A Comparison of Project, Program & Portfolio Management Responsibilities and who should be responsible for what. By R. Max Wideman



Similar documents
Project Management Framework

Description of Program Management Processes (Initiating, Planning) 2011 PROGstudy.com. All rights reserved

Ten Steps to Comprehensive Project Portfolio Management Part 1 An Introduction By R. Max Wideman Introduction Project

OE PROJECT CHARTER TEMPLATE

Governance in the Project Management World Published January 2013.

Ten Steps to Comprehensive Project Portfolio Management Part 8 More Tips on Step 10 By R. Max Wideman Benefits Harvesting

Project Management Guidelines

Ten Steps to Comprehensive Project Portfolio Management Part 3 Projects, Programs, Portfolios and Strategic Direction By R.

PROJECT MANAGEMENT METHODOLOGY SECTION 3 -- PLANNING PHASE

How To Manage Project And Portfolio Management In Microsoft Office 2010

Assessing the Appropriate Level of Project, Program, and PMO Structure

Develop Project Charter. Develop Project Management Plan

Service Management Transformation: An 8 Step Process for Organizational Effectiveness

ITS Project Management Methodology

Best Practices Statement Project Management. Best Practices for Managing State Information Technology Projects

The Agile PMO. Contents. Kevin Thompson, Ph.D., PMP, CSP Agile Practice Lead cprime, Inc E. Third Avenue, Suite 205 Foster City, CA 94404

Project Management Methodologies By Jason Charvat, published by Wiley, NJ, 2003 (A book review by R. Max Wideman)

Value to the Mission. FEA Practice Guidance. Federal Enterprise Architecture Program Management Office, OMB

The Project Management Life Cycle By Jason Westland (A book review by R. Max Wideman)

The 10 Knowledge Areas & ITTOs

WHY DO I NEED A PROGRAM MANAGEMENT OFFICE (AND HOW DO I GET ONE)?

The following is intended to outline our general product direction. It is intended for information purposes only, and may not be incorporated into

Partnering for Project Success: Project Manager and Business Analyst Collaboration

The Standard for Portfolio Managem

Section 6. Governance & Investment Roadmap. Executive Governance

PROJECT MANAGEMENT PLAN TEMPLATE < PROJECT NAME >

Managing Successful Programs (2007) Page 2 of 11. Book Structure

APPENDIX X1 - FIFTH EDITION CHANGES

Program Management Professional (PgMP) Examination Content Outline

Cisco Unified Communications and Collaboration technology is changing the way we go about the business of the University.

1. What is PRINCE2? Projects In a Controlled Environment. Structured project management method. Generic based on proven principles

Positive Train Control (PTC) Program Management Plan

OPTIMUS SBR. Optimizing Results with Business Intelligence Governance CHOICE TOOLS. PRECISION AIM. BOLD ATTITUDE.

2007 & 2008 Dennis L. Bolles and Darrel G. Hubbard 1

ITIL Service Lifecycles and the Project Manager

The Fast Track Project Glossary is organized into four sections for ease of use:

Introduction. Book Structure

Mapping COBIT 5 with IT Governance, Risk and Compliance at Ecopetrol S.A. By Alberto León Lozano, CISA, CGEIT, CIA, CRMA

CRM SUCCESS GUIDELINES

Portfolio Management Professional (PfMP)SM. Examination Content Outline

MGMT 4135 Project Management. Chapter-16. Project Oversight

project portfolio management

Project Management Guidebook

Chapter 4. The IM/IT Portfolio Management Office

California Enterprise Architecture Framework

Project Portfolio Office April Information and Communications Technology P ROJECT PORTFOLIO O FFICE M AY 2014 D RAFT. Page 1

Project Management Simple Answers to Simple Questions

PROJECT MANAGEMENT FOR NON-PROJECT MANAGERS

Driving PPM Adoption Through Effective Change Management

Frank P.Saladis PMP, PMI Fellow

The growing importance of EPMO (Enterprise Project Management Office) in today s organizations

Enterprise Architecture (Re)Charter Template

QAIassist Software Development Methodology Implementation Guide

SOA Governance and the Service Lifecycle

by David Hebert, Managing Director, Oracle Applications, Answerthink and Dr. David Oppenheim, Director, Delivery Services, Answerthink

