BUY OR BUILD DATA CENTRE BEST PRACTICE GUIDE. White Paper

Size: px
Start display at page:

Download "BUY OR BUILD DATA CENTRE BEST PRACTICE GUIDE. White Paper"

Transcription

1 BUY OR BUILD DATA CENTRE BEST PRACTICE GUIDE White Paper Morris Pentel Publication date: January 2013

2 BUY OR BUILD DATA CENTRE BEST PRACTICE GUIDE EXECUTIVE SUMMARY For most large organisations there is a growing need for data centre capacity. Shaped by competing data trends, this need has become the heart of one of the most significant decisions for IT Directors. Providing data centre capacity to meet the growing needs of the organisation has become a higher priority and its importance is likely to increase over the next few years. The drive towards the use of Big Data applications and personalised content is shaping the consumer landscape and will see a dramatic increase in the amount of data that organisations will need to manage. With massive growth in data centre capacity being delivered by third party suppliers to meet the increasing demand, the role of the privately-owned data centres is reducing. HIGHLIGHTS The key drivers for most organisations are security, availability and cost Data Centre design is now significantly more sophisticated and this is impacting operational costs through the delivery of more efficient data centres Buying services: Significantly lower risks than building Benefits come on-stream much faster You can buy in increments as you grow No or little capex required Building your own Much higher risk of delays and cost overruns Capex may be expended months before any deliverable and ROI is likely to take significantly longer. The facility is unlikely to be fully utilised for a lengthy period Skills and locations are now at a premium The growth in the third party supply market means that state of the art data centres are being commissioned. IMPORTANT CONSIDERATIONS In a recent study as part of this series, The Data Centre Power Efficiency Study 2012, we asked what factors are driving the internal agenda around data centres. For most of 125 respondents, security, resilience and cost were the top three drivers. However this does not mean that other factors such as location were not considered but were a slightly lower priority. We also found that there is a significant level of misunderstanding about the role of new data trends, such as Big Data and personalisation among IT professionals. These trends are both helping to shape the customer experience of the next three years. 2

3 SECURITY 4.50 RESILIENCE COST FLEXIBILITY SUPPLIER REPUTATION PUE ABILITY TO PROVIDE NETWORK SERVICES ABILITY TO PROVIDE OWN MANAGED SERVICES SUPPLIER TYPE LOCATION Base: 125 data centre decision-makers working in large organisations, mean score if you were considering working with a new data centre provider for the first time, how important are the following in your selection criteria? (1 not at all important, 5 very important) As the growth in data centre requirements increases across all enterprises, scarcity of qualified resource with skills in all of the disciplines required to deliver the solution is also a significant barrier. BUY -V- BUILD There has been a significant change in Data Centre best practice over the last three years. The viability of building your own data centre has been reducing over the last few years, driven by complexity of data centre requirements and design, scarcity of resource and the increasing range of offers from third party suppliers in a maturing market. The decision drivers around BvB have in some ways become much simpler as conditions have changed. These trends mean that best practice is now focused on how to get the best from third party suppliers rather than the question of BvB. One of the key decisions at the heart of the data centre agenda has to be the question of BvB. For many, this is a relatively simple decision on the use of opex over capex. Third party suppliers will offer opex pricing models which are based on usage. In challenging financial conditions this has some key advantages around cost including ability to pay for additional capacity when it is brought on stream rather than paying for space which lies empty in anticipation of future need. Such flexibility means that cost is more predictable as needs change. The viability of building your own data centre has been reducing... driven by complexity of data centre requirements and design, scarcity of resources and by the increasing range of offers from third party suppliers in a maturing market. CE10734 Version 1 January

