7. Verification of Durability



Similar documents
1.5 Concrete (Part I)

L4. Pipes Materials and Loads

EVALUATION OF THE PERFORMANCE OF THE PROTECTIVE SURFACE COATINGS FOR CONCRETE

SPECIAL COMPOUND FOR RHEOPLASTIC AND ANTI-CORROSION SUPERCONCRETE WITH VERY HIGH DURABILITY

11 CHAPTER 11: FOOTINGS

Chapter 2 Basis of design and materials

1.054/1.541 Mechanics and Design of Concrete Structures (3-0-9) Outline 1 Introduction / Design Criteria for Reinforced Concrete Structures

INTRODUCTION TO BEAMS

Fire-Damage or Freeze-Thaw of Strengthening Concrete Using Ultra High Performance Concrete

STUDY ON THE CHLORIDE DIFFUSION COEFFICIENT CALCULATED FROM A SIMPLE ACCELERATED CHLORIDE PENETRATION TEST USING ELECTRICITY

TABLE OF CONTENTS CHAPTER NO. TITLE PAGE NO. ABSTRACT

DESIGN OF SLABS. Department of Structures and Materials Engineering Faculty of Civil and Environmental Engineering University Tun Hussein Onn Malaysia

Hardened Concrete. Lecture No. 14

How To Determine The Effect Of Frost Deterioration On Chloride Penetration And Carbonation

DESIGN OF SLABS. 3) Based on support or boundary condition: Simply supported, Cantilever slab,

Field Damage Inspection and Static Load Test Analysis of Jiamusi Highway Prestressed Concrete Bridge in China

The Concrete Life Cycle: Maintain to Sustain. Fred Goodwin BASF Construction Chemicals (EB-N) Beachwood OH

Properties of Concrete with Blast-Furnace Slag Cement Made from Clinker with Adjusted Mineral Composition

Deflection Calculation of RC Beams: Finite Element Software Versus Design Code Methods

Service Life of Chloride-Contaminated Concrete Structures

Design of reinforced concrete columns. Type of columns. Failure of reinforced concrete columns. Short column. Long column

Performance-based Service Life Design of Reinforced Concrete Structures Exposed to Chloride Environments

CAUSES, EVALUATION AND REPAIR OF CRACKS IN CONCRETE

TIME DEPENDENT CHLORIDE DIFFUSION COEFFICIENT FIELD STUDIES OF CONCRETE EXPOSED TO MARINE ENVIRONMENT IN NORWAY

Page 1 of Sven Alexander Last revised SB-Produksjon STATICAL CALCULATIONS FOR BCC 250

Chapter 5 Bridge Deck Slabs. Bridge Engineering 1

MASSACHUSETTS INSTITUTE OF TECHNOLOGY 6.436J/15.085J Fall 2008 Lecture 14 10/27/2008 MOMENT GENERATING FUNCTIONS

Chapter - 3 Design of Rectangular Beams and One-way Slabs

The following sketches show the plans of the two cases of one-way slabs. The spanning direction in each case is shown by the double headed arrow.

SLAB DESIGN. Introduction ACI318 Code provides two design procedures for slab systems:

Numerical modelling of shear connection between concrete slab and sheeting deck

The AASHO Road Test site (which eventually became part of I-80) at Ottawa, Illinois, was typical of northern climates (see Table 1).

Local Authority Building Control Technical Information Note 3 Driven and In-situ Piled Foundations

Seismic Isolation Retrofitting of Japanese Wooden Buildings

Example Specification for Concrete using Current Building Code Requirements

PROPERTIES AND MIX DESIGNATIONS

Fire and Concrete Structures

16. Beam-and-Slab Design

MATERIALS AND MECHANICS OF BENDING

Chloride threshold values

TO DETERMINE THE SHELF LIFE OF IBUPROFEN SOLUTION

Pavement Thickness. esign and RCC-Pave Software. Roller-Compacted Concrete Pavement: Design and Construction. October 24, 2006 Atlanta, Georgia

In-situ Load Testing to Evaluate New Repair Techniques

Service Life Estimation and Comparison with Present Conditions of Existing Reinforced Concrete Structures

Introduction. Eurocodes. Specification. Cost

A transverse strip of the deck is assumed to support the truck axle loads. Shear and fatigue of the reinforcement need not be investigated.

