Testing and Demonstration Results of the 350m Long HTS Cable System Installed in Albany, NY



Similar documents
Development Trends of Superconducting Cable Technology for Power Transmission Applications

SUPERCONDUCTING CABLE SYSTEMS

High-temperature Superconducting Cable Technology and Development Trends

HIGH-CAPACITY HIGH TEMPERATURE SUPERCONDUCTING POWER CABLES

AMSC s Superconductor Cable Technologies for Electric Utilities

Max. Length of HTS Cables in the Future

HTS Cables: Pitfalls and Potential LIPA Cable Project. J. Maguire American Superconductor. DOE Wire Workshop January, 2007 Panama City, FL

Large Current and Low AC Loss High Temperature Superconducting Power Cable Using REBCO Wires

Superconducting and Solid-State Electronic Fault Current Limiter Technologies The shift from demonstration projects to Business-as-Usual solutions

WIRE AND CABLE ENGINEERING GUIDE

EFFICIENT ELECTRICAL ENERGY TRANSMISSION AND DISTRIBUTION INTERNATIONAL ELECTROTECHNICAL COMMISSION

LNG Fuel Tank System LNG Tank overview

Underground Cable Temperature Monitoring in the Real World

SCADA Controlled Multi-Step Automatic Controlled Capacitor Banks & Filter Banks

Development of Radiation Resistant Quadrupoles Based on High Temperature Superconductors for the Fragment Separator

FIXED CHARGE: This is a cost that goes towards making the service available, including

Distributed Temperature Monitoring of Energy Transmission and Distribution Systems

TAN δ (DELTA) CABLE TESTING OVERVIEW AND ANSWERS TO FREQUENTLY ASKED QUESTIONS. What Is Tan δ, Or Tan Delta?

The commissioning of the LHC: first the technical systems, then the commissioning with beam

Statement of Work. 3.0 Details of Service Pre Start-up Cooling Start-up Service. Installation Service. Table of Contents. 1.0 Executive Summary

SHE Transmission. 2015_10_30 Transmission Losses Strategy Rev 2.0 October 2015

ELECTRICAL ENGINEERING DESIGN CRITERIA APPENDIX F

E-Highway2050 WP3 workshop April 15 th, 2014 Brussels

Energy losses of superconducting power transmission cables in the grid

Stephen G. Whitley, Senior Vice President & Chief Operating Officer

The electrical energy produced at the gen

HERZ-Thermal Actuators

Oil and Coolant Circulating Heating System. Model - OCSM

ELECTRICAL INSULATION TESTING OF HV EQUIPMENT UP TO 33kV

Insulation Resistance Testing of Low Voltage Cables in the Field

Fundamentals of Modern Electrical Substations Part 1: Mission of Electrical Substations and their Main Components

Nuclear Power Plant Electrical Power Supply System Requirements

DEVELOPMENT OF A TWIN SCREW EXPRESSOR AS A THROTTLE VALVE REPLACEMENT FOR WATER-COOLED CHILLERS

MOBILE SYSTEM FOR DIAGNOSIS OF HIGH VOLTAGE CABLES (132KV/220KV) VLF-200 HVCD

ANCILLARY EQUIPMENT AND ELECTRICAL EQUIPMENT Power Supply Systems and Electrical Equipment for Desalination Plants - Y.M. Hamud and A.H.

POWER AND VOLTAGE RATING

BB-18 Black Body High Vacuum System Technical Description

Monitoring Underground Power Networks

Controlling a 2-phase CO 2 loop using a 2-phase accumulator

DISCUSSION OF CROSS-LINKED POLYETHYLENE INSULATED CABLES FOR UNDERGROUND PORTIONS OF THE MIDDLETOWN-NORWALK 345 kv PROJECTS.

