Riggflytting av Maersk Drilling Jack-ups



Similar documents
6. Feb København Vinterkonferanse 2009 Norsk Forening for Ledende Bore og Brønnpersonell

Offshore Structures. Offshore Drilling Equipment

Maersk Drilling Annual Result 2014

Maersk Drilling Rig Fleet

Career on a drilling rig

GENERAL OCEAN TOW RECOMMENDATIONS FOR JACKUP DRILLING UNITS International Association of Drilling Contractors (I.A.D.C.) February 13, 1991

Noble Denton marine services - marine warranty survey

Maersk Drilling One billion, zero incidents

International Association of Drilling Contractors

Horizon Survey and Geotechnical Companies

Platform Technologies for Offshore Renewable Energy Conversion Diego Vannucci, RINA

OWPST & Titan 200 & UK Offshore

MERMAID FLEET PROFILE SUBSEA SERVICES

INSTALLATION and LOGISTICS of OFFSHORE WIND FARMS

Profile. Offshore Oil & Gas To meet the global demand for energy. Offshore and EPC Contractors

Self-Elevating Platforms Guidelines for Operations and Towages UNCONTROLLED

Hurricanes and the Offshore oil and Natural Gas Industry

Not getting any younger - a perspective on Ageing Rigs

Offshore Oil and Gas. Experience and Capabilities

PRELIMINARY RESULTS SBM OFFSHORE NEW CEO IN 2008

PETROLEUM PRODUCTION MASTERCLASSES

SBM OFFSHORE Q TRADING UPDATE SOLID PERFORMANCE WITH IMPROVING MARKET

Exceed Your Career Expectations

Maersk Resilient. Maximised drilling efficiency and uptime. Optimised for concurrent activities

maersksupplyservice.com S-TYPE ANCHOR HANDLING TUG SUPPLY VESSEL Visit our web site at: maersksupplyservice.com

An Overview of Seabed Surveys (High resolution Geophysical Site Surveys)

AGM presentation 13 May 2009

MESA Report on the Accident to the Mobile Offshore Drilling Unit Maersk Victory on November

TECHNICAL POLICY BOARD SELF-ELEVATING PLATFORMS GUIDELINES FOR ELEVATED OPERATIONS

Accident Report. Injury Pacific Way. 26 November 2005 Class A

MOBILE OFFSHORE UNITS

Resolution A.1079(28) Adopted on 4 December 2013 (Agenda item 10)

Monobuckets and the competitiveness versus monopiles and jacket structures.

Manual: Nearshore CPT Testing NEARSHORE CONE PENETRATION TESTING (TOP PUSH TECHNIQUE)

INTRODUCTION OF KEY STAFF

The Use of Coatings for Corrosion Control on Offshore Oil Structures. J. Peter Ault, P.E. Consultant Ocean City, NJ

REDACTED VERSION DEEPWATER CHAMPION EMERGENCY RESPONSE MANUAL VOLUME 1 OF 2. Non Controlled

Preparation. Preparation. Step 2 Prepare an emergency kit. Step 1 Prepare your emergency plan. Step 4 Tune into warnings

PROJECT MANAGEMENT SERVICES

TECHNICAL INFORMATION

Offshore oil and gas Services and solutions

How To Get A Marine Safety License

JRC MOU Location & Move Warranty Survey Scope of Work (A revision on behalf of the JRC)

COWI offshore wind marine engineering services

International Legal Regime of Offshore Structures- Environmental Concerns By Violeta S. Radovich

Pipelines and seabed intervention

DANISH ENERGY AGENCY S GUIDELINES ON SAFETY- AND HEALTH RELATED CONDITIONS ON OFFSHORE INSTALLATIIONS, ETC. HEALTH & SAFETY CASES

MATTHEW FENTON. Telephone

Life-of-Field. seabed-to-surface

Engineers at Liftech designed the structure of the first container crane and have designed and reviewed thousands of container cranes since.