An Alternative Approach of Operating a Passive RFID Device Embedded on Metallic Implants

FAST JOINING AND REPAIRING OF SANDWICH MATERIALS WITH DETACHABLE MECHANICAL CONNECTION TECHNOLOGY

Tension Development and Lap Splice Lengths of Reinforcing Bars under ACI

Design and Construction of Cantilevered Reinforced Concrete Structures

MULTI-TIGHT 2K. The New Generation for Waterproofing Buildings

Strength of Concrete

State of Louisiana Office of Information Technology. Change Management Plan

Detecting Possibly Fraudulent or Error-Prone Survey Data Using Benford s Law

Weirs for Flow Measurement

Fame Design Ltd (10295) Plot # A-115/116,BSCIC Hosiery I/A, Narayangonj, Bangladesh ( , ) 18.June.2014

Solution for Homework #1

Concrete for industrial floors

Rapid Chloride Permeability Testing

Aluminium systems profile selection

Saint Gobain Gyproc India Ltd. (Formerly India Gypsum Ltd.)

REHABILITATION OF THE FIGUEIRA DA FOZ BRIDGE

Embedded Parts Introduction - Anchors

Foundation Experts, LLC Specializes in Foundation Repair and Waterproofing

Hydraulics Laboratory Experiment Report

Numerical analysis of size reduction of municipal solid waste particles on the traveling grate of a waste-to-energy combustion chamber

The elements used in commercial codes can be classified in two basic categories:

A Decade of Performance of FRP-Repaired Concrete Structures

MECHANICS OF SOLIDS - BEAMS TUTORIAL 1 STRESSES IN BEAMS DUE TO BENDING. On completion of this tutorial you should be able to do the following.

How to Identify, Evaluate & Repair Shrinkage Cracks in Poured Concrete

DYNAMIC ANALYSIS OF THICK PLATES SUBJECTED TO EARTQUAKE

Building Diagnostic Tests as Assessment Tools 診 斷 樓 宇 狀 況 的 測 試 : 樓 宇 檢 驗 的 評 估 工 具

APE T CFRP Aslan 500

CE 366 SETTLEMENT (Problems & Solutions)

Program COLANY Stone Columns Settlement Analysis. User Manual

Seismic Risk Prioritization of RC Public Buildings

INFLUENCE OF GPS TECHNOLOGY ON COST CONTROL AND MAINTENANCE OF VEHICLES

MILMAN & ASSOCIATES STRUCTURAL CONSULTING ENGINEERS/ PROJECT MANAGERS

Properties of Concrete for use in Eurocode 2

DESIGN OF VACUUM SECTION OF A LEAF COLLECTOR MACHINE

Structural Retrofitting Process and Techniques

DIFFRACTION AND INTERFERENCE

European Technical Assessment ETA-10/0153 of 10/06/2015

The Impact of Market Demands on Residential Post-Tensioned Foundation Design: An Ethical Dilemma

Hydrophobe VII., Lisbon

DURABILITY OF MORTAR LININGS IN DUCTILE IRON PIPES Durability of mortar linings

Detailing of Reinforcment in Concrete Structures

Frost Damage of Roof Tiles in Relatively Warm Areas in Japan

STRUSOFT EXAMPLES PRE-STRESS 6.4

CHLORIDE INGRESS IN OLD DANISH BRIDGES. Søren Lundsted Poulsen, Henrik Erndahl Sørensen Danish Technological Institute, Taastrup, Denmark

Formwork for Concrete

BLS 100 Orifice Plate DIN 19206

Chapter 8. Flexural Analysis of T-Beams

RELIABLE, SIMPLE AND CHEAP PERFORMANCE FIELD TESTS FOR PREDICTING LONG TERM DURABILITY OF CONCRETE STRUCTURES

Concrete Design to Eurocode 2

Transcription:

