwater runoff to enter or exit an infiltration practice by means other than those intended by design or prevent stormwater runoff from entering the infiltration

practice at all. This condition can result in erosion, channelization, or flooding of surrounding areas, which can further exacerbate the misalignment or create other problems. Inlet structures can become misaligned for several reasons, including frost heave of the soil, vehicular collision, and geotechnical failure. Misaligned inlet structures should be repaired or replaced as soon as possible to reduce detrimental impact. Any obstructions should be removed immediately to ensure proper operation of the infiltration practice. 6)Is there standing water in the infiltration basin or trench? Standing water in an infiltration practice is the result of one of three possibilities: (1) rainfall has occurred recently such that stormwater runoff has not had 48 hours to infiltrate, (2) the infiltration rate of the practice is slow such that stormwater runoff does not infiltrate within 48 hours, but does infiltrate given enough time, or (3) the infiltration practice is clogged and does not infiltrate any stormwater runoff. If it has rained in the last 48 hours (question 2), then the infiltration practice may be functioning properly and requires additional assessment (level 2 or higher). If, however, it has not rained in the last 48 hours, it is likely that the infiltration practice is either option (2) or (3). Question 6a provides clues that may determine whether the infiltration practice is clogged. Surface sheen is caused by hydrocarbon substances such as automotive oil or gasoline and may indicate illicit discharges. If hydrocarbons are proven not to be illegally discharged into the infiltration practice, then a surface sheen may indicate that stormwater runoff is stored in the infiltration practice such that the small amounts of hydrocarbons typically found in stormwater runoff are accumulating. If this is happening, then the infiltration practice is failing. There are several illicit discharge manuals available for identifying, locating, and eliminating illicit discharges (e.g., Brown et al. 2004). Stormwater runoff with a murky color is evidence of a high suspended solids concentration that is most likely made up of fine particle sizes, such as clays and silts, because sand particles settle out of standing water very rapidly (as discussed in Chapter 10: Sedimentation). Stormwater runoff with a murky color further indicates that the watershed may be a significant source of fine particle suspended solids, which can quickly clog an infiltration practice. Stormwater runoff with a green color from algae or biological activity has been stored in the infiltration practice for a long period of time such that microorganisms have developed. The infiltration practice is not infiltrating stormwater runoff and is therefore failing. 7)Is there evidence of illicit storm sewer discharges? An illicit discharge manual (e.g., Brown et al. 2004) should be consulted for identifying and locating illicit stormwater discharges. 8)Does the infiltration basin or trench smell like gasoline or oil? If an infiltration practice smells like gasoline or oil it is possible that hydrocarbon substances such as automotive oil or gasoline are being illicitly discharged into the practice or upstream in the watershed. If

hydrocarbons are proven not to be illegally discharged into the infiltration practice, then an oil/gasoline smell may indicate that stormwater runoff is stored in the infiltration practice such that the small amounts of hydrocarbons typically found in stormwater runoff are accumulating. For more information on identifying, locating, and eliminating illicit discharges, refer to a manual such as Brown et al. (2004). 9)What is the approximate percentage of vegetation coverage in the practice? Vegetation in the bottom of an infiltration basin can increase the infiltration effectiveness. Plants can lose 30% of their root structures annually, which produces macropores. Macropores in a infiltration practice can increase the infiltration rate of the basin or trench so that more stormwater runoff is infiltrated. Additionally, vegetation can reduce overland flow velocities and can therefore reduce erosion and resuspension of captured solids. Infiltration trenches typically have a larger grain size so that vegetation cannot grow without clogging of the pores. Vegetation can also be an indication of the drain time of an infiltration basin. Terrestrial vegetation often cannot withstand long periods of inundation, and some cannot withstand short periods of inundation. If an infiltration practice has an abundance of terrestrial vegetation, it is likely that the practice infiltrates stormwater runoff quickly (< 48 hours) and is therefore operating properly. If, however, the infiltration practice has signs of aquatic vegetation, the practice may not be infiltrating stormwater runoff and is therefore failing. 10)Are there indications of any of the following in the bottom of the infiltration basin or trench? Sediment deposition may indicate that pretreatment devices have reached sediment storage capacity, are not efficiency removing settable solids, or are not present. Sediment deposition may also indicate a significant source of sediment in the watershed that may require remediation to prevent downstream pollution. Sediment deposition reduces the surface area available for infiltration and therefore can reduce the stormwater runoff volume that is infiltrated. Erosion or channelization indicates that the velocity of flow entering, or in, the infiltration practice is large or that stormwater runoff is entering the infiltration practice by means other than those intended by design. Erosion or channelization indicates that the velocity of flow entering, or in, the infiltration practice is large or that stormwater runoff is entering the infiltration practice by means other than those intended by design. In either case, stormwater runoff is not stored such that significant infiltration is occurring in the areas where erosion and channelization are present. Vegetation, especially with deep roots, can increase and maintain infiltration rates in infiltration basins and trenches. If the surface of the infiltration practice becomes clogged or sealed, vegetation can provide pathways for stormwater runoff to penetrate the surface and subsequently infiltrate into the underlying soils. Excessive vegetation, if greater than the optimal vegetative density, can negatively impact the performance of the system. Thus, vegetation in infiltration basins and trenches should only be controlled to reduce the plant density or if it is undesirable for aesthetic or nuisance reasons. Bare soil or lack of healthy vegetation significantly different from the original design may indicate that the infiltration practice is not operating properly. For example, if the infiltration basin or trench was

