Greater New Orleans Hurricane & Storm Damage Risk Reduction System



Similar documents
Greater New Orleans Hurricane and Storm Damage Risk Reduction System

GAO HURRICANE KATRINA. Strategic Planning Needed to Guide Future Enhancements Beyond Interim Levee Repairs. Report to Congressional Committees

New Orleans Hurricane Storm Damage Risk Reduction System Tour March 23 24, 2012

New Orleans Hurricane and Storm Damage Risk Reduction System

EXPERT REVIEW PANEL ON GREATER NEW ORLEANS HURRICANE AND STORM DAMAGE RISK REDUCTION SYSTEM DESIGN GUIDELINES: Final Report

PART 2 NEW ORLEANS DRAINAGE CANALS

5.0 OVERVIEW OF FLOOD DAMAGE REDUCTION MEASURES

Evaluating the Condition of Seawalls/Bulkheads

STRUCTURES Excavation and backfill for structures should conform to the topic EXCAVATION AND BACKFILL.

TFMA 2015 Spring Conference Dallas, TX. John E. Bourdeau Jr: FEMA Region 6, Risk Analysis Branch

Comprehensive Recommendations Supporting the Use of the Multiple Lines of Defense Strategy to Sustain Coastal Louisiana 2008 Report (Version I)

Release of EC USACE Process for the National Flood Insurance Program (NFIP) Levee System Evaluation. Frequently Asked Questions

U.S. Army Corps of Engineers

FINAL Environmental Impact Statement (EIS) for the

The success of the hurricane protection around Chevron s refinery at Pascagoula, MS, during Katrina

Emergency Management THERE WHEN YOU NEED US

SECTION STORM DRAINAGE STRUCTURES. 1. Trench excavation, backfill, and compaction; Section

Oakwood Beach Storm Damage Prevention Project NJDEP-Bureau of Coastal Engineering Glenn Golden, Project Manager U.S. Army Corps Civil Works Programs

Contractor of the Year

US Army Corps of Engineers BUILDING STRONG

A New Coastal Engineering Graduate Program

Failing Coastal Wood Infrastructure on the Great Lakes

FINAL TECHNICAL MEMORANDUM AWD FLOWS THROUGH FLOOD DAMAGE REDUCTION AREA July 16, 2012

Managing Our Water Retention Systems

USACE Dam Safety Program Current Approach & Methodology

Lockport Pool Chicago Sanitary & Ship Canal Illinois Waterway

Storm tide is the water level rise during a storm due to the combination of storm surge and the astronomical tide.

8 Sub-Basins acres. 5 Outflow Locations 29 billion gallon/day capacity. Drainage Basin 1. 17th st. canal. pump st. 12. pump st. 19. pump st.

CRS Report for Congress

Storm tide is the water level rise during a storm due to the combination of storm surge and the astronomical tide.

MARYLAND AVENUE BACKUPS DURING AUGUST 31, 2014 STORM EVENT COMMUNITY OUTREACH

U.S. Naval Academy. Flood Damage Reduction Project Using Structural and Non-Structural Measures

Index. protection. excavated drop inlet protection (Temporary) Block and gravel inlet Protection (Temporary)

Lower Raritan Watershed Management Area Stormwater & Flooding Subcommittee Strategy Worksheet LRSW-S3C1

Overview of Deep Mixing at Levee LPV 111, New Orleans, LA

Flood Emergency Response Planning: How to Protect Your Business from a Natural Disaster RIC005

Review Plan. F-4 Channel Rehabilitation. Tropicana and Flamingo Washes, Clark County, Nevada for Plans and Specification

Storm Protection. Storm Protection

Rehabilitation of Locks on the Kentucky River

Norfolk Flooding Strategy Update. Presentation to Norfolk City Council March 27, 2012

Specification for Pipe Coating Repairs Offshore

Analysis of the Interstate 10 Twin Bridge s Collapse During Hurricane Katrina

SECTION 1 GENERAL REQUIREMENTS

Structural Damage Due to Floods

Swannanoa River Flood Risk Management Study

CRS Report for Congress

A Systems Engineering Based Assessment of The Greater New Orleans Hurricane Surge Defense System Using the Multiple Lines-of-Defense Framework

REBUILDING BELMAR ABFE FLOOD MAPS &THE REBUILDING PROCESS

SSPEED Center Phase III: Developing a Houston- Galveston Area Protection System (H-GAPS)

