LEReC Engineering. J. Tuozzolo, C-AD Chief Mechanical Engineer (LEReC Project Engineer)

Similar documents
Large Systems Commissioning

10 Project Costs and Schedule

Linac RF Commissioning with the SNS HPRF Systems

The commissioning of the LHC: first the technical systems, then the commissioning with beam

Status of the Diamond Storage Ring RF Systems. Morten Jensen on behalf of Diamond Storage Ring RF Group

Development of a Low Frequency Superconducting RF Electron Gun. September 2010

Activities at the University of Frankfurt (IAP)

THE ALIGNMENT STRATEGY FOR THE SPIRAL2 SUPERCONDUCTING LINAC CRYOMODULES

Status of Radiation Safety System at

Design and Fabrication of a Power Supply House in Brazil

Brookhaven Magnet Division - Nuclear Physics Program Support Activities

Reliability and Availability Aspects of. the IPHI Project

Institute of Accelerator Technologies of Ankara University and TARLA Facility

The STAR Project: Southern european Thomson source for Applied Research

FLS 2010 Storage Ring Working Group Session 4: Future ring technology and design issues

FCC JGU WBS_v0034.xlsm

K O M A C. Beam Commissioning of 100-MeV KOMAC Linac. Korea Multi-purpose Accelerator Complex 양 성 자 가 속 기 연 구 센 터

Final 6MSD Weekly Scheduling Meeting. 1:30, MCC Conference Room

BEPC UPGRADES AND TAU-CHARM FACTORY DESIGN

MSU View of RIA R&D Priorities. R.C. York August 2003

Peter C. Vander Arend Cryogenic Consultants, Inc. Allentown, Pennsylvania

FLASH Commissioning and Startup

OVERVIEW OF PROTON DRIVERS FOR NEUTRINO SUPER BEAMS AND NEUTRINO FACTORIES*

Catherine LeCocq, Robert Ruland. February, 2008

Status Overview The Australian Synchrotron. Steven Banks Control Systems Group

FIVE PROJECTS OF HIGH RF POWER INPUT COUPLERS & WINDOWS FOR SRF ACCELERATORS*

Projects and R&D activities

A. Martinez, A. L. Klebaner, J. C. Theilacker, B. D. DeGraff, M. White and G. S. Johnson

Industrial Involvement in the Construction of Synchrotron Light Sources

DIRECTIONAL FIBER OPTIC POWER MONITORS (TAPS/PHOTODIODES)

HVAC air curtains. Type InduAir

Cryogenic Current Comparator Status at GSI/FAIR -

Lasers Design and Laser Systems

BEAM OPERATION OF THE PAL-XFEL INJECTOR TEST FACILITY

RF SYSTEM FOR VEPP-5 DAMPING RING

source at CERN G.McMonagle AB/RF

Project X: A multi-mw Proton Source at Fermilab. Steve Holmes Extreme Beam Lecture Series

3D Conjugate Heat Transfer Analysis of the Next Generation Inner Reflector Plug for the Spallation Neutron Source

Lecture 7 Thermal Insulation & Cryostat Basics. J. G. Weisend II

Status of the SOLEIL project Commissioning from Linac to beamlines

Thermal insulation. Don t be afraid of low temperatures. Institute for Technical Physics Holger Neumann

Mechanical Operation and Maintenance Vacuum Group

Systems, Inc. Energy Advanced

Cathode Ray Tube. Introduction. Functional principle

Status of EVOLVE boiling flow regime experiments

Figure 1: Lattice drawing for the APS storage ring.

Zero Degree Extraction using an Electrostatic Separator

LHC MACHINE PROTECTION

Lynx Broadband Installation Manual for Residential Packages with a 20 db Amp Quick Start Guide (first two pages)

Results: Low current ( ) Worst case: 800 MHz, GeV, 4 turns Energy oscillation amplitude 154 MeV, where

Proceedings of the Sixth Workshop on RF Superconductivity, CEBAF, Newport News, Virginia, USA

MECHANICAL AND THERMAL ANALYSES OF THE CABLE/ STRAND STRAIN TEST FIXTURE

Heat. Investigating the function of the expansion valve of the heat pump. LD Physics Leaflets P Thermodynamic cycle Heat pump

