WELCOME. Please sign in Representatives are available to answer questions Please complete a comment sheet

Similar documents
Parkhill Road Sewage Pumping Station Class EA Study

PRINCETON WASTEWATER SERVICING STUDY Municipal Class Environmental Assessment. Oxford County

Class Environmental Assessment Schedule B Project File Report

PUBLIC WORKS COMMITTEE REPORT. Held Thursday, April 3, 2014 at 8:30 a.m. In the Classroom, Town Hall

UPDATED FUNCTIONAL SERVICING and STORMWATER MANAGEMENT REPORT

Phases 2 & 3, & Addendum Urban Structure Plan Options for West Whitby

SERVICING REPORT SITE PLAN AND PLAN OF CONDOMINIUM BLOCK 53 FERRIS DRIVE PLAN 58M-379 & PART OF LOT 4, REGISTERED PLAN 622 WELLESLEY, ONTARIO

West London Dyke Flood Control Structure Master Plan Appendix A

Central Area Community Improvement Plan

Challenges. Estimated Damages from 100-Year Flood

ENVIRONMENTAL CODE OF PRACTICE FOR CONCRETE BATCH PLANT & ROCK WASHING OPERATIONS

DAYBREAK ATTACHED RESIDENCE DISCLOSURE STATEMENTS Acknowledgement of Receipt Form

Guidelines for. Permeable Pavement

2010 Salida Community Priorities Survey Summary Results

Notice of Study Commencement and Invitation to Participate

REPORT TO WILDERNESS MOUNTAIN WATER SERVICE COMMISSION MEETING OF TUESDAY, MARCH 31, 2015

The purpose of this meeting is to inform the public of the updates to the project, and to get input before the finalization of the project.

GUIDELINE FOR MUNICIPAL MANAGEMENT PRACTICES FOR STREET SWEEPINGS & CATCH BASIN CLEANINGS

4. Environmental Impacts Assessment and Remediation Targets

London Borough of Waltham Forest LOCAL FLOOD RISK MANAGEMENT STRATEGY. Summary Document

WEST LONDON PIPELINE AND STORAGE LIMITED AND UNITED KINGDOM OIL PIPELINES LIMITED

SOIL-MAT ENGINEERS & CONSULTANTS LTD.

Application for Approval to Construct or Upgrade and Operate a Storage Facility October 2015 CSB CSB13001

Emergency Operations Plan ANNEX K - UTILITIES RESTORATION ESF #3, #12 I. MNWALK REQUIREMENTS. Item #: 1, 4, 46, 53, 54

SPECIAL USE PERMIT JCSA Groundwater Treatment Facility Staff Report for the November 5, 2001, Planning Commission Public Hearing

Application No.: Steve Rush, representing Rocky Mountain Power Rocky Mountain Power Project Location: approximately 1600 N E.

TOWN OF ALTONA 2016 FINANCIAL PLAN

Appendix A Alternative Contracting General Engineering Consultant RFP. Appendix A

Attachment 1 CARRUTHERS CREEK FLOOD MANAGEMENT and ANALYSIS DRAFT TERMS OF REFERENCE

FLOOD CONTROL REMEDIATION AND FACT SHEETS FOR RESIDENTS ASSOCIATIONS IN MARKHAM

Public Information Meeting Nyon Oil Inc.

SOIL AND GROUNDWATER MANAGEMENT PLAN For Site Located at 420 South Avenue Rochester, New York NYSDEC Spill No PREPARED FOR: PREPARED BY:

BEYOND THE STORM: Toronto s Climate Change Adaptation Program. Its about Risk and Cost Management. David MacLeod Toronto Environment Office

FINAL PLAN OF REMEDIAL ACTION

City of Hill Country Village Residential Construction/Development Packet

K M D Hire Services, LONDON ROAD, NANTWICH, CW5 6LU

Small Business Permit Service

REQUEST FOR PROPOSALS CENTRAL NEW YORK ECONOMIC DEVELOPMENT REAL ESTATE SITE PROFILE DATA BASE SYRACUSE, NEW YORK MARCH 25, 2013

The Bond Release Process for New Subdivision Developments: An Overview for Homeowners Associations DRAFT Revised

Spill Control Prevention Plan (SCPP)

Kitchener s Stormwater Utility

DIRECT TRANSFER COAL FACILITY SPILL RESPONSE PLAN

HERITAGE PROPERTY TAX RELIEF PROGRAM GUIDELINES & APPLICATION Community Services Department Planning Division

1. GROUP PRESENTATION 2. ENGINEERING AND PROJECT DEVELOPMENT 3. LICENSING AND AUTHORIZATIONS 4. SERVICES 5. ENVIRONMENTAL SERVICES 6.

