BUILDING ENVELOPE COMMISSIONING FOR THE EVERYDAY COMMISSIONING AGENT



Similar documents
BECx& Building Airtightness. Presented by: Eric Amhaus Principal

Total Building Commissioning: Case Study of the U.S. District Courthouse in Salt Lake City, Utah, USA

FIELD TESTING SERVICES

Evaluating the Field Performance of Windows and Curtain Walls of Large Buildings

Sample Company SECTION GENERAL COMMISSIONING REQUIREMENTS PART 1 GENERAL 1.1 SUMMARY AND CONTRACT RESPONSIBILITIES

Avoiding Air Barrier Pitfalls

Exhibit C: Scope of Work and Schedule of Deliverables

continuing professional education. As such, it construed to be an approval or endorsement by

WATER LEAKAGE IN GLAZED CURTAIN WALL SYSTEMS:

Preventing Ice Dams on Roofs

DuPont Tyvek Commercial Air Barrier Assemblies Exceed Air Barrier Association of America, ASHRAE 90.1

MOCK-UP TEST REPORT. Rendered to: TUBELITE, INC. PROJECT: 200 Series Curtain Wall Mock-Up

Table of Contents PART 1 WINDOW SELECTION GUIDE. Window and Door Selection Guide

Impact-Resistant Windows and Sliding Glass Doors

foot skylight) is enough to knock a worker off their feet. A 10 mph wind gust on a 5 x 6 skylight develops a wind force of 270 lbs.

Quality Assurance and Diagnostic Water Leakage Field Check of Installed Storefronts, Curtain Walls and Sloped Glazing Systems

LEED PRESENTATION OUTLINE

Commissioning of Mission Critical Facilities

*Trademark of The Dow Chemical Company A business unit of The Dow Chemical Company and its subsidiaries Copyright 2003 The Dow Chemical Company.

Assessing Curtain Walls

Guide Specification SECTION COMMISSIONING OF HVAC PART 1 - GENERAL 1.1 SUMMARY

Water Damage on Construction Sites. A guide to loss prevention

SECTION ALUMINUM FRAMED ENTRANCES and STOREFRONTS. System 402 Flush-Glazed Screw Spline Storefront

The Science of Rough Opening Preparation and Window Installation to Minimize Air Leakage

Uncovering Myths and Opportunities of Advanced Building Envelope Technologies: BIPV, Roofing and Windows

metal Duil~ing manufacturers Association

TEST REPORT. Report No.: A Rendered to: BAMCO INC. Middlesex, New Jersey. PRODUCT TYPE: Wall Cladding System SERIES/MODEL: Dry Concept

Natatorium Building Enclosure Deterioration Due to Moisture Migration

Mario D. Gonçalves, Patenaude-Trempe 1 Pierre Gendron, Patenaude-Trempe 2 Tony Colantonio, PWGSC 3. Abstract

ST. MONICA FOOD PANTRY HOUSTON, TEXAS

Building Energy Codes 101 October 23, Matthew Giudice Building Policy Associate Midwest Energy Efficiency Alliance

Water Damage & Repair

Table 1: Prescriptive Envelope Requirements: Residential WOOD FRAME WALL R-VALUE MASS WALL R-VALUE CEILING R-VALUE

Building Owners Guide to a Duro-Last System!

Commissioning of Fire Protection and Life Safety Systems. Presented by: Charles Kilfoil Bechtel National Waste Treatment Plant Richland WA

Water Damage During Construction

Residential Windows, 3 rd edition Corrected index 1

CITY OF WHITE BEAR LAKE BUILDING INSPECTION DEPARTMENT 4701 Highway 61 White Bear Lake, MN Fax: Re-Roofing: Asphalt Shingles

Shingle Roofing: What s below the surface is important

Comment Form on Proposed Gut Rehabilitation Alternatives

HIGH PERFORMANCE BUILDING ENVELOPES. Dave Seifert

Roof Insulation Building. Energy. Environment friendly e-library

Mortenson Construction Virtual Mockups A Collaborative Solution

Energy Code Compliance With SIPs. Frank Baker, PFB Corporation Don Ferrier, Ferrier Custom Homes