GUIDELINES FOR UTILITY INSTALLATIONS Part 1 - Wire Lines and Communications Cables

Appendix F Benefit-Cost Analysis of Flood Protection Measures

The Army Corps of Engineers and the Flood Risk Challenge

Federal Triangle Stormwater Working Group Federal Triangle Floodproofing Seminar BUILDING STRONG SM

C. Section TESTING LABORATORY SERVICE.

1997 Uniform Administrative Code Amendment for Earthen Material and Straw Bale Structures Tucson/Pima County, Arizona

Jacksonville Port Authority: Fire and Rescue Marine Fire Station #40, Jacksonville, Florida

The Basics of Chapter 105 Waterways and Wetlands Permitting in PA

201 WATER STREET FORWARDERS MUSEUM AND VISITORS INFORMATION CENTRE

RESUME Lee A. Knuppel, P.E.

Table 4.9 Storm Drain Inlet Protetion Applicable for

SECTION STORM DRAINAGE TABLE OF CONTENTS

HURRICANE ISAAC. National Disaster Recovery Framework (NDRF) Long Term Recovery Group (LTRG) Citizens Advisory Committee (CAC)

1. GENERAL ADVISORY BASE FLOOD ELEVATION (ABFE) QUESTIONS

Capabilities Statement for Project Management Oversight Services. Presented to:

Loss-Consistent Categorization of Hurricane Wind and Storm Surge Damage for Residential Structures

Jefferson Parish Department of Water Emergency Plan

USACE Civil Works Infrastructure Investment Trends: Glide-Path to Benign Neglect?

LOWELL REGIONAL WASTEWATER UTILITY SPECIFICATIONS FOR THE LOWELL MA CONCRETE FLOODWALL REPAIRS

Outlet stabilization structure

April 17, 2015 SUMMARY OF SUBJECT MATTER

Piers, Wharves & Docks

Flood Risk Management

Flood Risk Management

Mouth of the Columbia River Jetties Major Rehabilitation Study

ORDINANCE NO

How to Become a Navy Engineer For $78,000 in USD

Flood Mitigation and Management in Bangkok Metropolitan Area

SIMULATION OF SEDIMENT TRANSPORT AND CHANNEL MORPHOLOGY CHANGE IN LARGE RIVER SYSTEMS. Stephen H. Scott 1 and Yafei Jia 2

SECTION POINT REPAIRS TO SANITARY SEWERS. A. Repairs to existing sewer lines by replacing short lengths of failed pipe.

Building Foundation and Structure

SECTION REMOVAL OR ABANDONMENT OF EXISTING UTILITIES AND UNDERGROUND STRUCTURES. 1. Trench excavation, backfill, and compaction; Section

Levees in Texas A Historical Perspective

Chapter 3 Pre-Installation, Foundations and Piers

Transcription:

Greater New Orleans Hurricane & Storm Damage Risk Reduction System SLFPA-East Update Col. Robert Sinkler, Commander Hurricane Protection Office July 15, 2010 US US Army Army Corps Corps of of Engineers Engineers

1. Public Discussion Rules Agenda 2. USACE Accepted Measures to Inhibit Corrosion 3. Independent External Peer Review (Corrosion and Bending Moment) 4. Settlement Calculation Factors Likely Stopping Point 5. IHNC Storage Capacity 6. Why is the Work Being Expedited? 7. Post Hurricane Storm Surge Damage Repair 8. Design-Life Provided for Back-Up 9. SLFPA-E Construction Execution Team 10. St. Bernard T-Wall Decision 11. Mr. Goin s Comments (Hand-Out) Working Draft 2

Public Discussion Rules Will not publicly discuss speculative subsidence, settlement and sea-level rise projections beyond 50- years (will do it privately) Will not publicly discuss speculative performance of a well-maintained system beyond 100-years of age (will do it privately) Will not publicly discuss speculative performance of the 100-year HSDRRS at higher surge levels (will do it privately) Will not publicly discuss speculative performance of HSDRRS resiliency at higher surge levels than 500- yr (will do it privately) Working Draft 3

Practice has generally not been to Double Protect USACE Accepted Measures to Inhibit Corrosion Over-sized cross sections of piles (addition of a corrosion allowance). Coal tar epoxy* or other coating. Application of a polyethylene sleeve (on steel pipe piles). Zinc Coating. Electro-chemical (cathodic) protection. Casting in cement, mortar or concrete. All are being used in the HSDRRS! Working Draft *The Current HSDRRS Design Guidelines 4DO NOT Address All!

