1 Report to: Cabinet Member for Culture and Leisure Date: 5 November 2009 Report by: Written by: Report Title: Head of Cultural Services Jane Mee, Museums & Records Manager Joint Museum Storage Project with Southampton 1. Purpose of Report: 1.1 To advise of a joint initiative with Southampton which entails reviews of a number of museum collections to ascertain their relevance to council policy and priorities and an options appraisal to identify a series of solutions to address the museum and archive collection storage issues affecting both services. 2. Recommendations: 2.1 That the joint storage project is approved subject to the successful outcome of a funding bid to the Museum Libraries and Archive Council (MLA). 3. Background: 3.1 The collections that tell the stories of Portsmouth and Southampton are a valuable resource. However, their full potential for public engagement is not being achieved because they are currently managed in subject silos, distributed across a range of storage facilities with limited public access and provide varying standards of collection care. Individually, Portsmouth and Southampton are developing a strategic approach to managing these collections. However, shared challenges and shared needs will be addressed more cost effectively and dynamically through a partnership approach. 3.2 At the heart of this approach is the shared aspiration to make our collections accessible so they can be readily and effectively used to engage a wide range of audiences and to contribute to the delivery of a broad range of local, regional and national objectives relating to learning and social cohesion for example. 3.3 The current cost of Portsmouth s main museum and archives stores is 91,612 per annum. This includes some staff costs. The project described below may deliver some economies of scale. However, in the first instance it should be understood in terms of better care of collections, better use of collections and hence better value for money. 1

2 4. Joint Storage Initiative with Southampton: 4.1 The aims of the project are: To create a set of relevant, accessible, well-cared for and well-used museum and archive collections across the PUSH area. To identify and evaluate a range of storage options including solutions that involve both separate and shared storage solutions and a mix of both. To raise public awareness and understanding of the issues round collecting (and dispersal / disposal) and collection management through a series of workshops, store tours, other events and through the use of the local media. To disseminate learning and best practice with colleagues across the region and more widely. 4.2 The collection reviews and storage options appraisal form the first phase of the project. The second phase will be implementation. The dissemination meetings which mark the end of phase one, will provide an opportunity to seek the involvement of other museum services enabling us to potentially provide a storage solution serving the museums of the PUSH sub-region. 4.3 Project costs and programme are shown in the matrix below. Funding for the full cost of the project has been requested from the MLA. Project element Cost Timetable Project management 20,000 Appoint Nov 2010 Collection reviews 105,000 Complete SCC May, PCC Sept* 2010 Storage options appraisal 60,000 Complete May 2010 Public programme 15,000 Start Jan 2010 Contingency (@10%) 20,000 Total: 220,000 *Plan to bring this forward if possible 5. Collection Reviews: 5.1 The following collections will be the focus of the collections review. They have been selected due to: their size (bulk archaeology, social history for example), issues round storage and access (large objects including vehicles) and where there is a need to confirm relevance (this is a particular issue for Portsmouth s decorative art collection, especially the furniture). Southampton: Large objects and groups of objects in heritage collections (including those on loan) such as furniture, ship models, tools, guns, swords 2

3 Bulk archaeology collections (bulk material - shell, charcoal, stone etc - collected during excavations in the city which can be discarded once information has been recorded) Museum art collection (ships and local views). Portsmouth: Large objects and groups of objects including vehicles, cannon, interiors/fittings and trade and craft tools Social history including furniture, domestic equipment, tools, guns Bulk archaeology collections (stone, soil, shell which can be discarded once information has been recorded and samples taken) Decorative arts, specifically the furniture collection - an external assessment of the integrity, coherence and the regional / national significance of the collection is required and recommendations as to how it should be developed Natural sciences - an external assessment of the regional / national significance of the collection is required and recommendations as to how it should be developed. 5.2 The collection reviews will enable the two services to better understand how the two city s collections relate to and complement each other and how we should position and align them further through future collecting. To enhance this further and future collaborative working, the project will also include familiarisation visits and formal and informal skill sharing. 6. Storage Options Appraisal: 6.1 An options appraisal is required to identify and evaluate options for storage. This will need to include a range of options encompassing both shared and separate storage elements, options with elements located both within and outside the boundaries of the two unitary authorities. It is envisaged that options will be influenced by the collection reviews and having a better understanding of the synergy between the collections and the knowledge and specialisms of the staff of the two services. Aspirations for enhanced access will also influence the evaluation of options. The views of stakeholders - including Members - will also be key. The options appraisal will therefore include: Identifying storage requirements, including both space and environmental conditions. This will draw on work already undertaken - Portsmouth has a report from external specialists and Southampton has undertaken an internal review - and the findings of the collection reviews. Design input to make most cost-effective and efficient use of the building/s Supporting facilities required - learning space, space for staff, volunteers and researchers, loading bays, quarantine facilities etc 3