Demo Permit Guide For Homeowners

Town of Ware Board of Health. Regulations for Percolation Tests, Soil Evaluations, Design, and Technical Review of Subsurface Sewage Disposal Systems

Town of Huntsville Municipal Asset Management Plan

TOWN OF SAUGEEN SHORES WATER AND SANITARY SEWER SERVICING MASTER PLAN 2014 REPORT

CONTENT COPY OF ORIGINAL

5 NINTH LINE TRUCK RESTRICTION UPDATE TOWN OF MARKHAM

Vital Earth Composting Facility Flood Risk and Drainage Statement

The Town of Lakeshore Basement Flooding Information to Residents

Flood disaster preparedness and resilience

Public Hearing. City Council Study Session. February 11, 2013

City of Bakersfield Public Works Department Sewer System Management Plan December 2014

APPENDIX 4. Risk Tables

What Is An On-Lot Sewage Disposal System?

Innovative Stormwater Solutions in Coastal Areas 2015 APWA Stormwater Conference

LOWELL CHARTER TOWNSHIP PLANNING COMMISSION PUBLIC HEARING AND REGULAR MEETING April 14, 2008 PUBLIC HEARING ON RIVERSIDE MOTORSPORTS SPECIAL LAND USE

City of Surrey PLANNING & DEVELOPMENT REPORT File:

AMENDED ENVIRONMENTAL COMPLIANCE APPROVAL NUMBER 2152-A3YN6H Issue Date: November 13, 2015 L. & G. General Auto Body Limited. ite4656 Yonge Street

Town of Ajax Heritage Property Tax Rebate Program Information Brochure

Clear Water Projects in Cooksville Creek Watershed

Iowa Smart Planning. Legislative Guide March 2011

Brookdale Site. CB6 Update April 1, 2015

Growth Management in the City of Brampton

KAWERAU DISTRICT COUNCIL BUSINESS DISASTER RECOVERY PLAN 2011

Definition of Tower from the Bradley County Zoning Resolution

Ontario Ministry of the Environment - Record of Site Condition # Record of Site Condition Under Part XV.1 of the Environment Protection Act

Executive Director, Engineering & Construction Services Director, Purchasing & Materials Management Division

SITE PLAN APPROVAL PROCESS INTRODUCTION

5 March 12, 2014 Public Hearing

On Site Sewage System Maintenance Inspections. March Building and Development Branch Ministry of Municipal Affairs and Housing

TOWN OF SURFSIDE UTILITY UPGRADE PROJECT Project Completion

Area No. 8 Test Pit No. 191

Emerging Technologies in Wastewater Collection Systems

483/503 GARRETTS GREEN LANE GARRETTS GREEN BIRMINGHAM B33 0TL

Guidelines for Excavations

2014 ASSET MANAGEMENT PLAN Building, Stormwater & Linear Transportation

Stormwater Credit Open House Q&A

FLOOD PLAIN DESIGNATION AND PROTECTION

BUILDING MOVE PROCESS INSIDE CITY LIMITS

Biofiltra on: West Hylebos Log Yard

Township of Enniskillen. Asset Management Plan

Re: Proposal for Innovative Options for Providing Stormwater Infrastructure and Services

INFRASTRUCTURE, FLOOD PROTECTION AND REMEDIATION. Infrastructure Flood Protection Remediation Policies

PICP Construction. Why PICPs The Big Picture. Key things to know about PICPs

Contents. 1.0 Introduction Project definition Project brief Accommodation guidelines Objective 4

