RFI Response RFP: HSCG88-16-R-PQQ015 Replace HVAC Bldg A & C San Diego, CA.



Similar documents
A. The Commissioning Authority (CxA) has been contracted or will be contracted directly with the Owner for this project.

Presentation Outline. Common Terms / Concepts HVAC Building Blocks. Links. Plant Level Building Blocks. Air Distribution Building Blocks


UNIVERSITY OF MISSOURI Heating Ventilating and Air-Conditioning (HVAC) March

HVAC Simplified Approach Option

SECTION TESTING, ADJUSTING, AND BALANCING FOR HVAC INTRODUCTORY INFORMATION

UNIFIED FACILITIES GUIDE SPECIFICATIONS

HVAC Systems: Overview

Commissioning - Construction Documents (Page 1 of 6)

Innovent LASER Packaged Fresh Air Conditioning Units

ASTACEA4 Inspect complex/central air conditioning systems

Example Retrocommissioning Measure: Opening Throttled Discharge Valves

Design Guide. Retrofitting Options For HVAC Systems In Live Performance Venues

1. What percent of a commercial business s energy usage comes from their HVAC system? A. 13% B. 23% C. 33% D. 43% E. 53%

Element D Services Heating, Ventilating, and Air Conditioning

QUESTIONS TO ASK WHEN REPLACING YOUR HVAC TOGETHERWESAVE.COM

Air Conditioning. The opportunity for energy efficiency. Low cost actions to reduce energy usage now

Terms of Reference Air Handling Unit (HVAC System) Cleaning

HVAC Checklist - Long Form

Basics of HVAC Cleaning

Sample Company SECTION GENERAL COMMISSIONING REQUIREMENTS PART 1 GENERAL 1.1 SUMMARY AND CONTRACT RESPONSIBILITIES

SECTION PACKAGED ROOFTOP AIR CONDITIONING UNITS NON-CUSTOM

Replacement of Heating, Ventilation, Air Conditioning (HVAC) Units In Apartments Located at 641 Fifth Avenue. Photo Essay

Guide Specification SECTION COMMISSIONING OF HVAC PART 1 - GENERAL 1.1 SUMMARY

for Plans Examiners and Building Inspectors

Glossary of HVAC Terms

ENHANCED LABORATORY HVAC SYSTEM

NEBB STANDARDS SECTION-8 AIR SYSTEM TAB PROCEDURES

SAM HOUSTON STATE UNIVERSITY

2 STEPS TO CONDUCTING YOUR HVAC ASSESSMENT

COMPETENCY ANALYSIS PROFILE Refrigeration and Air Conditioning Systems Mechanic - Branch 1 313A

SECTION PACKAGED ROOFTOP AIR CONDITIONING UNITS

KU DESIGN GUIDELINES APPENDIX XVI RECOMMENDED BAS I/O CONTROL POINTS BY EQUIPMENT / SYSTEM

HVAC Processes. Lecture 7

HEATING, VENTILATION & AIR CONDITIONING

Building Energy Systems. - HVAC: Heating, Distribution -

Mechanical Systems Proposal revised

Variable Air Volume - VAV

Rev. No. 0 January 5, 2009

SECTION HEAT PUMPS

DEPARTMENT OF CODES AND BUILDING SAFETY FLOOD RECOVERY INFORMATION

Attached is a link to student educational curriculum on plug load that provides additional information and an example of how to estimate plug load:

Guidelines for energy efficient heating, ventilation and air conditioning (HVAC) systems

Variable Refrigerant Flow Systems

Home Management Checklist: Spring

Topics for Today. Order of Magnitude Mechanical Estimating. Order of Magnitude Estimate Goal. Project Delivery Methods. Questions for Client

Advanced Energy Design Guide LEED Strategies for Schools. and High Performance Buildings

