Cost Reduction Potential in the Offshore Grid

Similar documents
Offshore Wind in Germany

Green and Secure. Challenges of increasing RES feed-in from a TSO perspective and from a power market point of view. René Müller

High Voltage Direct Current Transmission

OFFSHORE WIND TOWARD 2020 ON THE PATHWAY TO COST COMPETITIVENESS

Germany. Key issues. 1. General overview

Voltage Source HVDC Overview Mike Barnes Tony Beddard

E-Highway2050 WP3 workshop April 15 th, 2014 Brussels

HVDC Technology for Large Scale Offshore Wind Connections

Requirements for Offshore Grid Connections. in the. Grid of TenneT TSO GmbH

Wind Power. Offshore

QUALITY CONTROL Prepared: V. van Gastel / team TenneT Reviewed: M. Müller Approved: F. Wester BACKGROUND MATERIAL...

POWER TRANSMISSION FROM OFFSHORE WIND FARMS

An Introduction to High Voltage Direct Current (HVDC) Underground Cables

Viking Link Interconnector

Completion of Acquisition: New England - New York Cross Sound Cable

European Subsea Cable Report & Forecast

ULTRANET. The energy transition in Germany - Siemens supplies converters for grid expansion to Amprion and TransnetBW

Optimization of the coupled grid connection of offshore wind farms

Polish Offshore Grid SA

HVDC PLUS and SVC PLUS: Reliable and Cost-effective Power Transmission Solutions with Modular Multilevel Converters

Business Area Distribution

POLITICAL DECLARATION OF THE PENTALATERAL ENERGY FORUM

How To Manage A Project

TenneT. Stakeholder engagement and Consultation Process OWFs. Day 1 ONL Michiel Müller / Rob van der Hage

Trends in offshore wind economics the past and the future

Ubiquitous Computing in Business Processes Part V

SSE Greater Gabbard Offshore Wind Farm Supply Chain Engagement

HVDC Light & SVC Light Reference list

Grid connection of near shore wind farms

Wind Farm Zone. Offshore wind energy. in the Netherlands. Project & Site Description. # Borssele


Magnus Callavik, ABB Power Systems, HVDC, Västerås, Sweden Phone: +46(0)

CONCEPT OF THE OFFSHORE GRID DEVELOPMENT ON THE BALTIC SEA

Grid requirements with scattered load balancing and an open electricity market Poul Alberg Østergaard * Aalborg University

Perspectives for ESS in Germany and Europe legal situation and applications StoREgio energy storage system association

Electrical Considerations for HVDC Transmission Lines. Joe Mooney, PE

EuroAsia Interconnector Project Submarine power cable

Network Interconnection of Offshore Wind

[ REPORT ON EU ELECTRICITY MARKET TRANSPARENCY: COUNTRY COMPARISON ]

Challenges to integrate Renewables In the French and European Power System. Michel Béna, SmartGrids Director

Siemens presents new DC grid connection for offshore wind farms Siemens AG 2015 All rights reserved. siemens.com/grid-access-solutions

Infrastructure in a low-carbon energy system to 2030: Transmission and distribution. Final report. for. The Committee on Climate Change

Neart na Gaoithe Meet the buyer event. Chris Whitehead Facilitator

Ernst Rauch Munich Re 29 June 2010

Germany's energy transition: Status quo and Challenges.

Sharing Lessons Learned and Good Practice in Offshore Transmission

Power Generation. Lilian Macleod Power Supply Manager National Grid

Smart Meters Executive Paper

Q1: Which further key design criteria should be reflected in cross-quality market areas?

SmartGrids SRA Summary of Priorities for SmartGrids Research Topics

Financing Renewables and Energy Efficiency Projects in Developing Countries

UK content analysis of Robin Rigg Offshore Wind Farm operations and maintenance

Brochure Introducing HVDC

Nordex SE. Nordex goes Offshore

Curriculum Vitae Fredrik Rüter 1 December 2014

INTRODUCTION TO HARMONIC ASSESSMENT IN POWER SYSTEMS

Title: IEC WT 01 vs. IEC Development of a new standard and innovations in certification of Wind Turbines. mike.woebbeking@gl-group.