Structure Survey Findings:

BEST 2 WB 3 4 SIX WAYS FOR CONDENSATION IN BUILDINGS. Wagdy Anis, FAIA, LEED ap*

Exterior Elevated Elements Inspection Guidelines

IECC Compliance Guide for Homes in Virginia

September 3, Ric Boyd, Public Works Director Ketchikan Gateway Borough 344 Front St. Ketchikan, AK 99901

Residential Weatherization Plus Program

ROOFS, SNOW AND ICE DAMS

solutions & tips six Wise Energy Guide Building envelope solutions and simple tips AIR SEALING

NANSULATE NANOTECHNOLOGY BASED SOLUTIONS TO REDUCE HEAT LOSS THROUGH WINDOWS

2009 IECC Update. Scope. Content. International Energy Conservation Code

ELIGIBLE REPAIR PROJECT PARAMETERS

Risk Bulletin. Mold Prevention and Control for Mechanical and HVAC Contractors. XL Group Insurance

SECTION METAL WALL PANELS

Design Development Quality Management Phase Checklist Project Phase Checklist Series

10DBMC International Conference On Durability of Building Materials and Components LYON [France] April 2005

DUPONT TYVEK BUILDING WRAPS VS. ZIP SYSTEM WALL SHEATHING

Home Energy Evaluation Report for Fritz Kreiss and Catherine McQueen

Installer Training and Certification Overview

Contract for Weatherization Management Address City & State

Williamson and Associates, Inc. Report of Building Exterior Condition Evaluation, dated January 2 nd, (68 pages)

T H E A A M A C E R T I F I C A T I O N P R O G R A M

JOSEPH P. SOLINSKI. Membership affiliations and committee board standings are maintained with the following industry organizations:

Home Inspection Report

ENERGY STAR Qualified New Homes Thermal Enclosure Checklist. Water Management Checklist. Eli Caudill

Commercial Roof Management

Roof Repair Project Report. Fairbank Complex 40 Fairbank Road Sudbury, Massachusetts. February 14, RBA Project No

Introduction to Energy Codes & Green Building Programs

Field Water Testing - Lessons Learned

INNOVATIVE. ADAPTABLE. ENERGY EFFICIENT.

Non Invasive Roof Leak Detection Using Infrared Thermography

research highlight Highly Energy Efficient Building Envelope Retrofits for Houses

Architectural Testing

Structural Assessment Report

A. The Commissioning Authority (CxA) has been contracted or will be contracted directly with the Owner for this project.

CITY PLAN REVIEW AND INSPECTION. Lisa Fleming Brown, CPM

Volume II- Project Development Processes

Energy Design Resources Commissioning Plan Outline Template

research highlight Water Penetration Resistance of Windows - Study of Codes, Standards,Testing, and Certification

The Future in Fire Protection and Life Safety Cx. David J. LeBlanc, PE, FSFPE

) SIGNIFICANT CHANGES INCLUDING CODE COMMENTARY

CHAPTER VII. TITLE: STANDARDS FOR NEW ROOFING July 2015 CONSTRUCTION, RE-ROOFING CONSTRUCTION AND ROOFING SYSTEM GUARANTEE REQUIREMENTS

The Prefab Package. Modular EIFS construction offers benefits to today s busy jobsites. Building Envelope. Roland Serino, P.E., of Dryvit Systems Inc.