Informe Técnico IT - CDT

Development of Radiation Resistant Quadrupoles Based on High Temperature Superconductors for the Fragment Separator

1. INTRODUCTION. There are different frequency bans according to the range of frequencies shown: 1.1 Electromagnetic Spectrum

CABLE DESIGN AND RELATED ISSUES IN A FAST-CYCLING SUPERCONDUCTING MAGNETS

R&D Support Services. Ad Astra Rocket Company

Cleaning Methods of SRF Power Couplers. Mircea Stirbet

Sulfur Tail Gas Thermal Oxidizer Systems By Peter Pickard

The APS Machine Protection System (MPS) *

SUPERCONDUCTING CABLE SYSTEMS

THE TAIWAN LIGHT SOURCE AND SUPERCONDUCTING CAVITY

Firsts. A Year of. for US Delivery and Fabrication. December First Nuclear Grade Hardware Delivered

1.1 SYSTEM DESCRIPTION.1 Data system includes data outlets and wiring for office and school applications.

Buildings Construction Procurement Strategy

Development of High Stability Supports for NSLS-II RF BPMS

L.I. Chubraeva. Corr. Member of RAS

1/9/2013. Terminology Calculating Heat Transfer Code Requirements Design Examples and Sustainability

Status of the HOM Damped Cavity for the Willy Wien Ring

Flow distribution and turbulent heat transfer in a hexagonal rod bundle experiment

Bulk Storage the OIL SAFE Way. Three System Types. Establish Best Practice

HERZ-Thermal Actuators

The D-Wave 2X Quantum Computer Technology Overview

AMSC s Superconductor Cable Technologies for Electric Utilities

SHORT STRAIGHT SECTION TYPES IN THE MATCHING SECTIONS

Facilities Perspectives

Materials. Estimating Steel. Players. Materials. Shop Drawings. Detailing Process. Standard shapes. Fabricated members, Built-up sections

Physics 42 Lab 4 Fall 2012 Cathode Ray Tube (CRT)

THE TESLA TEST FACILITY AS A PROTOTYPE FOR THE GLOBAL ACCELERATOR NETWORK

Should SMTF Include RIA?

Element D Services Plumbing

The BESSY HOM Damped Cavity with Ferrite Absorbers. Review of prototype cavity test results, taperedwaveguidesvshomogenouswaveguides

Convection Ovens. BX Classic. Models BX4 / FG 189C, BX / FG 158C, BX10 / FG 180C. Operator's Manual

DEVELOPMENT OF THE SWISSFEL UNDULATOR BPM SYSTEM

PRO 5000 CPE 1D Quick Installation Guide

SECTION PACKAGED ROOFTOP AIR CONDITIONING UNITS NON-CUSTOM

HIGH-CAPACITY HIGH TEMPERATURE SUPERCONDUCTING POWER CABLES

Incubator with mechanical convection

understanding medium frequency induction melting furnace and its components

SpectraTec II. Polarized Multi-Laser Source BLUE SKY RESEARCH WAVELENGTHS. The SpectraTec II

Lab 4: Magnetic Force on Electrons

LIU CABLING & OPTICAL FIBRES STRATEGY. Georgi Minchev Georgiev EN-EL-CF

Tune and Chromaticity Tracking in the Tevatron. C.Y. Tan 09 May 2006

ADDING AN ELECTRIC AUXILIARY FAN TO RADIATOR STACK ON 03 ALPINE COACH

Towards large dynamic range beam diagnostics and beam dynamics studies. Pavel Evtushenko

Possible Upgrades and New Design. F. Velotti and B. Goddard

Progress status of EMR Geneva

Consideration of a high-capacity foil cable:

Transcription:

LEReC Engineering J. Tuozzolo, C-AD Chief Mechanical Engineer (LEReC Project Engineer) Layout, Infrastructure, and Engineering IP 2:00 location - available. Engineering interface issues. Engineering support team planning Baseline schedule.