Why Data Governance - 1 -

PMO Director. PMO Director

Presented By: Leah R. Smith, PMP. Ju ly, 2 011

White Paper. Business Analysis meets Business Information Management

PMP Examination Tasks Puzzle game

Quantifying and Delivering Value with Geospatial Network Infrastructure Management Solutions

Agile project portfolio manageme nt

HP Project and Portfolio Management: not just for IT. White paper

IO4PM - International Organization for Project Management

How to Structure Your First BPM Project to Avoid Disaster

State of Kansas Information Technology Vendor Management Program Executive Summary

Day 5: Project Management, Program Management, and Trends

Capability Maturity Model Integration (CMMI SM ) Fundamentals

PMO Starter Kit. White Paper

IT Service Desk Unit Opportunities for Improving Service and Cost-Effectiveness

Program Management: Opportunity or CLM?

Final. North Carolina Procurement Transformation. Governance Model March 11, 2011

By Ronald Ireland and Mary Adamy, Oliver Wight Americas, Inc.

Sound Transit Internal Audit Report - No

Operationalizing the Strategic Plan Defining projects & programmes

FIXING PROJECT MANAGEMENT: A MUST-HAVE

Visual Enterprise Architecture

Nydia González 1, Franck Marle 1 and Jean-Claude Bocquet 1. Ecole Centrale Paris, FRANCE

IT Portfolio Management

Project Management Certificate (IT Professionals)

Crosswalk Between Current and New PMP Task Classifications

ORGANIZED FOR BUSINESS: BUILDING A CONTEMPORARY IT OPERATING MODEL

Project Portfolio Management

Project Management Best Practice Benchmarks

<name of project> Software Project Management Plan

Global Payroll? A Few Planning Considerations. Human Resources Globalization

Business Analysis Standardization & Maturity

STRENGTHS AND WEAKNESSES OF CURRENT SUPPLY CHAIN MANAGEMENT AND INITIATIVES FOR THE FUTURE. Diana-Maria DIACONU (NIDELEA) 1 Cristina ALPOPI 2

Quick Reference Guide Interactive PDF Project Management Processes for a Project

Template K Implementation Requirements Instructions for RFP Response RFP #

PMAP. Project Management At Penn PMAP

Project Management. In this Guide

Integration Mgmt / Initiating Process Group 4.1 Develop Project Charter

Enhance State IT Contract Expertise

Project Governance Plan Next Generation Project Oregon Military Department, Office of Emergency Management, Program (The OEM 9-1-1)

Collaborative and Agile Project Management

Scheduling Process Maturity Level Self Assessment Questionnaire

Transcription:

A Comparison of, & Management Responsibilities and who should be responsible for what. By R. Max Wideman This analysis was inspired by Darren Radford, coauthor of Going Beyond The Waterfall, published by J. Ross Publishing 2014, in Table 1.1 on p6, titled: "Differences between project, program and portfolio management" Published here December 2014 9/29/14 Introduction In a corporate context, many people use the term " Management" in the broader sense of deploying projects in the corporate environment. That is, instead of meaning the conduct of a single project. These projects quite often span across, or are based in, multiple divisions and/or departments of the organization as a whole. So if a broader definition is accepted, then for purposes of managing a significant number of projects, we can visualize project management as a tiered management structure. Each level up this structure represents a progressive order of magnitude in management responsibility. Such a scenario necessarily involves a considerable number of people, often with conflicting concerns, interests, priorities and demands that need managing. Hence, the need for a strong and clear management structure from the corporate executive level down to those working at the activity level. In the last couple of decades, four project "responsibility" levels have come to be recognized, that is, from the project level up: ; ; ; and Executive (at the corporate level). So, for purposes of clarification, these "levels" may be defined as: : A temporary endeavor undertaken to create a unique product, service or result. 1 (That is to say, for a single project); : A group of related projects, subprograms, and program activities managed in a coordinated way to obtain benefits not available from managing them individually. 2 : s, programs, sub-portfolios, and operations managed as a group to achieve strategic objectives. 3 Executive: The senior level of management of a corporation having the power to direct, authorize, and give high level approvals. The Tables that follow summarize the findings of our study. Assumptions: 1. The organization in question is large, with a significant number of projects in play 2. Top management is focused on remaining competitive, maintaining technological efficiency, and/or improving services to customers 3. The number of projects at play exceeds the resources available. 4. The organization as a whole has an assessed project management maturity level of 3/5 or higher. 5. " management" is more than "The application of knowledge, skills, tools, and techniques to project activities to meet the project requirements." 4 (Emphasis on single project added.) Instead, " Management is the totality of managing projects throughout the organization and at all levels." 5 1 A Guide to the Management Body of Knowledge, Fifth Edition, PMI, PA, 2013, Glossary, p553 2 Ibid 3 Ibid, p551 4 Ibid, p554 5 R. Max Wideman, October, 2014.

