Earned Value Exercise. Su-Cheng Wu. MET AD 644: Project Risk, and Cost Management. Paul B. Cook, PhD PMP



Similar documents
Project Cost Management

Rules on using templates. MECH 896 Professional Development for MEng Students. Assignment #6A: Questions. Homework Discussion

PROJECTS SCHEDULING AND COST CONTROLS

Profesor: Francisco Javier Sanz Pérez. by fjspsv, PMP Test C07_01

Earned Value Management Changes to the Glossary and Chapter 7 of the PMBOK Guide Third Edition.

Earned Value Management (EVM) is a technique that is used to track the progress and status of a project and forecast its likely future performance.

INSE 6230 Total Quality Project Management

IST 302 : Project Cost Management

Earned Value Formulae

Using Earned Value Management for Improving Processes. By Cynthia K. West

Earned Value. Valerie Colber, MBA, PMP, SCPM. Not for duplication nor distribution 1

COINS EVA Earned Value Analysis

Earned Value Management Tutorial Module 6: Metrics, Performance Measurements and Forecasting. Prepared by:

An introduction to Earned Value Analysis

700 Analysis and Reporting

Chapter 7. (PMBOK Guide)

Project Cost Management

Introduction to earn value management in Civil Engineering

Brainstorm. What is Cost and Project Cost Management?

Tracking Budgets and Schedules

Module 5 Cost Management PMP Exam Questions

IQPC IT Project Management Conference Sydney Recent Advances in Project Prediction Techniques

CPM -100: Principles of Project Management

Procurement Management S# What? Formula Additional Notes CPPC CPFF CPAF CPIF T&M FPEPA FPAF FPIF FFP

EARNED VALUE MANAGEMENT. CASE STUDY USING MICROSOFT PROJECT

How To Manage A Project

Earned Value Analysis Exercise

AACE International Recommended Practice No. 86R 14

Project Cost Management

Earned Value Management Guidelines

PMI Lexicon of Project Management Terms

GPMCEP GLOBAL PROJECT MANAGEMENT, LLC C O U R S E

The Two Most Useful Earned Value Metrics: the CPI and the TCPI

Integration of Income Management and Cost Management: A Complementary for Financial Analysis of Projects. Abstract. Introduction

Managing Project Budgets with MS Project. Sonja Streuber, PMP, SSBB

CVR/IT Consulting LLC

Project Management. ZEUS Student Seminar on 14 th November 2003 by Riko Wichmann. Riko Wichmann, MPY Zeus Student Seminar - PM,

PROJECT COST MANAGEMENT

Forecasting Project Schedule Completion by Using Earned Value Metrics

Adjust MS Project default settings to meet the needs of your project. Loading Analysis is an iterative process. Where are you overloaded?

EVM.01. Earned Value Analysis Why it Doesn't Work

Project Management Glossary

Appendix A of Project Management. Appendix Table of Contents REFERENCES...761

Earned Value and Agile Reporting

Estimating Cost at Completion - Judgment & EV Information

Assignment 2: Microsoft Project Toolset. Eric Palmer & Mahindra Bheodari. Kennesaw State University. IS 8100 Spring 2015

Unit 5: Cost Management (PMBOK Guide, Chapter 7)

Earned Value Management Tutorial Module 8: Reporting. Prepared by:

Project Management: Tracking Progress and Earned Value with MS Project 2003

LEADING EDGE FORUM CSC PAPERS 2012 EARNED SCHEDULE: FROM EMERGING PRACTICE TO PRACTICAL APPLICATION

L10: Budgeting and Cost Control. Olivier de Weck

Appendix D Glossary Of Terms

Certification Exam Objectives: PK0-003

A Gentle Introduction to Earned Value Management Systems

PMP Exam Preparation Answer Key

Selftestengine..PMI-SP.270 questions PMI-SP. PMI Scheduling Professional

Towards a Complete Earned Value Analysis. Sam Sharp and Peter Hall. Paper # 166

earned value management

plans based on actual cost, schedule and technical progress of work [1, 9].