USACE Position on Oversized Steel In some cases an oversized sheet pile section may be specified to provide for the anticipated loss of section resulting from corrosion. o EM 1110-2-2504, Design of Sheet Pile Walls, Paragraph 9-2.b.(4). Dated 31 March 1994. USACE policy on use of an oversized section as an alterative in addressing steel pile corrosion is consistent with other federal and state agencies, as well as private industry design guides. Working Draft 5

Current HSDRRS Design Guidelines Do Not Specifically Address Corrosion "5.6.8 Painting Only coal tar epoxy shall be used. Steel sheet, H and Pipe pilings that will be installed in new fill, disturbed materials or fluctuating water tables shall be painted with a coal tar epoxy system. The H-piles and sheet piling shall be painted 3 inches above the stabilization slab and to a 5 ft. minimum below new fill material, disturbed soil or the lowest elevation of fluctuating water tables. Piles exposed in water (i.e. cutoff pilings in breakwaters) shall be coated the full height exposed to water plus a 5 embedment length. Use engineering judgment for final painting requirements." Using accepted methods to address corrosion other than painting with coal tar epoxy is within current HSDRRS Design Guidelines. Working Draft 6

St. Bernard H-Pile Dimensions Oversized Steel = More Strength (not drawn to scale) H14X89 (with oversized steel) Depth: 13.8 in. Flange Width: 14.7 in. Flange Thickness: 0.6 in. Web Width: 11.25 in. Web Thickness: 0.6 in. 30-50% more crosssectional area than structurally needed in top 5-7 feet! Working Draft 7

St. Bernard H-Pile Cross Section Maximum Corrosion Potential Maximum Cross-Sectional Area Required O&M Manual Requires Joint Periodic Inspections of H-Piles Working Draft 8

Next Step on Corrosion Follow-up meeting at 2pm today to further discuss way ahead (includes SLFPA-E, OCPR and ERDC experts). Working Draft 9

Independent External Peer Review (IEPR) Recommend that the next (future) version of HSDRRS Design Guidelines specifically address: Corrosion Bending Moment All substantive HSDRRS Design Guideline changes do undergo an IEPR. Working Draft 10

Settlement Calculation Factors Meets Current HSDRRS Design Criteria Historical data. Soil samples from the foundation tested to determine values for settlement calculations. Computer modeling used to predict settlement over time. Most settlement would occur in the first 15 years after project completion. Many of the levees in St. Bernard Parish are on ground that has already been consolidated to some degree. Working Draft 11

H-Piles There is No Hydraulic or Soil Induced Load that Will Break These Piles! Working Draft 12

There has Never Been a Documented Case of a Pile Supported T-Wall failure. Working Draft 13

Bayou Dupre November 2005 I-Wall Concrete Pile-Founded T-Wall Working Draft 14

IHNC Storage Capacity For a 100-yr Storm Surge: Closure elevation: +3 feet Rainfall (10-year, 24 hour event): +0.8 feet Pumping into the basin: +2 feet Overtopping: +1.5 feet Wind setup: +0.5 feet Water elevation of less than 8 feet For a 500-yr storm surge, the IHNC Basin will rise to an elevation of less than 10 feet. The IHNC Basin will be able to safely hold water to the top of the wall, which is at elevation +12 feet at its lowest point. (Hurricane Gustav Elevation) Working Draft 15

Why is the Work being Expedited? Operational Deadline: 1 June 2011 The Corps operational goal is to provide [100-yr] level of risk reduction by June 1, 2011. (24 Feb 09 Congressional Testimony) Most HSDRRS work is funded by Congress with Flood Control and Coastal Emergency (FCCE) appropriations. Federal expectation is that work will be expedited as if under emergency conditions. A major U.S. Urban Area does not have the Hurricane Storm Surge System its needs. Working Draft 16

USACE Authorities and Activities Public Law 84-99 (Annual Flood Control and Coastal Emergency Appropriations from Congress) Disaster Preparation Emergency Operations Repair any active flood control work Repair any Federally constructed hurricane or shore protection work Rehabilitation Water Assistance Advance Measures Hazard Mitigation Post Hurricane Storm Surge Damage Repair Working Draft 17