designed to include vegetation and that vegetation has died or is unhealthy, it could indicate standing water has remained in the system for excessively long time periods. This may also be indicated if the plants are transitioning from the original vegetation to wetland species. Litter and debris in an infiltration practice are indications that pretreatment practices are failing or not present. Litter and debris may limit the effectiveness of infiltration practices by reducing the surface available for infiltrating stormwater runoff. Most infiltration basins and trenches are designed to pass runoff within 48 hours. If it has been more than 48 hours since the end of the last runoff event and the infiltration basin or trench still has standing water on the surface, it is an indication that the basin or trench is clogged and/or not operating properly. 11)Are there indications of any of the following on the banks of the infiltration basin or trench? Erosion or channelization on the banks of an infiltration practice indicates that stormwater runoff is entering at a large velocity by means other than those intended by design. Erosion and channelization on the banks can fill the practice with sediments from the bank and subsequently reduce effectiveness by clogging the soil or sealing the surface and reducing the volume available for stormwater storage. Soil slides or bulges indicate that the soil is, or potentially will be, unstable and further sliding or bulging may lead to complete bank failure. If this occurs, the filtration unit could become completely clogged and the collapsed soil could be washed downstream. Animal burrows may also lead to soil failure and clogging of the infiltration basin or trench as described in the previous paragraph. Seeps and wet spots indicate subsurface flow into the infiltration basin or trench and could lead to soil slides or erosion and channelization on the banks of the practice. Poorly vegetated areas can lead to increased erosion, which can clog the infiltration basin or trench and lead to the collapse of the bank. Trees on constructed slopes can damage the infiltration practice and the loss of leaves in the autumn can lead to clogging of the infiltration basin or trench. 12)Is the bottom of the infiltration basin or trench covered with a layer of silts, clays, or both? A visible layer of silts, clays, or both is a likely indication that the infiltration practice is clogged. Infiltration basins collect particles on the surface and in the pore spaces of the soil. Silts, clays, or both present on the surface of the basin or trench indicates that the pore spaces within the soil are likely filled or that stormwater runoff is stored in the basin or trench long enough for these fine particles to

