Disputes and Claims. 3 Processes Dispute Resolution and Administrative Claims Process



Similar documents
SECTION 1 GENERAL REQUIREMENTS

Structures Construction Pre-Work Checklist PRE-WORK SHEET FOR PROJECT MANAGERS

~iffiui ~ Bridge Condition Survey. Inspection Date: 21 May 2003 District: San Angelo County: Tom Green Highway:

MEMORANDUM West Swann Avenue, Suite 225 Tampa, Florida Phone (813) Fax (813)

EXHIBIT A SCOPE OF SERVICES WATER SERVICE REPLACEMENT PROJECT. BROWARD OPERATIONS CENTER 5548 NW 9 th AVENUE FORT LAUDERDALE, FLORIDA 33309

Rehabilitation of the Red Bank Road Bridge over Hoover Reservoir. Presented By: Doug Stachler, P.E.

Value of Instrumentation Systems and Real-Time Monitoring: An Owner s Perspective

Paving Capitalization Work Categories and Treatments

SECTION REMOVAL OR ABANDONMENT OF EXISTING UTILITIES AND UNDERGROUND STRUCTURES. 1. Trench excavation, backfill, and compaction; Section

Successful Approach to the Repair of Reinforced Concrete Support Structures in Delayed Coking Units

CONCRETE REPAIR GUIDELINES. Concrete repairs can be broken down into four basic types, plus special repairs and planing.

2015 ODOT Bridge Design Conference May 12, DeJong Rd Bridge High- Seismic Zone Case Study: Bridge Rehab vs. Replacement.

IH-635 MANAGED LANES PROJECT, SEG. 3.2

Contract Administration

SECTION III-06 Surfacing Page 1 Revised 3/2/10. See the DESIGN GUIDELINES in Section I-06 for requirements for cross slope of the roadway.

Safe & Sound Bridge Terminology

ALBEMARLE COUNTY SERVICE AUTHORITY

CONSTRUCTION PERMIT REQUIREMENTS

September 1, 2003 CONCRETE MANUAL CONCRETE PAVEMENT REHABILITATION

Failing Coastal Wood Infrastructure on the Great Lakes

SECTION POINT REPAIRS TO SANITARY SEWERS. A. Repairs to existing sewer lines by replacing short lengths of failed pipe.

C. Section TESTING LABORATORY SERVICE.

Elevating Your House. Introduction CHAPTER 5

1 OF 7. there will be few "surprises" as the work progresses.

WILDCAT CANYON ROAD SPECIFICATION NO SLIDE REPAIR BIDDER'S PROPOSAL (continued)

CAPPELEN MEMORIAL BRIDGE REHABILITATION

High Strain Dynamic Load Testing of Drilled Shafts

Chapter 3 Pre-Installation, Foundations and Piers

Nevada DOT Cold In-Place Recycling Federal Highway Administration National Review Close out meeting, August 25, 2005

Emergency repair of Bridge B421

The unit costs are based on the trend line of the 3 low bids for the average quantity.

San Antonio Water System Standard Specifications for Construction ITEM NO. 854 SANITARY SEWER LATERALS

Project Information. New Hope - Lambertville Toll Bridge - Pavement Rehabilitation & Approach Bridges Repairs -

Contractor of the Year

Developing Critical Path Method Scheduling (CPM)

STAYFLEX CORROSION CONTROL AND THERMAL INSULATION SYSTEM

BUSINESS DEVELOPMENT INITIATIVE SMALL BUSINESS PROGRAM GUIDANCE FOR RESERVING CONTRACTS

APPLICATION FOR DEMOLITION & RIGHT-OF OF-WAY PERMIT

GLOSSARY OF TERMINOLOGY

SECTION SHEETING, SHORING AND BRACING

Preservation, Repair and Rehabilitation of Concrete Bridges, Pavements and Tunnels in Virginia

738-B-297 POLYMERIC CONCRETE BRIDGE DECK OVERLAY. (Adopted )

GARDEN CITY SKYWAY SUBSTRUCTURE REHABILITATION

TABLE OF CONTENTS. Manhole, Frame, and Cover Installation (includes Drop Manhole) Additional Manhole Depth

1.3.2 Method of construction and restoration of existing water service connections. This shall include:

A. This Section includes rubberized asphalt sheet membrane waterproofing systems.

Storm Sewer Trenchless Upgrade Alternatives and Recommendations

ATLAS RESISTANCE Pier Foundation Systems

FLOOD DAMAGE PREVENTION ORDINANCE

BUSINESS DEVELOPMENT INITIATIVE SMALL BUSINESS PROGRAM GUIDANCE FOR RESERVING CONTRACTS

Pavement Management Implementation: Success Stories for Maryland Counties

Hartsfield-Jackson Atlanta International Airport s

Baton Rouge Foundation Repair

Photo 2. View showing flour mill, machine shed, veranda and saw mill + storage shed.