BSD Technical Standard Division 23: HVAC

The Different Types of Air Conditioning Equipment for IT Environments

Energy Efficiency in Industrial HVAC Systems

Air Conditioner Water Heater - A Product of HotSpot Energy LLC

Building Commissioning

REAL OPERATING COST SAVINGS FROM RETRO- COMMISSIONING OPPORTUNITIES FOR SAVINGS IN ACADEMIC MEDICAL CENTERS

3/29/2012 INTRODUCTION HVAC BASICS

Key energy-efficient features of your new home

SECTION HEATING, VENTILATION AND AIR CONDITIONING EQUIPMENT

PROPERTY INSPECTION OR ASSESSMENT OF DAMAGES

HVAC Claims: Repair vs. Replacement

Chilled Water HVAC Systems

ALBUQUERQUE PUBLIC SCHOOLS Facility Design & Construction / Maintenance & Operations

FREQUENTLY ASKED QUESTIONS about HERS and CHEERS Provided by the California Energy Commission Consumer Energy Center

air conditioners how to choose a cooling system

MEETING AGENDA. Project Administrator:

Evaluate, Clean, and Tune Guidance

CONTROL STRATEGIES FOR HVAC SYSTEMS

HVAC Characteristics. Test Space HVAC Characteristics

Sample - Existing Building Commissioning Plan

Modeling and Simulation of HVAC Faulty Operations and Performance Degradation due to Maintenance Issues

Using Time-of-Day Scheduling To Save Energy

newsletter engineers energy-saving strategies for Water-Source Heat Pump Systems volume 36 2 providing insights for today s hvac system designer

SECTION HVAC AIR-DISTRIBUTION SYSTEM CLEANING

NOTICE INVITING BIDS. CIVIC FACILITIES AIR CONDITIONING REPLACEMENT PROJECT, CIP No

HVAC Systems in Schools & Commercial Buildings and Radon

Thermal Imaging for Home Inspectors

Flexibility, Efficiency In San Antonio Arena

This permit does not include replacement or upgrading of the existing electrical panel or service (a separate electrical permit must be obtained).

Glossary of Heating, Ventilation and Air Conditioning Terms

COMMISSIONING OF HVAC SYSTEMS

AIR CONDITIONING EFFICIENCY F8 Energy eco-efficiency opportunities in Queensland Foundries

APPLICATION GUIDE. Comparison of Latent Cooling Performance of Various HVAC systems in a Classroom Application

Before You Start an Energy Efficiency Retrofit The Building Envelope

The Only GUY To Call. Why are my utility bills so high? What can I do to lower my energy expenses?

DATA CENTER COOLING INNOVATIVE COOLING TECHNOLOGIES FOR YOUR DATA CENTER

Design Consultant (Electrical Services) Design Deliverables and Responsibilities Allocation (Stage E+)

Air Conditioner Water Heater Model ACWH18

Phone: (201) Phone: (212) Fax: (973)

Heating Load HERS: Calcs Duct Seal and Test (h), (m)1-3 & 11

CHAPTER 8 HVAC (Heating, Ventilation, and Air-Conditioning)

Residential HVAC Load Sizing Training October 14, David Kaiser Green Code Plan Reviewer

Heating Ventilation and Air Conditioning Diagnostics for Single Family Homes

Lesson 36 Selection Of Air Conditioning Systems

Air Conditioning Equipment

Replacing Your Heating and Air Conditioning System

Dehumidification Frequently Asked Questions

RESIDENTIAL HEATING OIL SERVICE CONTRACT ANNUAL COST $276.00

By Tom Brooke PE, CEM

Bring the fresh in. Dedicated Outside Air Systems

SECTION TESTING, ADJUSTING, AND BALANCING

Transcription:

1. There is verbiage in the hazardous material report referring to a state licensed abatement contractor. Within the recommendations part of the report (page 64 of 111 of the specification pdf) is the statement EAI recommends that any identified LBPs be removed by a state-licensed abatement contractor prior to any activities that may disturb the materials. Is this merely a recommendation by a consultant or is it a requirement of this contract that the abatement subcontractor have a California contractor s license? Will any other subcontractor be required to have a California contractor s license? R: All installation shall be performed as allowed by State licensed contractors. 2. Building A scope states to convert the existing constant air volume AH-2 to variable air volume. Confirm new supply fan and return fan VFDs and motors with grounding rings should be included in the scope of work? R: The conversion shall be from Constant Air Volume (CAV) to Variable Air Volume and Temperature (VVT), not Variable Air Volume (VAV). 3. Page 40, Section 7) VAV Terminal Units states use parallel type Fan-Powered VAV terminal units with temperature rise across electric reheat coils with ECM fan motors. The existing reheat coils are hot water. Please confirm a digital single duct VAV box with hot water reheat coils is acceptable? Fan-Powered VAV box with electric reheat will not be required. R: This is a design-build project. Contractor shall follow his engineer and manufacturer s recommendations. 4. Building C scope states to demolition of air handler unit. Confirm the air handler unit to be demo is AH-1 (located in the boiler mechanical room) serving the Recreation Area? 5. Confirm the base work Building C will have new VRF fan coils serving the Recreation Area? 6. Does the VRF outdoor heat pump unit Qty (5) require any enclosure around the concrete pads? R: No fence screening required.

7. Please confirm pre-tab air-balance readings should be included in the scope of work for Building A? R: Provide pre-tab air balance readings are not necessary. 8. Is a 3rd party commissioning agent involved? If so what level of commissioning will be done? a. Submittal review b. Construction document review c. Pre-functional testing d. Functional performance testing R: Third party commissioning agent is not required. TAB agent shall be a first subcontractor to the prime; and financially and corporately independent of the mechanical subcontractor. 9. Is a warranty coverage required for refurbished items such as existing pumps and air units? R:For refurbished items, provide one-year full warranty. 10. Where existing equipment is to be reused has it been verified for capacity, head or static pressure requirements for the addition of new equipment? 11. The specifications call for temporary heating and cooling. Where temporary heating and cooling is required what are the design conditions for temperature and humidity? R: Portable fans and heaters are acceptable for temporary cooling and heating needs during shutdown of HVAC system for construction. The acceptable temperature is 65 F in winter. Assume 24 hours 7 days operation. 12. What are the hours of operations for the temporary heating and cooling system? R: See response in #11. 13. Are there any spaces that require special temperature and humidity conditions such as IT rooms or others? R: No. 14. Page 53, para 3.01.A The SOW indicates to To minimize interruption of building operation, contractor shall shut down one structure at a time, as well as

Provide temporary heating and cooling equipment during construction to allow continued operation of the building. This will be difficult and expensive to accommodate as written. If temporary heating and cooling equipment is construed as portable fans and electric floor heaters, no problems. From a shut-down perspective, Bldg A is no problem. However, the new condensing units for the (5) individual VRF systems in Bldg C will require removal of the existing chiller before any new work can commence. This means that all 5 sections of Building C will be without central heating and air one work commences and until work is finished. Can portable fans and portable floor heaters be used in these buildings for the duration of construction in those building? R: See response in #11. 15. Page 3, para 1.03 indicates all site work shall be between the hours of 7:00 am and 5:00 pm, Monday through Friday. Page 53, para 3.01.A indicates Working on after working hours or weekend may be required to minimize interruption of building operation.. Can we assume we can work weekends or nights when required and coordinated in advance? 16. The SOW only calls for cleaning of ductwork in Bldg A, not Bldg C. Please confirm. 17. Existing ductwork in Bldg A and C is in fair to poor condition. Our concern is that this ductwork is appx 30 years old, and air leakage through existing failed duct joints may compromise functionality of the new system. Our recommendation to avoid this issue is to (minimally) remove existing duct insulation, inspect all ductwork, repair or replace with new any damaged ductwork discovered, reseal all duct joints, and re-insulate. Alternatively, for not much more cost new ductwork throughout could be provided. The age and apparent condition of the existing ductwork indicates it is at the end of its service life. Will the CG provide direction for this issue? R: See Schedule B for Revised Option Items. Inspection of ducts shall be part of the Base Item. Two (2) new Option Items are now included in the Schedule B: 1. Repair Duct Work, 2. Replace all Duct work with new. 18. Will the Construction Docs be required to be submitted and approved to/by the City of San Diego Plan Check Dept? R: No