PMP PREP QUICK STUDY GUIDE BY THE PERSIMMON GROUP

FERMI RESEARCH ALLIANCE PROCEDURES PROJECT MANAGEMENT. Head, Office of Project Management Oversight

Earned-Value Benchmarks for Re-baselining Your Project

technical tips and tricks

Chapter 7: Project Cost Management. Munawar

Project Cost Management. Richard Boser

THE APPLICATION OF PERFORMANCE MEASUREMENT TECHNIQUE IN PROJECT MANAGEMENT : THE EARNED VALUE MANAGEMENT (EVM) APPROACH

PERFORMANCE AND QUALITY IN PROJECTS Project Management and Leadership 2016D, PhD, PMP

Earned Value Management and the Government Program Office. Blair Alan Knapp Jr. MSPM PMP

Create Stoplight charts using Milestones Professional

Expert Reference Series of White Papers. Importance of Schedule and Cost Control

PMP SAMPLE QUESTIONS BASED ON PMBOK 5TH EDITION

Project Control with ProTrack

Simple Earned Value (Using MS Project 2010)

Expert Reference Series of White Papers. Tips and Techniques to Pass the PMP Exam

Agile Project Management Controls

INTEGRATED COST AND SCHEDULE CONTROL IN PROJECT MANAGEMENT

QUALITY AND PERFORMANCE IN PROJECTS. Project Management and Leadership 2015D, PhD, PMP

PMP SAMPLE QUESTIONS BASED ON PMBOK 5TH EDITION

Information Technology Project Management, Sixth Edition. Note: See the text itself for full citations. More courses at cie-wc.edu

Abstract. Earned Value Management Basics

pm4dev, 2008 management for development series Project Budget Management PROJECT MANAGEMENT FOR DEVELOPMENT ORGANIZATIONS

Earned Value Management System (EVMS) and. Project Analysis Standard Operating Procedure (EPASOP)

PMP Exam Tips on Cost Management, Fourth Edition. Parallels between Cost and Time estimating:

Project Management Center

A Framework for Project Metrics

Applied Project Management ( APM )

DCMA DCMA-EA PAM October 2012

Pune, MH, India. 2 P.G. Student, Imperial College of Engineering & Research, Wagholi, Pune, MH, India. wit.vaishnavi@gmail.com

Towards a Multi-Dimensional Framework for Assessing the Value of. Software Projects

Lecture Slides for Managing and Leading Software Projects. Chapter 8: Measuring and Controlling Work Processes

What is the Health of my Project?

Young Hoon Kwak Associate Professor School of Business The George Washington University

PERCEPTION. Tracking Progress & EAC

National IT Project Management Methodology

performance management system that is based on Earned Schedule Management.

Certification Preparation Course LATVIKON (R.E.P.)Centre

SoaDssPm: A new Service-Oriented Architecture of the decision support system for the Project Management.

Principles of Project Management

Transcription:

Earned Value Exercise 1 Running head: Earned Value Exercise Earned Value Exercise SuCheng Wu MET AD 644: Project Risk, and Cost Management Paul B. Cook, PhD PMP

Earned Value Exercise 2 Case 1: Background: You have a project that is scheduled to be completed in 10 days at a budgeted cost of 100,000. At the end of day 6 you do an analysis and you determine the job is 70% complete and you have spent 65,000. Assumptions: 1) The following Earned Value Analysis was performed under the assumption that the baseline plan has a purely linear distribution rate of a) daily planned value, b) daily planned % complete. 2) For the EAC, this report uses the EAC formula of EAC = BAC/CPI, which is one of the EAC formulas; assuming the current trend of the cost performance will be typical of the project going forward. (Anbari, 2003)

Earned Value Exercise 3 Questions and Answers: 1. What is the project s earned value? At Day 6 th, EV = 70,000.00 2. What is the project s budget at completion? BAC = 100,000.00 3. Is the project ahead, behind schedule or on time? Ahead of schedule. 4. Is the project expected to complete on budget, under or over budget? Under budget. 5. What is the project s SPI? At Day 6 th, SPI = 1.17 6. What is the project s CPI? At Day 6 th, CPI = 1.08 See file: WuS_assign8_EVM_Calculator.xls EV Calculation Details: BAC 100,000.00 Day 6th Physical % Complete 70% Day PV Cum.PV AC (/Day) Cum. AC EV (/Day) Cum.EV CV SV CPI SPI TCPI 1 2 20,000.00 3 30,000.00 4 40,000.00 5 50,000.00 6 60,000.00 70,000.00 70,000.00 5,000.00 1.08 1.17 0.86 7 70,000.00 8 80,000.00 9 90,000.00 10 100,000.00