4 BUY OR BUILD DATA CENTRE BEST PRACTICE GUIDE It is also worth considering that only the very largest data centre requirements are likely to see a theoretical lower cost with Build. That lower cost may produce only minimal benefits considering the effort and resource involved. With a very active market of third-party data centre providers opening new facilities, there has never been a better time to look at what s on offer in the market. However the theory that it might cost less is unlikely to provide measurable benefits. Given the three to five year cycle of initial return on investment (see costs over leaf) it is debatable whether there are any real benefits, but significant risk. BUILDING RISKS At a time when professional data centre operators are adding so much capacity, building your own makes sense in only a few situations. For most organisations what is available is both cheaper and built to a better standard than is economic to build by the average enterprise. As the growth in data centre requirements increases across all enterprises, scarcity of qualified resource with skills in all of the disciplines required to deliver the solution is also a significant barrier. In some ways this is the tipping point of a quiet revolution, like the use of cloud services or the move towards BYOD (Bring your Own Device). As we move into the age of Big Data, less and less organisations will be able to justify the cost and effort involved in delivering the private data centre. It seems likely that only the very smallest and largest organisations will operate in this way in the medium term. But it is not just a cost issue. Designs are becoming more sophisticated, leveraging better cooling and more efficient power usage. Quality site locations are at a premium. These factors impact the cost and value of the data centre making the build your own solution less and less attractive. As a one-off exercise, finding the site, the people to deliver on time and the budget is a significant risk. With the real value of data centres design being best-in-breed efficiency, most organisations simply cannot afford to match the investments of professional providers. As the growth in data centre requirements increases across all enterprises, scarcity of qualified resource with skills in all of the required disciplines is also a significant barrier. Best Practice - Third party providers are inevitable more aware of the innovations and best practice of their competitors and therefore able to build those innovations into their designs. They also update their facilities on a regular basis to maintain competitiveness. COST When looking at building a data centre you are considering the Total Cost of Ownership(TCO) over a six to eight year period. Front end costs are extremely high and the benefits take a long time to come on-stream with Return of Investment (ROI) thresholds sometimes not appearing for three or four years. The design and implementation costs are paid for well in advance of operational availability of the data centre, and the time period from the search for a site to becoming operational can be 18 months or longer. When looking at building your own data centre, these long cycles for ROI combined with the attendant risks have reduced the attractiveness of direct ownership. Site and building costs together with IT Infrastructure costs need to be funded well in advance of any operational benefits. However, the largest element in large scale data centre costs is power. Analysts suggest that around 70% of operating cost is power consumption. Therefore operational efficiency and a keen eye on energy pricing is a must. In a recent report around power efficiency in this series The Data Centre Power Efficiency Study 2012 the Customer Experience Foundation concluded that the majority of organisations were not on top of their energy costs. 4

5 PUE (BASIC EQUATION) POWER UTILISATION EFFICIENTCY TOTAL POWER FACILITY = : IT EQUIPMENT POWER Best Practice In-house builds are capital-intensive and do not pay back for many years. Working with third party data centre suppliers can change that to an Opex on-demand model, a much more cost efficient route. PUE (POWER USAGE EFFECTIVENESS) In addition to this lack of focus on operational cost, very few organisations have a handle on PUE cost impacts. PUE measurements are not universally standard as various different ways of measuring the elements of the PUE equation exist. However this variation is marginal when considering overall cost. A 0.1 point drop in PUE at today s prices is equivalent to a headcount reduction of full time staff for a large data centre. Over the lifecycle of a data centre this is a significant reduction. The average PUE in the US according to American Government published figures is around 2.0 and it is probably slightly higher in the UK. Best practice from third party suppliers in PUE now produces data centres with PUE ratings of This means that most organisations can save 0.9 points or the cost of headcount at today s prices. However, this is not the whole story. We are all expecting significant rises in the cost of power over the next few years and this will magnify the impact of PUE saving. It is also worth noting that the impact of PUE reductions is measured in hundreds of thousands of tons of CO2 emissions across UK PLC. Many commentators on environmental issues see the growth of data centres as an additional and significant threat to air quality and public health. It is therefore possible that during the immediate future we will see an increased focus on CRC (Carbon Reduction Commitment) tax schemes. As we head towards the next election it is likely to be higher on the political agenda. CONTROL For some organisations the need to have control over every aspect of their computing and data environment is translated into the requirement to build and operate their own data centre. With the range of offerings in the market place, this need for control may be more an emotional feeling rather than the necessity it was five years ago. Security options from third parties can range from shared server environments to complete secure and dedicated environments meeting the highest government security standards. Not all suppliers will offer a complete range of these facilities but it is relatively simple to find one that will meet your requirements. Where control is a major issue then co-location offerings are more attractive. The third party supplier delivers the physical infrastructure allowing the organisation the opportunity to focus on their core operational skill. Best Practice Although control is highly desirable, third party suppliers of data centres now offer plenty of controls, considered equal to most in-house arrangements. With this barrier removed, working with the supplier to embed SLAs and KPIs that are easily measurable is the best option. CE10734 Version 1 January