CONDENSATION IN REFRIDGERATED BUILDINGS

MOISTURE MANAGEMENT DURING THE CONSTRUCTION PROCESS

TARRANT COUNTY DETAIL STANDARDS

Denver International Airport Data Center Commissioning Plan

Transcription:

BUILDING ENVELOPE COMMISSIONING FOR THE EVERYDAY COMMISSIONING AGENT Building Envelope for the Everyday CxA Presented by: Mark F. Warren, CCP, LEED AP Senior Vice President - WSP Flack + Kurtz Anand Seth, PE, CEM, CPE Engineering Principal - Cannon Design

AIA Quality Assurance Learning Objectives 1. Understanding of Building Envelope Cx and how to integrate into the cx process 2. Understand the roles and responsibilities of BE Cx 3. Knowledge of the Common Pitfalls of BE Cx 4. Case Studies/Lessons Learned from actual projects

INTRODUCTION Items Covered in this presentation: Overview of the Commissioning Process Why Building Envelope Commissioning Integrating Building Envelope Cx into Project The Owner s Perspective The CxA s Perspective Common Pitfalls Testing Lessons Learned

THE COMMISSIONING PROCESS

THE COMMISSIONING PROCESS Organization and Preparation Commissioning Specs (Expanded for Building Envelope) Design Reviews (Expanded for Building Envelope) Scrub Specs Installation Inspections Review Submittals, RFI s, Change Orders, etc. Equipment Start-Up (Expanded for Building Envelope) Performance Verification Performance Testing (Expanded for Building Envelope) Building Simulation Correction of Deficiencies Re-Test of Systems

THE COMMISSIONING PROCESS Construction Manager / General Contractor o Process management o Direct the participation of sub-contractors o Site Inspection Sub-Contractors o Demonstrate correct system installation during functional testing o Mock up testing Manufacturers and Vendors o Provide documentation

BUILDING ENVELOPE COMMISSIONING WHAT IS CONSIDERED BUILDING ENVELOPE? Roof Walls Windows (Casement, Storefront) WHY? The interior and the building enclosure are interdependent. Envelope Commissioning is different than Forensic investigation. Which is conducted when a problem is identified usually after occupancy.

BUILDING ENVELOPE COMMISSIONING What are the Issues? Roofs o Uplift due to high winds, water leakage Walls o Damage due to improper water drainage and water proofing Doors o Water leakage o Ability to open per ADA guidelines Windows o Air and/or Water leakage

BUILDING ENVELOPE COMMISSIONING Exterior Enclosure Performance Objectives To Control: o Heat Flow o Air Flow o Noise o Fire o Light o Infrared o Ultraviolet To Eliminate: o Rain Penetration o Moisture Build-up Structural Performance o Durability o Security o Reliability o Aesthetics o Value o Constructability o Maintainability o Sustainability

BUILDING ENVELOPE COMMISSIONING ASHRAE CLIMATE ZONES 10

BUILDING ENVELOPE COMMISSIONING PREDESIGN Owners Project Requirements: (Review Only) - Owner's Vision & Directives - Project Budget & Schedule - Occupant Requirements - System Performance & Integration - Restrictions & Limitations - Training & Warranty Requirements - Quality of System, Materials & Construction - Operations & Maintenance -Benchmarking & Project Documentation -Building Envelope Testing requirements (ASTM E 1105-00) (ASTM E 907-96) 11

BUILDING ENVELOPE COMMISSIONING SD and DD Prepare B.O.D. Document: (Completed By Subconsultant) - Description of each system option considered: - Exterior Enclosure - Sub-systems - Materials and Components - Interaction of Building Exterior Enclosure with: - Heating - Cooling - Mechanical and Natural Ventilation - Lighting - Building Interior - Reasoning for Final Building Exterior System - Inter-relationships - Stiffness/deflection of support structure - Daylighting vs. Artificial Lighting - Impact on Mechanical Systems - Operational Assumptions Determine Systems Manual Structure: (By Subconsultant) - A systems manual is developed for each major building exterior enclosure system - Roof - Skylights - Atria - Exterior Walls - Windows - Doors - Sealants & Expansion Joints - Control Joints - Flashings - Shading Devices - Curtain Walls - Plaza Decks - Planters - Below-Grade - Balconies - Floors - Others - Calculations 12

BUILDING ENVELOPE COMMISSIONING CONSTRUCTION DOCUMENTS Cx Process Requirements for Const. Doc. Phase - Systems to be Documented and Tested - Schedule of Building Exterior Enclosure for: - Witnessing Testing Activities - Systems and Equip. Accessibility for maintenance and Cx - Completion of Construction Checklist - Activities relative to substantial completion/project closeout - Include in Building Exterior Enclosure Spec: - Specific Component performance documentation requirements - Use of construction checklists - Cx Process Activities 13