Earned Value Exercise 4 EAC 92,857.14 VAC 7,142.86 ETC 27,857.14 PCIC 70% PCIB 70% Case 2: Background: Consider the following table of activities: After 8 days of work, activity A has been completed on time. Activity C has 4 deliverables and 3 have been completed. Assuming each day s work costs 100, what is the Cost Variance, the Schedule Variance, the CPI and SPI? Activity Predecessor Duration (days) Start None None A Start 2 B A 2 C A 4 D B,C 2 E D 4 F C 4 G F 3 H E,G 1 End H None 1. Draw the network diagram 2. Complete the forward and backward passes. 3. What activities are on the Critical Path? Please Mark in Red. 4. Which activities have total slack? Which activities have free slack? (Calculate Slack Allowance.)

Earned Value Exercise 5 Answer: 1, 2, 3, 4: Assumption: 8 days of work had passed, only activity A has been completed. Activity B, is assumed to be started right after Activity A s completion, but not 1 % is completed. Activity F could not have been started since Activity C only has 3 out of its 4 deliverables completed. Activity D could not have been started since Activity C is not completed. Table below shows what had been started and highlighted cell shows the earned or completed deliverables. Activity Started/ Day Earn Value 1 A Earned 2 A Earned

Earned Value Exercise 6 3 B C Earned 4 B C Earned 5 B C Earned 6 B C 7 B C 8 B C Earn Value Analysis: The table below shows on day 8th, with the baseline schedule following the Network Diagram above (Appendix E), the Cost Variance is 900, Schedule Variance is 700, CPI is 0.36 and SPI is 0.42. Day PV Cum.PV AC (/Day) Cum. AC EV (/Day) Cum.EV CV SV CPI SPI 1 100.00 100.00 100.00 100.00 100.00 100.00 2 100.00 200.00 100.00 200.00 100.00 200.00 3 200.00 400.00 200.00 400.00 100.00 300.00 4 200.00 600.00 200.00 600.00 100.00 400.00 5 100.00 700.00 200.00 800.00 100.00 500.00 6 100.00 800.00 200.00 1,000.00 0.00 7 200.00 1,000.00 200.00 1,200.00 0.00 8 200.00 1,200.00 200.00 1,400.00 0.00 900.00 700.00 0.36 0.42 Reference Anbari, F. (2003). Earned Value Project Management Method and Extensions. Project Management Journal; Dec 2003; 34, 4; ABI/INFORM Complete P.12 Earned Value Examples:

Earned Value Exercise 7 Let's look at a simple example to see how earned value is calculated and used: You are building a 4sided fence. Each side is of equal length and you estimate that each side will contain the same material and labor costs as well as take the same amount of time to complete. You estimate that the project will take 4 days to complete and your budget, including a contingency reserve is 4,000. At the end of 3 days, you are asked to prepare an Earned Value calculation in order to determine how the project is progressing. You determine that as of the end of day 3, total costs incurred are 3,500. and 70% of the project is completed. BAC (budgeted cost at completion) = 4,000. Your Actual % completed is 70%. Therefore your EV (earned value) = BAC X Actual % completed, or EV = 4,000. X.70 = 2,800. Next, your PV (planned value) = BAC X Planned % completed, or PV = 4,000. X 75% (3 of 4 days) = 3,000. Therefore, your SPI (schedule performance index) = EV / PV, or 2,800. / 3,000. =.933, which means you are behind schedule. Your SV (schedule variance) = EV PV, or 2,800 3,000 = 200. Your CPI (cost performance index) = EV / AC (actual costs), or 2,800 / 3,500 =.8, which means you are over budget. Your CV (cost variance) = EV AC or 2,800 3,500 = 700. Forecasting ahead, your EAC (estimated cost at completion) = BAC / CPI, or 4,000. /.8 = 5,000. Your VAC (variance at completion) = BAC EAC or 4,000. 5,000 = 1,000. Your ETC (estimated cost to complete) = EAC AC or 5,000. 3,500. = 1,500.