CITY OF EL PASO: SUN METRO Legislative Update Briefing

Similar documents
Mid-Coast Corridor Transit Project San Diego, California New Starts Project Development (Rating Assigned November 2014)

Chapter 8 Funding Considerations

30 Years of Smart Growth

Eagle Commuter Rail Denver, Colorado Final Design (Based upon information received by FTA in November 2010)

Light Rail Transit in Phoenix

Performance Measures. First Quarter 2012

ORANGE COUNTY TRANSPORTATION AUTHORITY. Final Long-Range Transportation Plan - Destination Attachment A

Financial Plan & Implementation. Matrix

Chapter VIII: Long-Term Outlook and the Financial Plan

What we build today will create Denver s tomorrow. Signature development projects will strengthen our economy, create jobs and improve neighborhoods.

STATE OF DELAWARE DEPARTMENT OF TRANSPORTATION CAPITAL TRANSPORTATION PROGRAM TRANSIT FACILITIES 3-306

MANAGEMENT PLAN. Fiscal Year

Executive Summary. Does a Streetcar Make Sense in Anaheim

2014 SFMTA Transit Fleet Management Plan March 2014

Southwest Light Rail Transit Minneapolis-St. Paul, Minnesota New Starts Project Development (Rating Assigned November 2014)

Transportation Funding Overview SAMCo. Victor Boyer, Executive Director San Antonio Mobility Coalition (SAMCo) January 10, 2006

From the FTA 5310 Circular (C9070.1F): 1. ELIGIBLE CAPITAL EXPENSES. Funds for the Section 5310 program are available for capital expenses as defined

Transportation Best Practices for Serving Low Income Residents National Resource Network 311 for Cities

Operating Budget. MARIN TRANSIT SHORT RANGE TRANSIT PLAN Chapter 5: Financial Plan

ATTACHMENT K 5310 ELIGIBLE COST

Transit in the United States 3. Operating Costs and Performance Measures 13. Quality of Transit Service 19. ADA Compliance Bus 28

FISCAL YEAR 2014 SOLICITATION FOR PROPOSALS FOR FEDERAL JOB ACCESS AND REVERSE COMMUTE AND NEW FREEDOM PROGRAM FUNDS EVALUATION CRITERIA

CHAPTER 5-CMPO TRANSPORTATION VISION PLANS (2035 & BEYOND)

South Waterfront Area Dave Unsworth

FINANCIAL PLAN. Any future earmarks are assumed to carry their own limitation and not reduce the regular limitation identified in these calculations.

Narrative Response/Attachment 1 (WisDOT TAP- Second Round Application ID-SWBP22)

Cost and Financial Analysis

METRO. Fiscal Year 2013 Monthly Board Report. June 2013 (Third Quarter Fiscal Year-to-Date)

Coordinated Plan Update and Funding for Transit

City Services Benchmarking: Public Transportation

PUBLIC TRANSPORTATION DEPARTMENT MUNICIPALITY OF ANCHORAGE 2009 TRANSPORTATION GRANT APPLICATION PACKET

Presto Fare Card ibus (Automated Stop Announcements, Cameras) Transit Operating System Replacement

Transition from SAFETEA-LU to the new MAP-21 Federal Transportation Act

How To Vote On A Transit Plan In Ventura County

National Transit Database - NTD

STRATEGIC BUSINESS PLAN QUARTERLY KPI REPORT FOR: FISCAL YEAR 2015, QUARTER 2 (JULY THROUGH DECEMBER 2014)

Performance Goals and Objectives:

4. Technology Assessment

Transportation. McKinley County Map of Roads. Trucking. Federal Express RAC Transport United Parcel Service Yellow Freight Line

Jess Linn Principal Planner, Development Services Division Miami-Dade Regulatory and Economic Resources

SOUTHWEST-TO-NORTHEAST TRANSPORTATION CORRIDOR STUDY

Transportation Alternatives

Employer Transit Benefits Toolkit. Brought to you by godcgo

MAP-21. A Guide To Transit-Related Provisions MAP-21. Moving Ahead for Progress in the 21st Century

J. Craig Venter Institute, La Jolla Transportation Demand Management Plan

HYBRID BUSES COSTS AND BENEFITS

Enhanced Mobility of Seniors and Individuals with Disabilities

Frequently Asked Questions (FAQs) about DART

Triangle Transit Financial Plan. Durham Orange Light Rail Transit Project

Los Angeles Union Station, CA Sustainable Neighborhood Assessment. April 22-23, 2014

TRANSIT PERFORMANCE MEASURE TOOLBOX EXECUTIVE SUMMARY

WHY NOW? GAS? The Design. Nopetro

Chicago Neighborhoods 2015: Assets, Plans and Trends A project of The Chicago Community Trust

Equity in Transportation for People with Disabilities

Analysis of the Obama Administration s FY 2017 Budget Proposal for Transportation

Fiscal impact analysis of three development scenarios in Nashville-Davidson County, TN

When is BRT the Best Option? 1:30 2:40 p.m.