TECHNICAL SPECIFICATION SERIES 8000 PRECAST CONCRETE

RESOLVING DISPUTES WITH YOUR CONTRACTOR

AWWA Small Systems Pipe Repair Checklist, as published in July 2008 Opflow Question of the Month

Challenging Skew: Higgins Road Steel I-Girder Bridge over I-90 OTEC October 27, 2015 Session 26

2006 ICRI Baltimore Washington Chapter Outstanding Repair Project Award George Washington University Ross Hall Façade Restoration

WSDOT Bridge Elements

5 ALTERNATIVE SOLUTIONS AND EVALUATION

REQUEST FOR QUALIFICATIONS FROM FOUNDATION REPAIR CONTRACTORS BROOMFIELD DEPOT FOUNDATION REHABILITATION PROJECT

City of Hilshire Village Pine Creek Ln Reconstruction

DIVISION 4300 STORM DRAINAGE

INCREASE OF DURABILITY AND LIFETIME OF EXISTING BRIDGES. PIARC TC 4.4 EXPERIENCE.

Structural Audit of Buildings

TOWN of NEW BOSTON. Bid Package. Refurbishment and Upgrade of Basement of the New Boston Town Hall

Permit No. Permit Fee: $ Permit Expires (D+90 days): Business Name: Applicants Name: Telephone Number: Address:

Public Works Operations Manual Standard Operating Procedures for Water and Sewer WS-A412 Water Connection Repair

Repair and Strengthening of Bridge Substructures

MHD BRIDGE SECTION WEIGHTED AVERAGE UNIT PRICES GUIDELINES FOR THE USE OF THE WEIGHTED AVERAGE UNIT PRICE TABULATION SHEETS

WATERPROOFING FOR CONCRETE STRUCTURES

SECTION SITE PREPARATION

VOLUME V GUIDELINES FOR DESIGN CONSULTANT TABLE OF CONTENTS APPENDIX B: MASTER CONSTRUCTION SPECIFICATIONS AND PREPARATION GUIDE, DIVISIONS 0-10

Asphaltic Wedge Paving

CITY OF SAN ANTONIO. Issued By: Transportation and Capital Improvements Date Issued: February 10, 2016 ID NO.:

DRAFT MAINTAINING HOUSTON S STREETS REPAIR, REHABILITATION, RECONSTRUCTION. Using the Full Range of Tools for a Challenging Job

MATERIALS: The Contractor shall provide the latest version of Primavera SureTrak software.

EAST LYME HIGH SCHOOL

CCU Engineering Specifications. Section PRECAST CONCRETE PRODUCTS

Pro-Lift Steel Pile Foundation Repair

DUDERSTADT FOUNDATION & CONSTRUCTION, LLC.

The Bond Release Process for New Subdivision Developments: An Overview for Homeowners Associations DRAFT Revised

High Density Polyethylene Liners for Rehabilitation of Corroded Pipelines

QUESTIONS & ANSWERS LOG

SCHEMATIC AND PROJECT BUDGET APPROVAL EAST CAMPUS NURSING EDUCATION AND CLASSROOM

Section 402. STORM SEWERS

LEGACY REPORT ER ICC Evaluation Service, Inc. Reissued November 1, Legacy report on the 1997 Uniform Building Code

Attachment 5 Electrical Engineering

Transcription:

Disputes and Claims 3 Processes Dispute Resolution and Administrative Claims Process Default Process C&MS 108.02 Partnering OR PN 108 -Dispute Review Board (DRB) Considered for use on projects over $20 M and/or of a highly technical nature OR PN 109 Dispute Resolution Advisor (DRA) Considered for use on projects between $5M & $20M

