The CM Perspective. Preconstruction Phase



Similar documents
Developing Critical Path Method Scheduling (CPM)

CONSTRUCTION PROGRESS DOCUMENTATION (SCHEDULING)

REQUEST FOR PROPOSAL FOR CONSTRUCTION MANAGEMENT SERVICES. Part I: Proposal Information

SPECIFICATIONS - DETAILED PROVISIONS Section Project Control Schedule C O N T E N T S

SECTION PROJECT PLANNING AND SCHEDULING PART 1: GENERAL 1.1 DEFINITIONS

Spec. Standard: 11/27/ Revision: 11/27/06

Test Fragen. October 2003 Project Management Wilhelm F. Neuhäuser IBM Corporation 2003

Test Fragen + Antworten. October 2004 Project Management Wilhelm F. Neuhäuser IBM Corporation 2003

Construction Management Standards of Practice

This request for qualifications seeks the following type of service providers:

PROJECT MANAGEMENT BASICS

Notes. Score. 1 Basic Services 1.1. A few instances; could have been more proactive

EXHIBIT 2-2-C PROGRESS SCHEDULES

Volume II- Project Development Processes

Request of Qualification Proposal for Construction Management Services

Tel: (617) Fax: (617) OWNER S PROJECT MANAGER GUIDELINES M.G.L. c. 149, 44A1/2

SECTION COST LOADED CRITICAL PATH SCHEDULE

SECTION a - CONSTRUCTION PROGRESS DOCUMENTATION

Corrected Form: Revised Attachment 7B Cost Proposal Distribution Exhibits A1 and A2 Attached

MONTGOMERY COLLEGE JOB CLASS SPECIFICATION

Importance of Project Schedules. matter what happens on a project. projects, especially during the second half of projects

763XXX Timing Analysis, Critical Path Method (CPM) Project Schedule

Project Time Management

SECTION CONSTRUCTION PROGRESS DOCUMENTATION PART 1 - GENERAL 1.1 RELATED DOCUMENTS

U.S. Department of Veterans Affairs. Facilities Management. Critical Path Method. Guidelines for Preparation of CPM Schedule Volume I

Manage Deliverables - Construction Step 6. July 12, 2012

UNION CITY BOARD OF EDUCATION 3912 BERGEN TURNPIKE UNION CITY, NEW JERSEY REQUEST FOR QUALIFICATIONS CONSTRUCTION MANAGEMENT SERVICES

Adrian Public Schools

CONSTRUCTION PROJECT MANAGER/ SENIOR CONSTRUCTION PROJECT MANAGER

MT. SAN ANTONIO COMMUNITY COLLEGE DISTRICT

Scheduling Estimating Module

ITEM DOCUMENT CONTROL MANAGEMENT DESCRIPTION:

CSC 443: IT Project Management Midterm 1 exam - Spring semester March 21 st, 2012

GREENBURGH CENTRAL SCHOOL DISTRICT No. 7 REQUEST FOR PROPOSALS CONSTRUCTION MANAGEMENT SERVICES

Chapter 2: Project Time Management

CRITICAL PATH METHOD (CPM) SCHEDULES

UNIFIED FACILITIES GUIDE SPECIFICATIONS ************************************************************************** SECTION TABLE OF CONTENTS

Independent School District No. 1 Strive Achieve Succeed Go Beyond Lewiston, Idaho

DESERT WILDLIFE UNLIMITED POB 1388 Brawley, CA NOTICE TO BIDDERS ALAMO RIVER TREATMENT WETLANDS AT SHANK ROAD

School Building Authority of West Virginia BUILDING INFORMATION MODELING (BIM) EXECUTION PLAN SBA FORM 191

General Contractor Pre-qualification Requirements

MODEL SCHEDULING SPECIFICATION

Memorandum. Jeff Jasper, P.E. Director, Division of Design. Technical Support TEBM, Division of Construction. From: Jeremiah Littleton, P.E.