Game Guide THE QUEST FOR OIL. A computer game about gaining and applying detailed insights into the geographical underground and global oil industry.

Benefits of Navigational Port Studies

Curriculum Vitae SAN FRANCISCO, USA, RESIDENT SURVEYOR. British Subject and USA permanent resident

FLEET LIST OFFSHORE SUPPORT VESSELS

Conceptual benefits with a cylindrical hull for FPSO, FLNG, drilling and floating powerplant applications

Marine integrity monitoring Offshore oil and gas

DEPARTMENT OF MARINE SERVICES AND MERCHANT SHIPPING (ADOMS) Boatmaster s Licenses

Safety and Environmental Management Manual (SEMM) Index

Mærsk Gallant. Harsh environment jack-up. Capabilities for subsea handling HP/HT drilling

LINKING SEABED TO SURFACE

Structural concepts for minimum facility platforms for Marginal field development in western offshore, India

International Oil, Gas, Energy and Marine Specialists

EXPERIENCE WITH DP-SYSTEMS ON BOARD

Depth-independent solution for Offshore Wind the WindFloat

DRIL-QUIP, INC. OFFSHORE DRILLING AND PRODUCTION EQUIPMENT.

The advice. The expertise. Wherever you are.

EMAS AMC. Floater & FPSO installation SURF installation Lewek Crusader EMAS MARINE. Lewek Fulmar and Lewek Lark


positioned for innovation Viking SeaTech Survey

Risk Management of Docking Mobile Offshore Units

KNUD E. HANSEN A/S. Design of Wind Turbine Installation Vessel Pacific Orca for Swire Blue Ocean

MARINE WARRANTY SURVEYING FOR OFFSHORE PROJECTS AND ISSUES FACED IN THE CURRENT MARKET

Case Study of Emergency Disconnect Sequence in the Gulf of Mexico

maersksupplyservice.com L-Type ANCHOR HANDLING TUG SUPPLY VESSEL Visit our web site at: maersksupplyservice.com

Marine Accidents SØULYKKESRAPPORT FRA OPKLARINGSENHEDEN

Woods Hole Group, Inc. Oceanography and Measurement Systems Division INTEGRATED REAL-TIME MONITORING SYSTEM

HV Submarine Cable Systems Design, Testing and Installation

National Transportation Safety Board

AADE-07-NTCE-30. Underwater Seafloor Drilling Rig Adel Sheshtawy, AADE, USDR Inc.

Oil and Gas Offshore.

Introduction BAM and Van Oord GBF - Concrete Centre Conference, December 2012

Drilling Performance Benchmark Metrics Overview: Benchmark Metric Definitions Below the Mudline (BML) SPUD Date Kick Off Point (KOP) KOP Date

Shallow Water Swath Bathymetry from Small Platforms. Advances in Seafloor Mapping Sonar, 30 Dec 2009 Systems Engineering & Assessment Ltd.

Customer Type of contract Vessel / location Month / Year

Training and Certification Requirements for the Crew of Fishing Vessels and their Applicability to Small Commercial Vessels and Large Yachts

Barge Invest AS Eide Marine Services AS Eide Contracting AS Eide Flotel Services AS Eide Marine Tech AS Haugesund Innkvartering AS

K.M. Dastur Reinsurance Brokers Pvt. Ltd.

Visiongain. -v1531/ Publisher Sample

DRILLING PRODUCTS AND EXPERIENCE

OFFSHORE INDUSTRY REQUIREMENTS AND RECENT METOCEAN TECHNOLOGY DEVELOPMENTS

PROJECT CARGO RISK MANAGEMENT

Fact Sheet SEAFARER CERTIFICATIONS

Assessment of Hydrocarbon Explosion and Fire Risks. Professor Jeom Paik. The LRET Research Collegium Southampton, 11 July 2 September 2011

Maritime Human Resources Solutions Seminar. Robert Cadigan President & CEO Newfoundland & Labrador Oil & Gas Industries Association