TOWN OF GRIMSBY ASSET MANAGEMENT PLAN

DRAFT POLICIES COUNTY OF HALIBURTON OFFICIAL PLAN UPDATE

ENCE 4610 Foundation Analysis and Design

WASHINGTON COUNTY PLANNING COMMISSION MINUTES

Quick Fact Booklet FOR START-UP AND EXPANDING BUSINESSES

Performance Audit: Rental Housing Licensing Program February 2012

11 Software License and Hardware Maintenance and Support Agreement Extensions

SNOW REMOVAL AND ICE CONTROL OPERATIONS MANUAL TABLE OF CONTENTS

ADDENDUM NUMBER TWO (2)

Draft Environmental Impact Statement. PORT OF OSWEGO AUTHORITY Lead Agency, State Environmental Quality Review Act

3.6.1 Existing Conditions - Police, Fire, Ambulance, Water, Sewer, & Solid Waste

4. New $ Minimum Plumbing, HVAC, Alarms, Sprinklers, and any permanent systems 5. Replacement $ Minimum

Transcription:

WELCOME Please sign in Representatives are available to answer questions Please complete a comment sheet Place it in the box or send it to the Consultant undertaking the study or to the Town of Wasaga Beach at the address provided on the comment sheet 1

Problem Statement In order to enhance potable water delivery in the west end of the community, the Town of Wasaga Beach is undertaking a planning process (Schedule C) to consider storage options and sites for a new water reservoir. The assessment will investigate all aspects of the water system including water pressure, fire flow volumes, adequate storage volume, existing servicing and future development. The Town intends to ensure that all areas within the current Town boundary limits are adequately serviced by the municipal water system. In addition, the Town is also considering layout options and site locations for a new (satellite) maintenance depot in the west end of Town. Given the geographic layout of the Town, the current Public Works Maintenance facility located in the east end, does not efficiently support present operations. Projected growth in demand for services will further overload the current facility and diminish current levels of service. 2

This Project is being planned in accordance with the Municipal Engineer s Association s (MEA) Municipal (October 2000, as amended in 2007 & 2011) document. The MEA Planning and Design Process Flow Chart is provided for public information. At the present time, the Wasaga Beach West End Water Storage Facility and Maintenance Depot Class Environmental Assessment is in Phase 2. WE ARE HERE 3

Map of Study Area The study area for these two projects is described as the Town limit west of 58 th Street. 4

Map of Service Area 5

Water Storage Requirements The need for additional water storage was identified in a Report titled: Ultimate Water Supply and Distribution System Model Update prepared by Ainley & Associates Limited, March 2014. A total water storage requirement of 24,641 m 3 was identified for full build out of the Town (27, 012 units) Based on the following: MDD = 1.478 m³/ day / unit 30% increase in per unit demand to allow for long term future planning (1.921 m³/ day / unit) Fire flow of 378 L/s for 6 hours The additional storage requirement was derived as follows: Location of Storage Available Storage (m 3 ) East End Elevated Tank 2,841 Powerline Road In-Ground Reservoir 3,410 Sunnidale Elevated Tank 9,550 Total Existing Storage 15,801 Additional Storage Required 8,840 6

Water Storage Distribution Analysis It was determined that the additional water storage volume (rounded to 9,000 m³) should be distributed across the Town in order to provide better distribution capabilities. Six water storage alternatives were considered for the additional required capacity as follows: Alternative 1 9,000 m³ elevated tank in the west end Alternative 2 9,000 m³ in-ground tank in the west end built in 2 stages Alternative 3 4,500 m³ elevated tank in the west end and 4,500 m³ in-ground at Powerline Road site Alternative 4 4,500 m³ in-ground tank in the west end and 4,500 m³ in-ground at Powerline Road site Alternative 5 Do Nothing Alternative 6 Limit Growth 7

Identification of Alternative Solutions In order to deal effectively with the aspects of the problem statement, a range of practical alternative solutions were identified for the water reservoir, including Do Nothing and Limit/Manage Growth. Do Nothing Due to the capacity of the existing water storage the Municipality will inevitably be required to increase their water storage in order to remain in compliance and to maintain the health and safety of the citizens of Wasaga Beach. The Do Nothing alternative is therefore considered not viable and was not carried forward to the detailed evaluation stage. Limit/Manage Growth Placing a limit on growth does not align with the Town of Wasaga Beach approved Official Plan. Viable alternative solutions for the water reservoir were evaluated to identify a recommended preferred solution. 8