19. Bldg A the SOW (para 1.01.a.1.a) indicates (in essence) to demo existing reheat coils and replace with new VAV Terminal Units (TU s) with reheat coils. These TU s would be provided with air from an older, to-be-re-furbished constant volume cooling only AHU, with a new bypass damper being provided for air volume control. The SOW (para 1.01.a.1.d) also indicates Implement all mandatory control strategies per California Title 24 as allowed by the modification. It would appear this project would not be allowed per T24 requirements, due to the simultaneous heating and cooling, as well as the lack of airflow reduction before heating is implemented. Please advise. R: Contractor shall calculate max. cooling (primary) airflow; min. cooling (ventilation setting) airflow, min. heating (max. of ventilation and 30% of primary) airflow (during cooling mode) settings. All hot water reheat coils shall be sized to satisfy space heating requirement at min heating airflow setting. New DDC control shall incorporate, include but not limit to, zone temperature control, night setback, morning warm up, economizer control, hot water temperature reset and all applicable control strategies that are not restricted by the existing equipment. In addition, cut off hot water boiler and pump when outside air temperature reaches 65 F and above. 20. Bldg C - Page 39, para 1.04.E indicates an economizer shall be provided. This is on the VRF system. There is no manufacturer that sells a VRF system with an economizer cycle for the refrigerant. Can we assume this requirement is void? R: Delete Page 39, par 1.04E. 21. Bldg A Page 56, para 3.03 calls for cleaning, flushing, and pressure testing of all existing piping systems that are to be reused. These piping systems are over 30 years old, and have been through several earthquakes. We plan on performing an air test first, followed by a hydro test at 1.5X minimum working pressure, or 100 psi, whichever is greater. Should the piping/joints fail the hydro test who will be responsible for the cost of piping repairs? More importantly, a failure may result in water damage; who will be responsible for cleanup? With the unknowns of this system, would the USCG want to consider replacing all existing heating water piping in building A? R: Visual inspect the entire hot water heating piping system for leaks prior to replacing hot water reheat coils, report all leaks to KO. Assure no leaks on all new work and repair as necessary before insulate the pipes. No pressure test is required. 22. Bldg A and C: New HVAC equipment to be provided will be furnished to replace existing equipment. No new HVAC zones will be provided, except if requested in the future by the USCG. Please confirm.

R: Provide HVAC system and zones in accordance with functions of the buildings and engineer s recommendation and applicable codes. 23. Page 48, para 1.06.K: A two year unlimited warranty is specified. However, on page 9, para 1.13 a one year warranty is indicated. Is the requested warranty one or two years? R: Two Years 24. Bldg C Can we assume that routing of new VRF refrigerant piping can follow the same routing as the existing chilled water piping? On this same topic, some new piping may be required to cross from building to building at the ceiling of the covered walkway. Can this piping be exposed? R: For Building C, each structure shall have its own independent heat pump or heat recovery system and control. If some new piping is required to cross from building to building, this piping shall be properly protected in accordance with manufacturer s recommendations and applicable structural codes. 25. Bldg A and C Should we plan on adding attic insulation? R: Only Building A as instructed by the spec. 26. Bldg A page 31, para 1.01.a.d: SOW indicates to provide major maintenance and rehab work on the existing HVAC equipment. Para 1.04, fifth para calls out all coils, and fins shall be of copper or factory corrosion resistant coatings. This section also indicates 250hr salt test finish for indoor and 1000hr salt test for outdoor equipment. Can we assume these requirements (for coils and cabinets) do not apply to the existing ahu/condensing unit? Note that if these requirements are applicable, it would probably be cheaper to provide new equipment than to dis-member existing equipment and rebuild using new components. R: Paragraph 1.04 applies to new equipment. 27. The specification 01 61 00 Part 3 Execution 3.01 Special Requirement F.2 states all refrigerant pipe joints shall be brazed. Due to the building wood structure and potential fire risk we would like to use a mechanical joint connection method that is approved by the VRF manufacture. VRF Manufactures have approved mechanical fitting methods for refrigerant piping installations for applications such as this. Will a mechanical fitting connection vs. a brazed joint method be allowed for refrigerant piping?

R: No mechanical joint connection is allowed.