MANAGING MAINTENANCE OPERATIONS IN THE OFFSHORE INDUSTRY

SSP Offshore. Well Containment. April 2011

Allianz Global Corporate & Specialty Hull, Protection & Indemnity and Marine Liability Insurance

Transcription:

Riggflytting av Maersk Drilling Jack-ups 11. 12. november 2009, Clarion Hotel Stavanger Claus Schiller, Head of Towmasters Departement Per Frederiksen, Towmaster/ Kaptajn Introduction to Maersk Drilling & Maersk FPSOs

Maersk Drilling s Offices Houston Maracaibo Stavanger Aberdeen Copenhagen Esbjerg Baku Cairo Dubai Singapore (yard team) Brunei Rio Perth

Drilling rigs Jack-up rigs (12) MAERSK ENDURER MÆRSK GIANT MÆRSK GUARDIAN MÆRSK GALLANT MÆRSK INNOVATOR MÆRSK INSPIRER MAERSK RESILIENT MÆRSK RESOLUTE MÆRSK RESOLVE MÆRSK REACHER MAERSK COMPLETER MAERSK CONVINCER 1984 1986 1986 1993 2003 2004 2008 2008 2009 2009 2007 2008 Egyptian Drilling Company (3 jack-ups) SENUSRET KAMOSE - ZOSER Cantilevered drilling Barges (4) MAERSK RIG 61 MAERSK RIG 62 MAERSK PATHFINDER MAERSK PIONEER Semi-submersible (4) MAERSK EXPLORER MÆRSK DEVELOPER MÆRSK DISCOVERER DEEPWATER SEMI 3 1994 1995 1998 1998 2003 2009 2009 2010 Management (2 Semi-submersible) KAN TAN IV NAN HAI VI

Fleet location North Sea 7 Harsh envir. jack-ups GoM 1 Harsh envir. jack-up, mng 1 Deepwater semi-subs Egypt Venezuela 10 Drilling barges 1 Harsh envir. jack-up Egypt (EDC) 3 Jack-ups 39 Land rigs 22 Workover rigs Caspian Sea 1 Semi-submersible UAE 1 High efficiency jack-up Brunei 2 375 ft jack-up Singapore (under construction) 1 High efficiency jack-up 2 Deepwater semi-subs Australia 2 semi-subs - mng

Causes of 226 Jack Up accidents over the 1979/1988 period Operators World-wide 60 50 40 30 20 10 0 Soil Tow Blow-out/fire Collision Design Storm Other Fatigue Jacking War

Jack-up Accident Statistics 2000-2006 15 14 13 12 11 10 9 8 7 6 5 4 3 2 1 0 Hurricane Punch-through Blow-out Structural failure Jacking system failure Leg structural damage Fire Collision Scour Other fundation failiures

Transport of Drilling Rigs Dry Tow Wet Tow Heavylift Tugs

Dry Tow

WET TOW Higher Risk involved Higher Insurance Premium MINIMAL FREEBOARD MUST ALLOW FOR SUITABLE Weather Windows

Offloading Semi Submersible off Congo

Punch-Through

Punch Through!!! (Or Fast Rapid Penetration)

Punch Through The Noble David Tinsley experienced the "punch-through" while conducting preloading operations on May 8 2009 All three legs have penetrated the sea floor off the coast of Qatar, causing severe damage to the jack-up and its legs.

Punch Through Vantage Drilling Rig, Sapphire Driller experiences a bow leg run / punch through in the early morning hours (03:00) on 30/Oct/2009. It appears a zero air gap preload was being conducted, which most likely minimized potential structure failure

MAERSK VICTORY Punch-through 1997 Adelaide, Australia

RPD = Rack Phase Difference - MIGHT RESULT IN A BOW-LEGGED APPEARANCE

Maersk Drilling Towmasters Maersk Drilling employs presently nine (9) Towmasters and three (3) Towmaster trainees They have a total Towmaster Experience of 81 years where they have been in charge of more than 1700 Rig Moves Maersk Drilling are moving their own and management units with a Towmaster in charge of rig and rig move operations. The Towmaster is taking over the responsibilities of the OIM

