The New Line of Business IT System - A Successful Procurement



Similar documents
STATES OF JERSEY INTERNAL AUDIT: FOLLOWING UP THE REPORT OF THE COMPTROLLER AND AUDITOR GENERAL (P.A.C.3/2014) RESPONSE OF DEPARTMENTS

Outsourcing. Knowledge Summary

Property Management (Factoring) Policy. Approval date July 2014 Review date July 2017 Approved by Link Group Board.

Outsourcing. Definitions. Outsourcing Strategy. Potential Advantages of an Outsourced Service. Procurement Process

LSB Procurement Framework

SUBMITTED TO: NORFOLK AND SUFFOLK COLLABORATION PANEL - 3 SEPTEMBER 2014 ERP (ENTERPRISE RESOURCE PLANNING) PROJECT UPDATE

House of Commons Corporate Governance Framework

1. Evolution of infrastructure procurement in NSW. 2. Market consultation and outcomes. 3. Response and implementation. 4. Project Deed Evolution

ADVERT POSITION: SPECIALIST: CONTRACTS MANAGEMENT JOB LEVEL: 6 DURATION 3 YEAR CONTRACT LOCATION: NATIONAL OFFICE PORTFOLIO: DSU

JOB DESCRIPTION. Position Title and Number: Senior Procurement Officer (100618) Health, Wellbeing & Commissioning

CONTRACTS STANDING ORDERS (CSOs) 2015 / 2016 CSO

PRCA Communications Management Standard (CMS) for In-House Teams

Procedures for Tenders and Contracts. October Huon Valley Council Procedures for Tenders and Contracts October 2014 Page 1 of 14

Practice Note. 10 (Revised) October 2010 AUDIT OF FINANCIAL STATEMENTS OF PUBLIC SECTOR BODIES IN THE UNITED KINGDOM

CONTRACT MANAGEMENT POLICY

Version Author Revisions Made Date 1.6 David Sharkey Executive Board 27 March Robin Hunt

Governance of the Business Transformation Partnership Responsible Officer: Executive Director (Business Development)

Guide to choosing consultants

PM Governance. Executive Team ADCA ADCA

University of Brighton Sustainable Procurement Strategy

Welsh Government Response to the Report of the National Assembly for Wales Public Accounts Committee on Grant Management in Wales Final Report

Governance and Audit Committee 23 November 2015

Contract Standing Orders and Procedure - A Guide For Council Employees

North London Muslim Housing Association

Meeting the Decent Homes Standard

CODE OF PRACTICE DEALING WITH THE RELATIONSHIP BETWEEN THE NATIONAL AUDIT OFFICE AND THE COMPTROLLER AND AUDITOR GENERAL

Guide to choosing a Consultant

Best Practice in Design of Public-Private Partnerships (PPPs) for Social Infrastructure, particularly in Health Care and Education

Procurement of Goods, Services and Works Policy

Palliative Care Link Nurse Program

Research and information management strategy Using research and managing information to ensure delivery of the Commission s objectives

Human Resources Officer

Department of Health PFU & PPP Forum. Benchmarking and market testing in NHS PFI projects. Code of Best Practice

Essex Fire Authority. Fleet Management. Internal Audit Report (4.12/13) 28 February 2013 FINAL. Overall Opinion

How to do Business with the London. Borough of Sutton

DATA SECURITY ASSESSMENT REQUIREMENTS QUESTIONNAIRE RESPONSE GUIDANCE, EVALUATION AND MARKING SCHEME CROWN TRAVEL SERVICES REFERENCE NUMBER RM1081

Procurement Training & Certification Catalogue 2015

UoD IT Job Description

Construction (Design and Management) Regulations 2007

Data Quality Policy. Appendix A. 1. Why do we need a Data Quality Policy? Scope of this Policy Principles of data quality...

