Brookhaven Magnet Division - Nuclear Physics Program Support Activities



Similar documents
Development of Radiation Resistant Quadrupoles Based on High Temperature Superconductors for the Fragment Separator

DOE LHC Quarterly Review. Magnet Production Cable Testing Cost to Complete issues. Mike Harrison, BNL July 26, 2004

LHC MACHINE PROTECTION

MECHANICAL AND THERMAL ANALYSES OF THE CABLE/ STRAND STRAIN TEST FIXTURE

CABLE DESIGN AND RELATED ISSUES IN A FAST-CYCLING SUPERCONDUCTING MAGNETS

Lecture VI Magnetic Design

MEMS mirror for low cost laser scanners. Ulrich Hofmann

The half cell of the storage ring SESAME looks like: Magnetic length =

THE ALIGNMENT STRATEGY FOR THE SPIRAL2 SUPERCONDUCTING LINAC CRYOMODULES

Vehicle Design Summit Electric Hub Motor (V2) Eric Conner Harvey Tang Matthew Peddie

Review Questions PHYS 2426 Exam 2

BARE PCB INSPECTION BY MEAN OF ECT TECHNIQUE WITH SPIN-VALVE GMR SENSOR

The Cost of Superconducting Magnets as a Function of Stored Energy and Design Magnetic Induction times the Field Volume

1. The diagram below represents magnetic lines of force within a region of space.

Magnetism. d. gives the direction of the force on a charge moving in a magnetic field. b. results in negative charges moving. clockwise.

PHYS 222 Spring 2012 Final Exam. Closed books, notes, etc. No electronic device except a calculator.

Chapter 27 Magnetic Field and Magnetic Forces

Introduction. Magnet Coordinate System

Mark Jaski. Multi-Bend-Achromat (MBA) Magnets

Types of 3D Scanners and 3D Scanning Technologies.

HIGH-ENERGY COLLIDER PARAMETERS: e + e Colliders (I)

Quantum Computing for Beginners: Building Qubits

Lecture 7 Thermal Insulation & Cryostat Basics. J. G. Weisend II

CHAPTER 4 DESIGN OF INTEGRAL SLOT AND FRACTIONAL SLOT BRUSHLESS DC MOTOR

B.TECH. (AEROSPACE ENGINEERING) PROGRAMME (BTAE) Term-End Examination December, 2011 BAS-010 : MACHINE DESIGN

Machine Tool Inspection & Analyzer solutions

Sensor/Raft Metrology Status

Vibration Suppression R&D at University of British Columbia. Tom Mattison UBC

A METHOD OF CALIBRATING HELMHOLTZ COILS FOR THE MEASUREMENT OF PERMANENT MAGNETS

Subminiature Load Cell Model 8417

Physics 41, Winter 1998 Lab 1 - The Current Balance. Theory

PCB Component Placement Inspection

The D-Wave 2X Quantum Computer Technology Overview

Measurement of Charge-to-Mass (e/m) Ratio for the Electron

ILV. Laser Welding: Line Scanners for Beam Shaping and Guiding. Alfred G. Arlt. Sulzbacher Str Schwalbach/Taunus DIPL.-ING. ALFRED G.

Synthetic Sensing: Proximity / Distance Sensors

Expression of Interest in providing design and manufacturing of detectors for the construction of the European X-ray Free Electron Laser Facility

Precision Miniature Load Cell. Models 8431, 8432 with Overload Protection

Cryogenic Performance of Millitech Model FBI-22 Waveguide Isolator.