IFC ESMAP- RENEWABLE ENERGY TRAINING PROGRAM. Wind Module. II. Wind Project Development, Implementation, and Financing

Cost Benefit Methodology for Optimal Design of Offshore Transmission Systems

Study on flexibility in the Dutch and NW European power market in 2020

By CDG 450 Connectivity Special Interest Group (450 SIG)

Industrial Power Control

EWE's approach to double grid connection capacity by using DERflexibility

Passion for Offshore. Wind Power & Renewables Division Market Unit Offshore

Roundtable - Energiewende: Finanzierung des Netzausbaus im Übertragungsnetz

The Use of Cables for Extra High Voltage Transmission

Scorecard MD&A - General Overview

PNE WIND AG. Presentation January Buchholz wind farm

Enlarged Wind Power Statistics 2010 including Denmark, Germany, Ireland and Great Britain

About T&D Europe : The association

Preparatory Paper on Focal Areas to Support a Sustainable Energy System in the Electricity Sector

Storage Battery System Using Lithium ion Batteries

Egypt Renewable energy Projects. Eng. Lamya Youssef Head Of FIT Unit Central Unit Egyptian Electricity Transmission Company EETC

Feasibility Study of Deep Water Power Cable Systems. Enrico Colombo CESI S.p.A

Offshore Electricity Transmission: Consultation on tender exercises under the enduring regime (178/11)

Germany's renewable energy sector in the context of energy transition.

Submarine Power Cables. State-of-the-art production facility, more than 100 years of experience and reference installations around the world.

MAXIMISING YOUR. Offshore wind assets ASSET OPERATION & MAINTENANCE SERVICES

The Energiewende in the Power Sector: State of Affairs 2014

2012 San Francisco Colloquium

MINISTERIE VAN ECONOMISCHE ZAKEN GENERAL COST COMPARISON BETWEEN UNDERGROUND CABLES AND O.H. LINE SYSTEMS FOR H.V. TRANSMISSION

We appreciate your feedback

Potential cross-border balancing cooperation between the Belgian, Dutch and German electricity Transmission System Operators

MENA Wind Power Outlook

Transcription:

Cost Reduction Potential in the Offshore Grid Dr. Markus Glatfeld, Managing Director, TenneT Offshore GmbH

TenneT two TSOs, one company Europe s first transnational TSO Connections to 10 TSOs in the center of the European electricity market 21.000 km of ehv- and hv-lines 2.2 bn. turn over in 2013 2.600 employees secure the power supply for 36 m. people

Offshore grid connection projects Current project overview Project Project Capacity (MW) Capacity Commissioning Year of (MW) operation Operational In operation alpha ventus alpha ventus 60 60 2009 2009 BorWin 1 BorWin 1 400 400 2010 2010 Riffgat Riffgat 108 108 2014 2014 Under construction/ awarded Under construction BorWin2 800 2015 BorWin2 BorWin3 800 900 2015 2019 BorWin3 DolWin1 900 800 2019 2014 DolWin2 DolWin1 800 900 2015 2014 HelWin1 576 2014 DolWin2 HelWin2 900 690 2015 2015 DolWin3 SylWin1 900 864 2017 2015 HelWin1 Nordergründe 576 111 2014 2016 DolWin3 900 2017 HelWin2 690 2015 built / awarded 7.109 SylWin1 In tender phase Nordergründe BorWin4 864 111 900 2015 2016 Ʃ To be tendered until 2024 according to O-NEP2014 7.109 3 DC-connections 2.700

2009 2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022 2023 2024 While investments are expected to decrease, O&M costs will become more and more relevant Current situation & prognosis TenneT is currently involved in more than 10 offshore grid connection projects in parallel. CAPEX vs. OPEX CAPEX OPEX As a consequence, investment costs are currently at an all-time high. Following the TCO-approach, TenneT s main challenges are managing the current project peak; realizing cost reduction potential in the projects; preparing for efficient O&M.

TenneT has significantly contributed to the establishment of a reasonable grid development Implementation of O-NEP In 2011, TenneT urged the German government to establish new regulatory guidelines to guarantee for a sustainable grid development. As a consequence, the Offshore Grid Development Plan (O-NEP) was implemented. TenneT is involved in all stages of the O-NEP elaboration and in constant exchange with BNetzA. Scenario framework First draft NEP/ O-NEP publication by TSOs public consultation by TSOs Second draft NEP/ O-NEP publication by TSOs public consultation by BNetzA Confirmation document detailed assessment of calculation and environmental impacts publication by BNetzA

The multitude of projects tendered has caused market bottlenecks and increased prices Consequences of unguided grid development Between 2007 2014, a total of 9 HVDC grid connection systems have been awarded. Initially, only ABB, Siemens and Alstom participated in the tenders. While the number of bidders stagnated, offer prices increased significantly. In order to foster competition, TenneT adapted its tender strategy in 2013. Price development for HVDC projects Development of bidders x t t