QUESTIONS and ANSWERS RFB , Metal Clad Switchgear and Power Control Room

Part 1 System Modeling & Studies for Existing Systems

At Load Power Factor Correction Phase 2: Refrigerated Vending Machines

Digital Energy ITI. Instrument Transformer Basic Technical Information and Application

CUSTOMER REQUIREMENTS AT POWER SUBSTATIONS

Section 7. Evaporator thermistor. Under-and-over pressure safety switches. Connections to the ECU

Earth Fault Detection Basics in Theory

Unified requirements for systems with voltages above 1 kv up to 15 kv

Sanitary Type Electronic Flow Switches

Power transformers. Generator step-up and system intertie power transformers Securing high-quality AC transmission

Earthing Guidance Notes

Understanding Power Factor and How it Affects Your Electric Bill. Presented by Scott Peele PE

Hybrid Modeling and Control of a Power Plant using State Flow Technique with Application

Medium Voltage Electrical Distribution

Power System review W I L L I A M V. T O R R E A P R I L 1 0,

Short Circuit Current Calculations

Electric Power Systems An Overview. Y. Baghzouz Professor of Electrical Engineering University of Nevada, Las Vegas

How To Clean Water From An Ammonia Refrigeration System

A Practical Guide to Free Energy Devices

HIGH VOLTAGE SHORE CONNECTION

INDUSTRIAL AND COMMERCIAL SERVICE TRANSFORMER & METERING INSTALLATION SPECIFICATION

Visions become real. Temperature control and cooling systems. The innovative and reliable solution

Heating, air-conditioning, cooling

Indoor coil is too warm in cooling mode or too cold in heating mode. Reversing valve or coil thermistor is faulty

Ammonia Detection System Codes and Design Specifications

Cable Consulting International

SERVICE MANUAL 12VDC WALL THERMOSTAT AIR CONDITIONING SYSTEMS ROOFTOP UNITS ONLY

PG&E Transmission Interconnection Handbook. Section L3: SUBSTATION DESIGN FOR LOAD-ONLY ENTITIES AND TRANSMISSION-ONLY ENTITIES

KNOW YOUR OPTIONS: 230 KV POWER CABLES

16300 MEDIUM VOLTAGE DISTRIBUTION

The Impact of Transmission Cable System Construction and Design on Commissioning Test Options & Results

Current Limiting Protector For Systems rated kV and continuous currents through 5000A.

superconductors, while also working on integrating the new 2nd generation superconductors based on Y(RE)Ba 2 Cu 3 O X Ca 2

SIMULATING HYBRID ENERGY GRIDS IN SMART CITIES FOCUS ON ELECTRIC ENERGY SYSTEMS

VOLTAGE REGULATOR AND PARALLEL OPERATION

OptiNet Applications. A Review of the Unique Requirements for a Facility Monitoring System. White Paper Series

Fundamentals of Power

Medium voltage arc flash eliminator units VAM 3ED,

Submit shop drawings for equipment provided under this section Shop drawings shall indicate:

Technical Specification for the Cryogenic Testing of HTS Current Leads

Hyperlinks are Inactive

MOUNTING AND OPERATING INSTRUCTIONS

ETC TWO STAGE ELECTRONIC TEMPERATURE CONTROL

How To Use High Temperature Superconductor For A Power Source

Preventing Overheated Boiler Incidents

Large Systems Commissioning

Generation Interconnection Feasibility Study Report-Web Version. PJM Generation Interconnection Request Queue Position Z1-055

rpsa FIRE PROTECTION ENGINEERS

Three phase circuits

Section kv Power Cables

The D-Wave 2X Quantum Computer Technology Overview

Benefits of Cold Aisle Containment During Cooling Failure

3. TYPES OF SERVICE AVAILABLE. 3.1 Scope

..OR How To Protect your 3-Phase Equipment Investment with 3-Phase Monitors from Time Mark...