Comparison of, and responsibilities Page 2 of 6 For the project management domains shown, responsibilities are tabulated briefly for each project management level. The entries demonstrate the changes in focus between the management levels. Management Generally Domain Level Comparative Responsibilities Contextual Environment Objectives driven; tactical, predictable, reliable, performance-based tools and techniques; time limited. Target is product completion; awareness of stakeholder involvement. Overall program goals driven; generally complex and uncertain; requires flexibility and responsive, learning-based approach; time is indefinite. Target is overall program progress; cultivation of stakeholder support. Corporate vision and strategy driven; tools to identify, select, prioritize, balance, and initiate the right mix of projects; effectively a part of permanent corporate management. Target is realizing benefits; coordination of stakeholder commitment. Governance "Rules of engagement" set by Management Office, if present. If not then by Management Office, if present. If not then by corporate policies and procedures. Executive "Rules of engagement" set by Management Office, if present. If not then by corporate policies and procedures. "Rules of engagement" set by corporate policies and procedures, consistent with corporate vision, strategies and culture. "Rules of engagement" set by Board of Directors and related corporate stakeholders. Management Business-like agreements; authority-based directive style; conflict resolution; single purpose and rational decisionmaking; activity authorization. Focus is on project objectives. Style: authoritarian. Exploratory change for the better providing vision and leadership; management of powerful stakeholders, including sponsor engagement; intuitive decision-making. Focus is on program goals. Style: facilitation. Management, coordination and accounting for business benefit. Focus is on corporate portfolio strategies; Business Case acceptance; and program authorization. Style: Stakeholder leadership, administration.

Comparison of, and responsibilities Page 3 of 6 Stakeholders Primarily: Office, project's client, sponsor, team members, and hired resources. Clear and concise, two-way. A broader range of stakeholders who have an interest in the project, e.g. Management Office, members of the public benefitting or impacted by the project, media and related actors. Public relations style. Corporate office, investors, politicians, public at large. Communicate with stakeholders relative to the overall portfolio. Political style. Planning Standard approach: What must be done to reach a future objective, how, who and when. Detailed delivery plans created. Overall program plan to drive stakeholder engagement; establish milestone sequence and pacing; allocation of internal resources and overview of external resources; and benefits realization planning. Convert corporate vision into a viable selection of projects; maintain executive support; scan the internal and external environments for changes impacting the portfolio; modify the portfolio accordingly; create and maintain necessary standardized reporting practices suited to this level; ensure optimum benefits reaping. Body of knowledge domains Core project management functions Scope scope boundaries clearly limited; deliverables clearly defined, or set within rolling wave planning. Broad scope with flexible boundaries; multiple deliverables; alignment with strategic goals. Custodian of metrics, benchmarking and lessons learned. Evolving scope consistent with corporate vision and strategies. Creation of one or more project portfolios accordingly, optimized for effectiveness and efficiency. Maintain vigilance for internal and external changes and risks and obtain executive approval for necessary redirection. Quality Grade clearly specified; testing to ensure compliance. Establish required quality grade across a program; testing criteria and frequency. Custodian of recommended practices. Provide overview of overall quality approach; requirements and standards for each portfolio.

