The Bond Release Process for New Subdivision Developments: An Overview for Homeowners Associations DRAFT 6-4-08. Revised 9-25-08



Similar documents
Bond Release Process for New Subdivision Developments in Fairfax County

SECTION EIGHT BONDING REQUIREMENTS

PLANNED UNIT DEVELOPMENT & SIDEWALK WAIVER REQUEST STAFF REPORT Date: November 7, 2013

Chapter 2 PLAN AND PLAT REVIEW PROCESS

SECTION SITE PREPARATION

Land Disturbance, Erosion Control and Stormwater Management Checklist. Walworth County Land Conservation Department

DESCRIPTION OF WORK:

Close-Out Documents... 9

City of Valdosta Land Development Regulations. Table of Contents

ORDINANCE NOW, THEREFORE, BE IT ORDAINED BY THE CITY OF BRENTWOOD, TENNESSEE, AS FOLLOWS:

A Guide for the Homeowner/Builder

VILLAS OF TRADITIONS AT GREY OAKS

Interlocking Concrete Pavement Institute (ICPI) Model Stormwater Ordinance for Permeable Interlocking Concrete Pavements August 2010

TREE PERMIT APPLICATION Private Property- Section MBMC COMMUNITY DEVELOPMENT DEPARTMENT

The checklist utilized by the Authority will be similar to that which is shown below. Project Name: Location: Consulting Engineering Firm:

CLACKAMAS COUNTY ZONING AND DEVELOPMENT ORDINANCE

WESTFIELD-WASHINGTON ADVISORY PLAN COMMISSION December 7, SPP-24 & 1512-ODP-24

CONSTRUCTION PERMIT REQUIREMENTS

ADA POST INSPECTION CHECKLIST. Job No. Route County Location

8.1.3 General Design Guidelines. The following guidelines shall be used when designing inlets along a street section:

Adopted 9/23/98 CHATTAHOOCHEE CORRIDOR PLAN. The goals of the Chattahoochee Corridor Plan (hereinafter also referred to as the Plan ) are:

Guidelines for. Permeable Pavement

Moving a House in Pasadena

CONFORMITY WITH PLANS; DRAINAGE.

Definition of Tower from the Bradley County Zoning Resolution

CITY OF VAUGHAN SCHEDULE O LOT GRADING DESIGN FOR RESIDENTIAL DEVELOPMENT

Frequently-Asked Questions about Floodplains and Flood Insurance FLOOD INSURANCE

9. Does the County of San Diego keep home plans on file for existing homes?

Homeowner s Guide to Drainage

Development Services Department City of San Antonio. Permits & Licenses. Development Services Manager. Deputy Historic Preservation Officer

Town of Beaumont. Lot Grading Guidelines

Planning and Zoning Commission Johnston, Iowa June 29, 2015

Harris County Flood Control District. Policy, Criteria, and Procedure Manual

Answers to Commonly Asked Questions

City of La Vernia 102 E. Chihuahua Street, La Vernia, Texas Phone: (830) Fax: (830)

APPLICATION PROCESS FOR LAND DISTURBING PERMIT

Hempfield Township LOGGING/HARVESTING PERMIT APPLICATION. Per Section of the Code of the Township of Hempfield

RESIDENTIAL BUILDING PERMIT REQUIREMENTS

Building, Plumbing, Electrical and Residential Water and Sewer Inspection Requirements

When is a Permit Required? What Types of Permits are Required? The most common types of projects that require permits are:

SECTION ELEVEN: ACTIVITIES REQUIRING A CERTIFIED EROSION AND SEDIMENT CONTROL PLAN 1

AREA: 2.37 acres NUMBER OF LOTS: 1 FT. NEW STREET: 0 LF. Single-family, Non-conforming machine shop

7.2 CONDITIONAL APPROVAL

SITE-SPECIFIC BEST MANAGEMENT PRACTICES (BMP) PLAN REVIEW CHECKLIST

SEMINOLE PRATT WHITNEY ROAD & NORTHLAKE BLVD. FREQUENTLY ASKED QUESTIONS

in Marina Del Rey Prepared by: County of Los Angeles Department of Public Works

Guidelines for Fiber Optic Cable Permits

FILE NO.: Z-6915-C. Gamble Road Short-form PCD and Land Alteration Variance Request

SITE-SPECIFIC BEST MANAGEMENT PRACTICES (SSBMP) PLAN/STORM WATER POLLUTION PREVENTION PLAN (SWPPP) REVIEW CHECKLIST

Chapter 3 SENSITIVE AREAS AND VEGETATED CORRIDORS

ENGINEERING DESIGN GUIDELINES. for SUBDIVISIONS OR COMMERCIAL DEVELOPMENTS

Guidelines for Control of Water Runoff on Small Lots. Revised 6/09

Extreme Wet Weather in Brookfield. How to Keep Your Basement Dry During Heavy Rains and Floods

