Report Czech pilot site HeERO International Conference 15 th November 2012 Zagreb
Summary Strategy for the e-call Deployment in the country Main stakeholders (Consortium) Test Site description Overview of the current testing activity Main result of the tests Main issues and proposed solutions/countermeasures Plans for the future Dissemination 2
Strategy for the e-call Deployment in the Czech Republic Building of ITS applications - Governmental strategic documents and laws, including relevant implementing decrees 10 August 2011 - the Governmental Resolution No 599 National Strategy of Road Traffic Safety (BESIP) for the period of 2011 2020 13 June 2012 - amendment to Act No 13/1997 Coll. on road infrastructure (transposition of Directive 2010/40/EU) 3
Project Consortium within Czech Pilot Site 4
Test site description IVS Sherlog Trace GSM/GPS module u-blox, LEON G-100 IVS Telematix GSM/GPS module u-blox, LEON G-200, FW 7.65 ENG PSAP 1 test site: Prague, 4-6 agents seats involved in ecall testing PBX OmniPCX Enterprise, CCIVR, PSAP modem Alcatel-Lucent CTI Genesys, customised Call Taker application, GIS TMS interface implemented MNO Telefónica Czech Republic, ecall Flag implemented 5
Test site description test PSAP in Prague 10x ecall testing Car 13x IVS (2 different vendors) 6
Overview of the current situation CZ solution architecture 7
PSAP - TMS interface operator submits data whenever during the call information update is possible functional and ETE test towards real system 8
PSAP-TPS interface 9 phone call between TPSP and PSAP operator followed by TSD transmission consequent process identical to the public ecall/msd handling TSD Resend/Update tested
ecall tests general info test initiation - June 2012 intensive tests with detailed measurements August till now equipment for testing: test PSAP in Prague 10x ecall testing Car 13x IVS (2 different vendors) 2012 focused on: KPI values transmission MSD location accuracy drive direction total time overhead 10
ecall handling - summary 11
ecall tests IVS installation 12
ecall tests types and properties ecall handling in PSAP: automatic processing of incoming ecalls (non-stop dispatch and save all incoming ecalls) manual dispatching with live operator (direct feedback, and with call back and re-send msd function) Types of tests: basic ecall pre-defined routes bottlenecks geozones IVS has a geographically limited area of ecall activation ecall testing Car ecall PSAP 13
Czech Pilot Site - ecall handling - summary 14
ecall tests tunels Desc. Motorway Value D5 Lenghts Point Geometry Type 400 m Portal POINT(- 821646.564984-1077319.531771) Portal POINT(- 821271.518108-1077383.693230) Uvnitr POINT(- 821483.184775-1077350.620313) 15
ecall tests showcase traffic info Traffic info WEB ecall real test with traffic management centre 16 PSAP GIS Traffic info on VMS
Cross-border interoperability test 11 September 2012
ecall tests showcase interoperability Bad Schandau, Border GER First interoperability test between CZE and GER Czech ecall testing car successfully communicate with German PSAP : MSD OK, CallBack OK 18
ecall tests first results Key results from SEPTEMBER 2012 testing Description of parameters Results No. of ecalls(september 2012) (KPI) 5 000 Avg. time for call establishment mobile network (KPI) Avg. duration of voice channel blocking (KPI) Avg. duration until MSD is presented in PSAP (KPI) Avg. VINdecoding duration Avg. transmission time to traffic management 4-6 sec 4-6 sec 14-17 sec 1-2 sec 2-5 sec Success rate of received MSDs 99% Otherstatistics Description of parameters The average number of kilometers driven by ALL testing car Average testing car generate 1 Call per Results 23 000/month 4,6 Km 19
Main Issues-problems with the standards Problem FALSE CALLS (HeERO - Faulty mobile phones problem.doc) According to Czech telco experts the currently running HeERO project has not taken into consideration the document EN 16454. Czech Pilot Site proposed to incorporate this standard into the scope of HeERO testing activities. 20
Plans for the future analysis of KPI parameter anomalies evaluation of special tests focusing on ecall behaviour in impaired conditions of GSM/GPS signal IVS bugs fixes (areas: logging procedure, GPS freezing, in-band modem transmission reliability) In band modem benchmark test with Qualcomm PSAP modem change request implementation (better identification of not correct MSD parameters) Preparation of environment for test phase 2 21
Public / User Acceptance Safety-relevant and safety-critical applications - the conformity assessment of components and testing and verification of reliable function. Before the introduction of a new product on the market Regular inspection during the operation time. Failure in the critical situations - the public could loose their trust in these systems. 22
Dissemination Journals & Magazines 23
Conference & Trade Show LOCAL AND REGIONAL INFORMATION SOCIETY 2-3 April 2012, Hradec Králové, Czech Republic
Public Event ROAD SAFETY DAY 2012 28 June 2012, Prague, Czech Republic
Media reaction Reference to HeERO
Conference & Trade Fair PRAGUE FIRE & SECURITY DAYS 2012 18 September 2012, Prague, Czech Republic
Police Conference TRAFFIC INFORMATION AND ITS IMPACT ON THE ROAD SAFETY 24-25 September 2012, Červená nad Vltavou,Czech Republic
Conference ecall Days 2012 27-28 September 2012, Berlin, Germany 30
ITS World Congress 19th ITS World Congress 22-26 October 2012, Vienna, Austria 31
Plans for the Dissemination in 2013 NATO Days in Ostrava - Security & Safety usually in September every year Associated programme, International Aviation Industry Exhibition Weekend show, Ostrava Leoš Janáček Airport 32
33
34
35
36
37
38 Thank for the attention
39 Questions?