Cathode Ray Tube. Introduction. Functional principle

DIRECT CURRENT GENERATORS

Large Systems Commissioning

Technical Specification for the Cryogenic Testing of HTS Current Leads

Efficiency, Dispersion and Straylight Performance Tests of Immersed Gratings for High Resolution Spectroscopy in the Near Infra-red

Objectives. Capacitors 262 CHAPTER 5 ENERGY

Eðlisfræði 2, vor 2007

HOBBING MACHINE TYPE ZFWZ 8000x40

Zero Degree Extraction using an Electrostatic Separator

EXPERIMENTAL ANALYSIS OF HEAT TRANSFER ENHANCEMENT IN A CIRCULAR TUBE WITH DIFFERENT TWIST RATIO OF TWISTED TAPE INSERTS

Introduction to Nuclear Magnetic Resonance Spectroscopy

Event display for the International Linear Collider Summer student report

Activities at the University of Frankfurt (IAP)

Physics 121 Sample Common Exam 3 NOTE: ANSWERS ARE ON PAGE 6. Instructions: 1. In the formula F = qvxb:

Lasers Design and Laser Systems

Electron Charge to Mass Ratio Matthew Norton, Chris Bush, Brian Atinaja, Becker Steven. Norton 0

Mercury TM 1500P PCB-Mount Digital Encoders

ENGINEERING METROLOGY

Proceedings of the Sixth Workshop on RF Superconductivity, CEBAF, Newport News, Virginia, USA

Automatic Voltage Regulator User s Manual

The commissioning of the LHC: first the technical systems, then the commissioning with beam

Magnetic Field and Magnetic Forces

Chapter 33. The Magnetic Field

EFFECT OF OBSTRUCTION NEAR FAN INLET ON FAN HEAT SINK PERFORMANCE

Wir schaffen Wissen heute für morgen

Manufacturing and Testing of Accelerator Superconducting Magnets

LHC optics measurement & correction procedures. M. Aiba, R. Calaga, A. Morita, R. Tomás & G. Vanbavinckhove

Status of High Current Ion Sources. Daniela Leitner Lawrence Berkeley National Laboratory

View of ΣIGMA TM (Ref. 1)

BARREL ALIGNMENT- A CRITICAL FACTOR IN REDUCING EXTRUDER WEAR

L.I. Chubraeva. Corr. Member of RAS

R&D Support Services. Ad Astra Rocket Company

Understanding Tracker Accuracy and its Effects on CPV

Owner s Manual

BEPC UPGRADES AND TAU-CHARM FACTORY DESIGN

NOVEL FOCUSING OPTICS FOR IR LASERS Paper 1504

1. Units of a magnetic field might be: A. C m/s B. C s/m C. C/kg D. kg/c s E. N/C m ans: D

Tube Control Measurement, Sorting Modular System for Glass Tube

* This work is an official contribution of the National Institute of Standards and Technology and

E/M Experiment: Electrons in a Magnetic Field.

Information about the T9 beam line and experimental facilities

Chapter 21. Magnetic Forces and Magnetic Fields

Beam Laser Pointer Service Manual

Minimum requirements for the 13 ka splices for 7 TeV operation

Spherical Aberration Corrections for an Electrostatic Gridded Lens

Physics 221 Experiment 5: Magnetic Fields

Thermal Modeling Issues Concerning the Mechanically Pumped Two-Phase CO 2 Cooling for the AMS-2 2 Tracker

Optical laser beam scanner lens relay system

Lab 4: Magnetic Force on Electrons

Magnetic Field of a Circular Coil Lab 12

Miniaturizing Flexible Circuits for use in Medical Electronics. Nate Kreutter 3M

EXPERIMENT O-6. Michelson Interferometer. Abstract. References. Pre-Lab

Torque motors. direct drive technology

Power Plant Electrical Distribution Systems

Transcription:

Brookhaven - Nuclear Physics Program Support Activities Spin Program support E-Cooling R&D RIA RHIC Operations Support Funding

AGS Warm Siberian Snake AGS Warm Snake Magnetic element designed and built in Japan by RIKEN Shipped to BNL for high power testing: field shape, temperature rise

AGS Warm Siberian Snake Measurements included operating temperature rise v s water flow, field quality, field integral

AGS Cold Siberian Snake AGS Cold Snake Replace the existing 5% partial snake with a more powerful 30 % one. Polarisation 45% -> 70% Issues Complex geometry (variable pitch helix) Large aperture, high field (20cm, 3T) No cryogenic infrastructure Cooldown -helium back-up from remote dewar Cooling from cryo-coolers for DC operation, 2W heat load max AGS beam loss induced quenching energy removal