BUILDING ENVELOPE COMMISSIONING CONSTRUCTION QA/QC Plan & Site Specific Testing Plan: (By Subconsultant) - Verify QA/QC Requirements: - Field Testing - Manufacturing Performance Testing - Submittal & Shop Drawings - Laboratory testing for Custom Systems - Sample Construction - Formal Mock-up Testing Submittal - Inspection - Pre Construction/installation meeting - Participants Required for Testing - Cx Team will develop a range of test verification procedures both QA/QC - Components - System/Assembly - Intersystem - Owners Project Requirements - Random Sampling Pre-Construction Cx Process Meeting: - Special Issues relative to sequencing and early installation of equipment should be discussed - Pre-Construction Conference (Pre-Bid Conference) Observe & Witness Testing: (By Subconsultant) - AHSRAE Guideline 0-2005 listed items - The Cx Authority is to verify that tests were performed - The Cx is to re-verify test standards and performance criteria to be consistent and appropriate for the building enclosure being tested. - Verify test Pass/Fail 14

BUILDING ENVELOPE COMMISSIONING OCCUPANCY AND OPERATIONS Training For Building Envelope: (By Subconsultant) - Seasonal Weather Cycles: - Responsibilities of each O&M position - Certification of training comprehension - A method of updating operating personnel to changes - Repair/modifications/decommissioning - Post-Occupancy Performance Verification: - O&M document directory - Emergency Operating Procedures - Operating Manual meeting O.P.R. - Annotation of changes in operation - Maintenance Manual, Warranty info. & verified equipment performance data - Changes in Maintenance Procedures, Performance verification log forms & modification and repair docs. - Equipment test reports - Non-Conformance logs - As-built, guides and schedules - Training during Occupancy & Operations Phase: - Roles & Responsibilities - Means of determining level of comprehension - Methods of cross-training & tracking - Short Narrative of essential exterior enclosure design characteristics. 15

BUILDING ENVELOPE COMMISSIONING ROLES AND RESPONSIBILITIES: Commissioning Agent o Write testing plans o Direct and document testing Architect, Engineer Design Team o Incorporate requirements into specs o May attend testing Owner Project Managers o Witness functional testing o Final approval of Cx work products 16

BUILDING ENVELOPE COMMISSIONING Roles and Responsibilities of Team Owner CxA members Pre-Design Owner, or Owner's Representative Commissioning Authority Architect Structural Engineer Mechanical Engineer Electrical Design Engineer Lighting Design Professional Interior Systems Design Prof. Exterior Enclosure Consultant 5.2.2 Owner's Project Requirements A R I I I I I I I P I I I 5.2.4 Commissioning Plan A P I I I I I I I I 5.2.4.4 Issues Log & Report R P U U U U U I U U U U U U I I 5.3.1 Design 6.1.1 Acceptance & Commissioning Process Record Owner's Project Requirements (OPR) Update - All Phases Design Team Bldg Env Sub Contractors Specialists Bldg Ops Exterior Enclosure Manufacturer Construction Manager General Contractor R P U U U U U U U U U U U U U Exterior Enclosure Contractors A R I I I I I P I I I I I I I I I I I I 6.2.2 Basis of Design - All Phases A R I I I I I P I I I I I I I I I I I 6.2.3 Commissioning Plane - Update R P U U U U I I 6.2.4 Construction Specifications for Commissioning R R U P I R I I 6.2.4 Construction Checklists R A R R I R I I 6.2.5 Systems Manual Outline A P I I I I I I R U U 6.2.6 Cx Specification A R P R I I I I 6.2.7 Commissioning - Focused Design Reviews A R U U U U U P U I I I I I Issues Log & Report A P U U U U U I U I I I I Acceptance & Commissioning 6.3, 6.4 Process Report Construction Pre-Bid Conference Commissioning 7.2.2 Briefing A P U U U U U I I I I I I I R P I I U I I I 7.2.4 Owner's Project Requirements A U P U U U I I I 7.2.5 7.2.6 Commissioning Plan & Inspection Checklists Update Pre-Construction Commissioning Process Briefing R R I P U U U U U I I I A P I I U U U U U I I I 7.2.7 Submittal Review Comments R R U P U U U U U I I I 7.2.8 Commissioning Milestone Schedule A P I I U U U U U I I I 7.2.9 Test Procedures A R I P I U U U I I I I I I I Test Contractor Electrical Contractor Indoor Air Quality Specialist Accoustic Specialist Vibrtation Specialist Moisture/Mildew Specialist Measurement/Verification Specialist Information Technology Specialist Physical Security Specialist Blast (and Chem-bio) Security Facilities Management Facilities Engineer (O&M) Occupants Key Notes P - Provide A - Approve R - Review I - Input From U - Use Test Procedures - Components A R I P I U U U I I I I I I I Test Procedures - Systems A R I P I U U U I I I I I I I 17