4 Identification and assessment of potential sites against criteria informed by corporate policy and consultation with key stakeholders and including capital and ongoing revenue costs. 6.2 Southampton has a pressing need to have a storage solution identified by May 2010, as their main store has to be vacated in Portsmouth also needs to identify an alternative to its main museum store at Hilsea as the Primary Care Trust requires this site. 7. Involving the Public: 7.1 As part of this project we want to increase public understanding about what museums do. We propose therefore to engage the general public, special interest groups and other stakeholders in the issues surrounding collecting and collection management through workshops, tours and other events so at very least people have an informed view about the issues involved. We will also begin the process of directly involving people in the choices we make - what to collect, what to let go. We will evaluate changing views and perceptions resulting from participation. 7.2 The project will also benefit from a communications plan and we propose to employ a PR specialist to help us develop and implement this. 8. Delivering Corporate Priorities: 8.1 The joint storage project with Southampton, including involvement of the wider public, is very much in accordance with the Council s Efficiency and Involvement priority and establishes good practice for the museums sector. 8.2 By developing stores to facilitate access to our collections museums also directly contributes to the Council s aspirations for learning for both adults and children encompassed in the priority to Raise standards of English and Maths. 8.3 As the joint storage project would lead to easier access to our collections we would also hope to positively impact on both visitor numbers to Portsmouth and to the museums service. 9. Legal Issues The City Solicitor has advised that the recommendations made in this report are within the competence of the Cabinet Member to approve 4

5 10. Equality Impact Assessments The actions proposed relate to enhancing access for a range of users. There seems no requirement for an EIA at this stage. 11. Financial Implications Costs relating to the preparation of the bid have been met from within the existing Museum and Records service budget. If the bid is successful and the storage project goes ahead, it is likely that efficiencies due to the economies of scale created by working in partnership with Southampton City Council will be realised. Signed: Stephen Baily, Head of Cultural Services Background List of Documents Section 100D of the Local Government Act 1972 The following documents disclose facts of matters which have been relied upon to a material extent by the author in preparing this report. Title of Document Location None The recommendations set out above were approved/approved as amended/deferred/rejected by the Cabinet Member on: Signed: Cabinet Member for Culture and Leisure 5

Report to: Executive Member for Culture and Leisure 20 September 2007. Written by: Michael Gunton Archives and Development Manager

Report to: Executive Member for Culture and Leisure 20 September 2007. Written by: Michael Gunton Archives and Development Manager Report to: Executive Member for Culture and Leisure 20 September 2007 From: Head of Culture Written by: Michael Gunton Archives and Development Manager Report on: Archive Storage Issues 1. Purpose of the

More information

3. Contribute to meeting annual income target through effective promotion of our services and accurate financial procedures

3. Contribute to meeting annual income target through effective promotion of our services and accurate financial procedures 1. JOB TITLE Job Title: HERITAGE ASSISTANT Reports to: Public Services Manager Service: Surrey Heritage/ Cultural Services / Customers and Communities 2. JOB PURPOSE (A short statement of no more than

More information

1.1 To update Cabinet on Heritage City status and to seek Cabinet support for the principle of a Worcester application for Heritage City status.

1.1 To update Cabinet on Heritage City status and to seek Cabinet support for the principle of a Worcester application for Heritage City status. Report to: Cabinet, 27 th October 2015 Report of: Cabinet Member for History and Heritage Subject: HERITAGE CITY STATUS 1. Purpose of Report 1.1 To update Cabinet on Heritage City status and to seek Cabinet

More information

Marketing & Audience Development Manager

Marketing & Audience Development Manager Marketing & Audience Development Manager Job Description & Person Specification Full Time Fixed Term Contract (3 Years) - Newmarket Salary: 25,000-28,000 per annum (depending on experience) Responsible

More information

Our core value is that we aspire to be world class in what we do. Properties in Care Business Plan 2009-2014

Our core value is that we aspire to be world class in what we do. Properties in Care Business Plan 2009-2014 Our core value is that we aspire to be world class in what we do Properties in Care Business Plan 2009-2014 1.0 CONTENTS 1.0 Introduction 2 2.0 Activities and Actions 8 3.0 Staffing and Resources 20 PIC

More information

City of Holdfast Bay Draft Tourism Plan 2010 14

City of Holdfast Bay Draft Tourism Plan 2010 14 City of Holdfast Bay Draft Tourism Plan 2010 14 Our Vision Adelaide s premier seaside destination. Council believes that a thriving tourism industry opens our City to the world, and benefits our local

More information

ABERDEEN CITY COUNCIL. Name of Committee : Resources Management Committee

ABERDEEN CITY COUNCIL. Name of Committee : Resources Management Committee ABERDEEN CITY COUNCIL Name of Committee : Resources Management Committee Date of Meeting : 29 March 2007 Title of Report : CRM System Procurement Lead Officer : Jacek Nowak, Head of Customer Relations

More information

Project Appraisal and Scrutiny Committee Recommendation. E-mail, file storage system and server upgrades

Project Appraisal and Scrutiny Committee Recommendation. E-mail, file storage system and server upgrades Cambridge City Council To: Report by: Scrutiny committee: Wards affected: Executive Councillor for Customer Services and Resources James Nightingale, Head of ICT Client Services Strategy and Resources

More information

HLF Application Royal College of Music Museum Brief for Project Business Plan for the Music Museum

HLF Application Royal College of Music Museum Brief for Project Business Plan for the Music Museum HLF Application Royal College of Music Museum Brief for Project Business Plan for the Music Museum 1. Background 1.1 THE ROYAL COLLEGE OF MUSIC MUSEUM TODAY The Museum is open from 11.30am to 4.30pm, Tuesday

More information

JE PANEL/BENCHMARKING REF NO: 867/4 EVALUATION DATE:

JE PANEL/BENCHMARKING REF NO: 867/4 EVALUATION DATE: 1. JOB TITLE Job Title: Project Manager (Transport Infrastructure) Reports to: Design Programme Manager Service: Highways and Transport Environment & Infrastructure Date: November 2014 2. JOB PURPOSE To

More information

Performance Management 2013/14: March 2014

Performance Management 2013/14: March 2014 Performance Management 2013/14: March 2014 Sustainable Development Committee Director of Social and Community Services Community Education and Training Business Plan Progress All Business Plan actions

More information

Maturity Model. March 2006. Version 1.0. P2MM Version 1.0 The OGC logo is a Registered Trade Mark of the Office of Government Commerce

Maturity Model. March 2006. Version 1.0. P2MM Version 1.0 The OGC logo is a Registered Trade Mark of the Office of Government Commerce Maturity Model March 2006 Version 1.0 P2MM Version 1.0 The OGC logo is a Registered Trade Mark of the Office of Government Commerce This is a Value Added product which is outside the scope of the HMSO

More information

CRAFT NORTHERN IRELAND STRATEGIC PLAN 2014 2017

CRAFT NORTHERN IRELAND STRATEGIC PLAN 2014 2017 CRAFT NORTHERN IRELAND STRATEGIC PLAN 2014 2017 Innovative Craft 2014-17 March 2014 STRATEGY 1 Context o 1.1 Craft Northern Ireland history o 1.2 Evaluation o 1.3 Other considerations in developing a new

More information

Clerk to the Education and Culture Committee ec.committee@scottish.parliament.uk. EDUCATION AND CULTURE COMMITTEE: WRITTEN EVIDENCE 22 April 2014

Clerk to the Education and Culture Committee ec.committee@scottish.parliament.uk. EDUCATION AND CULTURE COMMITTEE: WRITTEN EVIDENCE 22 April 2014 Clerk to the Education and Culture Committee ec.committee@scottish.parliament.uk EDUCATION AND CULTURE COMMITTEE: WRITTEN EVIDENCE 22 April 2014 Historic Environment Scotland Bill The Society of Antiquaries

More information

The Institute Business Plan - Review

The Institute Business Plan - Review Guildford Institute Strategic Plan to 2020 Foreword The objects of the Institute are set out in its Memorandum of Association [Art3]. They may be summarised as follows: To promote and advance the education

More information

Building Schools for the Future. Communications and Engagement Plan

Building Schools for the Future. Communications and Engagement Plan Building Schools for the Future Communications and Engagement Plan 1.0 Project Background BSF is a unique transformational project that will transform teaching and learning for young people, teachers and

More information

Investors in People 2013 - Communications Plan. Introduction What is IiP?

Investors in People 2013 - Communications Plan. Introduction What is IiP? Investors in People 2013 - Communications Plan Introduction What is IiP? Investors in People specialises in transforming business performance through our employees. It is designed to help the Council achieve

More information

Royal Borough of Kensington and Chelsea. Data Quality Framework. ACE: A Framework for better quality data and performance information

Royal Borough of Kensington and Chelsea. Data Quality Framework. ACE: A Framework for better quality data and performance information Royal Borough of Kensington and Chelsea Data Quality Framework ACE: A Framework for better quality data and performance information March 2010 CONTENTS FOREWORD 2 A CORPORATE FRAMEWORK FOR DATA QUALITY

More information

Agenda item: Environment & Community Safety Decision meeting

Agenda item: Environment & Community Safety Decision meeting Title of meeting: Agenda item: Environment & Community Safety Decision meeting Date of meeting: 14 th November 2014 Subject: Report by: Wards affected: Key decision: Full Council decision: Waste Disposal

More information

Successful Destination Management

Successful Destination Management Successful Destination Management What does this mean? Aviva Pearson MSc, BSc, FTS, MTMI Not the usual speech... Destination Management is about... Making me excited A Destination Manager must make me

More information

Place Scrutiny Briefing AGENDA ITEM 13

Place Scrutiny Briefing AGENDA ITEM 13 Place Scrutiny Briefing AGENDA ITEM 13 Meeting date: 13.7.15 Heading: Joint Spatial Plan and Joint Transport Study - Update Ward: All Bristol wards Author: Sarah O Driscoll Ext. No: 36722 Officer presenting

More information

UNIVERSITY OF SUSSEX. 1. Advertisement Ref: 482

UNIVERSITY OF SUSSEX. 1. Advertisement Ref: 482 UNIVERSITY OF SUSSE 1. Advertisement Ref: 482 Student Recruitment Services Marketing Manager Permanent, full time Salary range: starting at 30,728 and rising to 36,661 per annum. It is normal to appoint

More information

BRIEF BEAMISH MUSEUM County Durham Museums Learning Network schools marketing project. 1.0 About the project. Summary

BRIEF BEAMISH MUSEUM County Durham Museums Learning Network schools marketing project. 1.0 About the project. Summary BRIEF BEAMISH MUSEUM County Durham Museums Learning Network schools marketing project 1.0 About the project Summary County Durham Museums Learning Network, coordinated by Beamish Museum, is seeking to

More information

Archaeology in the UK Today:

Archaeology in the UK Today: Archaeology in the UK Today: Money, Power and Politics Robert Somers & Kathleen Hawthorne Lecture 1 Introduction and overview of archaeology in the UK today Lecture 2 How did it get that way? History and