Approved Meter Sockets and Cabinets

Transcription:

1 Testing and Demonstration Results of the 35m Long Cable System Installed in Albany, NY C. S. Weber, SuperPower, Inc.; R. Lee, S. Ringo, The BOC Group; T. Masuda, H. Yumura, SEI and J. Moscovic, National Grid Abstract The Albany Cable Project team (BOC, National Grid, Sumitomo Electric, SuperPower) have built and tested a 35-m long cable and cryogenic system rated at 48 MVA (8A rms, 34.5-kV). The cable system included the world s first demonstration of an cable-to-cable joint (or splice) as well as some novel design aspects in both the cryogenic refrigeration system and the terminations. The cable was installed and began operation in July 26. This paper will summarize the testing and operational aspects of the cable system and its integration into the existing National Grid 34.5-kV network. Index Terms Cryogenic Refrigeration Systems, High Temperature Superconductors, Cables, Superconducting Cables I. INTRODUCTION rguably three of the most important considerations that A electric utility personnel must consider in evaluating and introducing new technologies into their existing networks are: the overall reliability of the technology and its support systems, the impact that the new technology will have on the existing network; and what the relative cost/benefit analysis looks like compared to other available technologies. To prove the feasibility and reliability of underground cables, demonstration projects have been planned and executed around the world. In the United States there are currently three such demonstration projects underway [1][2][3]. Although these projects have widely varying performance characteristics, such as operating voltage & current levels, they all have a common underlying goal to address the fundamental questions of how cables will Manuscript received August 28, 26. This work was supported in part by the U.S. Department of Energy under Contract #DE-FC36-3GO1331 and by the New York State Energy Research and Development Authority under Agreement #6481. C. S. Weber is with SuperPower, Inc., Schenectady, NY 1234 USA (phone: 518-346-1414; fax: 518-346-68; e-mail: cweber@ igc.com). R. Lee (e-mail: Ron.Lee@boc.com) and S. Ringo. (e-mail: Steven.Ringo@boc.com ), are with The BOC Group, Murray Hill, NJ 7974 USA. T. Masuda (e-mail: masuda-takato@sei.co.jp) and H. Yumura (e-mail: hiroyasu-yumura@sei.co.jp) are with Sumitomo Electric Industries Ltd., Osaka, 554-24 JAPAN. J. Moscovic (e-mail: Jon.Moscovic@us.ngrid.com) is with National Grid, Albany, NY 1224, USA perform in a typical utility setting. The Albany Cable Project (ACP) is a collaborative effort between SuperPower (prime contractor/2g wire supplier), Sumitomo Electric Industries ( cable manufacturing, installation and testing/bscco wire supplier), The BOC Group (Cryogenic refrigeration System (CRS)/ system monitoring), and National Grid (host utility/system protection). The program is funded by a combination of the aforementioned industrial partners, the Department of Energy (DOE) through its SPI program and the New York State Energy Research and Development Authority (NYSERDA). The cable system that has been installed operates at 34.5 kv and has a nominal current carrying capacity of 8 Amperes. The total length of the cable from end to end is 35 meters comprising of two sections; one 32m long and one 3 m long. The two cable sections were pulled into underground ducts using conventional cable pulling techniques and they were then joined together in an underground vault [4]. The joining of two independent cable sections is important to show that lengths of cable can be connected together to make a long cable installation possible. The first phase of the ACP consists of two cable sections made with SEI s CT-OP BSCCO wire[4]; a 35m long return pipe, and the BOC designed CRS. A follow-on phase of the program will replace the 3m BSCCO cable section with an equivalent length cable made from YBCO wire fabricated by SuperPower. Following the installation of the cable system, a series of pre-energization testing was completed to verify its performance and that all back-up systems were working properly. Phase 1 of the ACP went into operation on the grid on July 2, 26. There have been no interruptions in service since the cable went online and stable operation has been maintained throughout. This paper describes the results of the pre-energization testing and looks at the impact on load flows when an cable of various lengths is installed in part of National Grid s 34.5 kv network in Albany, NY. II. CRYOGENIC REFRIGERATION SYSTEM A. Refrigeration Arrangement The Albany Cryogenic Refrigeration System (CRS) employs a hybrid arrangement that accepts refrigeration from