6 BUY OR BUILD DATA CENTRE BEST PRACTICE GUIDE SCALABILITY One of the key factors to consider when looking at a data centre provider has to be scalability and the ability to meet changing needs for computing power, storage and network links. The capability to respond to changing requirements, adding space and power density efficiently is essential as is an on-demand model with a sound commercial proposition and clear ROI. Is the solution capable of providing additional space or indeed less space in a flexible way when and if your needs change? Are you locked in to an inflexible long term contract that means scalability comes at significant cost? A requirement today could be for 10 rack spaces with an option for a further 5 racks that may be needed in the future. Best Practice Suppliers who provide scalable options built into their offering without adding cost until those options are invoked. A good supplier should also be able to identify additional impacts of any expansion. Denser racks will have additional power and cooling needs and these should be clearly articulated by your supplier. The impact of getting this part right is that you are less likely to need to move location quickly and in the future that improves the return on investment. SECURITY AND PROTECTION Our research programme suggested that security is one of the highest priorities in any decision around the data centre, so physical security is an important consideration. A data centre provider should offer a range of security options to ensure your information is protected at all times. Biometric security, keypad, card readers and digital camera placement are some of the physical tools. Best Practice - Sophisticated Data Centre designs will incorporate motion sensors and thermal cameras which have an impact on overall energy efficiency, switching off lights in unused areas and identifying hot spots. Security procedures for highly secure facilities will include tactics to ensure that mobile devices with recording capabilities are not allowed in secure areas. It is important to understand that technology is only part of the security picture. Physical security starts well beyond the server room and will include an approach with un-named buildings that are protected from ram raids by appropriate physical barriers behind fences that prevent visibility of the site. RESILIENCE AND REDUNDANCY A supplier will have an N+1 design providing redundancy in power, cooling and network Infrastructure, to give the maximum uptime. Separate diverse routes for power and networking tend to be more expensive to get right. When delivered as a service (by a third party), the costs are shared and with opex options this becomes attractive. It is important to understand the design and SLAs offered in order to recognise the benefits of a third party. Sometimes diverse routing is built into a design but the power or network joins a single track or pipe to the cabinet. This is not real redundancy. Other factors to be considered are the design for backup power generation and UPS (Uninterruptable Power Supply). A third party supplier should be able to identify how long backup systems will to keep running in the event of a major failure, and in most cases this will mean the number of gallons of diesel they have in their on-site tanks. One of the other cost factors involved in the resilience and redundancy picture is replication to a second site. Where mission critical applications and data are involved, best practice should include the ability to respond to a complete loss of a site. In this case the only solution is a second site where data is constantly replicated. Few organisations can produce a business case to build that second site and 6

7 therefore turn to third party suppliers for a solution. Given this reliance on outside organisations for part of the solution, the value of ownership of the primary data centre is less clear. A single supply relationship is likely to produce more financial benefits. Best Practice A good design should have completely diverse routes to the data centre site for key services. A great design will have diverse routes to each cabinet. It is important to understand if there are any single points of failure in the design where diverse routes may meet in the same physical location or trunking. The acid test should be to identify if there is a single point on the way to the cabinet where an interruption will cause failure. In best practice, services only meet at the actual cabinet. There will also be layers of physical security noted above. COOLING Cooling is one of the key cost factors because it forms a significant part of the power cost. The best practice focus is on efficiency. This can mean that the cooling units are the most modern and energy efficient but consideration must also be given to what is being cooled. Some designs will cool servers rather than rooms, saving money. Best Practice Strategy - The cooling strategy should focus on the server rather than the whole room. This is much more energy efficient and has a direct impact on cost. Good strategies will probably involve several strands of coordinated activity including techniques for the dissipation of heat as well as refrigeration. As a strategy, free air cooling (using cooler outside air) is becoming common and doesn t require refrigeration for many days of the year cutting power consumption further. LOCATION Location selection is driven by ease of access and convenience of travel. The ideal data centre location must be close to rail, motorway and airport links with zero flood risks. It should take account of power and network connectivity availability. Land costs vary significantly according to location and this has an impact on budgets. Connectivity speeds have an impact on customer and staff experience potentially raising costs. Ensuring both diversity and speed is a key challenge with which a third party supplier can help. Best Practice - To deliver real resilience, power and connectivity must be available from multiple suppliers. The need for high security combined with this profile means that good sites are few. One third party supplier s search for the right site in South East England took nearly two years. Issues such as planning permissions must be considered which again raises questions around the practical viability of building a facility from scratch rather than finding one that has already been commissioned. MIGRATION RISKS Moving a data centre is a technically risky event (by definition because it is a change of state) but good practice amongst the experts results in few real failures so experience and good planning are obviously key. One of the most common concerns during a data centre migration is around service interruption. Another is around loss of data during the migration process. This applies to any move whether internal or to a third party site. However, there is an advantage when working with a third party supplier. You should be able to access their experience of moving data centres on a regular basis. Your data centre supplier should be well practiced in managing a variety of infrastructure challenges. Internal moves are far less frequent so the risks can be higher. Best Practice - A good provider will be able to articulate a clear risk mitigation strategy. They should also be able to provide you with expert support on any planned move. Some provide internal resources and others work with specialist third parties depending on the size and complexity of the requirement. CE10734 Version 1 January