More information

LEARNING OUTSIDE THE CLASSROOM HERITAGE SECTOR PARTNERSHIP STAFF PERFORMANCE MONITORING AND MANAGEMENT

LEARNING OUTSIDE THE CLASSROOM HERITAGE SECTOR PARTNERSHIP STAFF PERFORMANCE MONITORING AND MANAGEMENT LEARNING OUTSIDE THE CLASSROOM HERITAGE SECTOR PARTNERSHIP Guidance Notes STAFF PERFORMANCE MONITORING AND MANAGEMENT WHAT DO WE MEAN BY STAFF PERFORMANCE MONITORING AND MANAGEMENT? You expect your team

More information

1. Trustees annual report

1. Trustees annual report 1. Trustees annual report Accounting and reporting by charities Overview and the purpose of the trustees annual report 1.1. The primary purpose of the trustees annual report (the report) is to ensure that

More information

Northern Ireland Environment Agency Corporate Social Responsibility

Northern Ireland Environment Agency Corporate Social Responsibility Northern Ireland Environment Agency Corporate Social Responsibility September 2011 Introduction This document has been prepared by the Northern Ireland Environment Agency (NIEA) in line with general NICS

More information

1. The transfer of the service vehicle fleet and pool car fleet management to the County Council from 1 July 2013.

1. The transfer of the service vehicle fleet and pool car fleet management to the County Council from 1 July 2013. Cabinet Member for Finance and Resources and Cabinet Member for Highways and Transport Ref No. HT11(12/13) Service Vehicles Procurement Strategy November 2012 Report by Director of Business Change Key

More information

1 Executive Summary... 3. 2 Document Structure... 4. 3 Business Context... 5

1 Executive Summary... 3. 2 Document Structure... 4. 3 Business Context... 5 Contents 1 Executive Summary... 3 2 Document Structure... 4 3 Business Context... 5 4 Strategic Response... 6 4.1 Exploiting SharePoint... 6 4.2 Improving Business Effectiveness... 7 4.3 Improving Governance...

More information

UK TO HOST 2015 EUROPEAN OUTDOOR SUMMIT

UK TO HOST 2015 EUROPEAN OUTDOOR SUMMIT PRESS INFORMATION 16 TH October 2104 UK TO HOST 2015 EUROPEAN OUTDOOR SUMMIT The Outdoor Industries Association (OIA) is pleased to announce that it has been awarded the contract from The European Outdoor

More information

Strategic Guidance for Community Planning Partnerships: Community Learning and Development

Strategic Guidance for Community Planning Partnerships: Community Learning and Development Strategic Guidance for Community Planning Partnerships: Community Learning and Development COMMUNITY LEARNING AND DEVELOPMENT: STRATEGIC GUIDANCE FOR COMMUNITY PLANNING PARTNERSHIPS EXECUTIVE SUMMARY This

More information

Tourism Product Development and Marketing Strategies in the COMCEC Region

Tourism Product Development and Marketing Strategies in the COMCEC Region Standing Committee for Economic and Commercial Cooperation of the Organization of Islamic Cooperation (COMCEC) Tourism Product Development and Marketing Strategies in the COMCEC Region COMCEC COORDINATION

More information

PROPOSED FINAL DRAFT. Revised under the Auspices of the ICOMOS International Scientific Committee on Interpretation and Presentation.

PROPOSED FINAL DRAFT. Revised under the Auspices of the ICOMOS International Scientific Committee on Interpretation and Presentation. The ICOMOS Charter for the Interpretation and Presentation of Cultural Heritage Sites PROPOSED FINAL DRAFT Revised under the Auspices of the ICOMOS International Scientific Committee on Interpretation

More information

Good Practice Guidelines for Indicator Development and Reporting

Good Practice Guidelines for Indicator Development and Reporting Good Practice Guidelines for Indicator Development and Reporting A contributed paper Third World Forum on Statistics, Knowledge and Policy Charting Progress, Building Visions, Improving Life 27-30 October

More information

ICT Digital Transformation Programme

ICT Digital Transformation Programme Officer and Date Item Cabinet 11 th May 2016 Public ICT Digital Transformation Programme Responsible Officer: Clive Wright, Chief Executive Email: Clive.wright@shropshire.gov.uk Tel: 01743 252007 1.0 Summary

More information

MBA Business Administration (Information Technology)

MBA Business Administration (Information Technology) MBA Business Administration (Information Technology) International Students Can Apply UKPASS Code: Course Length: Start Dates: Department: P051837 12-18 Months Full-Time, 2-3 Years Part-Time January 2016,

More information

Progress Report Template -

Progress Report Template - Progress Report Template - Text in italics is explanatory and should be deleted in completed documents. Project Name Project Website Report compiled by CHARTER UNIVERSITY OF EXETER http://projects.exeter.ac.uk/charter/

More information

Individual Executive Member Decision

Individual Executive Member Decision Individual Executive Member Decision Title of Report: Report to be considered by: Date on which Decision is to be taken: Forward Plan Ref: Purpose of Report: Community Learning Supply Chain Charges and

More information

Aberdeen City Council self evaluation 2010 Public Library Quality Improvement Matrix (PLQIM)