The Lambton County Homeowner's BUILDING PERMIT INFORMATION GUIDE

1.7.0 Floodplain Modification Criteria

The City of Basehor, Kansas

CHAPTER 10 - PERMIT PROCEDURES AND BONDING REQUIREMENTS

PERFORMANCE AGREEMENT AND SURETY PROCESS FOR SUBDIVISIONS AND SITE PLANS

SERVICES THAT MAY ONLY BE PERFORMED BY A NEW JERSEY PROFESSIONAL LAND SURVEYOR

APPENDIX I DEVELOPMENT PROCESS CHECKLIST

SITE IMPROVEMENT PLANS CHECKLIST

APPLICATION FOR DEMOLITION & RIGHT-OF OF-WAY PERMIT

PROFFER STATEMENT REZONING TLZM LEEGATE November 1, 2013

BUSINESS USE PERMIT APPLICATION

DRAINAGE :: DRAINAGE CONCERN FREQUENTLY ASKED QUESTIONS

How To Install An Overhead Sewer

Activity Yes No N/A Notes

5901 Milwaukee Street Planned Unit Development (GDP) (Second Addition to Grandview Commons)

Town of Elkton & Cecil Soil Conservation District Checklist for Joint Agency Review Stormwater Management / Erosion and Sediment Control

NEW HOME CONSTRUCTION

Electronic Signature and Fee Payment Confirmation

BUILDING PERMIT APPLICATION APPLICABLE TO CITY LIMITS AND ETJ CHAPTER 18, General

Right-of-Way Permit Application Process (Plans that affect District owned or maintained right-of-way)

Architectural Review

Downspout Disconnection Program FAQs

Chesapeake Bay Preservation Ordinance Waiver and Exception Process Guidance for Activities in the Resource Protection Area (RPA)

Permit No. Permit Fee: $ Permit Expires (D+90 days): Business Name: Applicants Name: Telephone Number: Address:

CERTIFICATE OF APPROVAL OF LOCATION (CAL) APPLICATION Page 2

SECTION 3 SANITARY SEWER DESIGN

A Residential Owner s Guide to PERMITS. Elgin CITY OF PLANNING & NEIGHBORHOOD SERVICES

Application No.: Steve Rush, representing Rocky Mountain Power Rocky Mountain Power Project Location: approximately 1600 N E.

THE CORPORATION OF THE CITY OF GUELPH. THEREFORE the council of the Corporation of the City of Guelph enacts as follows:

REQUEST FOR ELECTRIC SERVICE Commercial

CITY OF HIGHLAND PARK, ILLINOIS Stormwater Management Fact Sheet

City of Douglas Commercial Building Permit Site Application

BEFORE YOU BUILD GUIDE

TOWN OF BRENTWOOD TH PLACE BRENTWOOD, MD (301) FENCE PERMIT APPLICATION

Single-Family Permit Handbook. City of Bellevue. Welcome! When is a permit required? Development Services Handout P-1

Summary and Description of 2014 Enhancements to New Jersey Model Stormwater Control Ordinance for Municipalities

DOÑA ANA COUNTY DESIGN STORM CRITERIA GUIDELINES FOR COMMERCIAL AND RESIDENTIAL SITES. Run-off Analysis Methods

Transcription:

The Bond Release Process for New Subdivision Developments: An Overview for Homeowners Associations DRAFT 6-4-08. Revised 9-25-08 Fairfax County requires developers to post a performance bond if they are building public infrastructure within a new housing subdivision. This brochure summarizes: * What is public infrastructure? * What are performance bonds? * Why are performance bonds collected from developers? * How and when these performance bonds are returned to developers? * What role homeowners associations play in bond release? What is public infrastructure? When a developer builds a new housing subdivision, they often must construct public infrastructure. This infrastructure typically includes: * Public Streets * Public Sidewalks * Public Sewers * Storm Drainage Facilities * Waterlines * Traffic Signals * Landscaping required by the county * Streetlights What are performance bonds? When building public infrastructure, a developer must enter into an agreement with the county; the agreement details what public infrastructure must be built and by when. As part of the agreement, a developer must also post a security. This security is often called a "bond," although the security may take other forms of financial guarantees, such as a letter of credit or cash deposit. [Federation suggested addition: Insert a few sentences briefly explaining how subdivision development can be phased in, and in what sequence the key phases occur.] The performance bond s amount is equal to the approximate cost of building the public infrastructure shown on an approved site plan. In addition to a performance bond, a developer may be required to provide a conservation deposit. This deposit is required if the development disturbs more than 2,500 square feet of land. It ensures that erosion and sediment controls are installed and maintained properly during the project. The deposit also can be used to clean-up or repair any damage caused by erosion or sediment from the project. [Note from Federation: See our question below on the conservation deposit, in the section entitled What are the conditions for releasing a performance bond? ] What s the purpose for a performance bond? A performance bond ensures that the county can pay to build the required public infrastructure if the developer fails to do so.