OWNER S PERSPECTIVE A professional team including architect/engineer/qualified contractors have been engaged Any VE conducted does not impact quality Contractors, Project and Construction Managers are conducting all needed tests to ensure Quality Building envelope should have NO problems QA/QC process via Controller The reality may well be different.

QUESTION & ANSWER: PART I

COMMISSIONING PROVIDER S PERSPECTIVE Must Detail Building Envelope Requirements in Specification Integrating Building Envelope into Cx Specifications Clearly Define the Roles of all Participants Define the required Building Envelope Testing Destructive Testing? Factory Testing? Must make clear to Owner that CxA is acting in their best interest.

COMMISSIONING PROVIDER S PERSPECTIVE Clarify role of Third Party Independent Testing firm Coordinate with Architect on Design Review requirements Building Enclosure Consultant role vs Building Envelope Cx firm Roles if project is delivered as Design/Build or Design Assist

COMMON PITFALLS If the Envelope testing is bypassed Envelope may have issues Water leaks Snow/ice formation on windows Excessive infiltration Visual damage Condensation observed on interior window frames Ice formation observed on exterior near panel seams and weep holes

COMMON PITFALLS Building envelope moisture entry [Aldous 2008] Damage to brick façade of pool building due to lack of proper sealing and air management Photosensor sees the electric lamps rather than task-plane illumination Failed window film applications Photosensor (for daylight harvesting) shaded by duct Air leakage in an underfloor airdistribution system

COMMON PITFALLS Foam thickness not per specification on Mock Up causing a rejected system. High moisture content of wood did not allow adhesive to bond correctly barrier developed air pockets Damage to waterproofing membrane at footing AVB Membrane seams are opening up at the soffit

COMMON PITFALLS Who is developing the Enclosure Testing? Who will approve the submittals? Who will determine what is acceptable testing? Key peer review vs Cx review? Leader of Mock up testing? Review of day to day BE craftsmanship?

Field Testing TESTING Infra red testing of roof and windows o This is a workhorse of envelope Commissioning o Can be used for roof and windows o No destructive work is required for testing o Better done in winter or colder months Window water leakage testing using field rigs Document problems Note issues to be resolved

TESTING

INFRARED TESTING Roof Thermal Bridging

ENVELOPE TESTING Thermogram: Infrared Image Control Photo: Visible Light Image The building may be experiencing stack effect. The warm thermal patterns in the thermogram may be caused by small amounts of warm air exfiltration.

ENVELOPE TESTING Thermogram: Infrared Image Control Photo: Visible Light Image Note heat losses around the window frames. These metal frames often conduct a substantial amount of heat because metal is an excellent conductor of heat and cold, and the frames typically do not have as much R-value as high efficiency glazing, or insulated wall sections.