59 7. Verification of Durability The performance verification performe thus far has shown that the structural performance is higher than the performance requirements. That performance must not be lost because of eterioration of materials uring the esign service life of the structure (performance item 10 efine in Section 2.2). Verification is performe, therefore, to ascertain that the concrete an reinforcing bars use for the floor slabs an the beams meet the urability requirements. 7.1 Carbonation-Inuce Corrosion Verification concerning the corrosion of reinforcing bars ue to carbonation of the concrete is mae for the lower (bottom) reinforcing bars in the floor slab an in the beam in accorance with Section 2.2 of SSCS/Mate. 7.1.1 Calculation of esign value of carbonation epth The esign value of carbonation epth y is calculate using the following equation: y = γ α t (7.1.1) cb α = α k β e γ c where γ cb (=1.15) is a safety factor to account for the variation in the esign value of carbonation epth y, α is the esign carbonation rate (mm year -1/2 ), t is the esign service life, α k is the characteristic value of carbonation rate (mm year -1/2 ), β e (= 1.0) is a coefficient representing the extent of environmental action, an γ c (= 1.0) is the material factor for concrete. For the characteristic value of the carbonation rate coefficient α k, the following equation propose in Section 6.4.3 of SSCS/Mate is use: α k = γ p α p α p = 3.57 + 9.0 W/C (7.1.2) where γ p (= 1.1) is a safety factor to account for the accuracy in etermining α p an W/C is the water-to-cement ratio of concrete. Assuming that the water-to-cement ratio W/C of the concrete is 0.45, α k = 1.1 ( 3.57+9.0 0.45) = 0.53 mm year -1/2 is obtaine. Therefore, the esign value of carbonation rate coefficient α is calculate as follows: α = 0.53 1.0 1.0 = 0.53 mm year -1/2. Since the esign service life is 50 years, the esign value of carbonation epth y is calculate from Equation 7.1.1. y = γ α t = 1.15 0.53 50 = 4.3 mm cb 7.1.2 Calculation of the critical epth for reinforcement corrosion The critical epth for reinforcement corrosion y lim is calculate from the following equation: y lim = c c k (7.1.3) where c is the concrete cover an c k is the remaining non-carbonate cover thickness.

60 Design value Limit value Verification Table 7.1.1 Result of verification for carbonation in the slab W/C 0.45 α p (mm year -1/2 ) 0.48 γ p 1.1 α k (mm year -1/2 ) 0.53 γ c 1.0 β e 1.0 α (mm year -1/2 ) 0.53 t (year) 50 γ cb 1.15 y (mm) 4.3 c (mm) 70.0 c k (mm) 25.0 y lim (mm) 45.0 γ i 1.0 γ i y / y lim 0.10 Jugment OK in the beam Since the esign concrete cover over the bottom reinforcement in the floor slabs an beams is 70 mm an the remaining non-carbonate cover thickness c k is 25 mm (because of a salty environment), the critical epth for reinforcement corrosion y lim is obtaine as y lim = 70 25 = 45 mm. In this calculation, as mentione in Section 3.7.1 construction error in concrete cover is not taken into account. 7.1.3 Verification results Table 7.1.1 summarizes the conitions for verification an the verification results. From these results, it can be conclue that the reinforcement in the floor slab an in the beam will not corroe ue to the carbonation of concrete. 7.2 Chlorie-Inuce Corrosion Verification concerning the corrosion of reinforcement ue to ingress of chlorie ions is mae with respect to the bottom reinforcement in the floor slabs an in the beams in accorance with Section 2.3 of SSC/Mate. This section eals only with the verification process for the bottom reinforcement in the floor slabs. Verification for the bottom reinforcement in the beams can be performe in a similar manner. 7.2.1 Calculation of chlorie ion concentration at reinforcement The esign value of chlorie ion concentration C at a reinforcement location is calculate using Equation 7.2.1. It is assume here that the chlorie ion concentration of concrete uring mixing is zero. C 0.1c = γ clco 1 erf (7.2.1) 2 Dt where γ cl (= 1.3) is a safety factor to account for the scatter in C, C o is the chlorie ion concentration at the concrete surface, c is the concrete cover, D is the esign value of iffusion coefficient of chlorie ions in