1004 VEHICLE AND FLEET SERVICE POLICY. I. Legislative Authority:

Summary of MAP-21 Matrix

Philadelphia County. Land Use and Growth Management Profile

Connecticut s Bold Vision for a Transportation Future

City of Orlando Economic Development Tools for Job Growth and Economic Prosperity

DRAFT. Martha's Vineyard Coordinated Human Services Transportation Plan

Fleet Management Services

RDA Development Opportunities

The financial plan was prepared in conjunction with the Technical Working Group. Refer to Table 3-1: Funding and Implementation Plan.

Transcription:

CITY OF EL PASO: SUN METRO Legislative Update Briefing Updated March 2014

OUR VISION The mission of Sun Metro is to provide a first-class public transportation service to all El Pasoans and visitors so they can experience safe, reliable, professional, courteous customer service and economic opportunity. 2

TRANSIT REAUTHORIZATION Support a long-term bill that establishes a dedicated trust fund mechanism that supplements existing revenues, preserves dedicated revenues to the Mass Transit Account, and maintains a strong federal program for public transportation 3

TRANSIT REAUTHORIZATION Restoration of the bus capital funding to the pre-map 21 level of $948 million Bus and Bus Facilities program was reduced from $984 million in FY 2012 to $422 million in FY 2013 a cut of more than 57 percent at a time of increasing ridership Support to adjust Bus and Bus Facility (Sec. 5339), State of Good Repair (SGR) (Sec. 5337), and New Starts (Sec. 5309) funding and reestablish a 20/40/40 capital investment ratio among these three grant programs 4

PRESIDENT'S FY2015 BUDGET INCLUDES $302 BILLION, 4-YEAR REAUTHORIZATION Sun Metro supports President Obama s Fiscal Year 2015 budget proposal for increasing investment in transportation and for recognizing the need to address the imminent shortfall in the Highway Trust Fund and the Mass Transit Account before the current transportation legislation, (MAP-21) expires on September 30 5

ALTERNATIVE FUELS TAX CREDIT The Alternative Fuels Tax Credit provides public transportation providers with financial assistance in the form of a tax credit, to assist with converting their bus fleets from diesel to compressed natural gas Sun Metro s tax credit is over $2.5 million annually Alt fuels tax credit expired Dec 2013 Support extension of the Alternative Fuels Tax Credit, retroactive Jan 2014 6

COMMUTER TAX BENEFIT In 2013, commuters who use public transportation could receive tax free benefits up to $245 per month Public transit and vanpool commuters will now see their maximum allowable pre-tax and tax-free benefit plunge to $130 per month Support to re-establish the Commuter Tax benefit to 2013 levels of $245 per month 7

SNAPSHOT OF SUN METRO 17 million bus passengers in 2013 200,000+ paratransit trips 166 buses 65 ADA (LIFT) buses 12 JARC (Job Express) vans 100% CNG bus fleet 643 employees (city and under contract) Annual operating budget over $66 million Fixed Route managed by First Transit 8

SUN METRO S MAJOR ACHIEVEMENTS! 2008 Texas Transit Association Outstanding Metropolitan System Award! Texas Municipal League Intergovernmental Risk Pool recognized Sun Metro for reducing accident claims by 45%! First Transit Award for Lowest Collision Rate per 100,000 Miles! Gold 2009! Silver 2010! Bronze 2011 & 2012 9

SUN METRO S MAJOR ACHIEVEMENTS! Southwest Transit Association Spotlight Awards (2009, 2010, 2011 and 2012)! 2011 American Public Transportation Association Outstanding Public Transportation System! Ranked 4 th in the nation by Brookings Institute for Share of Working-Age Residents with Access to Transit (94.3%) 10

CURRENT AND FUTURE DEVELOPMENTS New Operations & Maintenance Facility ($38M: FTA $712K) Four BRT Corridors known as Sun Metro Brio ($140M: 42.6% FTA) Five Points Transit Center Renovation ($1.25M: FTA and local) Two additional transfer centers ($10M: FTA and local) Proposed Streetcar System ($95M: State and local) Three Transit-Oriented Development (TOD) communities Northgate Transfer Center & TOD ($10M Tiger/$5M local) Far-East Transfer Center & TOD Five Points Terminal & TOD 11

NEW TRANSIT OPERATIONS CENTER OPERATIONAL MAY 2014 12

ABOUT THE TRANSIT OPERATIONS CENTER! Location: Montana at Lorne Road! Built on 35.5 acre site:! 26,099 sq. ft. Operations Building! 95,778 sq. ft. Maintenance Building! 13,913 sq. ft. Fueling Dispenser Facility! 9,227 sq. ft. Bus Wash Facility! Construction Cost: approx. $27.6 million! Fueling Facility: public-private partnership with Clean Energy! Bus parking area with canopy to house fleet 13