8 BUY OR BUILD DATA CENTRE BEST PRACTICE GUIDE APPROPRIATE SUPPLIERS If the balance of best practice now favours Buy rather than Build then the final question has to be the profile of suppliers? This will depend on the nature and size of the requirements and the type of customer organisation. There are many options. For smaller organisations with relatively simple requirements, shared services with no frills are available. For larger organisations, the choice is a little more complex. It is important to go through a supplier selection process that looks at needs today and in the future. Suppliers must demonstrate their design efficiency credentials as well the fundamentals such as price and service offerings. Good data centre suppliers build facilities that allow customers to deploy services rapidly and in a flexible way. Our research combined with market intelligence suggests that third party suppliers can be broken down into four groups. (See table) Each of these groups can provide different advantages but our research strongly suggested that Communication Service Providers are seen as significantly more credible by large organisations. Their expertise in service continuity together with their ability to offer network connectivity clearly impacted this perception. Organisations like Cable&Wireless Worldwide with new data centre facilities offer a range of options from simple co-location to full managed services. This state-of-the-art centre and others like it are hard to beat in a build your own scenario. The expertise available to customers and the location and design mean they have successfully leveraged their years of experience to provide facilities that most organisations will not be able to match. The competition in the market is driving the delivery of state of the art facilities that have to be considered when looking at Data Centre requirements and the question of Build or Buy. 28% 34% Co-location/data centre providers (e.g. Equinx, Telecity, Telehouse) 13% 13% Hosting providers (e.g. Rockspace, Savvis) Systems Integrators and IT companies (e.g. Accenture, Cap Gemeni, Fujitsu, HP, IBM) Communications Service Providers (e.g. Cable&Wireless Worldwide, BT Global services, Colt, Verizon) Base: 125 data centre decision-makers working in large organisations, how credible do you consider the following types of supplier in terms of provision of data centre services? (respondents who identified supplier as highly credible) CE10734 Version 1 January

9 CONCLUSION AND RECOMMENDATIONS In conclusion, data centre best practice nowadays favours working with a third part supplier. The advantages of scale, reduced Capex and the latest design and technology, high security, a choice of locations makes this the most compelling option. Shown below is a basic best practice checklist: 1. Buy v Build decision Ensure that you have a clearly articulated build requirement that you have costed realistically before making contact with suppliers. 2. Best Practice Get advice from third party suppliers on how they benchmark, and the various standards they have to meet. 3. Business Continuity Has proper consideration been given to service interruption and how has this been articulated to you? 4. Design A good design should demonstrate security, diverse routing, power efficiency and consideration of customer needs such as customer facilities and flexible offerings. Where possible visit as many third party data centres as you can to get design ideas. 5. Length of contract most suppliers will offer a range of contract lengths. Ensure that you take the one that meets your needs for stability with opportunities for review. 6. Location Your staff will probably have to spend time in the data centre so what are the transport links? 7. Penalties Ensure there are financial penalties built into the SLAs for any service interruption or security failure. 8. PUE It is important to understand your stated PUE and that of your supplier and whether it has been achieved. It should demonstrate good design as well as the latest and most efficient technology. 9. Security Use common standards to define what is the right level for your needs. Paying for unneeded levels of security can be expensive. Remember physical security is as important as IT security. 10. Growth Ensure that possible future growth is considered and built in to your business case. This additional space should be delivered on flexible terms. HOW CABLE&WIRELESS WORLDWIDE CAN HELP Building and running your own data centre infrastructure puts the onus on you to manage your computing and data, and absorb escalating costs as you add capacity. It ties up your IT employees when they could be contributing to your business prosperity. We provide a range of crucial benefits allowing customers to deploy services rapidly and in a flexible way: Utmost efficiency saves money Power Usage Effectiveness (PUE) of 1.25 ensures no money is wasted on expensive power Ideal locations Eight across the UK, well connected to road and ground transport Highest level of security Secure to Government List X and fully compliant to ISO Highest quality The power density enables you to fully occupy cabinets with the best ancillary equipment and Uptime Institute Tier III accredited The best connectivity and network options Our data centres are directly connected to our Multi-Service Platform network, meaning that you are a core component of the secure Cable&Wireless Worldwide Wide Area Network. There is also Internet access. FIND OUT MORE For more information about our co-location proposition and how Cable&Wireless Worldwide can enable you to build a more agile platform for growth while driving down your operational costs, and to arrange to meet with a data centre specialist, please contact us: T: E: HostingEnquiries@cw.com CE10734 Version 1 January