Dispute Resolution and Administrative Claims Process STEP 1. On-Site Determination Meeting Project Personnel STEP 2. District Dispute Resolution Committee (DDRC) DDRC District Construction Administrator (DCA) Planning & Engineering Administrator (P&EA) District Deputy Director (DDD)

Dispute Resolution and Administrative Claims Process STEP 3. Director s Claims Board Notice of Intent to File a Claim Certified Claim (Notarized) DCB DD Construction DD Engineering DCA of another District

Claims Resolution History Year Total # of Claims # Heard by DCB # Heard by ADR # Dropped or Settled 2008 21 14 2 7 2009 25 17 3 5 2010 18 13 0 5 2011 11 4 0 7 2012 12 7 1 4 2013 12 8 0 4

Claims Resolution History DISTRICT PROJECT DESCRIPTION OUTCOME 7 1060(09) Qty. Disagreement (304 Base & Asphalt Surface Course) Court of Claims 9 0251(12) Casing for Wet Holes DCB Accepted 12 1041(10) Deficient Deck Grid Installation DCB Accepted 8 0233(12) Centerline Markings DCB Accepted 6 0341(11) Shop Applied Inorganic Zinc Primer DCB Accepted 6 0541(12) SWPPP Costs Pending 12 0249(12) Kelly Bar DCB Accepted 7 0512(12) Column Repair Pending 12 3012(10) Utility Delay/ Reinforcing Steel on Beam Flanges District-Resolved 8 0468(12) Surface Preparation of Bridge Deck District-Resolved 2 0168(11) Unsound Patches District-Resolved 10 0626(11) Readjusting Ph. Deck/ Temp. Pavement Final Calcs. District-Resolved

2013 CLAIMS Demand vs. Award DEMAND AWARD % TOTAL STEP 3 CLAIMS $568,033.41 $80,791.41 14.2

DISTRICT 2 DISPUTE RESOLUTION ODOT Project 11-0168 SR -2 Edison Bay Bridge Ottawa/ Erie Co.

DISTRICT 2 DISPUTE RESOLUTION ODOT Project 11-0168 SR -2 Edison Bay Bridge Ottawa/ Erie Co.

Item 519: Number of Square Feet of exposed surface of all completed patches.

Item 519.irrespective of the depth or thickness of the patch

Final Acceptance Inspection

Step 1 ODOT Patches do not meet specifications-repair/replace them. Contractor We disagree, would like to move to Step 2

Step 2 Contractor Patches being variable depthlends to differences in sounding Sounding with claw hammer is not scientific method to determine patch quality Area around Galvanic Anodes may sound different due to differences in patch material

Step 2 Cont d. Vibration from live overhead traffic may have caused bonding issues 61% of all work was performed by force account, but ODOT never requested any changes in methodology during the force account work

Step 2 Cont d All patches were sounded at the times the forms were removed ODOT Bridge Manual does not recommend patching spalls over traffic or other safety sensitive areas because of potential debondingcould create a hazard

Step 2 ODOT Does not meet specifications Contractor never sounded patches Worried that patches may fall at some point injuring boaters/fisherman

Step 3 Preparation Could not verify original plan design Difference of opinion as to original design Difference of opinion of a repair plan Potential repair-fiber Wrap -requires experience Contractor wanted to settle outstanding payment issues and close out project District agreed to perform any future fixes under a new contract

Settlement Split the cost of the Pull-Off Test 50-50 Approximately $10,000 ea. Split the 2-inch Depth issue 50-50 Approximately $ 4,000.00 ea. Contractor agreed to refund $40,000 to the project ODOT agree to modify the contractors C-95 scores related to the patch work Prime Contractor agree to waive his 5% mark-up on the Settlement items.

Best Practices All parties wished they would ve paid more attention to thoroughly sounding the original patches as they were completed in the first season. Clarity of plan notes and what s included in the bid item for payment

Thank You

DISTRICT 10 DISPUTE RESOLUTION Project: 11-0626 (HOC 56 16.45) District Step 2 Dispute Resolution 10-110626-01 10-110626-02

Claim 10-110626-01 Pile Encasement Background: This project included the replacement of a three span continuous slab on capped pile abutments and piers. To protect against scour, the district Bridge Engineer and Designers prefer to encase new piles with polyethylene pipe and Class C concrete, and tried to express this by inserting a plan note. The Dispute involves whether the Contractor has the option to galvanize the piles in lieu of the encasement.