AGS Snake - Coil Geometry

AGS Snake Status Inner and outer coils

8.813 Cold Snake Central Region: Warm Measurements 80 8.812 AGS Cold Snake 60 AGS Cold Snake Transfer Function (T/kA) 8.811 8.810 8.809 8.808 8.807 8.806 Std. Dev. = 0.01% Field Angle (deg.) 40 20 0-20 -40 8.805 3 Tesla at 350 A -60 Twist = 2.15 deg./cm 8.804-80 -0.3-0.2-0.1 0 0.1 0.2 Axial Position (m) 0.3-0.3-0.2-0.1 0 0.1 Axial Position (m) 0.2 0.3

Cold Snake Central Region: Warm Measurements Normal Quadrupole (unit at 31 mm) 1.2 1.0 0.8 0.6 0.4 0.2 0.0-0.2-0.4-0.6-0.8-1.0-1.2-1.4-0.3-0.2-0.1 AGS Cold Snake 0 0.1 0.2 0.3 Axial Position (m) Skew Quadrupole (unit at 31 mm) 0.6 0.4 0.2 0.0-0.2-0.4-0.6-0.8-1.0-1.2-1.4-1.6-1.8-2.0-0.3-0.2-0.1 AGS Cold Snake 0 0.1 0.2 0.3 Axial Position (m)

Cold Snake Central Region: Warm Measurements 2.0 3.4 Normal Sextupole (unit at 31 mm) 1.5 1.0 0.5 0.0-0.5-1.0-1.5-2.0 AGS Cold Snake Skew Sextupole (unit at 31 mm) 3.2 3.0 2.8 2.6 2.4 2.2 2.0 1.8 1.6 AGS Cold Snake -2.5-0.3-0.2-0.1 0 0.1 0.2 Axial Position (m) 0.3 1.4-0.3-0.2-0.1 0 0.1 Axial Position (m) 0.2 0.3

AGS Snake Status Bore tube wound corrections elements: H&V dipoles + solenoid

AGS Snake Status Preparing the cold mass for vertical cold testing, estimate July 12th to start the first cold tests

AGS Snake Status Scheduled for end of construction - ready for final cold testing - on 9/28/04. This schedule has no contingency which given the complexity of the device is probably somewhat optimistic. A complete series of tests are planned since this is a stand alone device. We intend to deliver the magnet to CAD in early December

RHIC II e-cooling R&D: Solenoid development Solenoid Requirements 2 Tesla axial field (possibility of a 5T requirement ) Up to 30-meter total length (in two or more sections) 100 mm coil ID (gives approx. 89 mm cold bore diameter; warm bore needed?) B t /B axial < 10-5 on-axis straightness How about off-axis? At least ~5 mm radius zone is needed just to make measurements.

E-Cooling Conceptual design Working on the end configuration which would include short (phase advance) quadrupoles

Dipole Correction Coils B /B z ~ 10 5 implies a straightness of 10 µm over 1 meter length. This may not be achieved with mechanical alignment alone. Winding imperfections are also likely to produce transverse fields on-axis. Goal is to achieve as close to 1 10 5 as possible with construction tolerances and mechanical adjustment (expect ~ a few 10 4 ) Correct the remaining errors with an array of ~ 150 mm long, printed circuit dipole correctors. Two sets of correctors per axis are required.

Printed Circuit Dipole Correctors 2 Layers of 4 oz Copper patterns; 159 mm ID, 150 mm long 1.25 x 10 3 Tesla central field at 2 A; DB/B ~ 10 3 at 50 mm Mounted on cryogenic heat shield to minimize dissipated power (approx. 190 W/m expected at full power).