Recommended Water Storage Solution A criteria assessment table was developed rating each of the options as best (3), moderate (2) or least preferred (1) Alternative # 3 is the recommended water storage solution (4500m³ elevated tank in the west end and 4500m³ in-ground reservoir on Powerline Rd.) West End Elevated Tank West End In-Ground Tank West End Elevated & East End In-Ground West End In-Ground & East End In-Ground Land Requirement 3 1 3 2 Aesthetics 3 1 2 1 Opportunity to Create Wasaga Beach Landmark 3 1 3 1 Security of Supply (Need for Standby Power) 3 1 2 1 Water Quality* 2 6 6 6 Meeting all Demands Across Future Network* 2 2 6 6 Access to Storage (Health and Safety) 1 3 2 3 Initial Capital Cost* 2 6 4 6 Future Capital Cost 3 1 1 1 Long Term Operation and Maintenance Cost 3 1 3 2 Energy Costs 3 1 2 1 Total 28 24 34 30 *A weighting of 2 has been applied because this criteria is of higher importance resulting in ratings of least preferred = 2, moderate = 4 and best = 6. 9

Proposed Upgrades to Powerline Road Facility 10

Maintenance Depot Requirements A Needs Assessment was conducted which determined the need of a satellite maintenance depot in the west end of Wasaga Beach. The Assessment identified that the depot will allow for more timely repairs and services, improved winter maintenance and is necessary to service the proposed developments in the west end. The area necessary to provide these services was identified as 3.5 hectares. To adequately serve the Wasaga Beach community, the new satellite maintenance depot requirements are as follows: Office Area For office staff and dispatch Will include meeting, training rooms and washroom Utility Area For building utilities, cleaning materials and storage Staff Facilities Incudes kitchen, lunch room, locker rooms and washrooms Depot Includes storage and vehicle bays for parking, truck washing and repair Sand and Salt Shed - Storage Yard Gas facility, parking, material storage and a communication tower 11

Potential West End Sites Phase 2 Options All potential site options within the study area were considered. 7 sites were identified as feasible options and were short listed for additional consideration. A location map outlines the location of the sites on the next slide. 12

Map of Seven West End Sites 13

Background Information A desktop study was completed for the seven proposed sites. The following information was reviewed with respect to these sites: Geotechnical Information from previous geotechnical study Land Use Plan, Information from the Town Official Plan National Heritage Plan, Information from the Town Official Plan Well Head Plan and Active Information from the Town Official Plan Proposed Developments Information from the Town Official Plan Existing Sewers and Water Mains Information from engineering records 14

Geotechnical Information Based on the previously completed geotechnical investigations the general ground conditions at the seven sites are summarized as follows: Soils Sites 1 and 2 have soils consisting of silt and clay with possibility of silty sand Sites 3 and 4 consist of fine sand underlain by impervious soils Site 5 is in an area of well graded, fine or gravely sand Sites 6 and 7 consist of fine sand possibly underlain by impervious soil Ground water levels Sites 1, 2,3 and 4 have a deeper ground water table. Sites 5, 6 and 7 have a more shallow ground water table. All sites are suitable (geotechnically) for the proposed use 15

Potential Layout Identified Area No. 1 CONCEPT ONLY 16

Potential Layout Identified Area No. 2 CONCEPT ONLY 17

Potential Layout Identified Area No. 3 CONCEPT ONLY 18

Potential Layout Identified Area No. 4 CONCEPT ONLY 19

Potential Layout Identified Area No. 5 CONCEPT ONLY 20

Potential Layout Identified Area No. 6 CONCEPT ONLY 21

Potential Layout Identified Area No. 7 This property was considered as a potential site however due to limited size, it was unable to meet the required needs of the project. CONCEPT ONLY 22