settle out or for the stored stormwater runoff to evaporate. The infiltration practice is not likely infiltrating stormwater runoff in less than 48 hours as recommended by design guidelines (Minnesota Stormwater Steering Committee 2005). 13)Are any overflow structures clogged? Infiltration basins and trenches typically have overflow structures instead of outlet structures. Outflow for an infiltration practice is intended to go into the soil such that deep percolation or evaporation occurs. The overflow structure should be free of any debris, sediment, vegetation, and other obstructions so that stormwater runoff can easily exit the infiltration practice in the event of a large storm event. If the overflow structure is partially or completely clogged, surrounding areas may be flooded by stored stormwater runoff. Any obstructions should be removed immediately to ensure proper operation of the infiltration practice. 13b)Are any of the overflow structures askew or misaligned from the original design or otherwise in need of maintenance? Misaligned overflow structures often allow stormwater runoff to enter or exit an infiltration practice by means other than those intended by design or prevent stormwater runoff from entering the infiltration practice at all. This condition can result in erosion, channelization, or flooding of surrounding areas, which can further exacerbate the misalignment or create other problems. Overflow structures can become misaligned for several reasons, including frost heave of the soil, vehicular collision, and geotechnical failure. Misaligned overflow structures should be repaired or replaced as soon as possible to reduce detrimental impact. Any obstructions should be removed immediately to ensure proper operation of the infiltration practice. Other issues requiring maintenance include large cracks in concrete structures, corrosion, dents or malformation of the structure, etc. 14) Inspector's Recommendations. When is maintenance needed? Maintenance is needed before the next rainfall for: Completely clogged inlet or overflow Standing water more than 48 hours after runoff has entered the practice (determine the cause) Significant erosion on the banks or within the basin Damaged/misaligned/askew inlet or overflow such that flooding or structural instability of adjacent roadways or infrastructure may result Maintenance is needed before the next rainy season for: Partially clogged inlet or overflow Misaligned inlet or overflow structures that have resulted in some erosion Vegetation coverage less than 50% of the design coverage Significant sediment deposition (capacity testing for scheduling) Litter, large debris, and solid waste Sediment deposition downstream of the practice

Erosion downstream of the practice Evidence of illicit discharge Excessive or invasive vegetation Maintenance is needed within a year or two for: Misaligned inlet/outlet structures that have not resulted in erosion Some sediment deposition (capacity testing for scheduling) References Brown, E., D. Caraco, and R. Pitt. 2004. Illicit Discharge Detection and Elimination: A Guidance Manual for Program Development and Technical Assessment. Center for Watershed Protection, Ellicott City, MD. Minnesota Stormwater Steering Committee. 2005. The Minnesota Stormwater Manual. Developed by Emmons and Olivier Resources for the Stormwater Steering Committee, Minnesota Pollution Control Agency, St. Paul, MN. http://www.pca.state.mn.us/water/stormwater/stormwater-manual.html

Scheduling Maintenance for Porous Pavements The following section provides discussion about each question answered on the field data sheet above. 1)Has visual inspection been conducted on this location before? It is important to determine whether this location has been previously assessed so that assessment efforts are cost effective (i.e., neither duplicated nor wasted). If previous assessment has occurred, the current assessment should verify that actions suggested by the previous assessment were completed and are effective. 2)Has it rained within the last 48 hours at this location? Porous pavement is designed to drain the design storm volume (i.e., water quality volume, maximum storage volume) immediately (Minnesota Stormwater Steering Committee 2005). Assessing a porous pavement within 48 hours of a rainfall event may provide additional assessment clues than assessment during a long dry period. Additionally, rainfall within the last 48 hours at a location will alter how answers to other questions in this assessment are interpreted. 3)Is there standing water on top of the porous pavement? For any runoff volume that does not exceed the design storm, porous pavement should not have any standing water. Standing water on top of porous pavement is the result of two possibilities: (1) substantial rainfall above design has occurred recently such that the stormwater has not been able to infiltrate, (2) the porous pavement is clogged and does not infiltrate sufficient stormwater. 4)Are there indications of any of the following on top of the porous pavement? Sediment deposition may indicate a significant source of sediment in the watershed that may require remediation to prevent downstream pollution. Sediment deposition limits the porous pavement surface area available for infiltration and therefore can reduce the stormwater runoff volume that is infiltrated. Litter or debris, on a porous pavement may indicate that pretreatment practices are failing or not present. Litter and debris may also limit infiltration by reducing the surface available for infiltrating stormwater runoff. 5) Inspector's Recommendations. When is maintenance needed? Maintenance is needed before the next rainfall for: Standing water more than 48 hours after runoff has entered the practice (determine the cause) Maintenance is needed before the next rainy season for: Significant sediment deposition (capacity testing for scheduling) Litter, large debris, and solid waste Maintenance is needed within a year or two for: Some sediment deposition (capacity testing for scheduling)

References Minnesota Stormwater Steering Committee. 2005. The Minnesota Stormwater Manual. Developed by Emmons and Olivier Resources for the Stormwater Steering Committee, Minnesota Pollution Control Agency, St. Paul, MN. http://www.pca.state.mn.us/water/stormwater/stormwater-manual.html