Array of 150 mm long Correctors, 160 mm apart Superconducting 1.4E-03 1.2E-03 Can not correct in the Valleys Vertical Field (Tesla) 1.0E-03 8.0E-04 6.0E-04 4.0E-04 2.0E-04 0.0E+00-2.0E-04 Another layer, offset axially by half-pitch, is needed! -500-400 -300-200 -100 0 100 200 300 400 500 Z Position (mm)

Simulation to Check Correction Algorithm Superconducting 8.0E-04 6.0E-04 Field from Correctors 4.0E-04 By (Tesla) 2.0E-04 0.0E+00-2.0E-04-4.0E-04-6.0E-04-8.0E-04 Uncorrected Dipole Field Corrected -3500-2500 -1500-500 500 1500 2500 3500 Z Position (mm) Synthesized Field Errors

Simulation Results Residual By (Tesla) 1.0E-05 8.0E-06 6.0E-06 4.0E-06 2.0E-06 0.0E+00-2.0E-06-4.0E-06-6.0E-06-8.0E-06 Net Field after correction -1.0E-05-4000 -3000-2000 -1000 0 1000 2000 3000 4000 Z Position (mm)

e-cooler Solenoid Measurement System 3-D Hall probe system (expected resolution of ~10 3 radian) Magnetic needle and mirror system (expected resolution of ~10 5 radian; used at BINP, IUCF, Fermilab) BEAM SPLITTER MAGNETIC NEEDLE OPTICAL FILTER LASER MIRROR POSITION SENSITIVE DETECTOR

Measurement System Schematic Superconducting SOLENOID HIGH RESOLUTION CCD CAMERA BEAM SPLITTER GIMBAL MOUNT NMR ARRAY? HALL PROBES LASER INTERFEROMETER (Z-POSITION MEASUREMENT) LASER PROBE SLED SOLENOID

Gimbal mount for magnetic needle and mirror Superconducting Magnetic Needle Mirror

Setup for testing the measurement system Dipole Corrector Copper Solenoid 20 mt; 1.83 m long By exciting the dipole correctors at a known strength, the deflection of laser spot can be compared with the expected change in the solenoidal field direction. The complete measurement system is currently under development.

5T Solenoid

RIA R&D

RIA R&D

RIA R&D

RIA R&D

RIA R&D Test coils in progress. Since the FY04 funding only arrived in April we will try and complete a test coil comprised on 6 sub units in a magnetic mirror configuration and test in a vertical dewar by the end of the calendar year.

RHIC Magnet Systems Scope A large superconducting inventory of magnets: ~ 300 8cm dipoles ~ 400 8cm quadrupole/sextupole/corrector units 96 13cm IR quadrupoles 24 10cm IR dipoles 12 18cm IR dipoles 12 siberian snakes/spin rotators (48 helical dipole units)

RHIC Magnet Repair To date we have experienced failures in: A RHIC helical dipole cold mass A great deal of testing time in the magnet division was expended to track down the root cause of this failure. We suspected the quench detection algorithm was incorrect. Tests proved inconclusive, changes to the quench detection were made none the less A CQS correction element package A dipole layer A trim quadrupole in a CQS unit (in progress) The problem is believed to be the wiring card

NP Program Support Cryogenic engineering Cryogenic controls software Quench protection/magnet power supply system integration and fault diagnosis Quench protection system development AGS rapid cycling field measurements

Funding Nuclear Physics FY 2001 FY 2002 FY 2003 FY 2004 FY 2005 NP program magnet support $4,786 $4,740 $5,350 $5,874 $6,020 FTE's 25.5 26.5 28.5 29.0 29.0 RIA R&D $290 $350 (?) FTE's 2.0 2.5 CAD support non magnet FTE's 6.0 6.0 High Energy Physics LHC $9,707 $4,307 $2,302 $780 Base program $1,063 $990 $1,000 $1,000 44.0 30.6 18.8 12 Other $2,600 $3,840 $2,095 16.3 26.8 15 We assume that the magnet program will remain at this level of effort (~29 FTE s) for the foreseeable future. This represents ~40% of the s total activity. Obvious problem in FY05 from HEP

Summary The RHIC program support requirements are maturing (as is the machine): Magnetic measurements are becoming more subtle Magnet technology is becoming more complex No major production tasks anticipated in the near future. We are moving into a low volume, R&D, environment (spin, e-cooling, e-rhic). Possible issues with the helical dipoles. The other RHIC magnets appear to be very reliable. Planning on a constant level of effort