either a cryocooler or bulk liquid nitrogen. As shown in Fig. 1, the skid mounted CRS consists of a cold box housing a thermosyhon and liquid nitrogen pumps. The pumps circulate subcooled liquid nitrogen in a closed loop to the cable. The thermosyphon accepts refrigeration from either the primary cryocooler, or a backup bulk liquid nitrogen and vacuum blower combination. The CRS is also designed to provide cold nitrogen gas at any temperature and flow rate for the initial cable cooldown. Fig. 1. Cryogenic Refrigeration System. Hybrid refrigeration arrangement using interchangeable cryocoolers and back-up liquid nitrogen. The CRS design incorporates cost effective and reliable back-up of all key components in the event of failure. The primary back-up mechanism is bulk liquid nitrogen/vacuum blower operation in the event of cryocooler failure. In addition the pumps, all key instruments, and control loops have backup provisions. B. System Testing The CRS was tested extensively prior to cable installation as reported earlier [5][6]. Following cable installation and cooldown, the CRS was put through a series of performance tests which included confirmation of the various back-up systems. Fig. 2 shows a key performance experiment that was conducted prior to cable energization. The experiment began with the system operating stably at a baseline cable supply temperature of 72 K (±.5) and a heat load requiring about 3 Kw of refrigeration. The subcooled LN2 supply temperature setpoint was then step changed to 68 K which initially required about 8 Kw of refrigeration. The substantial increase in refrigeration was a consequence of the several hour time delay before the return liquid begins to drop in temperature. During this transition period, the peak refrigeration demand was easily satisfied using the unique arrangement of the CRS which permits operation in a hybrid mode. During hybrid operation both the cryocooler and (back-up) bulk liquid nitrogen/vacuum blower system operate. After 6 hours of hybrid operation, the system returned to normal cryocooler operation. Further experiments were conducted to verify stable backup operation including: Cryocooler failure, vacuum/liquid nitrogen back-up..6k momentary temperature rise before back-up. Single liquid nitrogen pump failure. 15% momentary drop in flow rate. Sensor failure: flow, pressure and temperature. No effect due to alternative control strategies. Site power failure. Back-up generator provides sufficient power for control equipment and liquid nitrogen pumps. Cooling provided by bulk liquid nitrogen without vacuum blower. Temperature to cable will rise slowly, but remain subcooled. C. Operation The overall cable system is monitored and controlled around the clock by the BOC Remote Operations Center (ROC) in Bethlehem, PA as shown in Fig. 3. The ROC is responsible for both operation of the CRS, and communication with the Eastern Regional Control Center (ERCC) of National Grid related to cable status and energization/de-energization. In addition to normal scheduled removal of the cable from service, there are procedures in place for emergency removal. 2 8 78 76 Coolant return North Termination South Termination 3 25 Temperature (K) 74 72 7 68 66 + -.5K Hybrid operation Coolant Supply Refrigeration power + -.1K 2 15 1 Cooling Power (Kw) 64 62 8 Kw peak 3 Kw nominal 6 1 2 3 4 5 6 7 8 9 1 11 12 13 Time (hours) Fig. 2. Pre-energization cryogenic system step response test. Setpoint change from 72K to 68K 5 Fig. 3. Remote Operations Center. Albany cable system is monitored from the BOC facility in Bethlehem, PA.