Aberdeen City Council self evaluation 2010 Public Library Quality Improvement Matrix (PLQIM) Scottish Library & Information Council Aberdeen City Council self evaluation 2010 Public Library Quality Improvement Matrix (PLQIM) Summary In March 2010 Aberdeen City Library and Information Service s

More information

Strategic Plan to 2016/17 incorporating Annual Plan 2012-13

Strategic Plan to 2016/17 incorporating Annual Plan 2012-13 Strategic Plan to 2016/17 incorporating Annual Plan 2012-13 Introduction and high level description of scope of service In 1 paragraph, describe what service(s) you deliver and to whom The overall strategic

More information

Portfolio Holder Decision Making Session FUTURE MANAGEMENT OF BISHOP S CASTLE LIBRARY

Portfolio Holder Decision Making Session FUTURE MANAGEMENT OF BISHOP S CASTLE LIBRARY Portfolio Holder Decision Making Session Portfolio Holder for Business, ip&e, Culture and Commissioning (North) Monday 21 st September, 2pm, Item 1 Public/Private FUTURE MANAGEMENT OF BISHOP S CASTLE LIBRARY

More information

Bedford Girls School Job Description. Director of Music

Bedford Girls School Job Description. Director of Music Bedford Girls School The School is committed to safeguarding and promoting the welfare of children and young people and expects all staff and volunteers to share this commitment. Bedford Girls School will

More information

Cultural Heritage Management, Master Degree French University in Egypt, Programme Course Contents

Cultural Heritage Management, Master Degree French University in Egypt, Programme Course Contents Cultural Management, Master Degree French University in Egypt, Programme Course Contents Semester 1 216 30 Introduction to Cultural heritage Hours Credits Course [Module] Contents 18 2,5 Ses1& 2, Definitions

More information

Cambridge University Library. Working together: a strategic framework 2010 2013

Cambridge University Library. Working together: a strategic framework 2010 2013 1 Cambridge University Library Working together: a strategic framework 2010 2013 2 W o r k i n g to g e t h e r : a s t r at e g i c f r a m e w o r k 2010 2013 Vision Cambridge University Library will

More information

Senior Project Manager (Web Content Management)

Senior Project Manager (Web Content Management) Senior Project Manager (Web Content Management) IT Services Portfolio & Project Management Office Salary Grade 8-40,046 to 45,053 per annum Fixed term contract for 2 years (** see below for contract information)

More information

ABOUT LOUGHBOROUGH UNIVERSITY LONDON

ABOUT LOUGHBOROUGH UNIVERSITY LONDON ABOUT LOUGHBOROUGH UNIVERSITY LONDON BUSINESS DEVELOPMENT MANAGER JOB REF: REQ15456 JULY 2015 As part of the University s ongoing commitment to redeployment, please note that this vacancy may be withdrawn

More information

Tower Hamlets Education Business Partnership JOB DESCRIPTION

Tower Hamlets Education Business Partnership JOB DESCRIPTION Tower Hamlets Education Business Partnership JOB DESCRIPTION Project Manager National Number Partners (12 Month Fixed Term) MAIN PURPOSE OF JOB 1. The post holder will increase the Number Partner schemes

More information

Argyll and Bute Council. Information Management Strategy 2014-2018

Argyll and Bute Council. Information Management Strategy 2014-2018 Argyll and Bute Council Information Management Strategy 2014-2018 Version 1.3 November 2014 $Hcxs4vps.Docx INDEX 1. INTRODUCTION... 3 1.1 Purpose of the Document... 3 2. INFORMATION MANAGEMENT OVERVIEW...

More information

Communication Capability Review: Department for Business, Innovation & Skills

Communication Capability Review: Department for Business, Innovation & Skills Communication Capability Review: Department for Business, Innovation & Skills 1 1 Management summary 1.1 The Communication Capability Review of the Department for Business, Innovation and Skills (BIS)

More information

Funding Awareness: Bi-Annual Report and Development Planning January - June 2015

Funding Awareness: Bi-Annual Report and Development Planning January - June 2015 1. Executive Summary This paper sets out the achievements of the Funding Awareness Team for the period January June 2015. Funding Awareness: Bi-Annual Report and Development Planning January - June 2015

More information

Volunteer Inclusion Programme. A Renaissance London publication

Volunteer Inclusion Programme. A Renaissance London publication Volunteer Inclusion Programme A Renaissance London publication 1 contents Contents Renaissance London is a strategic investment in museum development and public programmes, run in partnership by the London

More information

Managing Successful Programmes

Managing Successful Programmes Managing Successful Programmes Syllabus 2011 (Version 2.0 - July 2012) 1. Introduction The Managing Successful Programmes (MSP) guidance explains the programme management principles, governance themes

More information

Application Information Pack CRM Project Manager

Application Information Pack CRM Project Manager Application Information Pack CRM Project Manager Introduction to Girlguiding Thank you for your interest in the role of CRM Project Manager. This document provides information relating to the above vacancy

More information

Blackburn College Teaching, Learning and Assessment Strategy. 25 August 2015

Blackburn College Teaching, Learning and Assessment Strategy. 25 August 2015 Blackburn College Teaching, Learning and Assessment Strategy 25 August 2015 1 Introduction This document provides a Teaching, Learning and Assessment Strategy covering all of the College s Further Education