BRIO RAPID TRANSIT SYSTEM 14

ABOUT BUS RAPID TRANSIT 15

ABOUT BUS RAPID TRANSIT 16

ABOUT THE MESA BRT CORRIDOR Length: 8.6 miles Beginning of route: Downtown Transfer Center End of route: Westside Transfer Center Total no. of buses: 10 No. of stations: 22 Total: $27.1 million FTA funding: $13.5 million Operational: July/Aug 2014 18

ABOUT THE ALAMEDA BRT CORRIDOR Length: 14.5 miles Beginning of route: Downtown Transfer Center End of route: Mission Valley Transfer Center Total no. of buses: 14 No. of stations: 29 Total: $35.5 million Funding: 100% City of El Paso and Sun Metro Operational: Feb 2016 19

ABOUT THE DYER BRT CORRIDOR Length: 10.2 miles Beginning of route: Downtown Transfer Center End of route: Future Northeast Transfer Center Total no. of buses: 10 No. of stations: 22 Total: $35.7 million FTA funding (applied): $20.4 million Operational: Jan 2018 20

ABOUT THE MONTANA BRT CORRIDOR Length: 16.8 miles Beginning of route: Five Points Transfer Center End of route: Future Far East Side Transfer Center Total no. of buses: 14 No. of stations: 26 Total project cost: $43.3 million FTA funding (anticipated):$25.7 million Operational: May 2019 21

NORTHEAST TOD: BEFORE ACQUISITION Current Terminal Aerial View of Northeast Property (Before) 22

NORTHEAST TOD: AFTER ACQUISITION Current Terminal Aerial View of Northeast Property (Current) 23

NORTHEAST TOD: DOVER KOHL LAND USE RECOMMENDATIONS About the Northeast Transfer Center Houses multiple fixedroute services for local community Includes an additional structure and bays that are to be used by Sun Metro Brio Rapid Transit System 24

ABOUT THE NORTHEAST TOD: TIGER GRANT 25

ABOUT THE NORTHEAST TOD 26

ABOUT THE NORTHEAST TOD 27

ABOUT THE NORTHEAST TOD 7 acres to be used for development of the Northeast Transfer Center: TIGER grant Remaining 23 acres to be a Public-Private Partnership venture as a Transit-Oriented Development Proposed Build-out recommended by Dover-Kohl o 130,000 sq. ft. of retail o 500 to 800 residential units o Mid-block parking structure for 480 parking spaces o 7,300 linear feet of new streets 28

Sun Metro Funding for 7 acres: Tiger V Grant Award $10.3 Mill Local Match $ 4.7 Mill Project Components o Transit Center ABOUT THE NORTHEAST TOD $15.0 Mill o Multi-level parking garage with retail around parameter o Connecting street infrastructure Developer selection for city owned 23 acres Mar/ Apr 2014 29

PROPOSED FIVE POINTS TRANSFER CENTER & TOD 30

FIVE POINTS TRANSFER CENTER & TOD! Project is currently in its design stages! Designed to be a Public-Private Partnership project! Located at Montana Ave. and Piedras St.! Five Points will be the major connection between three Brio RTS lines (Alameda, Dyer, Montana)! Project development based on the El Paso Smart Code and New Urbanism standards! Pedestrian, Bicycle and Transit Friendly 31

PROPOSED FAR-EAST TRANSFER CENTER & TOD 32

FAR-EAST TRANSFER CENTER & TOD! Project is currently in its design stages! Designed to be a Public-Private Partnership project! 4.93 acre site located at RC Poe and Edgemere! Construction: $5 million! Station to the future Brio RTS Montana corridor! Fire Station #37 will be part of TOD! Project development based on the El Paso Smart Code and New Urbanism standards! Pedestrian, bicycle and transit friendly 33

PUBLIC-PRIVATE PARTNERSHIPS! Local Business Groups! CBA, DMD, CVB, Chamber of Commerce! Federal, State & Local Agencies! FTA, FHWA, TxDOT! LULAC, El Paso County, City of El Paso! Ft. Bliss Army Post! NMDOT (Gold Route)! Amtrak! Managed by First Transit! Privatization of paratransit service by MV Transportation! Academic Institutions! UTEP, EPCC, Texas Tech 34

PUBLIC AND PRIVATE PARTNERSHIPS! Bus Bench Franchises! El Paso Bench Ads, River Elms, Pinnacle Media! Private Business! Big Boy Concessionaire! Sun City Cabs! Mansfield Gas Equipment Services! Community Events! Arts in Motion by Creative Kids! Chalk the Block by MCAD! Mayor s Thanksgiving Meal/CVB! TOD Communities! Monticello, Northgate, Far-East, Five Points & Geltmore 35