IN SUMMARY: ENVELOPE TESTING Envelope testing a key commissioning element Required to verify: o Construction quality o Design intent is met Teamwork is critical o All parties must play their role o Follow contractual lines o Must be adequately specified Hidden issues are understood earlier 31

ENVELOPE TESTING REFERENCES AND DOCUMENTATION ROOFS: Factory Mutual (FM) Loss prevention Data Sheet 1-52 (FM 1-52) Provides two methods of uplift testing o Negative Pressure Test o Bonded uplift test ASTM E 907 (Standard test Method for Field Testing Uplift Resistance of Adhered Membrane Roofing Systems) Concerns in industry regarding accuracy and applicability of these tests 32

ENVELOPE TESTING REFERENCES AND DOCUMENTATION: American Architectural Manufacturers Association 101/I.S.2/A440-08 (North American Fenestration Standard/Specification for widows, doors and skylights) AAMA 502-08 (Voluntary Specification for Field Testing of Newly installed Fenestration Products) AAMA 503-08 502-08 (Voluntary Specification for Field Testing of Newly installed Storefronts, Curtain Walls and Sloped Glazing Systems) AAMA 511-08 (Forensic Investigations) ASTM E 2128 (Standard Guide for Evaluating Water Leakage of Building Walls) ASTM E 783 (Standard Test Method for Field Measurement of Air Leakage through installed Exterior windows and Doors) ASTM E 1105 (Standard Test Method for Field Determination of Water Penetration of installed Exterior Windows, Skylights, Doors and Curtain Walls and Doors by Uniform or Static Air Pressure Difference Measurement of Air Leakage through installed Exterior windows and Doors by Uniform or Cyclic Static Air Pressure Difference) 33

CASE STUDY: Albert Sherman Center 485,000SF New R+D Facility Seeking LEED Silver 300,000 SF of space for a wet research laboratory, clean rooms, core research space, administrative space and vivarium

CASE STUDY: Smithsonian Institution National Museum for African American History and Culture 15-acre site Last museum to be placed on the National Mall $500 Million Project Seeking LEED Gold

CASE STUDY: MSBA Massachusetts School Building Authority (MSBA) is the principal state agencies which supports public school projects in Massachusetts. REPRESENTATIVE PROJECTS: Avery Elementary School Freeman Elementary Maynard Middle School Wayland High School Hudson Middle School Willard Elementary School

CASE STUDY: MSBA DESCRIPTION Among other initiatives it has adopted envelope commissioning as an important step towards Quality assurance in their Green Repair program. Approximately 85 projects have been undertaken with Commissioning contracts totaling over $8 million. MSBA requested qualifications from qualified firms to generate a pool of Envelope Commissioning firms. These firms are given school window and roof replacements projects for Commissioning.

OBSERVATIONS CASE STUDY: MSBA This provides a systematic process of quality assurance to public schools envelopes. Before the program was initiated local school districts were less inclined to perform envelope commissioning. CxA was engaged in different stages of the project. In some cases only final field inspection was possible. In other full design review was possible. Envelope Cxing is still not well understood and roles and responsibilities not yet firmed. Several contractors are still not full team players.

LESSONS LEARNED Items to Improve Improved Coordination with Architect Regularly Scheduled Cx Progress Meetings with Owner Define testing early on in Schematic Design Utilize the OPR to better define BE testing requirements and Roles Design Review meetings to be mandatory Additional controls integration meetings needed Best Items to Repeat Availability to the Owner Flexibility of Cx Provider Scheduling and Testing Early Identification (Schematic Design) of Issues and Continued Tracking of Open Item Constant Communication with team using tools such as the Cx Matrix to track schedule Determine M+V roles during the design phase (Envelope) LEED NC requirements for Building Envelope

QUESTION & ANSWER: PART II

AIA Quality Assurance Portland Energy Conservation, Inc is a registered provider with The American Institute of Architects Continuing Education Systems. Credit earned on completion of this program will be reported to CES Records for AIA members. Certificates of Completion for non-aia members are available on request. This program is registered with the AIA/CES for continuing professional education. As such, it does not include content that may be deemed or construed to be an approval or endorsement by the AIA of any material of construction or any method or manner of handling, using, distributing, or dealing in any material or product. Questions related to specific materials, methods, and services will be addressed at the conclusion of this presentation.

Thank You!