Claim 10-110626-01 Pile Encasement

Claim 10-110626-01 Pile Encasement Contractor s Position: The contractor contended that the Standard Drawing CPP-1-08 called out on the plans allows the option of galvanizing or concrete encasing the piles. The contractor also pointed out that the plan note mentioned galvanizing in it. In the Contractor s opinion, the note reiterates the option of galvanizing in lieu of encasement.

Claim 10-110626-01 Pile Encasement District s Position: The District contended that the note does instruct the contractor to encase the piles. The District also contended that this same scenario happened on a previous project where the Area Engineer told the contractor in the future it was always going to be the District s preference to encase the piles. The District instructed CGCC to encase the piles after they were ordered with galvanizing.

Claim 10-110626-01 Pile Encasement Findings: The DDRC agreed that there is some confusion in the note shown in the plans because it included language taken directly from the Standard Drawing which includes how galvanizing will be paid for. The DDRC awarded Complete General Construction Company $13,522.11. The costs were not in dispute.

Claim 10-110626-01 Pile Encasement

Claim 10-110626-02 Downtime for H-Pile Decision Background: During construction of a three span continuous slab, the contractor damaged an HP10 x 42 pile while trying to achieve refusal, which the Department describes as penetrating bedrock for several inches as to a minimum resistance of 20 blows per inch. When the contractor tried to achieve this, the top of the piles began to deform. There was some downtime while the Department made a decision regarding the blow count, and remaining piles.

Claim 10-110626-02 Downtime for H-Pile Decision Contractor s Position: The contractor contended that it lost work time waiting on a decision from the Department to continue driving piling after piles were damaged. During the pile driving operation the Department stopped work after the first pile became damaged before reaching the required 20 blows per inch. There was some confusion as to whether the Department actually allowed the contractor to reduce the required blows, and a call was made to Central Office to see if that was an option. It took approximately three hours to get an answer back to the project. The contractor requested compensation for down time during this three hours of $970.71.

Claim 10-110626-02 Downtime for H-Pile Decision District s Position: The district believed by spec that it was up to the contractor to size the hammer to appropriately drive the piling to refusal without damage. It was the belief of the district that the hammer used was too large for the relatively small piles. The district also took the position that by spec the contractor is required to stop the pile driving operation when damage occurs.

Claim 10-110626-02 Downtime for H-Pile Decision Findings: The DDRC found that the project was correct when it stopped work after seeing the damage to the pile, and that the district was diligent in the response to help come up with a solution once the damage occurred. The DDRC ruled that the District did not owe damages in this case, Complete General accepted the ruling.

DISTRICT 12 DISPUTE RESOLUTION District 12 Presenters: Pat McCafferty, Area Engineer Greg Kronstain, District Construction Administrator

Step One Dispute Resolution Project - 12-0630 Contractor -The Great Lakes Construction Company. Project Details Bridge Reconstruction on 3 Structures over RTA and NS tracks. Active project that is 55% complete.

Step One Dispute Resolution

Step One Dispute Resolution Contractor s Disputes 1. Daily movement of concrete barrier wall 2. Flagging traffic into parking lot 3. Noise ordinance shutdown 4. RTA delay de-energizing catenary lines 5. RTA delay reattaching catenary lines

Step One Dispute Resolution for Barrier Wall Relocation and Flagging Costs Plan Location of Barrier Wall

Step One Dispute Resolution for Barrier Wall Relocation and Flagging Costs Contractor s Position - Excavation work required daily movement of barrier wall - Flagger required to maintain access to church parking lot

Step One Dispute Resolution for Barrier Wall Relocation and Flagging Costs Plan Excavation Limits

Step One Dispute Resolution for Barrier Wall Relocation and Flagging Costs Daily Movement of Barrier Wall w/ Flagger to Maintain Access to Church Parking Lot.