Temperature (K) 74 73 72 71 7 69 68 Return temperature Cable outlet pressure Supply temperature 67 8/12 8/13 8/14 8/15 8/16 8/17 8/18 Date To supplement direct communication between the ROC and ERCC, there is dedicated control logic embedded in the onsite PLC. The dedicated critical alarm logic considers conditions which require immediate cable de-energization. The logic employs a data set structure which groups similar and redundant measurements (e.g., cable/coolant temperature, cable pressure, flow rate). There must typically be a vote of two independent measurements within a data set, and a prescribed time delay, to initiate a critical alarm. The critical alarm is then communicated directly to the ERCC via two independent hard wired signals. The ROC has been monitoring and operating the cable system continuously since before the end of cable cooldown on June 23, 26. The cable was energized on July 2, 26 and has operated continuously and stably from that time. Fig. 4 shows key operating parameters during a 1 week period in mid-august 26. Power Cable inlet pressure Fig. 4. Post-energization cable system operating conditions. 14 12 1 8 6 4 2 Power (MVA) / Pressure (barg) voltage transformers were installed at one end of the cable to monitor current and voltage on each phase of the cable. An ION 86 meter was also installed to capture data in the event of any power quality issues such as a voltage fluctuation or fault current in the system. Upon completion of the cable system installation an overpressure test of the entire system was conducted in accordance with ASME cryogenic piping codes (B31.3). The test was conducted using warm nitrogen gas. The pressure was raised in steps up to 11% of the installed pressure relief devices (PRD) designed to protect the system should liquid nitrogen flow be stopped thereby trapping cryogenic fluid in the cable. After the maximum pressure was reached it was held for 1 minutes and then the pressure was reduced to 1% of the PRD setting and held for several hours. During this time all field constructed joints were leak checked. No leaks were found and the cable system was ready to be cooled down. The initial cooldown of the cable was completed without incident. A great deal of care was taken to ensure that no damage or leaks developed during the cooling process. Nitrogen gas was passed through the cable at various temperature and flow rates to maintain an even temperature gradient across the system. The final cooling was completed by filling the entire system with liquid nitrogen. When the system was filled liquid nitrogen began venting from the return line to the CRS as shown in Fig. 5. The temperature profile of the cable was continuously monitored by a fiber optic distributed temperature monitoring system developed by SEI. Thermal contraction and capacitance of the cable were also monitored throughout the cooldown process. 3 III. INSTALLATION AND INITIAL COOLDOWN After fabrication and successful completion of factory acceptance testing the cable section, return cryostat, terminations and joint components were shipped from Osaka, Japan to Albany, NY. The cable and return pipe were pulled into existing underground ducts using conventional cable installation techniques. Measurements taken of the cables before and after installation indicated that no damage was incurred during the installation process. The cable-to-cable joint fabrication was completed in the underground vault including fabrication and evacuation of the cryostat. The termination vessels were installed and connected to the cable at each end. Vacuum jacketed piping connections were made between the CRS and the south termination vessel and return pipe, as well between the north termination and return cryostat. It is important to note that independent vacuum spaces are maintained for each flexible cryostat, the two termination vessels and for each field installed connection. All vacuum spaces can be monitored and maintained separately. National Grid crews installed the necessary switches, surge arrestors, overhead conductor, and structures to connect the cable to the existing 34.5 kv network. Current and Fig. 5. Liquid nitrogen venting at end of the cooldown process. The contraction of the cable measured by load cells installed at both termination vessels. The termination vessels are fixed at each end to that all of the contraction forces must be absorbed within the cable itself. The maximum tension measured during the cooldown was approximately 8kg. This is a relatively low value that is enabled by the slack winding technique developed by SEI [7].