10 BUY OR BUILD DATA CENTRE BEST PRACTICE GUIDE CE10734 Version 1 January

11 CE10734 Version 1 January

12 CE10734 Copyright Cable and Wireless Worldwide plc. All rights reserved. Registered in England and Wales. No

OUTSOURCE or INSOURCE A Datacentre Buy or Build Guide

OUTSOURCE or INSOURCE A Datacentre Buy or Build Guide White Paper OUTSOURCE or INSOURCE A Datacentre Buy or Build Guide Yidan Wang V1.1 Oct 2013 A MATHEMATICAL APPROACH [ F - ( R + M + T )] x C = S Executive Summary The datacentre industry, which is a component

More information

DATA CENTRE CONSOLIDATION; WHAT CAN ORGANISATIONS ACHIEVE? White Paper

DATA CENTRE CONSOLIDATION; WHAT CAN ORGANISATIONS ACHIEVE? White Paper DATA CENTRE CONSOLIDATION; WHAT CAN ORGANISATIONS ACHIEVE? White Paper Publication date: November 2012 EXECUTIVE SUMMARY Data centre costs constitute a large part of most organisations IT budget. As they

More information

White paper. The 8 pillars of colocation. Written By: Adelle Desouza Matthew Gingell Rowdy VanRijn Victor Smith

White paper. The 8 pillars of colocation. Written By: Adelle Desouza Matthew Gingell Rowdy VanRijn Victor Smith White paper The 8 pillars of colocation Written By: Adelle Desouza Matthew Gingell Rowdy VanRijn Victor Smith Executive Summary With Gartner suggesting colocation grew by 8% last year alone, many are turning

More information

Data Centre Outsourcing a Buyer s Guide

Data Centre Outsourcing a Buyer s Guide Data Centre Outsourcing a Buyer s Guide The inside guide to deciding whether to outsource your data centre facility and operations and how to select an appropriate partner. This Guide will help you Determine

More information

ALWAYS ON GLOBALSWITCH.COM

ALWAYS ON GLOBALSWITCH.COM ALWAYS ON GLOBALSWITCH.COM Data Centre Design Considerations Kelvin Fong Managing Director, Hong Kong ALWAYS ON GLOBALSWITCH.COM Agenda 1. Introduction to Global Switch 2. Customer Requirements 3. Development

More information

7QUESTIONSYOUNEEDTOASKBEFORE CHOOSINGACOLOCATIONFACILITY FORYOURBUSINESS

7QUESTIONSYOUNEEDTOASKBEFORE CHOOSINGACOLOCATIONFACILITY FORYOURBUSINESS 7QUESTIONSYOUNEEDTOASKBEFORE CHOOSINGACOLOCATIONFACILITY FORYOURBUSINESS ExecutiveBrief P a g e 1 Executive Brief 7 Questions You Need to Ask Before Choosing a Colocation Facility for Your Business Choosing

More information

A Decision Maker s Guide to Cloud Computing and Managed Hosting

A Decision Maker s Guide to Cloud Computing and Managed Hosting A Decision Maker s Guide to Cloud Computing and Managed Hosting A Rackspace White Paper Autumn 2009 Executive Summary Organisations have never had so much choice about how to buy their hosting. From Dedicated

More information

A Decision-Maker s Guide to Cloud Computing and Managed Hosting

A Decision-Maker s Guide to Cloud Computing and Managed Hosting A Decision-Maker s Guide to Cloud Computing and Managed Hosting A Rackspace White Paper Autumn 2009 Summary Organisations have never had so much choice about how to host their applications. From Dedicated

More information

VISIT 2010 Fujitsu Forum Europe 0

VISIT 2010 Fujitsu Forum Europe 0 VISIT 2010 Fujitsu Forum Europe 0 Virtualization & Automation Room 13a Shaping tomorrow with you. Green Data Center Services Martin Provoost Director, Data Centers and Networks, Fujitsu UK & Ireland 14:00