61 concrete, t is the esign service life, an erf is an error function. Because the amount of measurement ata obtaine in the environment in which this open-type wharf is locate is not sufficient, the chlorie ion concentration at the surface C o is efine accoring to Table 2.3.1 of SSC/Mate. For the bottom reinforcement in the floor slabs, 9.0 kg/m 3 is use in view of the fact that the height from the mean monthly-highest water level (H.W.L) is about 2 m, an for the bottom reinforcement in the beams, 13.0 kg/m 3 is use because the beams is locate in the splash zone. The esign iffusion coefficient for chlorie ions in concrete D is calculate from the following equation: D 2 w w =γ cdk + Do l w (7.2.2) a w/l = 3 (σ se / E s + ε cs ) where γ c (= 1.0) is the material factor for concrete, D k is the characteristic value of iffusion coefficient of chlorie ions in concrete, D o (= 200 cm 2 /year) is a constant to represent the effect of cracks on transport of chlorie ions in concrete, w is the crack with, w a is the crack with limit specifie in Table 3.6.1, l is the crack spacing, σ se is the increment in stress of reinforcement from the state in which concrete stress at the portion of reinforcement is zero, E s is Young's moulus of reinforcement, an ε cs is compressive strain for evaluation of increment of crack with ue to shrinkage an creep of concrete. The characteristic value of the iffusion coefficient of chlorie ions in concrete D k is calculate by using the estimation formula for orinary Portlan cement-base concrete shown in Section 6.4.4 of SSC/Mate. D k = γ p D p log D p = 3.9 (W/C) 2 + 7.2 (W/C) 2.5 (7.2.3) where γ p (= 1.2) is the safety factor for the accuracy of D p. Since the water-to-cement ratio W/C of the concrete is 0.45, D k = 1.2 0.89 = 1.07 cm 2 /year is obtaine. The values neee for the calculation of the crack with w an the ratio of crack with to crack spacing w/l are those calculate in Table 4.7.1 for the bottom reinforcement parallel to the face line of the wharf at the mispan of the floor slabs, an those calculate in Table 5.7.2 for the bottom reinforcement in the beams. From these values, the esign iffusion coefficient of chlorie ions D can be obtaine as D = 1.0 1.07 + 0.00158 (0.245 / 0.245) 2 200 = 1.39 cm 2 /year. Therefore, since the esign concrete cover for the bottom reinforcement in the floor slabs is 70 mm an its esign service life is 50 years, the esign value of chlorie ion concentration C at the reinforcement location can be calculate as follows: C 0.1 0.1 70 1 c 1.3 9.0 = 1 cl Co erf = = 6.5 kg/m 2 erf 2 1.39 50 Dt γ 3 7.2.2 Threshol chlorie ion concentration for reinforcement corrosion For the threshol chlorie ion concentration C lim at the onset of reinforcement corrosion, a typical value of 1.2 kg/m 3, which is given in Section 7.4.5 of SSC/Struc, is use. Accoring to the results of stuies on the relationship between the chlorie ion concentration in the superstructure of open-type wharves an reinforcement

62 corrosion an chlorie-inuce eterioration, it may be possible to use a value greater than 1.2 kg/m 3 as the threshol value, although the value of 1.2 kg/m 3 is use as a stanar one for this verification. 7.2.3 Verification results Table 7.2.1 summarizes the conitions for verification an verification results for the bottom reinforcement in the floor slabs an the bottom reinforcement in the beams. The verification results inicate a high possibility of having corrosion an performance loss of the reinforcement in these members cause by chlorie ions uring the esign service life. It is, therefore, essential to consier a measure to ensure the require level of urability uring the esign service life. This is escribe in Chapter 9. Design value Table 7.2.1 Result of verification for chlorie-inuce corrosion in the floor slab in the beam Type of cement OPC OPC W/C 0.45 0.45 D p (cm 2 /year) 0.89 0.89 γ p 1.2 1.2 D k (cm 2 /year) 1.07 1.07 γ c 1.0 1.0 D o (cm 2 /year) 200 200 w/l 0.00158 0.00197 w a (mm) 0.245 0.245 w (mm) 0.245 0.245 D (cm 2 /year) 1.39 1.46 c (mm) 70 70 C o (kg/m 3 ) 9.0 13.0 t (year) 50 50 γ cl 1.3 1.3 C (kg/m 3 ) 6.5 9.5 Limit value C lim (kg/m 3 ) 1.2 1.2 Verification γ i 1.0 1.0 γ i C / C lim 5.42 7.92 Jugment NG NG 7.3 Freezing an Thawing Verification concerning freezing an thawing may be omitte because the site of the open-type wharf is free from freezing an thawing (Section 2.4 of SSC/Mate). 7.4 Chemical Attack Verification concerning chemical attack may be omitte because the superstructure of the open-type wharf is free from chemical attack [Section 2.6 of SSC/Mate]. 7.5 Alkali-Aggregate Reaction Verification concerning alkali-aggregate reaction may be omitte by ensuring eterioration resistance to alkali-aggregate reaction through testing of concrete materials an so on [Section 2.6 of SSC/Mate].

63 7.6 Water Tightness Verification of water tightness may be omitte because water tightness is not require for the superstructure of the open-type wharf [Section 2.7 of SSC/Mate].