s a bond required if a developer promises to build private amenities, such as driveways? No. Under state law, Fairfax County cannot require developers to post security for any private improvements, including: * Driveways * Private walkways * Mailboxes * Sprinklers * Landscaping other than that required by county ordinance However, private improvements can be required as a result of a specific condition approved in a zoning action by the Board of Supervisors. These improvements must be specifically set forth in the condition or shown on the plat that was approved as part of the zoning action. Which county agency collects the performance bond? The Environmental and Facilities Inspections Division EFID collects the performance bond from a developer. EFID also inspects public infrastructure to make sure it is built as shown on the site plan and meets the minimum county and state standards. When is a performance bond returned to a developer? A performance bond is returned after all of the required public infrastructure has been built and accepted for maintenance by the appropriate public agency. This process is commonly called "bond release." If a developer fails to build the required infrastructure, the county may take steps to acquire the performance bond and use those funds to complete the improvements. The county may not give this money to individuals or homeowners associations to complete the improvements on their own. [Federation question and comment: Who possesses the bond? The phrase above "... may take steps to acquire the bond is confusing to us, because the previous wording led us to believe that the county already possessed the bond, and would not therefore need to "acquire" it. Please add some wording to clarify this.] What are the conditions for releasing a performance bond? Generally, there are two main conditions that must be met before the county may release a performance bond. First, the public infrastructure must meet minimum county and state codes and construction standards. Secondly, the appropriate state or county agency must accept any infrastructure that such state or county agency will be responsible for maintaining. For example, any street or road dedicated to the public must meet the standards of the Virginia Department of Transportation VDOT to be accepted into the state system for maintenance by VDOT. Before a performance bond can be released, county and state agencies will inspect the public infrastructure constructed by the developer. The infrastructure must pass all inspections for the performance bond to be released. If it does not, the developer is provided a list of what must be improved or completed. This is commonly called a "punch list." If a subdivision was approved through a zoning action of the county, a tree inspection also will be conducted to determine whether any of the trees required to remain on the developed property need to be replaced. In some cases, the county may release a performance bond before it returns the conservation deposit to the developer. The conservation deposit is held until erosion and conservation measures are completed and pass inspection. 2

[Federation question: Does the HOA have a role in the release of the conse,vation deposit? If the answer is yes, then the Federation has the following suggestion addition: Explain more thoroughly what inspections are done for ensuring compliance with conse,vation measures. A specific question we would like answered is: To what extent may the developer alter the 100-year flood plain? Perhaps conse,vation deposit issues should be addressed in a separate section.] What does the county inspect as a condition for performance bond release? The county inspects public infrastructure and only those private improvements that are required as a result an approved zoning action. Such private improvements are not inspected for any minimum standards-unless some standard is required as a condition of an approved zoning action. If so, the county does require that private improvements required as part of an approved zoning action are installed as set forth in the specific condition required by the zoning approval. Generally, the county requires that: * The grading and drainage facilities have been completed in general conformance with the approved grading plan. * The grading and steepness of slopes are in general conformance with the approved plan and county regulations. * The developer has not created any obstructions that could result in flooding of a dwelling unit if the storm sewer failed or became clogged. This is called overland relief. * All areas are permanently stabilized to prevent erosion. The county may release the performance bond prior to completion of this work but hold the conservation deposit as a guarantee for the completion of stabilization of the site. * All dead and hazardous trees within the limits of the site have been removed. The county may release the performance bond prior to completion of this work but will then hold the conservation deposit as a guarantee for the removal of hazardous trees. * All required landscaping that is depicted on the approved plan is installed and healthy. The county may release the performance bond prior to completion of this work but will then hold the conservation deposit as a guarantee that required landscaping is planted. However, the county does not require a maintenance performance bond or a guarantee that plants will survive. * All applicable required conditions as a result of an approved zoning action have been installed or implemented. * The required sight distance has been provided at all intersections within the bonded development. The code requires a clear path of sight at intersections. The required length of the required sight distance is determined based on the design speed or posted speed of the adjacent roadway. * The public street or road right-of-way has been accepted for maintenance by the Virginia Department of Transportation. * The sanitary sewer has been accepted for maintenance by the county s Wastewater Collection Division. * The water line has been approved and accepted for maintenance by the appropriate water authority. * The required streetlights if any are installed or have been paid for. * The required sidewalks and trails are in good condition without cracks, excessive differential settlement between sidewalk panels, or excessive surface deterioration of the concrete. The inspection includes verification that the required cross slope has been provided and that there are no areas in the sidewalk or trail where water collects and remains for several days. * Driveway aprons in the public right-of way are not cracked or show signs of excessive surface deterioration. * All the required parking spaces are delineated as shown on the approved plan. * All storm drainage facilities have been installed in accordance with the approved plans and county regulations. 3