More information

Procurement Strategy 2013-2017 Delivering Social Value for our Community

Procurement Strategy 2013-2017 Delivering Social Value for our Community Procurement Strategy 2013-2017 Delivering Social Value for our Community Making Bath & North East Somerset an even better place to live, work and visit 1 Picture courtesy of Bath & News Media Group Our

More information

Houses of the Oireachtas Commission Communications Strategy 2012-2014

Houses of the Oireachtas Commission Communications Strategy 2012-2014 Houses of the Oireachtas Commission Communications Strategy 2012-2014 Increasing understanding and improving public perception of the Houses of the Oireachtas Houses of the Oireachtas Commission Communications

More information

Specialist work based placement in Archaeobotany with Historic England. Training Plan

Specialist work based placement in Archaeobotany with Historic England. Training Plan Specialist work based placement in Archaeobotany with Historic England Training Plan Introduction This document sets out the background to the placement, the desired outcomes and the skills it offers.

More information

COMMUNITY ENGAGEMENT PLAN

COMMUNITY ENGAGEMENT PLAN COMMUNITY ENGAGEMENT PLAN APRIL 2013 to MARCH 2015 Background The Council is committed to working closely with the public as part of fulfilling its community engagement role. Community engagement includes

More information

Scotland Your project business plan

Scotland Your project business plan Scotland Your project business plan Scotland Your project business plan Further copies available from: Email enquiries.scotland@biglotteryfund.org.uk Phone 0870 240 2391 Textphone 0141 242 1500 Our website

More information

COMMUNITY LEARNING DIRECTOR

COMMUNITY LEARNING DIRECTOR Jersey Heritage Information on the role of Contents: COMMUNITY LEARNING DIRECTOR About Jersey Heritage Our purpose Our aims Our standards Our visitor sites and commercial services Other services and events

More information

CABINET. Tuesday, 17th June, 2014. Present:- Councillor Burrows (Chair)

CABINET. Tuesday, 17th June, 2014. Present:- Councillor Burrows (Chair) 1 CABINET Tuesday, 17th June, 2014 Present:- Councillor Burrows (Chair) Councillors Blank Gilby Ludlow McManus Russell Serjeant Non Voting Members Brown Hill Hollingworth *Matters dealt with under Executive

More information

Project Manager Middleton: Paradise Regained

Project Manager Middleton: Paradise Regained Project Manager Middleton: Paradise Regained The restoration of the Garden s Regency landscape is an exciting and ambitious new project at the National Botanic Garden of Wales supported by a substantial

More information

Town Hall Gallery Art Collection Strategy

Town Hall Gallery Art Collection Strategy Art Collection Strategy 2010-2015 Responsible Directorate: Community Development Authorised by: Council Date of adoption: 13 December 2010 Review date: December 2014 Expiration date: 13 December 2015 1

More information

What we said we d achieve in 2011/12 Priority Outcome: Prosperity Economic Resilience

What we said we d achieve in 2011/12 Priority Outcome: Prosperity Economic Resilience What we said we d achieve in 2011/12 Priority Outcome: Prosperity Economic Resilience How did we do? RED AMBER GREEN Not Rated 5 0 14 2 We said we would: Facilitate economic growth through job creation

More information

CONTENTS. Preface 3 by Hon. Donald Tsang, Acting Chief Executive. Approaching a First Sustainable Development 5 Strategy for Hong Kong

CONTENTS. Preface 3 by Hon. Donald Tsang, Acting Chief Executive. Approaching a First Sustainable Development 5 Strategy for Hong Kong CONTENTS Preface 3 by Hon. Donald Tsang, Acting Chief Executive Approaching a First Sustainable Development 5 Strategy for Hong Kong Challenges for Hong Kong s Sustainable Development 8 Strategic Objectives

More information

DIGITAL STRATEGY 2014-2017

DIGITAL STRATEGY 2014-2017 DIGITAL STRATEGY 2014-2017 Digital Strategy CONTENTS Introduction 1 Our Vision 3 Benefits 5 Our Digital Design Principles 6 Our Strategy 8 Our Key Enablers 11 INTRODUCTION SFRS uses digital technology

More information

The Way Forward: Strategic clinical networks

The Way Forward: Strategic clinical networks The Way Forward: Strategic clinical networks The Way Forward Strategic clinical networks First published: 26 July 2012 Prepared by NHS Commissioning Board, a special health authority Contents Foreword...

More information

Bi-annual up-date on activity of Portsmouth Adoption Agency. Stephen Kitchman, Head of Children s Social Care & Safeguarding

Bi-annual up-date on activity of Portsmouth Adoption Agency. Stephen Kitchman, Head of Children s Social Care & Safeguarding Agenda item: Title of meeting: Subject: ren & Education Portfolio Decision Meeting Bi-annual up-date on activity of Portsmouth Adoption Agency Date of meeting: 06 March 2014 Report by: Written by: Wards

More information

Lottery Capital Programme: Feasibility Studies

Lottery Capital Programme: Feasibility Studies Arts Council of Wales Funding Application Help Notes Lottery Capital Programme: Feasibility Studies October 2012 Arts Council of Wales is committed to making information available in large print, braille,

More information

Skills Audit for Researchers

Skills Audit for Researchers Skills Audit for Researchers Date: Section 1: Research Management Skills 1) Research management to be able to: Project management 1.1) Apply effective project management through the setting of research