Comparison of, and responsibilities Page 4 of 6 Time Clear and controlled life span to meet project objectives. Planning of project activation to establish required sequencing of deliverables to satisfy program goals. Interpreting corporate strategies into portfolios. Obtaining corporate approvals for activation of major portfolios, programs and projects. Prioritizing, aligning and sequencing the required portfolio program-level components for maximum effect and resource efficiency. Cost Analyzing and costing work for purposes of estimating for project budget. Capturing project costs, and comparing to approved budget; estimating costs to complete; reporting forecasts over or under project budget. Assembling actual and forecast program costs-atcompletion; planning and deploying projects within programs to best advantage of corporate resources and cost. Broad costing of proposed corporate strategy initiatives to assess relevance, expected benefits, hence ROI, and unexpected consequences; advising on most cost effective compositions; recommending alternatives. Body of knowledge domains Facilitating functions Risk Generally specific, internal and local, impacting project performance with respect to product delivery. Assessing collective risks arising from multiple projects, perhaps acting on each other. Scanning the contextual environment for potential risks to a whole program; resolving conflicts at the project level. Promoting a corporate environment that minimizes risks to individual programs and projects; removing corporate roadblocks; resolving conflicts at the program level; managing reserves for major unexpected risk events.

Comparison of, and responsibilities Page 5 of 6 Resources Estimating timing and extent of required resources, and resulting cost; organizing efficient hand-on and hand-off of resources at start and finish of each corresponding activity. Planning and scheduling of project initiations in a program to minimize demand conflicts between its projects. General assessment of overall resource requirements for a given corporate initiative. Acquiring additional resources where necessary, including make-or-buy decisions. Procurement Obtaining bought-in resources as and when required by the project in question; sourcing of resources; recommending best-buy decisions (not necessarily at lowest cost.) Communications Identifying those resources required by multiple projects in the program and either modifying the program to improve efficiency, and/or arranging bulk purchases accordingly across several projects. Managing the distribution across several projects. Where appropriate, integrating portfolio requirements with corporate purchasing, or authorizing independent contracting and purchasing at the program/project level. Note: The closer the procurement arrangement is to the project level, the more effective will be the supply and delivery. Planning and organizing delivery of instructions at the project level. Regular progress reporting to project stakeholders and the management level, suitably packaged for each (e.g. forecast final delivery, forecast final cost, urgent risks, roadblocks and issues). Review project reports with view to resolving roadblocks and issues; rescheduling the program if appropriate; or escalating to level for resolution. Reviewing program reports for appropriate action; modifying portfolio plan to minimize impacts. Consolidating program/project reports for corporate consumption.

implementation Comparison of, and responsibilities Page 6 of 6 Monitoring & Control Change Management Monitor and control the work of producing the products the project was undertaken to deliver. Monitor the progress of program components to ensure overall goals; schedules; budget; benefits; of the programs are all contained. Provide governance to projects in the programs. Monitor aggregate benefit realization performance; and costto-value indicators. Provide governance to program management. Changes are to be avoided or minimized if possible; processes in place to keep changes managed, and controlled. Note: "Change Management" is the business of administering changes to scope, time, cost, etc. This is not to be confused with "Management of Change" meaning, for example, organizational change as a project. Expected from inside and outside the program; generally seen as opportunities. Changes in the broader external environment continually assessed. Overall portfolio managed accordingly. Success Measured by process compliance and product quality; timeliness; adherence to budget; customer satisfaction with product. Measured by the degree to which the products of the projects in the program create value, and/or deliver benefits from the capability created, and for clients served. Measured in terms of aggregate performance of business divisions and departments, and/or satisfies corporate vision and strategies, and/or lays the groundwork for future development. Conclusions When the different levels described are examined in the light of the various domains of project management, the responsibilities at each level become much clearer and should prove helpful. Without carefully documented clarification and structure, there is every possibility that overlap and competition for control will emerge with inevitable added cost. Hence, it is important to agree the division of responsibilities and corresponding boundaries between the parties. It is hoped that these tables will help. Note that the costs of and Management are corporate overheads and not project costs. It is also worth noting that we first talked about "Governance in the Management World" in January, 2013. Since then we have somewhat modified our view as shown in this current work. R. Max Wideman, Fellow PMI