* The fire marshal has inspected and approved all required fire lanes. * The county has received the results of all required third-party geotechnical testing and corresponding certifications required by county regulations. * Damage to properties from erosion and sediment or overclearing has been corrected. * The removal of temporary erosion and sediment controls, such as silt fences. The county may release the performance bond prior to completion of this work but hold the conservation deposit as a guarantee for the completion of stabilization of the site. * A property corner certification has been provided by the developer s engineer or surveyor. What doesn t the county inspect as a condition of bond release? * Private improvements that are not shown on the conditions adopted in a zoning action. * Performance standards for any private improvements that developers install, such as driveways, sprinklers or landscaping, unless they are in the conditions adopted in a zoning action. The county limits its involvement to ensuring that the private improvements that are depicted on the approved plan are installed. * Construction quality of the house, private driveway or landscaping that is not required or shown on the approved plan. * Relocation of utility boxes, storm drainage structures and infrastructure that exist in established easements. * Offsite property damage that resulted from work that was performed by utility companies. * Property damage that resulted from work that was performed by the developer, other than from a failure of the erosion and sediment controls. * Property damage that was caused by a homeowner or their contractor. * Drainage problems that are the result of work that was performed by a homeowner or their contractor. * Quality of construction that exceeds the minimum applicable standards of county and state regulations or the Virginia Department of Transportation s standards and specifications. Existing conditions outside the limits of clearing and grading. * Traffic controls and signals that are not depicted on the approved plan. * Installation of "no parking" signs that are not on the approved plan. * Providing a greater number of parking spaces than what is depicted on the approved plan or required by county regulations. * High ground water conditions that do not result in wet yards. * Quality or aesthetics of private amenities, such as fences, entrance features and private street light fixtures unless they are specifically required by the approved conditions of a zoning action. How is a performance bond released? First, the public infrastructure must pass final inspection, and a county or state agency must accept it for maintenance. Then, county inspectors submit paperwork to the county s Bonds and Agreement Branch. Assuming the developer has met all of the conditions, the performance bond will be released after this paperwork is reviewed and any outstanding fees to the county are paid. What happens after bond release? After a performance bond is released, a developer is not obligated to perform any additional work on the public infrastructure within the subdivision. After release, the public infrastructure will be maintained by the appropriate county or state agency. 4

How can homeowners associations participate in the bond release process? Before a performance bond is released, county inspectors and the developer will make a walkthrough inspection of the project. A representative of the homeowners association is invited and encouraged to join the walk-through inspection because: * It is an efficient way for an association representative to clarify any outstanding concerns they have about the public infrastructures in the development. * county staff can point out any infrastructure in the area owned by the association that it is responsible for maintaining, such as rain gardens, wet ponds, tot lots, common areas, etc. Before the inspection, homeowners associations can contact inspectors with the Environmental and Facilities Inspections Division if they have questions or concerns about the public infrastructure. However, association members should contact the county s Code Enforcement Division at 703-324-1937, TTY 711, if they have questions about the construction of homes. Homeowners associations can provide input, but they cannot require additional improvements that exceed the site plan requirements or the approved conditions of a zoning action. The county also cannot require a developer to upgrade infrastructure that meets the minimum standards of Fairfax County s "Public Facilities Manual" or Virginia Department of Transportation standards and specifications. What can delay bond release? If private improvements are installed in a public right-of-way without a permit, the county cannot release the performance bond. These improvements include sprinkler systems, masonry mailboxes, lighting and landscaping. The public right-of-way is the property that is required to be dedicated to the county for a public use such as a roadway, street or sidewalk. Private structures or landscaping, including trees, walls, brick or stone patios, or walkways, are not allowed in any sanitary or storm-drainage easements. Property owners should review the plats to determine the location of any easements on their property before they install any improvements. If private improvements are installed in county storm-drainage or sanitary sewer easements or in the right-of-way dedicated to the county without a permit, developers are required to remove them. How to get answers to your questions and concerns Call Fairfax County s Environmental and Facilities Inspections Division at 703-324-1950, TTY 711, if you have questions about the public infrastructure or bond release process, including: * What is considered public versus private infrastructure in your development? * What public infrastructure will be installed in your development? * What are the minimum standards for the public infrastructure in your development? * What are the opportunities for homeowners association input into the process? Fairfax County Department of Public Works and Environmental Services Environmental and Facilities Inspection Division 12055 Government Center Parkway, Suite 334 Fairfax, VA 22035 Tel: 703 324-1950, TTY 711 To request this information in an alternate format, call the Department of Public Works and Environmental Services Environmental and Facilities Inspection Division at 703 324-1950, TTY 711. 5