More information

HARLOW COUNCIL PERFORMANCE MANAGEMENT FRAMEWORK

HARLOW COUNCIL PERFORMANCE MANAGEMENT FRAMEWORK HARLOW COUNCIL PERFORMANCE MANAGEMENT FRAMEWORK July 2013 1 P age Contents Page 1.0 Definition 3 2.0 Context 3 3.0 Purpose and aim of the policy 4 4.0 Policy Statement 4 5.0 Framework for Performance Management

More information

2014-2017 Statewide Strategic Communications and Public Awareness Campaign

2014-2017 Statewide Strategic Communications and Public Awareness Campaign OVERVIEW The Massachusetts Board of Library Commissioners (MBLC) is the agency of state government with the statutory authority and responsibility to organize, develop, coordinate and improve library services

More information

Planning & Building Standards. Draft Customer Engagement Strategy August 2015

Planning & Building Standards. Draft Customer Engagement Strategy August 2015 Draft Customer Engagement Strategy August 2015 1. Introduction 1. Who are our customers? 2. What is engagement? 2. Consulting with our customers 7. Communicating with our customers 9. Planning information

More information

MARKETING & FUNDRAISING STRATEGY WORKSHOP FOR BAFA CONFERENCE by Debbie Liggins, Business Development Director, Orchestra of the Swan.

MARKETING & FUNDRAISING STRATEGY WORKSHOP FOR BAFA CONFERENCE by Debbie Liggins, Business Development Director, Orchestra of the Swan. MARKETING & FUNDRAISING STRATEGY WORKSHOP FOR BAFA CONFERENCE by Debbie Liggins, Business Development Director, Orchestra of the Swan Strategy Strategic planning focusses on longer range objectives and

More information

TOOL D14 Monitoring and evaluation: a framework

TOOL D14 Monitoring and evaluation: a framework TOOL D14 Monitoring and evaluation: a framework 159 TOOL D14 Monitoring and evaluation: a framework TOOL D14 For: About: Purpose: Use: Resource: Commissioners in primary care trusts (PCTs) and local authorities

More information

IT strategy. What is an IT strategy? 3. Why do you need an IT strategy? 5. How do you write an IT strategy? 6. Conclusion 12. Further information 13

IT strategy. What is an IT strategy? 3. Why do you need an IT strategy? 5. How do you write an IT strategy? 6. Conclusion 12. Further information 13 IT strategy made simple What is an IT strategy? 3 Why do you need an IT strategy? 5 How do you write an IT strategy? 6 step 1 Planning and preparation 7 step 2 Understanding your organisation s IT needs

More information

Employee Performance Management Policy and Procedure

Employee Performance Management Policy and Procedure Employee Performance Management Policy and Procedure Document Control Document Ref: HREPM001 Date Created: Sept 2007 Version: 1.4 Date Modified: April 2015 Revision due Author: Jane Milone Sign & Date:

More information

Seminar E3 Developing an Effective Leadership Culture to Support Business Change

Seminar E3 Developing an Effective Leadership Culture to Support Business Change Seminar E3 Developing an Effective Leadership Culture to Support Business Change Inji Duducu Group People Director Benenden @injiduducu The Benenden Story - transformation Background The Challenge April

More information

Overview of Washington Think Tanks

Overview of Washington Think Tanks Overview of Washington Think Tanks Paul B. Ginsburg, Ph.D. Presentation to 2006 Health Policy Synergy Workshop, IOM Center for Studying Health System Change (HSC) Research on changes in the organization

More information

Job No. (Office Use) Directorate Corporate Services Department Programme Management Office Reports to (Job Title) If No state reason

Job No. (Office Use) Directorate Corporate Services Department Programme Management Office Reports to (Job Title) If No state reason ROLE PROFILE Transformation Programmes Manager Role Profile Job Title Transformation Programme Manager Job No. (Office Use) C6074 Grade (Office Use) Directorate Corporate Services Department Programme

More information

Royal College of Music

Royal College of Music Royal College of Music ICT Strategy 2013 to 2017 ICT Strategy 2007 to 2017 update: 2013 2017 Optimisation stage Author Mark Soole Date 8 th October 2013 Version number V2.12 Status Approved Approval date

More information

Towards 2020 The British Museum s Strategy

Towards 2020 The British Museum s Strategy Towards 2020 The British Museum s Strategy 1 1. Principles and Purpose The British Museum is an Enlightenment ideal. Its Trustees are responsible for making it, in each generation, a continuing reality.

More information

Performance Detailed Report. Date. Last saved: 12/10/2007 13:18:00. Property asset management. Bristol City Council. Audit 2006/07

Performance Detailed Report. Date. Last saved: 12/10/2007 13:18:00. Property asset management. Bristol City Council. Audit 2006/07 Performance Detailed Report Date Last saved: 12/10/2007 13:18:00 Property asset management Audit 2006/07 - Audit Commission descriptor to be inserted by Publishing- Document Control Author Filename Bob

More information

CAPITAL INVESTMENT POLICY

CAPITAL INVESTMENT POLICY CAPITAL INVESTMENT POLICY Document Profile Box Document Reference: Version: 0001 Ratified by: Trust Board Date ratified: March 2009 Name of originator/author: Duncan Sellers Name of responsible committee/individual:

More information

Planning Application Non Technical Summary. Planning Application Document A May 2013. Defence College of Technical Training Lyneham