Step One Dispute Resolution for Barrier Wall Relocation and Flagging Costs Project Engineer s Position - Sheeting required to complete work as shown on plans and to maintain access to parking lot

Step One Dispute Resolution for Barrier Wall Relocation and Flagging Costs

Step One Dispute Resolution for Barrier Wall Relocation and Flagging Costs Area Engineer looked at the plans and went to site and talk to both parties

Step One Dispute Resolution for Barrier Wall Relocation and Flagging Costs D12 s Decision Sheeting not required. ODOT agreed to pay for one remobilizing of barrier wall. ODOT agreed to pay for additional asphalt to widen apron. ODOT agreed to pay for additional concrete base replacement. ODOT agreed to move waterline to avoid relocated barrier and additional pavement removal

Step One Dispute Resolution for Barrier Wall Relocation and Flagging Costs Placed Temporary Asphalt to Widen Apron

Step One Dispute Resolution for Barrier Wall Relocation and Flagging Costs New Concrete Pavement Required under Asphalt

Step One Dispute Resolution for Barrier Wall Relocation and Flagging Costs Waterline moved to stay within relocated barrier wall.

Step One Dispute Resolution for Noise Ordinance Contractor s Dispute 3. Noise ordinance shutdown

Step One Dispute Resolution for Contractor s Position Noise Ordinance - City notified contractor after the night crew had started to work. - Incurred extra costs leaving the project before putting in a full night of work.

Step One Dispute Resolution for Noise Ordinance Project Engineer s Position - Plan note did not allow night work.

Step One Dispute Resolution for Noise Ordinance Area Engineer looked at the plans and talked on the phone to both parties

Step One Dispute Resolution for Noise Ordinance D12 s Decision - Request for compensation denied. - Future night work would require a noise waiver from the City

Step One Dispute Resolution for RTA Delays (During Weekend Shutdown) Contractor s Dispute 4. RTA delay de-energizing catenary lines 5. RTA delay reattaching catenary lines

Step One Dispute Resolution for RTA Delays (During Weekend Shutdown) Contractor s Position - Incurred extra costs waiting for RTA to turn off the power to the catenary lines. - Incurred extra costs while RTA decided if the temporary protective structure (supporting the catenary lines) could be removed.

Step One Dispute Resolution for RTA Delays (During Weekend Shutdown) Project Engineer s Position - RTA s Special Provisions do not guarantee outages or the time they will occur.

Step One Dispute Resolution for RTA Delays (During Weekend Shutdown) Area Engineer looked at the plans, special provisions, and talked on the phone to both parties.

Step One Dispute Resolution for RTA Delays (During Weekend Shutdown) D12 s Decision - Request for compensation denied for RTA s delay to turn off the power to the catenaries, but compensation granted for the delay while waiting for the RTA decision of the canopy removal.

Dispute Resolution District 12- Project 10-1041

DisputeResolution Resolution of Disp. 12-101041-07, prior to Step 2 Project- 10-1041, Willow Avenue Lift Bridge Location-City of Cleveland Contractor- The Ruhlin Company Sub-Contractor- Perram Electric Project Bid Cost- $3.9M

Willow Avenue Lift Bridge

Willow Avenue Lift Bridge

DisputeResolution City of Cleveland project The project work- Replacing the lift span deck and stringers Rehabilitation of the electrical and mechanical systems Other related bridge repairs

DisputeResolution Dispute Description-Damage to the Automatic Transfer Switch (ATS) occurred during the rehabilitation of the electrical system. The Contractor agreed to replace the ATS at their cost in the original location. Estimated cost $9927. However, there was a differing interpretation of National Electrical Code (NEC) regarding the installation of this new equipment

Dispute Resolution Existing ATS New ATS

DisputeResolution Contractor Position- Replacing ATS in existing location is in compliance with C&MS 107.10 -Would restore property damage to a condition similar or equal to that existing before the damage - Would meet requirements of NEC 110.26

DisputeResolution National Electrical Code- Article 110.26 Space About Electrical Equipment Requires sufficient access and working space to be provided and maintained to permit ready and safe operation and maintenance for panels. Access was only available by ladder

DisputeResolution Electrical Schematic

DisputeResolution Contractor was directed to relocate ATS No agreement on NEC requirement ODOT agreed that the project did receive a considerable betterment

DisputeResolution New Location Actual Cost = $26,177 w/out markups = $21,605 Existing Location Est d. Cost = $9,927 w/out markups = $8,461 Difference = $13,144 labor diff. markup = $1,214 Total settlement = $14,358

DisputeResolution Summary- This settlement is an example of: Good communication between the Contractor and ODOT Working together for a resolution