Design Life for St. Bernard Structures Hydraulics drive the 50-year design elevations used for the structure elevation. Structures will provide one percent storm risk reduction in 2057. The 50-year design life is not an indicator of product life span. There is no factor for longevity. The walls and gates will remain structurally sound past the 50-year design life (if properly maintained). Design Corrosion Rate for Most Steel is 100 Years or Greater Working Draft 18

Design Life Case Study: IHNC Lock (It is Part of the Mississippi River Levee System) Built in 1923 by the Port of New Orleans. The Lock has exceeded its original 50 Year design life. It s the evolution of the barge industry and the increased sizes of the barge tows, and not the design life, that has resulted in the authorization to replace the Lock. Still in Operation Nearly 90 Years Later! Built on Timber Piles! Working Draft 19

Southeast Louisiana Flood Protection Authority East Construction Execution Team Robert Turner Regional Director SLFPA-E Stevan Spencer Chief Engineer SLFPA-E MAJ Hall HPO OIC Marcia St. Martin Executive Director Sewerage & Water Board Joe Becker General Superintendent Sewerage & Water Board John Ashley Branch Chief Pump Station Repairs Cost: >$70 M Contracts: Design-Build 5 Design-Bid-Build: 25 Total: 30 Permanent Pumps Dan Bradley Cost: >$1 B Branch Chief Contracts: Design-Build 2 Permanent Pumps Design-Bid-Build 9 Interim Closure Structures Total: 11 Outfall Canal Walls Storm Proofing Cost: >$250 M Contracts: Design-Bid-Build: 25 Total: 11 Monica Salins Pontchartrain Levee District Carl Anderson Sr. PM Levees Sam Morsie Sr. PM Floodwalls St. Charles Parish Cost: >$150 M Contracts: Design-Bid-Build 16 Total: 16 East Bank Jefferson Parish Cost: >$500 M Contracts: Design-Bid-Build 27 Total: 27 Fran Campbell East Jefferson Levee District Gerry Gillen Orleans Levee District Teresa King Orleans Metro PM CPT Schmidt OIC Sean Brunet Sr. PM Orleans Parish Orleans Metro Cost: >$100 M Contracts: Design-Bid-Build 10 Total: 10 Michael Grzegorzewski Orleans East PM Orleans East Cost: >$700 M Contracts: Design-Bid-Build: 12 Early Contractor Involvement :1 Total: 13 CPT Cali OIC Stuart Williamson Lake Borgne Basin Levee District CPT Wood OIC Harold Daigle Office of Coastal Protection and Restoration Ron Elmer IHNC Sr. PM Chris Gilmore St. Bernard PM St. Bernard Cost: >$1 B Contracts: Design-Bid-Build 3 Early Contractor Involvement 3 Total: 6 > $5 BILLION EXECUTED IN < 5 YEARS INTERNAL WORKING DRAFT AS OF: 13 Jul 20 2010 IHNC Cost: >$1.5 B Contracts: Design-Build 1 Design-Bid-Build 7 Early Contractor Involvement 1 Total: 9

St. Bernard T-Wall Decision Earthen levees considered but ruled out for St. Bernard New levee heights: 28 (Approx.) Existing levee heights: 14-20 Existing width, approx. 300 USACE illustration, not to scale Levee width necessary to meet new, more stringent post-katrina design criteria - approx. 900 Working Draft 21

Some T-Wall O&M Cost Savings 75% less mowing (Compared to a Levee) 75% less settlement-related maintenance (borrow material) 2057 elevation without having to address future lifts and future subsidence Less flood side and protected side armoring maintenance Working Draft 22

Katrina storm surge elevations were much higher elsewhere along the Gulf Coast. 500-YEAR STILL WATER ELEVATION*: EL +22.5 100-YEAR LEVEE ELEVATION: EL +28 HURRICANE KATRINA S STILL WATER ELEVATION* AT THIS LOCATION: EL +18 Top of Floodwall: EL +32 Top of Base Slab: EL +21 100-YEAR STILL WATER ELEVATION*: EL +18 Top of Stabilization Slab: EL +17.5 St. Bernard Parish Floodwall, near the IHNC Tie-In (not labeled to scale) *Still water elevation does not include waves 23 Working Draft

If Earthen Levees Were Built to Reduce Risk from a 100100-year Storm in St. Bernard Parish The expanded footprint would encroach into nearby waterways, and more than 1,450 acres of land would be impacted. Operation and Maintenance costs would be greater. Working Draft Construction would require about 25 million cubic yards of additional borrow material, further driving up the cost. 24 BUILDING STRONG