Maersk Drilling Towmasters RESPONSIBILITIES: Safety of Personnel and Unit Environment Assure Sea-worthy Condition Equipment in Safe Condition Equipment Operational Permit To Work System Daily Report to Shore Base and Towmasters Department

Maersk Drilling Towmasters WORK SCOPE INCLUDES: Prepare rigmove papers prior to rigmove Person in Charge (OIM) Unit's Stability Parameters Verify Weather Information Manning Requirements Maintain Accurate Event Log Prepare Rig Move Report Inspect Attending Vessels Raise Revision Request

Maersk Drilling Towmasters QUALIFICATIONS REQUIREMENTS: Master Mariner, Unlimited Incl. GMDSS, ARPA and First Aid Master Mariner, Liberia and Panama License Min. 8 years experience in Maritime Positions incl. 2 years offshore on MOU or AHT Proficient with Jacking Systems Proficient with Mooring Systems Knowledge of Safety Management System, Contingency Manual and Health and Safety Policy in force on board the MOU Valid Safety Training, Medical Certificates Participated in Geotechnical Assessments Successfully Completed Rig Move Courses

Training Programme for Towmaster Trainees # Qualifications / Curses Period Place 1 Jacking Simulator 5 days USA 2 Soil Evaluation /Special 2 days DGI, Lyngby 3 Offshore Meteorology 3 days DMI 4 Anchor Handling Simulator 5 days MTC, Svendborg 5 ARPA 3½ days Denmark 6 GMDSS 10 days Denmark 7 H 2 S, basic 1 day Denmark 8 First Aid 5 days Denmark 9 Management Seminar 5 days Denmark 10 Safety, world wide 5 days Esbjerg,MTC, NL 11 Rig Crew Resource 5 days MTC 12 Liberia/Panama Licences - - 13 DK/UK / Norway Medical - Lægekontoret 14 Towmaster assistant, 12 18 mdr All rig types approx. 20 rigmoves 15 Office, familiarization 3 weeks Office København 16 Towmaster Manual 2 days Incl. in pt. 15 17 Anchorhandler, onboard 2-4 weeks North Sea Recruiting from OIM, Barge Engineers and or AHTS Captains, Chief Officers Typical training period: 12 to 18 months - pending experiences 18 PC Driving Licence, - -

Various Towmaster assignments More than 1600 Rig Moves (start 1975) N kossa II Installation Curlew Towout + Installation North Sea Producer Towout + Installation Anasuria Towout + Installation Schiehallion Towout + Installation Varg Towout + Installation Draugden Troll Hibernia Harding Aasgaard, Towout & Installation Snoore B Maureen A ALC Sakhalin, Tow out of two Gravity Base Structures Towout and Installation of Pipe Lines Safety Case Preparations Marine Advisor for various Customers Planning and preparation of Procedures FPSO Sevan Hummingbird Towout + Installation FPSO Maersk Ngujima-Yin Installation

Tug Coordinator / Master TROLL A 2 GBS/Gas 1.000.000 Tons Displacement HIBERNIA - PRODUCTION PLATFORM TOW-OUT (78 meter draft) TROLL A - PRODUCTION PLATFORM TOW-OUT (30 meter draft) DRAUGEN - PRODUCTION PLATFORM TOW-OUT (228 meter draft)

Who is this Person? Who will ensure and be responsible for: - All Requirements - Procedures: Safety / Operational -Rules - Policies - Systems - Good Seamanship ARE FOLLOWED, COMPLIED WITH AND OBSERVED?