Location, Location, Location RHIC 2:00 IP, BRAHMS and AnDY out, CeC to be completed 2016 Tunnel w/crane Control Room/Instrumentation w/ac Laser Room w/ac (New) Utility Building Water/Cryogenics Cryogenic Recovery System (New) Power Supply Building w/ac Site Power 1002 Transformer Yard

Location, Location, Location RHIC 2:00 IP Large open experimental area with crane Good access, removable shield door. Available space in both ring support buildings. Existing utilities, communication, and cable trays. Fire protection systems installed. Cryogenic tap installed. Utility Building Water/Cryogenics Tunnel w/crane Site Power 1002 transformer yard Easy Tunnel Access Power Supply Building w/ac Water Systems

CeC PoP Preparation Building preparation completed for CeC: Brahms shielding removed. Cooling water tower/water pumps installed. Shielding penetrations enlarged (Folz) 1002B RF Coax run installed (Folz, Randazzo) Laser building ordered (Folz, Sheehy) RF Power supply installed (Folz, Zaltsman)

CeC PoP Preparation Building preparation for CeC in progress 2013: Laser building installation (Folz, Sheehy) Quiet helium source for SCRF (Orfin, Soria) Cryogenic return compressor (Than, Soria, Folz) 1002A ODH system installation (Folz) Move AnDY equipment from 1002D (Folz) Cable tray installation (Folz)

Design Issues CeC PoP test schedule/equipment available/interchangeable. SCRF gun and cavity performance/rf system (Sergey s talk). QHS performance distance to gun/solenoid/accelerator cavity 2:00 or 1:00. Cryogenic design margin. Beam dump design 250kW Beam line elements Injection/extraction ebending magnets 180 o turn configuration efocusing solenoid magnets ebpm s ecorrector magnets Magnet Power Supplies: solenoids, bends, and 180 return in series + individual corrector power supplies (CeC PoP). RF Amplifier/power supplies (gun, accelerator, buncher) Magnetic Shielding: mu metal or solenoid windings

2:00 IP Left or Right

1:00 Tunnel 24m to larger tunnel + 32m to QHS

2:00 Tunnel

Design Issues Beam line elements - efocusing solenoid magnet and vacuum chamber Magnet specifications: strength, length, aperture Solenoid magnet every 2M 5 beam tube (standard RHIC size, better conductance same ion pumps, available w/neg coating). 3 beam tube better solenoid field? Solenoid wind on tube, clamp over steel shell Both modeled little difference.

Design Issues Corrector magnet: spacing, strength, length, aperture. Bending/Alignment magnets TB Designed (5 inch aperture). 180 o bend magnets TB D 180 o bend instrumentation TB D (CeC PoP)

Design Issues Cryogenic performance - Quiet Helium Source (QHS): 200 W. Gravity fed helium supply and return. Large cryostat for LEReC then for CeC PoP. Fixed heat exchanger design 100% design margin for CeC PoP. Can shorten transfer lines if needed. 112 Mhz Cavity RF Load Estimate: Dynamic = 50W, Static = 8 W, FPC = 2 W Cryogenic transfer VJP: liquid supply = 2W, vapor return: 6W (8 meters 1 W/m) TOTAL Load Estimate: 68 W

Design Issues Beam Dump: 5.0 MeV electrons/0.25 MW power Copy ERL Beam Dump: 2.5 MeV electrons/1.0 MW power

RHIC Program Timeline Run 14 CeC PoP Gun (and cryogenic system) Commissioning. Run 15 CeC PoP Beamline commissioning. Summer 2015 02:00 Q3/Q4 equipment move. Building/tunnel infrastructure improvements. Run 16 CeC PoP Experiment Summer 2016 Cavity and beamline installation. Run 17 LEReC Component Commissioning Run 17? CeC PoP Experiment Continues?? Run 18&19 LEReC Operations

Timeline FY2013 Physics approach/preliminary design approved. FY2013 Design Safety Review Questionnaire completed. FY2013 Initial 2:00 Layout and LEReC Lattice. FY2013 SCRF Cavities physics design and performance specifications. FY2014 Engineering kick-off meeting/assignments/start bi-weekly engineering meetings FY2014 CeC gun cavity cryogenics commissioned, performance benchmark for quiet helium source. FY2014 LECeC Lattice frozen, energy, intensity, location, component specifications. FY2014 Engineering systems PDR, systems specifications, building requirements/system loads. FY2014 Order SCRF Cavities/cryostat, SC solenoid, RF amplifiers, buncher system. FY2014 Support building layout/equipment locations, cable tray, electrical service, AC & water loads. FY2015 Detailed cryogenic component design BNL PCSSR long lead procurements. FY2015 Detailed beamline design, ASSRC/FDR long lead component procurements. FY2015 Support building modification design/contracts (2015 shutdown modifications) FY2015 Move RHIC beamline components (2015 shutdown modifications) FY2016 Receive and test LEReC beamline and cryogenic components FY2016 2016 Shutdown installation LEReC beamline and cryogenic components FY2017 Engineering commissioning for LEReC beamline and cryogenic components FY2017 2017 Shutdown modifications/corrections to LEReC beamline and cryogenic components FY2018 Operations (Run 18)