CITY COLLEGE OF SAN FRANCISCO May 2008 PROJECT INSPECTION SERVICES

REQUEST FOR PROPOSALS (RFP) - Construction Management Services. Germantown School District Office

DEVELOPMENT OF BEST MANAGEMENT PRACTICES TO EXECUTE A SUCCESSFUL CAPITAL IMPROVEMENT PROGRAM

REQUEST FOR QUALIFICATIONS/REQUEST FOR PROPOSALS CONSTRUCTION MANAGEMENT SERVICES Various Projects RFQ/RFP No

AGREEMENT FOR PROFESSIONAL DESIGN SERVICES

The University of North Carolina Plan to Increase Utilization of Historically Underutilized Businesses in Construction Projects

Mid Michigan Community College

PROJECT AND CONSTRUCTION MANAGEMENT SERVICES FOR KUWAIT PORT AUTHORITY FOR PROJECTS AT SHUAIBA PORT

Facility Services PROJECT MANAGEMENT METHODOLOGY FRAMEWORK

1.040 Project Management

World s #1 most widely used construction management software.

CONSTRUCTION MANAGEMENT AGREEMENT BY AND BETWEEN NYU HOSPITALS CENTER - OWNER - AND - CONSTRUCTION MANAGER PROJECT DATED AS OF

Project Management Manual for Design and Construction Projects. (Revised August 2010)

Structures Construction Pre-Work Checklist PRE-WORK SHEET FOR PROJECT MANAGERS

REQUEST FOR PROPOSAL TO PROVIDE CONSTRUCTION MANAGEMENT AND GENERAL CONTRACTOR SERVICES SPRINGVILLE CITY NEW AQUATICS AND ACTIVITIES CENTER

Exhibit C: Scope of Work and Schedule of Deliverables

Time Management. Part 5 Schedule Development. Richard Boser

Information Technology Project Management, Sixth Edition. Note: See the text itself for full citations. More courses at cie-wc.edu

NZQA registered unit standard version 2 Page 1 of 5. Develop and implement a project plan to deliver on an Infrastructure works contract

CFL Guidelines for Developing October 2006 Critical Path Method Schedules (CPMs)

REQUEST FOR QUALIFICATIONS FOR CONSTRUCTION MANAGEMENT SERVICES

Engineering and Construction Contract Management Certificate Program (ECCM Workshops 1, 2, 3, 4, 5, 6) Certified Program

Project Scope Statement Example

Construction of A hospital Building

Construction Management and project process

MONTHLY PROJECT CONSTRUCTION PROGRESS REPORT #5

TLHAMATSI AFRICA PROJECTS CONSTRUCTION MANAGEMENT PRESENTATION. PRESENTED BY: BAKANG MOENG

Mechanical Contractor Pre-Qualification Packet. SPSC N180 Computer Data Room Phase II. Project No. CP Notice No. Notice

CAPITAL PROJECT COSTS!!! UNIVERSITY OF CALIFORNIA SANTA CRUZ

Alexandria National Cemetery SECTION NETWORK ANALYSIS SCHEDULE

REQUEST FOR QUALIFICATIONS (RFQ) FOR CONSTRUCTION MANAGEMENT SERVICES

SCHEDULING AND PROJECT MANAGEMENT

Using Construction Manager at Risk to Save Time and Money Laura McCluskey University Center Sioux Falls / South Dakota Board of Regents

EXHIBIT A SCOPE OF SERVICES CONSTRUCTION MANAGEMENT TEAM POSITIONS AND REQUIREMENTS

The Construction Project Manager

Request for Qualifications (RFQ NO ) CONSTRUCTION MANAGEMENT/OWNERS REPRESENTATIVE SERVICES APRIL 16, 2015

COAST COMMUNITY COLLEGE DISTRICT REQUEST FOR PROPOSALS #2013 FOR

ALABAMA STATE DEPARTMENT OF EDUCATION

TOWN OF MILFORD REQUEST FOR QUALIFICATIONS DESIGNER SERVICES FOR LIBRARY ROOF REPLACEMENT

UNIFIED FACILITIES GUIDE SPECIFICATIONS

ADMINISTRATIVE PROCEDURES

Prequalification Supplement for First Tier Subcontractors under CM at Risk Wake Technical Community College Early Site North Campus Project

Engineering, Procurement and Construction (EPC) Projects

DOCUMENT ADDENDA ADDENDUM NUMBER ONE (1) A. Project Name: BHFC New Single Family Dwelling Unit Dahlia Circle