Community Benefits in Procurement Procedure

MANCHESTER CITY COUNCIL REPORT FOR RESOLUTION COMMUNITY REGENERATION, OVERVIEW & SCRUTINY VALUE FOR MONEY ASPECTS OF HOUSING REPAIRS

JOB DESCRIPTION. 1.1 Post Title: Property Services Director Directorate: People 1 st Slough. Property Services Location: Airways House

Project reporting in FP6

Recruitment and Selection Procedure

Responsive Repairs and Void Maintenance Strategy

ABERDEEN CITY COUNCIL. Name of Committee : Resources Management Committee

Subcontractors and Supply Chain Partners Management Fee Policy

Contract Management Framework

QUALITY ASSURANCE OPERATIONAL FRAMEWORK. University of Liverpool. Liverpool, L69 7ZX. And. Laureate

Tendering to Public Sector Organisations

Local Healthwatch and NHS Complaints Service. Cabinet member: Cllr John Thomson - Adult Care, Communities and Housing

ARGYLL AND BUTE COUNCIL SUPPORT SERVICES REVIEW HR & PAYROLL EXECUTIVE SUMMARY- 2 NOVEMBER 2011

Supporting the local economy in Surrey. 14 th June 2012

Customer Engagement Delivery Plan

Performance Management and Service Improvement Framework

To respond to queries at the first-point-of-contact by provision of a dedicated HR duty system.

a) To achieve an effective Quality Assurance System complying with International Standard ISO9001 (Quality Systems).

Specific Responsibilities Associated Performance Measures 1. Excellence in Commercial Management 2. Excellence in Contract Performance

Reduce risk. Reduce cost. Raise performance.

Comhairle nan Eilean Siar Internal Audit Review Project Management and Project Delivery Technical Services department. Final Report 2014/15-21

Human Resources & Facilities Services. Service Delivery Plan 2014/15. Overview of the Human Resources Service

REPORT 4 FOR DECISION. This report will be considered in public

Page 97. Executive Head of Asset Planning, Management and Capital Delivery

ORDINANCE 22 UNIVERSITY OF LONDON RISK MANAGEMENT POLICY


PROCUREMENT MANAGER Support Services. Salary range 30,843 to 33,315 (Subject to Job Evaluation)

Back to Basics. Managing the Audit Department: Resource Management

Badger BC. Investments Ltd. Business Plan A wholly owned subsidiary of Broxbourne Borough Council

Environmental Association for Universities and Colleges (EAUC) EAUC Head Office, University of Gloucestershire, The Park Campus, Cheltenham

Contract Management Case Studies

Prudential Practice Guide

HILLCREST HOUSING ASSOCIATION LIMITED MAINTENANCE POLICY

Framework Agreement between the Department of Health and the NHS Trust Development Authority. Annex C: Finance and Accounting

PREQUALIFICATION INFORMATION

Environment Sustainability & Highways

Global recruitment and selection policy AUGUST 2013

Bawden Contracting Services Ltd Job Profile. Contracts Manager. Purpose of the Job

TERMS OF REFERENCE - MAJOR EVENTS PANEL

Central Hosting. Case Study

LGRF. Procurement Probity Plan. July 2012

A. Statement of Accountability

CHAPTER 11 THE GOVERNMENT OF THE HONG KONG SPECIAL ADMINISTRATIVE REGION GENERAL REVENUE ACCOUNT. Information Technology Services Department

The University of Finance Department - A Review

PRINCIPLES AND GOOD PRACTICES

Application Information Pack CRM Project Manager

Business continuity: awareness and training programmes

UNSOLICITED PROPOSALS

JOB DESCRIPTION. Team Leader Fleet Engineering. Environment & Sustainable Communities / Highways. Transport Operations / Vehicle Fleet & Depot

Department of the Environment and Local Government. Project Management. Public Private Partnership Guidance Note April 2000

DRAFT. Anti-Bribery and Anti-Corruption Policy. Introduction. Scope. 1. Definitions

To be used in conjunction with the Invitation to Tender for Consultancy template.

Thank you for your interest in employment with Maryhill Housing Association.

Procurement Transformation Division. Procurement guidance. Engaging and managing consultants. Includes definitions for consultants and contractors

(1) To approve the proposals set out in paragraphs to ensure greater transparency of partnership board activity; and

Association for Project Management Business Management System

PROGRAMME FOR INTERNATIONAL STUDENT ASSESSMENT (PISA) 2018: CALL FOR TENDER PROCESS. An Overview

Australian National Audit Office. Report on Results of a Performance Audit of Contract Management Arrangements within the ANAO

Application Information Pack Digital Project Intern

24,006 - with possible progression to 25,771 per annum (pro rata for part time) Grade 5

Transcription:

STATES OF JERSEY r ANDIUM HOMES REPAIRS AND MAINTENANCE FOLLOWING UP THE REPORT OF THE COMPTROLLER AND AUDITOR GENERAL (P.A.C.1/2015) RESPONSE OF CHIEF OFFICERS Presented to the States on 17th July 2015 by the Public Accounts Committee STATES GREFFE 2015 Price code: B P.A.C.1 Res.