Evaluation of Phase 2 Site Options Criteria Sub-Criteria Weighting (%) Site 1 Site 2 Site 3 Site 4 Site 5 Site 6 Land Use Planning 10 4 9 7 6 4 6 Existing Land use 5 2 4 4 4 3 5 Proposed/Potential Land Use 5 2 5 3 2 1 1 Natural Environment 15 9 10 13 15 8 12 Well Head Protection 3 3 3 3 3 3 3 Surface Water/Drainage 5 1 2 5 5 1 2 Geotechnical 2 1 1 2 2 2 2 Trees/Habitat 5 4 4 3 5 2 5 Social Environment 30 8 24 22 26 25 18 Noise Impact 5 1 5 4 4 4 3 Light Impact 5 1 5 4 4 4 3 Residential Impact 10 2 8 8 10 8 4 Traffic Impact 5 3 4 2 3 5 3 Visibility of Water Reservoir 5 1 2 4 5 4 5 Cultural Environment 5 1 4 4 3 2 1 Supporting Town Policies 5 1 4 4 3 2 1 Technical Considerations 25 17 21 21 20 22 22 Site Servicing (Power, Sewer, Water) 5 3 4 5 5 5 5 Adequate Size 5 5 5 5 3 3 5 Tank Hydraulic Performance 5 3 4 5 5 5 5 Depot Location 5 1 3 4 4 4 4 Truck Access 5 5 5 2 3 5 3 Economic Considerations 15 11 13.5 11 10.5 8.5 9 Cost 8 6 6.5 7 7.5 7.5 8 Commercial/Industrial Impact 7 5 7 4 3 1 1 Total 100 50 81.5 78 80.5 69.5 68 * A higher rating indicates that the site option is more preferred when compared against the respective criteria. 23

Phase 2 Recommended Site Site 2 is the recommended preferred site Overall site 2 presents the best alternative based on the evaluation criteria. This site will have the least impact on development in Wasaga Beach with minimum impact to the surrounding area. This site will provide increased water security and performance as well as increased maintenance and service to the residents located in the west end of Wasaga Beach. 24

Site 2 Preferred Site 25

Next Steps Phase 2 1. Review PIC #1 Comments (August 21, 2015) 2. Confirm recommended preferred west end site(s) Phase 3 3. Identify and evaluate design options 4. Complete investigations and studies including a detailed archeological assessment, geotechnical investigation, natural environment assessment and a storm water management study to confirm the impacts of the tower and depot. 5. PIC #2 6. Review PIC #2 comments 7. Confirm recommended preferred design option Phase 4 7. Draft ESR 8. Publish Notice of Completion of Class EA 9. Public and Agency review of DRAFT Environmental Study Report 10. Finalize Environmental Study Report based on comments received 11. Memo to Ministry of Environment Completion of Class EA 26

What Can you Do? Fill out a comment sheet Send your comments to: Mike Latimer, C.E.T. Project Coordinator Town of Wasaga Beach 30 Lewis Street Wasaga Beach L9Z 1A1 Tel: (705) 429-2540 Fax: (705) 429-8226 Email: m.latimer@wasagabeach.com Gary Scott, M.Sc., P.Eng. Vice President, Water Business Ainley Group 280 Pretty River Parkway Collingwood, Ontario L9Y 4J5 Tel: (705) 445-3451 ext. 147 Fax: (705) 445-0968 Email: scott@ainleygroup.com 27

The Town of Wasaga Beach West End Storage Facility and Maintenance Depot Public Information Centre July 22, 2015 7:00 p.m. to 9:00 p.m. Wasaga Rec Plex, 1724 Mosley Street COMMENT SHEET NAME OF RESPONDENT: Please print all responses. REPRESENTING (Agency, Municipality, Property Owner, Tenant, etc.): ADDRESS (Including Postal Code, Telephone Number & Email Address): COMMENTS (Please use the back of this sheet if necessary) Do you wish to be informed of additional PICs and the publication of the Notice of Study Completion? Yes No Please submit this comment sheet by August 21, 2015 to: Mr. Michael Latimer, C.E.T. Project Coordinator Wasaga Beach Public Works 30 Lewis Street Wasaga Beach, ON L9Z 1A1 Tel: (705) 429-2540 Fax: (705) 429-8226 m.latimer@wasagabeach.com Mr. Gary Scott, M. Sc., P. Eng. Project Manager Ainley Group 280 Pretty River Parkway Collingwood, ON L9Y 4J5 Tel: (705) 445-3451 Fax: (705) 445-0968 scott@ainleygroup.com