Transcription:

The CM Perspective The Elements of Project Management Preconstruction Phase Preconstruction: Setting the Project Up to Succeed Project Plan Critical Milestones Define all major deadlines and critical dates for Preconstruction, Bidding, and Construction phases. Milestone Deliverables Define in detail expectations of documents afor each defined milestone submittal/document Matrix of Responsibilities Define all stake holders and their responsibilities Detailed Schedule Define all tasks, interrelationships of tasks (predecessors and successors), durations, deadlines, and responsible stakeholder(s) Constructability Continual dialogue and review of documents. Analysis of proposed construction systems Site Utility Overlay Analysis/Coordination SD, DD, 30%, 50%, 90%, and Final Document reviews and coordination Structural Steel analysis and review MEP analysis and reviews Construction Logistics Planning Organization and Coordination of site for construction Value Savings Selected systems analysis Preliminary Construction Scheduling Project Expediting Services Phased delivery & fast tracking Pre-Purchasing of long lead materials, Pre-detailing of Structural Steel

Preconstruction Phase, Cont d. Estimating Systems analysis Incremental Document Estimates with tracking Document Development Division 0 & 1 Trade Packages Attachments and Supplemental Documents Bidding Advertising, Invitations to Bidders Bid Solicitation & Document Management Pre Bid RFI Management and Distribution Addendum Management and Distribution Bid Opening & Post Bid Analysis Contract Development and Distribution Precon to Operations Handoff Managing the Project Keys to Success Developing a team approach on the project Use Core Values as a guiding light Pre-construction meetings prior to the start of new trades or systems Centralized project management software (Prolog) Standardized procedures and forms (ISO9001) Schedule must be realistic and able to be used on a daily basis by project team. It all comes down to putting the right people on the project.

Project Documentation RFI s Must be clear and specific to one issue and provide a proposed solution. It helps to be able to speak with the design team to fully explain the issue and follow up with a confirming RFI through the architect. Meeting Minutes Action steps must be documented with a responsible party and specific due date. Responsible promising Description of the issue and methods to solve issue must be clear and concise to an outside party Submittals Prioritize and place critical submittals on CPM Schedule to avoid lead time delays Create a comprehensive submittal register and assign responsibility and due dates early. Change Management Firm, but fair CPM Scheduling Create a work breakdown structure and segregate the schedule by building/floor/quadrant in order to allow for sufficient detail. Avoid the use of start to start relationships with lag. Obscures the true float. Sub/Trade Contractor Management Termination of Subcontractors Notice Requirements, Time to cure Termination procedures Substitution of Listed Subcontractors PCC 4100-4114 requires any substitution due to clerical listing to be noticed by prime within two days of bid with proper affidavits. Failure to execute contract or provide bond, unlicensed contractor, bankruptcy, and failure to prosecute work are other reasons to substitute Hearing with Contracting agency may be required for substitution at the request of the substituted subcontractor Closeout Start early and have all possible closeout documents part of the submittal process. Set a value on closeout requirements on the schedule of values and release monies as the requirements are met. Develop and complete an incomplete work list prior to requesting punch list walk from owner and design team. If possible, develop a single comprehensive punch list.

Olympic size Pool is excavated Photo Date 07/05/2006 Prefab Yard for framing during foundations Phase One site development provided all mass grading, lime treatment and major utilities Including electrical service to utility yards. Parking lots are in With 1 lift of AC and all weather access is provided around campus Prefab Yard for framing during foundations Photo Date 10/08/2006 Theater Steel starting Steel Framed MU/Caf. structure complete 4 ea - 2 story Classrooms almost complete Landscaping and Hydroseed is now complete at fields and side slope areas to mitigate SWPPP needs

Theater is weather tight Photo Date 01/05/20076 Admin Building Gym/PE Bldg Superstructure installed Venture School In finishes Stadium ready for Synthetic turf and Rubber track MU/Caf is in finishes w/ Kit. Eqpt. going in Career Tech Bldg Std. CR bldgs Science CR is Pre-fab yard is busy building covered walk roof framing while concrete columns are cast. Playfields and Backstops Are in and will have 1 yr of growth before opening. All perimeter landscaping Is complete.