More information

Critical Environment Risk Management

Critical Environment Risk Management DATA CENTRE SECTOR Critical Environment Risk Management for Data Centres Exceptional Service, Exceptional People Data centre experience Norland supports some of the world s leading enterprise data centres

More information

Your guide to hosted data centres: How to evaluate potential providers

Your guide to hosted data centres: How to evaluate potential providers Your guide to hosted data centres: How to evaluate potential providers Finding the right hosted data centre More than ever, organizations require a secure, reliable and flexible data centre to meet growing

More information

The Use of Fresh Air in the Data Centre

The Use of Fresh Air in the Data Centre The Use of Fresh Air in the Data Centre White paper of a round table debate by industry experts on this key topic. Hosted by Keysource with participants including the Uptime Institute. Sophistication Through

More information

Infrastructure & Software

Infrastructure & Software Managed Services We can provide you with a fully managed service more than simply hosting or co-location but a full end-to-end and single point of contact service. Infrastructure & Software Datacentres

More information

Company Profile Outstanding data centres. Expertise you can trust. Europe s leading provider of premium carrier-neutral data centres.

Company Profile Outstanding data centres. Expertise you can trust. Europe s leading provider of premium carrier-neutral data centres. Company Profile Outstanding data centres. Expertise you can trust. Europe s leading provider of premium carrier-neutral data centres. Front cover image Routine checking This page New data centre capacity

More information

Common mistakes in datacentre planning

Common mistakes in datacentre planning Common mistakes in datacentre planning White Paper Last edited: March 2013 Document Control Document Information Title Author Common mistakes in datacentre planning Nick Ewing This document is based upon

More information

CYRUSONE COMPANY OVERVIEW BUILT FOR TOMORROW. READY TODAY.

CYRUSONE COMPANY OVERVIEW BUILT FOR TOMORROW. READY TODAY. CYRUSONE COMPANY OVERVIEW BUILT FOR TOMORROW. READY TODAY. ABOUT CYRUSONE GLOBAL DATA CENTER FACILITIES. A Global Leader 24 high performance data centers worldwide Servicing 9 of top 20 Global Fortune

More information

Zen Internet Case Study

Zen Internet Case Study Zen Internet Case Study About Zen Internet Zen Internet is an independent Internet Service Provider (ISP) that offers a full range of data, voice, and hosting services to businesses and residential users

More information

Company Profile Outstanding data centres. Expertise you can trust. Europe s leading provider of premium carrier-neutral data centres.

Company Profile Outstanding data centres. Expertise you can trust. Europe s leading provider of premium carrier-neutral data centres. Company Profile Outstanding data centres. Expertise you can trust. Europe s leading provider of premium carrier-neutral data centres. 02 / TelecityGroup Introduction Outstanding data centres. Expertise

More information

Making the Business and IT Case for Dedicated Hosting

Making the Business and IT Case for Dedicated Hosting Making the Business and IT Case for Dedicated Hosting Overview Dedicated hosting is a popular way to operate servers and devices without owning the hardware and running a private data centre. Dedicated

More information

The evolution of data connectivity

The evolution of data connectivity Leveraging the Benefits of IP and the Cloud in the Security Sector The CCTV and alarm industry has relied on analogue or Integrated Services Digital Network (ISDN) communications to provide data connectivity

More information

Colocation Hosting Primer Making the Business and IT Case for Colocation

Colocation Hosting Primer Making the Business and IT Case for Colocation Where every interation matters. Colocation Hosting Primer Making the Business and IT Case for Colocation White Paper February 2012 By: Peer 1 Hosting Product Team www.peer1.com Contents Overview 3 Why

More information

Delivering Business Intelligence with Open Source Software

Delivering Business Intelligence with Open Source Software Delivering Business Intelligence with Open Source Software WHITE PAPER by Chip Nickolett, Ingres Corporation Ingres Business Intelligence Series Table of Contents Preface...3 Balanced Scorecards...4 Business

More information

NIGERIA S PREMIUM DATA CENTRE

NIGERIA S PREMIUM DATA CENTRE NIGERIA S PREMIUM DATA CENTRE TIER III DESIGN CERTIFIED SECURE RELIABLE SCALABLE 1 WHY WOULD YOU WANT TO BUILD A DATA CENTRE? IT TAKES MILLIONS OF US DOLLARS TO BUILD AN EFFICIENT DATA CENTRE. A KEY ASSET,