New tender system helps to reduce grid connection prices Development of a tender strategy Joint tender for entire system (before 2013) Amount of potential bidders able to deliver all components converter and cables limited to just ABB, Siemens and Alstom. Split tender in 2 lots (from 2013 onwards) To assure more competition, TenneT introduced a split tender system : Lot 1: Onshore & Offshore Converter Lot 2: HVDC Cable The more projects the less capacities were available. The new tender structure attracted significantly more bidders offering additional capacities. little competition & scarce capacity balanced market prices & sufficient capacity & reduced delivery times

Extensive preparatory projects help to take the right decisions Two phase approach for planning and construction TenneT s projects start with a preparatory project. While the core project covers the entire construction & commissing up until the hand-over to operations (~ 5 years), preparatory projects (~2 years) include: connection concept; system technology concept; tender strategy; field explorations and expert assessments; performance of surveys and soil analyses. The O-NEP provides sufficient planning security to take this time and guarantee for a thorough project preparation.

Riffgat is a prominent example for the necessity of detailed preparatory projects Preparatory project example When TenneT took over the realization of the offshore grid connection Riffgat, a detailed magnetometer study revealed severe ammunition findings in the cable corridor. The realization of the windfarm was well-advanced, therefore TenneT could not influence the cable corridor at that stage in time. The ammunition clearance in the corridor caused a significant project delay and almost doubled the initial project budget. Clear benefit of thorough project preparation prior to construction. Cost for preliminary project Cost associated to amm. findings

TenneT has a close look on the advancement in the offshore technology Making use of standardization Technological advancements in the past years have significantly contributed to a more standardized realization of offshore grid connections. As transmission capacity has only little impact on the overall price and TenneT longed for a capacity standardization (900 MW), recent projects are tendered independent of announced OWF capacity. Transmission capacity per offshore grid connection MW 800 600 400 200 Grid Connection Capacity OWF Capacity BorWin1 BorWin2 DolWin1 HelWin1 SylWin1 HelWin2 DolWin2 DolWin3 BorWin3

The multitude of projects allows for a variety of economies of scale to be realized Selected economies of scale While the involvement in a multitude of projects holds challenges, it also allows for economies of scale: Frame Contracts The multitude of projects allows for a better usage of resources and bulk buying conditions (i.e. for helicopter flights). Standardization Concepts TenneT is engaged in the standardization of offshore components (i.e. AC-cables): less storage capacity of spare parts needed exchangeability of parts between projects possible

Potential risks make up a significant part of the expected O&M costs Breakdown of O&M costs (exemplary) TenneT is still in the progress of gaining valuable experience regarding the operation & maintenance of offshore grid connections. The maritime cost items are hard to predict due to external risk factors like weather, charter rates and licensing requirements, which are very significant in relation to the basic campaign prices. Platform O&M Contract Personnel Expenses Insurances Cable ARO Grid Losses Onshore Station Other Total Risks

An Operation & Maintenance strategy shall help to sustainably reduce O&M costs Overview of O&M Strategy Most maintenance costs are non-electric and platform related. In order to control these costs, TenneT investigates cost saving potentials by price reduction for example through make-orbuy decisions or frame contracts; tries to challenge recommended maintenance or inspection intervals; works on technical alternatives like monitoring; evaluates possible cost reduction potentials regarding insurances.

TenneT is engaged in various projects to further increase the degree of utilization of the offshore grid Project overview Transmission Capacity Management (TCM) Development of algorithms to increase the utilization of transmission capacity with regard to thermal limitations. Damage Reduction Concept Provision of a framework for damage reduction process and description of all available measures to avoid or reduce delays and outages: Providing a framework for damage reduction process Describing available measures to avoid or reduce delays and outages Evaluating and mitigating risks

Apart from the saving potential already realized, TenneT is looking for more cost reduction measures Conclusion TenneT is currently involved in over 10 offshore grid connection projects. Due to the implementation of the O-NEP, the current peak of investment costs will decrease as of 2015. By adapting the tender strategy, conducting preparatory projects and defining an O&M strategy, TenneT has already implemented various cost reduction measures. Once TenneT has gained further experience in operating offshore grid connections, further cost reduction measures are planned to be realized.

TenneT is Europe s first cross-border grid operator for electricity. With approximately 21.000 kilometres of (Extra) High Voltage lines and 36 million end users in the Netherlands and Germany we rank among the top five grid operators in Europe. Our focus is to develop a north-west European energy market and to integrate renewable energy. Taking power further