Planning Application Non Technical Summary. Planning Application Document A May 2013. Defence College of Technical Training Lyneham Planning Application Non Technical Summary Planning Application Document A May 2013 Defence College of Technical Training Lyneham 2 Defence College of Technical Training, Lyneham Integrating Technical

More information

GIANT S CAUSEWAY AND CAUSEWAY COAST WORLD HERITAGE SITE. Management Plan. Summary

GIANT S CAUSEWAY AND CAUSEWAY COAST WORLD HERITAGE SITE. Management Plan. Summary GIANT S CAUSEWAY AND CAUSEWAY COAST WORLD HERITAGE SITE Management Plan Summary FEBRUARY 2005 INTRODUCTION Background and Context The WHS Management Plan for the Giant's Causeway and Causeway Coast World

More information

The Community Infrastructure Levy: advice note for culture, arts and planning professionals

The Community Infrastructure Levy: advice note for culture, arts and planning professionals The Community Infrastructure Levy: advice note for culture, arts and planning professionals Martin J Elson, Emeritus Professor in Planning, Oxford Brookes University April 2012 Contents Aims of the advice

More information

Guidelines for Professional Library/Information Educational Programs

Guidelines for Professional Library/Information Educational Programs Guidelines for Professional Library/Information Educational Programs These guidelines were endorsed by the IFLA Professional Committee at its meeting in August 2012 Executive summary These guidelines replace

More information

Programme Manager Relationship Management System

Programme Manager Relationship Management System Programme Manager Relationship Management System Russam Ref 4573 Job Profile This document is a generic description for the role. Any specific requirements in the published advert should also be taken

More information

Management Board / Performance Panel / Cabinet. Corporate Improvement Officer (Performance) (Rachel Glynn)

Management Board / Performance Panel / Cabinet. Corporate Improvement Officer (Performance) (Rachel Glynn) Agenda Item No... REPORT TO: Management Board / Performance Panel / Cabinet DATE: 15 th May 2014 / TBC / 18 th June 2014 SERVICE AREA: REPORTING OFFICER: SUBJECT: WARD/S AFFECTED: Corporate Affairs Corporate

More information

Director of Income Generation job description and person specification

Director of Income Generation job description and person specification Director of Income Generation job description and person specification Job title Reporting to Key relationships Responsible for Director of Income Generation Chief Executive Internal: CEO, Executive Strategy

More information

Draft. Flintshire County Council Events Strategy 2014-2017. 1 Introduction

Draft. Flintshire County Council Events Strategy 2014-2017. 1 Introduction Draft Flintshire County Council Events Strategy 2014-2017 1 Introduction Events and festivals can be positive economic and social drivers encouraging financial and social investment by a wide range of

More information

Evaluability Assessment Template

Evaluability Assessment Template Evaluability Assessment Template Evaluability Assessment Template An Evaluability Assessment examines the extent to which a project or a programme can be evaluated in a reliable and credible fashion. An

More information

Accreditation Scheme for Museums and Galleries in the United Kingdom: Accreditation Standard

Accreditation Scheme for Museums and Galleries in the United Kingdom: Accreditation Standard Accreditation Scheme for Museums and Galleries in the United Kingdom: Accreditation Standard October 2011 Contents Introduction 4 Eligibility 6 Requirements for Accreditation 7 1 Organisational health

More information

Management and Leadership. Level 5 NVQ Diploma in Management and Leadership (QCF)

Management and Leadership. Level 5 NVQ Diploma in Management and Leadership (QCF) Management and Leadership Level 5 NVQ Diploma in Management and Leadership (QCF) 2014 Skills CFA Level 5 NVQ Diploma in Management and Leadership (QCF) Page 1 Level 5 NVQ Diploma in Management and Leadership

More information

Income, innovation and investment Contents

Income, innovation and investment Contents Income, innovation and investment Contents Part one Policy... 2 Chapter 1 Definitions... 3 Income... 4 Innovation and ideas... 6 Investment... 6 Chapter 2 Principles... 7 VAT... 9 Part two Policy procedure...

More information

Schools Liaison and Events Coordinator

Schools Liaison and Events Coordinator Schools Liaison and Events Coordinator Ref: 15-075 18,700 20,400 per annum Actual Salary 7,500 8,200 15 Hours per week, 52 Weeks per Year Fixed term until January 2017 The Marketing and Communications

More information

Asset Management Strategy

Asset Management Strategy Asset Management Strategy File Ref: CM.STD.6 Synergy Ref: NMP1331737 Version: 25/06/2013 City of Albany 2013 102 North Road, Yakamia WA 6330 PO Box 484, ALBANY WA 6331 Tel: (08) 9841 9333 Fax: (08) 9841

More information

Business Continuity Management Policy

Business Continuity Management Policy Business Continuity Management Policy Policy Holder: Authoriser: Caroline Gover, Head of Business Continuity Caroline Thomson, Chief Operating Officer Reviewed on: Feb 08 Reviewed on: Feb 08 Next Review

More information

Policy for Citizens Services and Libraries 2011 2014. Short version

Policy for Citizens Services and Libraries 2011 2014. Short version Policy for Citizens Services and Libraries 2011 2014 Short version Libraries must be local community centres, places for knowledge and citizens services, which in coherence with locally rooted activities

More information