ANDIUM HOMES REPAIRS AND MAINTENANCE FOLLOWING UP THE REPORT OF THE COMPTROLLER AND AUDITOR GENERAL (P.A.C.1/2015) RESPONSE OF CHIEF OFFICERS Departmental Response to: P.A.C.1/2015 Review title: Repairs and Maintenance Following up the Report of the Comptroller and Auditor General PUBLIC ACCOUNTS COMMITTEE INTRODUCTION We are pleased to see that Limited has accepted the 4 recommendations we made in our report P.A.C.1/2015, and that the company has responded to the report in a timely manner. Elements of the response nevertheless indicate that may be premature in its assertion that all 4 recommendations will be implemented in full by August 2015. Regarding the procurement of a new IT system, we note that negotiations with preferred suppliers are ongoing and, accordingly, that systems implementation has yet to begin. On that basis, it may be premature for to assert that the new IT system is configured to deliver appropriate improvements in management information as per our recommendation 2. Turning to our third recommendation, we are pleased to learn of the work being undertaken to review the constitution of the Tenants Forum and to encourage greater membership of the group. The key question, however, is whether that work is expected to improve the quality of links between the Tenants Forum and localised residents groups, thereby maximising s opportunities to obtain constructive feedback from tenants. If has doubts in this regard, the company may wish to consider further amendments to its tenant engagement programme. Page - 2

INTRODUCTION is pleased to have had opportunity to demonstrate the positive steps taken in the first 10 months following incorporation. The comments of both the Comptroller and Auditor General and the Public Accounts Committee help reinforce the foundations laid and commitments made within the company s Strategic Business Plan. RECOMMENDATIONS Recommendations To / Reject Comments Target date of action/ completion 1 Before completing procurement of its new Line of Business IT system, should endeavour to benchmark its estimate for the cost of the system against costs incurred by comparable social housing providers in other jurisdictions. The replacement Line of Business system is currently in the shortlisting stage of the procurement process, and the 3 final preferred suppliers have now been identified. Their responses to the Invitation to Tender and implementation costs fall well below the initial 500k budget. The due diligence checks against the final 3 preferred suppliers where reference site questionnaires were undertaken, the housing organisations declined to disclose the financials around the implementation costs. Complete Further benchmarking comparisons were also sought from housing specialists 3C Consultants, who were engaged in the provision of the Requirements Specification and internal workshops with colleagues, but they too were unable to advise of any benchmarking data. 2 should ensure that its new Line of Business IT system is suitably specified and configured to deliver appropriate improvements in management information concerning repairs and maintenance activity, as per the recommendations made in R.9/2015. The Requirements Specification that was published in the Invitation to Tender under section 7 Reporting, seeks 77 distinct areas where differing reports from General, Operational to Management Information, should form part of the solution. The final 3 preferred suppliers have all confirmed that their solutions will meet the requirements and, therefore, the P.A.C. recommendation. Complete Page - 3

Recommendations To / Reject Comments Target date of action/ completion 3 should offer to assist the independent Tenants Forum to review its links with localised resident groups during 2015 and, where necessary, to improve communication with resident groups on matters falling within the Forum s terms of reference. is currently working with the Tenants Forum to review their Constitution, which needs modernisation to reflect the significant changes made since incorporation, and to encourage greater membership of the group. A new recruitment drive will consist of An event being organised by, whereby colleagues from each service area will be available to talk to clients about the job they do, service they deliver and any proposed changes or new initiatives in those areas. August 2015 Invites will be sent to all current Forum members, all current members of residents associations/groups/ panels, estate reps, and also those identified by Community Contacts during their estate visits as being interested in client engagement. The invitation will be clearly drafted to encourage attendees not to bring personal issues, but to come with an open mind to learn about the services offered by, and, importantly, the role of the Tenants Forum and importance of client engagement. Current Forum member volunteers will be involved throughout the organisation of this event, from approving the invite letter and list of invitees, discussing possible venues, and agreeing if we want any introductory speeches/presentations. Forum members will also consider running a station themselves to talk to other clients about the Tenants Forum. So as to maintain momentum, the event will be held in July 2015. Following the event, attendees will be written to and invited to join Tenants Forum, following which the Constitution will be revised and updated. Page - 4