Rig Move Flow Chart / Towmaster Manual

Site Assessments Input/Output ENVIRONMENTAL DATA E.G.: - 100-Year Wind & Wave Data - 10-Year Current Data - Expected Installation Period, Directional or Seasonal

Site Assessments Output

Geotechnical Analyses Input/Output INPUT: Soil Data Soil Data should fulfil Requirements stated in the Towmaster Manual Unknown Areas / Locations will require Core Samples / Soil Data from below each spud can OUTPUT: Penetration Curves Predicted Spud Can Penetration into the Soil for Loads increasing to a certain Level FINAL PRELOAD

More Penetration Curves

General Engineering Location Evaluation LOCATION EVALUATION CONSITS OF: 1. Site Assessments 2. Geotechnical Analyses 3. Recommendations from Engineering to Towmaster incl. Preloading

Rig Move Flow Chart End of Engineering s Involvement when the Location Evaluation is issued Towmaster s Department Takes Over SOW / RMP

Warranty Certificate of Acceptance

MD Management Certificate of Acceptance COA Issued by Warranty Surveyor MD S Requirements signed by Warranty Surveyor Penetrations Analyses Engineering Assessments Location Evaluation issued by MD Engineering Seabed Survey Towmaster s Letter of Instruction Operation Plan: SOW, Passage Plan Copies of Sea Charts Other Relevant Drawings

CEO Certificate of Acceptance

Ready to commence the Move Go Ahead received ALL Papers signed RIG MOVE ACCEPTED BY MD CEO Tow Team Towmaster(s) & Warranty Surveyor sign on MODU Inspection / Approval of MODU Seaworthiness, Operational, Certificates, Manning (Down!) MODU signs over from Person in Charge (OIM) to Towmaster Overall Responsible Weather Forecasts (2 Independent) available Suitable Weather Window(s) indentified Departure / Transit / Arrival When Installed MODU signs back to Person in Charge (OIM)

Briefing / Approval of Vessels Vessels are normally provided by Operator / Client All Vessels shall be fit for the Purposed and Intended Operation All Vessels must be in Compliance with the Standards stipulated in COA, SOW, Operation Manual and by Attending Warranty Surveyor - Towing/AH Equipment, Manning, Bunkers All Certificates must be Valid General Aim: All General Operations shall be in Agreements with the NWEA GUIDELINES

Bollard Pull Required

Arrival & Installation of a Jack-Up

Arrival & Installation of a Jack-Up Pin Rig in Stand-off loc, approx 50 100 m to Final Run Anchors / utilization of DP Classed AHTV Re-connect Tugs 1. Winch Rig to Final Pos assisted by Tugs 2. Walk Rig to Final Pos assisted by Tugs Pin Rig in Final Final Position approved by Client Commence elevating Hull / Preloading Disconnect Tugs Recover Anchors Preload: Site Specific. Shallow / Deep Penetrations Punch Through / Rapid Penetrations Hold / Dump Preload Water Elevate Hull to Final Air Gap

Positioning of a Rig VERY CLOSE (Minus 1 meter) at a Platform with Pipelines Close to and between Spud Cans REQUIRES A STEADY HAND Fine tunings!

Spud Cans The Shoes of the Rig Area: 380 m 2 Diameter: 22 m Equivalent Shoe size (EU): 33.000!!!

Risk of Rapid Penetrations / Punch Through Minimum Air Gap Starting with hull at draft Preload as Close as Possible to Sea Level - Gain Buoyancy in Case of Rapid Penetrations - Weather and Sea State -Tide Preload one Leg at a time - Reducing overall Weight of the Rig and by then minimising Potential Structure Damages Close monitoring of the Initial Penetrations versus Seabed Reactions - First Indication of which Penetration Curve Spud Can follows: Lower or Upper Bound or?

Departure Freeing Legs Legs and Spud Cans are stuck in the Soil due to a Combination of Vacuum underneath Spud Can and Soil on top of Spud Can Jetting below Spud Cans will break down the vacuum and start filling up the Gap generated by Legs creeping upwards Hull Buoyancy is overcoming the Weight of Soil on top of Spud Cans

Freeing Legs Pull + Jet

Spud Can, seen from below Size, each of three: 200 380 m² NB! Tip & Jetting Nozzles

Freeing Legs PULL (No Jetting)

Thank you for your staying power STILL TIME FOR QUESTIONS!!!