C-AD Engineering & Technical Support Matrixed Support for the CeC PoP Project

Systems Engineers Engineering Support C-AD Accelerator, Facilities & Experimental Support, and R&D Divisions. CeC layout B. Martin (AD) SRF S. Belomestnykh (CeC, RD) RF Systems PS and LLRF A. Zaltsman (CeC, AD) Cryogenics R. Than, T. Tallerico, P. Orfin, J. Haung (CeC, AD) Beamline (Magnets and Power Supplies) G. Mahler, R. Lambiase (CeC, AD) Diagnostics D. Gassner, T. Miller, L. DeSanto (CeC, AD) Drive Laser & Photocathode Development B. Sheehy (CeC, RD) Conventional Facilities C. Folz, J. Scaduto, P. Feng (CeC, ESF) Cathode Insertion Fixture TBD Cavity Tuners, Power Coupler, Laser Port TBD Beam Line and Insulating Vacuum Systems M. Mapes (CeC, AD) RF Buncher TBD Beam Dump L. Snydstrup (CeC, AD)

Summary Physics/engineering co-ordination meetings are underway. Preliminary beam line design is underway. Site has been chosen/infrastructure. After review LEReC lattice will be frozen: SCRF system specifications Vacuum chamber/magnet specifications e beam instrumentation HI beam instrumentation Engineering team to be finalized and assigned. CeC PoP SCRF Cavity and cryogenic system commissioned Finalize 1:00 or 2:00 location

Tunnel Location Details Sector 2 Meters from IP2 S-Coord Label Yellow Inner Name S-Coord Label Blue Outer Name Q3 Q3 38.4 Start of warm sector Start of warm sector 10 Hz GOF Magnet 10 Hz GOF Magnet 0.25MBPM 41.0 MBPM2 Moveable BPM (LF Schottky) 2598.5 KKR-2 BBQ Kicker 0.25m BPM BTF Pick-up 1M Pick-up Beam Loss Monitor 0.25MBPM 41.5 2597.9 IPM-H Y-Ionization PM horizontal Beam Loss Monitor 42.0 2599.3 KKR-2 Hybrid Kicker 2599.1 KKR-2 PLL BBQ PU (Moveable) 44.0 Start of LEReC Cooling Section 46.8 2601.04 TMKH ARTUS Kicker Horizontal (start) 48.8 2603.04 TMKH ARTUS Kicker Horizontal (end) 49.0 2605.2 EDV Electron Det V EDV Electron Det V 53.0 2608 TMKV ARTUS Kicker V(or B-by-B longit damper) LM Lumi-Mon (6-way cross only) 55.0 2610 TMKV ARTUS Kicker V(or B-by-B longit damper) 2610.04 IPM-V B-Ionization PM Vertical Beam Loss Monitor 56.0 End of LEReC Cooling Section 56.6 2611.6 TWC Traveling Wave Cavity 2613 Future ARTUS Kicker V 2613 Future ARTUS Kicker H 2615 Future ARTUS Kicker V 2615 Future ARTUS Kicker H 2619 Future B-Ionization PM Vertical 61.8 2617.5 SC Long Pick-up (start) 64.0 SC Long Pick-up (middle) 66.0 SC Long Pick-up (end) 67.0 2622 Button BPM 2622.7 Button BPM 68.0 2623.5 WCM 2623.52 WCM 68.6 2624.2 DCCT DCCT 69.0 HF Schottky PU HF Schottky PU Pin diodes (2) 71.0 New Long SC pickup End of warm sector End of warm sector Q4 Q4

Right 2:00 Sector

Left 1:00 Sector

Yellow

Move Equipment Blue