More information

One Cloud doesn t fit all:

One Cloud doesn t fit all: One Cloud doesn t fit all: The emerging trends in multi-vendor cloud platforms To cloud or not to cloud is no longer the question. Organisations have moved beyond the deliberation stage, and with many

More information

Data centre strategies for business growth in a hybrid cloud world

Data centre strategies for business growth in a hybrid cloud world Data centre strategies for business growth in a hybrid cloud world A joint report from Pacnet and CIO Custom Solutions Group October 2014 Introduction The data centre has become an integral part of the

More information

Ingres Insights. with Open Source Software

Ingres Insights. with Open Source Software Ingres Insights DElivering Business intelligence with Open Source Software TABLE OF CONTENTS 3 Preface 4 Balanced Scorecards 5 Business Optimization 6 Business Intelligence (BI) 7 BI Examples 8 The Challenges

More information

THOUGHT LEADERSHIP. Journey to Cloud 9. Navigating a path to secure cloud computing. Alastair Broom Solutions Director, Integralis

THOUGHT LEADERSHIP. Journey to Cloud 9. Navigating a path to secure cloud computing. Alastair Broom Solutions Director, Integralis Journey to Cloud 9 Navigating a path to secure cloud computing Alastair Broom Solutions Director, Integralis March 2012 Navigating a path to secure cloud computing 2 Living on Cloud 9 Cloud computing represents

More information

White Paper. Cloud Computing. Effective Web Solution Technology Investment. January 2011. www.k-bc.co.uk

White Paper. Cloud Computing. Effective Web Solution Technology Investment. January 2011. www.k-bc.co.uk White Paper Cloud Computing Effective Web Solution Technology Investment January 2011 www.k-bc.co.uk Cloud Computing The future of effective technology investment The benefit of web solution technology

More information

Leveraging the Private Cloud for Competitive Advantage

Leveraging the Private Cloud for Competitive Advantage Leveraging the Private Cloud for Competitive Advantage Introduction While it is universally accepted that organisations will leverage cloud solutions to service their IT needs, there is a lack of clarity

More information

Raising Inlet Temperatures in the Data Centre

Raising Inlet Temperatures in the Data Centre Raising Inlet Temperatures in the Data Centre White paper of a round table debate by industry experts on this key topic. Hosted by Keysource with participants including the Uptime Institute. Sophistication

More information

Beyond security: ATEC s contribution to Birmingham Airport s management systems

Beyond security: ATEC s contribution to Birmingham Airport s management systems Critical infrastructure / transportation Airports Beyond security: ATEC s contribution to Birmingham Airport s management systems As progressive transport hubs such as Birmingham Airport (BAL) invest in

More information

Colocation, Hot Seat Services, Disaster Recovery Services, Secure and Controlled Environment

Colocation, Hot Seat Services, Disaster Recovery Services, Secure and Controlled Environment Colocation, Hot Seat Services, Disaster Recovery Services, Secure and Controlled Environment 3 Company Overview Confisio DataCenter was formed to help organisations tackle the ever increasing challenges

More information

Matthias Machowinski, Directing Analyst for Enterprise Networks and Video, Infonetics Research, 20152

Matthias Machowinski, Directing Analyst for Enterprise Networks and Video, Infonetics Research, 20152 The Cold, Hard Facts About Uptime Executive Summary By the year 2020, when the Internet of Things is in full swing and Internet-connected devices and data are as important as electricity, data center uptime

More information

A New World Of Colocation

A New World Of Colocation Colocation Whitepaper A New World Of Colocation Can colocation service providers evolve their service offerings to satisfy today's commercial needs, demands and expectations; while differentiating themselves

More information

Effective Storage Management for Cloud Computing

Effective Storage Management for Cloud Computing IBM Software April 2010 Effective Management for Cloud Computing April 2010 smarter storage management Page 1 Page 2 EFFECTIVE STORAGE MANAGEMENT FOR CLOUD COMPUTING Contents: Introduction 3 Cloud Configurations

More information

UNIQUE A COMPLETE, FLEXIBLE HOSTED TELEPHONY AND UNIFIED COMMUNICATIONS SOLUTION, HELPING YOU CREATE A PROPOSITION THAT IS