Results of the capacitance and tan delta measurements of the cable during the initial cooldown are shown in Fig. 5. As can be seen from the chart the capacitance of the cable decreased over time as the temperature of the cable decreased. When liquid nitrogen is introduced to the cable it begins to permeate the dielectric layers (PPLP) this will increase the dielectric constant of the cable. This is shown by the sharp rise in capacitance on the chart in Fig. 6. The cooling process of the cable is completed once the dielectric layers become fully saturated with liquid nitrogen and the capacitance of the cable becomes constant. 4 Ca pa 35 ci ta nc e 3 [ Capacitance tanδ 25 6/9 6/1 6/11 6/12 6/13 6/14 6/15 6/16 6/17 6/18 6/19 6/2 6/21 6/22 6/23 6/24 6/25 6/26 6/27 12: 12: 12: 12: 12: 12: 12: 12: 12: 12: 12: 12: 12: 12: 12: 12: 12: 12: 12: Time Fig. 6. Cable capacitance and tan delta during initial cooldown. IV. PRE-COMMISSIONING TESTS In order to ensure the cable met all of its performance specifications and was ready to be operated on the grid a series of pre-commissioning, or pre-energization tests were performed. These test included confirmation of the heat inleak through the cable cryostat, verification of the pressure drop across the cable, a DC critical current measurement, a DC withstand or hi-pot test, and finally a phase check between the cable and the conventional overhead circuit. Heat loss of cable was calculated by measuring the temperature rise across the cable at several flow rates. This requires very stable flow rates and temperature control over a period of days which the CRS handled easily. The measured values of heat loss were in good agreement with the design calculations. The total heat loss of the cable, excluding the terminations is approximately 1 kw with no electrical load applied. The total heat loss including the cable, joint, terminations, the return pipe and connection pipes is about 3.1 kw. This value does not include any losses associated with the CRS. The pressure drop across the cable excluding the termination was measured to be.75 bar at 5 L/min. The elevation difference between the two ends of the cable is about 1 m and is accounted for in the calculation of the expected pressure drop of.7 bar. Next the critical current of each cable conductor was measured using the 4 probe method and a DC current supply. Measured critical current for each of the three cable phases is about 2.3 ka at 73 K using the standard 1 µv/cm criterion. The temperature is the average between both cable ends at 4 4 3.5 3 2.5 ta nδ 2 [% ] 1.5 1.5 L/min. The measured critical current corresponds with that measured prior to shipping the cable from Japan. Hence, the cable incurred no damage or degradation during the transportation, installation and initial cooling processes. A DC withstand (or hi-pot) test was conducting according to the Association of Edison Illuminating Companies (AEIC C55-94) standard for 34.5 kv class underground cable. Voltage was applied to each phase of the cable in 1 kv increments up to 1 kv. The voltage was held constant for 5 minutes and then ramped down to zero. There were no indications of damage during this test. Finally, a phase check between each phase of the cable and the existing overhead line was conducted to ensure continuity from end to end. Upon completion of all precommissioning testing the cable was deemed ready to put into service on the grid. On July 2 th the cable was put into service on National Grid s network. The cable was connected from the Riverside substation and voltage was applied for several hours. Upon completion of the voltage soak test the cable was connected at both ends and current began flowing through the cable. There have been no interruptions since the cable has gone online and all parameters such as temperature, pressure and LN2 flow rate are being monitored and controlled by the BOC Remote Operations Center in Bethlehem, PA, without any onsite supervision. V. LOAD FLOW STUDIES The impact of a Cable installed on an electric grid system was studied using the PSS/E power flow program [7]. Several load flow scenarios were studied to look at the impact of installing about 4m of cable as well as if the entire line between the Riverside and Menands substations was replaced with a cable. A parallel 115 kv line runs between the two substations. Load flows were also simulated with this 115 kv line taken out of service to see what the impact would be in a contingency situation. A comparison of cable to XLPE (conventional underground type) and overhead conductor is shown in Fig.7. Comparing the various types of cables shows that the cable has a resistance approximately 3 times less than conventional XLPE cable and about 8 times less than overhead wire. The inductance of the cold dielectric cable is 6 times less than conventional wire and 21 times less than overhead wire. The capacitance of the is slightly less than conventional underground cable. Cable Type Cold Dielectric XLPE Cable Overhead Conductor Resistance Inductance Capacitance.1 ohms/km.3 ohms/km.8 ohms/km.6 mh/km.36 mh/km 1.26 mh/km 1.8 MVAR/km 1.4 MVAR/km.5 MVAR/km Fig. 7. Comparison of, XLPE and Overhead cable properties 4