Recommendations To / Reject Comments Target date of action/ completion 4 should review the management information at its disposal concerning the effectiveness of tenant engagement processes, and ensure that any weaknesses are addressed during procurement and implementation of the new Line of Business IT system. The Requirements Specification that was published in the Invitation to Tender under sections 2 Client Portal, 3 Communicating with Clients, and 18 Contact Management, and the level of detail contained within each of these sections, will address the weaknesses identified in the P.A.C. report. Complete CONCLUSION The P.A.C. recognised the shortfalls in management information as a result of underinvestment in the former Housing Department s IT infrastructure. The company s IT Strategy, now well into the procurement phase, is set to address those areas previously identified. We look forward to an opportunity to update the Committee on implementation plans as they develop. It was noted by the P.A.C. that the programme of procurement and delivery was ambitious. We do feel that it is realistic and achievable, but given the importance of a modern and effective IT infrastructure, expedient delivery is a fundamental necessity. The importance of a company/client relationship was explored in detail during the P.A.C. Hearing of February 2015. Again, is pleased to have received positive recognition for steps taken to engage with clients, which in turn informs the future business. approaches its client engagement ethic with enthusiasm and looks forward to the results of the revision of the Tenants Forum Constitution described in response to recommendation 3 above. Following the publishing of the C&AG s report on Housing Repairs and Maintenance on 5th February 2015, the following actions have already been implemented at the time of writing this response: R2 Develop, implement and monitor the effectiveness of a market development strategy for contractors. Procurement process underway for replacement Response Repair and Void Property Contracts. Market Development Bidders Meeting held, in which 37 local companies completed a marketing questionnaire and attended the workshop. Procurement strategy in development for further Bidders Meeting for replacement Kitchen and Bathroom Contracts in September 2015. Page - 5

Plans underway for a Working for market development workshop to be held later in 2015 to further develop the already successful Approved Contractors List. R3 Develop the management information system to enable the monitoring of variations to contractual rates and, where appropriate, corrective action. Developing Fixed Price Contracts to reduce incidences and need for price variations. Director approval needed for Schedule of Rate price variations. Schedule of Rate price variations line now included in monthly finance reporting (Management Team and Board). R4 Following future procurement exercises leading to the appointment of multiple contractors, establish target work allocations based on objective factors, including the assessed capacity of contractors. R5 Develop a suite of Key Performance Indicators on quality and timeliness, to inform decisions on the allocation of work between contractors. R6 Include in the Key Performance Indicators reported to senior management indicators to allow monitoring of the allocation of work between contractors. New suite of KPIs being introduced for Response Repair and Void Property Contracts (in procurement phase). Differential performance KPIs for all future multi-contractor work introduced. R7 Seek to increase participation rates in tenant satisfaction surveys through, for example, face-to-face and telephone interviews. R8 Develop Key Performance Indicators to facilitate monitoring of the results of tenant satisfaction surveys by contractor, and implementing appropriate corrective action. R9 Develop a suite of Key Performance Indicators to facilitate monitoring of responsive work by different trades and by priority categories, and implementing appropriate corrective action. Quarterly overall Response Repair performance satisfaction surveys continue. Post-repair face-to-face surveys per contractor implemented. Voucher draw scheme introduced to increase survey return rates. New suite of KPIs being introduced for Response Repair and Void Property Contracts (in procurement phase). Estate Standard face-to-face surveys implemented. Page - 6

R10 Extend tenant involvement in both decision-making and setting standards for housing repairs and maintenance. Recruitment of second Board Tenant Representative underway. Tenant Forum representatives engaged in new Response Repair and Void Property Contracts (in procurement). Academy/Service Improvement Panels in development. R11 Provide feedback to tenants on the results of satisfaction surveys and the action taken in response to concerns raised. Performance information included in latest Community News publication. Continued development of Social Media (Twitter/Facebook). Satisfaction data per contractor/subject published on website/social media. R12 Periodically review the operational impact of tenant engagement. Introduced as a standing item on monthly Programme Delivery Team meetings. Ian K. Gallichan Chief Executive Limited 3rd July 2015 Page - 7