5 The existing conventional overhead line that existed prior to installing the cable was used as the baseline for the load flow comparisons. Estimates of the MVA and MVAR loading in this configuration were made and compared to the other scenarios containing varying amounts of cable. A summary of the various scenarios is summarized in Fig. 8. When a portion of the line was replaced with an cable the loading simulation increased, but only slightly. This is because the overall resistance of the line is only slightly lower than the regular line. The next column in Fig. 8 represents a simulation done with the cable comprising the entire distance from Substation #1 to Substation #2. This scenario does have an effect on the load flows. With this representation the flow is 5 times the watts and double the vars and causes a change in load flow path. The change in flow is not what you would expect if looking at the one line diagram from a purely mathematical perspective. The reason that the flow does not entirely go to the path of least resistance is the fact that each substation has a different phase angle. This phase angle difference will limit the current going in each path. The final two columns in Fig. 8 represent the power flow analysis when the 115 kv line is taken out of service; first with the cable forming 4 meters and the rest conventional wiring and secondly with the entire line comprising cable from end to end. In the scenario where 4m of cable is installed and the 115 kv is out of service the loading increased significantly to 9.6 MVA and 13.9 MVAR. The final scenario simulates the load flow that results when an cable is installed between substations #1 and #2 and the 115 kv line is opened. This representation is the model that has the maximum load flow on Line #27; 13.7 MVA and 26.1 MVAR. Baseline (No ) 4 m of installed All from Sub #1 To Sub #2 4 m of and 115kV line out All and 115 kv line out MVA.3.4 3.4 9.6 13.7 MVAR 1.1 1.7 19.6 13.9 26.1 Fig. 8. Table comparing relative load flow scenarios on the electric grid VI. PRESENT LOADING CONDITIONS The cable is now in service on the 34.5kV National Grid 34.5 kv system. The following charts indicate the amount of flow and the cyclic natural of the load flow. 15 1 5-5 -1-15 #27 kw Flow 7/19/26 7/2/26 7/22/26 7/24/26 7/26/26 7/28/26 7/3/26 8/1/26 8/3/26 8/4/26 8/6/26 8/8/26 8/1/26 8/12/26 8/14/26 8/16/26 8/18/26 Fig. 9. Load flow in kw of Line #27 with cable in service Series1 Fig. 9 shows that the flow of energy can go in either direction through the cable. To date there have been no issues associated with the cable. National Grids ERCC reports that they have not treated this cable differently than any other cable or sub-transmission line in their system. Observations from this cable project yields many potential advantages from using this type of cable. Some of the advantages are as follows: The higher current-carrying capacity of cables will help a very congested underground area. A conduit that houses a cable carrying 2 amps will be able to be replaced with an cable and now carry 1 amps. This will relieve the over stressed part of a network system without having to dig and build a new duct bank. This will also have a reducing effect on the number of conductors on that portion of the network. Utilizing existing Rights-of-Way that are already in place if using the old duct banks will substantially decrease the costs for the permitting, construction and possibly environmental issues associated with a new installation. Very low EMF due to the construction of the cable is another benefit of this type cable. This benefits the utility by lower eddy current losses that would be generated on close metallic bodies; this also eliminates interference with telecommunications. This cable would lead to less cost for the system because of efficiency gains from the very small amount of losses due to heating. cables will give greater control of the grid system with phase angles and FACTS devices. VII. CONCLUSIONS In order for cable technology to be accepted by the electric utility community it is imperative to demonstrate that the technology is both reliable and to also evaluate the impact of operation in a real world utility application. Phase 1 of the ACP has been successfully installed, tested and energized on National Grid s 34.5 kv network in Albany, NY. The cable system has been successfully operating since July 2, 26 and is beginning to prove that the cable and CRS utilized in the ACP is both reliable and effective. Simulation studies have shown that introducing 4m of a cold dielectric

6 cable on the 34.5 kv electric grid in Albany, NY has no adverse effects on the system. REFERENCES [1] Weber, C. S., et al., Overview of the Underground 34.5 kv Power Cable Program in Albany, NY, IEEE Transactions on Applied Superconductivity 15, No. 2, pp. 1793-1797 (25). [2] Gouge, M. J., et al., Tests of Tri-Axial Cables, IEEE Transactions on Applied Superconductivity 15, No. 2, pp. 1827-183 (25). [3] Maguire, J. F., et al., Development and Demonstration of a Long Length Cable to Operate in the Long Island Power Authority Transmission Grid, IEEE Transactions on Applied Superconductivity 15, No. 2, pp. 1787-1792 (25). [4] K. Yamasaki et. al., Development of Bi-based Superconducting wires, SEI Technical Review, No. 58, June 24. [5] R. Lee, et al, Cryogenic Refrigeration System for cable, IEEE Trans.Applied Superconductivity, vol. 15, No.2, pp. 1798 181, June 25. [6] R. Lee, et al,. Performance Testing of a Cryogenic Refrigeration System for Cables, Advances in Cryogenic Engineering: Transactions of the Cryogenic Engineering Conference, vol. 51, pp. 773-781, 26. [7] Jon M. Moscovic, Impact Study of a High Temperature Super Cable installation on the Electric Grid National Grids Spotlight, July 26.