UNIQUE A COMPLETE, FLEXIBLE HOSTED TELEPHONY AND UNIFIED COMMUNICATIONS SOLUTION, HELPING YOU CREATE A PROPOSITION THAT IS WE MAKE IT POSSIBLE A COMPLETE, FLEXIBLE HOSTED TELEPHONY AND UNIFIED COMMUNICATIONS SOLUTION, HELPING YOU CREATE A PROPOSITION THAT IS UNIQUE WHOLESALE HOSTED CENTREX TAKING COMMUNICATION INTO THE CLOUD

More information

Introduction to AWS Economics

Introduction to AWS Economics Introduction to AWS Economics Reducing Costs and Complexity May 2015 2015, Amazon Web Services, Inc. or its affiliates. All rights reserved. Notices This document is provided for informational purposes

More information

How To Choose Data Center Colocation Over Cloud Computing

How To Choose Data Center Colocation Over Cloud Computing White Paper Cloud vs. Colo: Colo Wins on 4 out of 5 Key Criteria of new security threats, hacking attacks and data breaches every week. Couple that with major service interruptions and outages experienced

More information

Nomine: A Case Study in Network Infrastructure Development

Nomine: A Case Study in Network Infrastructure Development Nominee: Coreix Nomination title: Delivering highly tailored colocation, managed hosting, cloud and dedicated server solutions to the UK market Who we are Coreix Limited is a London based managed hosting,

More information

The Intelligent Data Centre

The Intelligent Data Centre The Intelligent Data Centre VIRTUS: Ahead of the Intelligent Data Centre Curve So What is an Intelligent Data Centre? The role of the data centre has changed. Over the last few years it has transitioned

More information

Why you should opt for an external data centre: 10 no-brainers LCL WHITE PAPER. LCL, your partner in data center outsourcing 1

Why you should opt for an external data centre: 10 no-brainers LCL WHITE PAPER. LCL, your partner in data center outsourcing 1 Why you should opt for an external data centre: 10 no-brainers LCL WHITE PAPER LCL, your partner in data center outsourcing 1 A data centre, even a small one, is a huge investment for any organisation.

More information

Data Center Checklist

Data Center Checklist Data Center Checklist The use of colocation and services has continued to increase, rapidly becoming the solution of choice for organizations requiring an efficient, secure, cost-effective way to manage

More information

10 steps to the Cloud for SMBs Introduction to Cloud computing. www.fasthosts.co.uk. Ask the Experts. Making Business Work Better Online

10 steps to the Cloud for SMBs Introduction to Cloud computing. www.fasthosts.co.uk. Ask the Experts. Making Business Work Better Online 10 steps to the Cloud for SMBs Introduction to Cloud computing This paper is designed to explain, in plain English, the real reasons behind how your business can benefit from Cloud computing, and help

More information

The forecast looks bright for cloud based telephony

The forecast looks bright for cloud based telephony The forecast looks bright for cloud based telephony +44 (0)1925 530 111 enquiries@square1products.com 1 Do I need to consider the cloud? There is much talk about hosted or cloud-based telephony and the

More information

The business case for cloud computing

The business case for cloud computing The business case for cloud computing Cutting through the hype and determining the benefits for your business For more information : claranet.co.uk - twitter.com/claranet To book an appointment or to discuss

More information

Managing Data Center Growth Explore Your Options

Managing Data Center Growth Explore Your Options Managing Growth Explore Your Options Managing Growth: Managing The increasing demand on data centers has forced many IT managers to look for new ways to manage data center growth, either by consolidating,

More information

Data Centre Harbour Exchange Square Campus, London Access to unrivalled connectivity.

Data Centre Harbour Exchange Square Campus, London Access to unrivalled connectivity. Data Centre Harbour Exchange Square Campus, London Access to unrivalled connectivity. TelecityGroup 6/7 Harbour Exchange London E14 9GE United Kingdom Tel: +44 (0)20 7001 0101 info@telecity.com www.telecitygroup.com

More information

Selecting a colocation provider needn't be a risky endeavour.

Selecting a colocation provider needn't be a risky endeavour. COLOCATION BUYER S GUIDE Selecting a colocation provider needn't be a risky endeavour. Guidance for assessing your own colocation requirements, and a framework to assess the providers on the market. An

More information

Cloud Computing: It s In Your Future. What You Need to Know about Logicalis and Cloud Computing

Cloud Computing: It s In Your Future. What You Need to Know about Logicalis and Cloud Computing Cloud Computing: It s In Your Future What You Need to Know about Logicalis and Cloud Computing Cloud computing is a transition that is changing the way you will buy, build, operate and consume information,

More information

Data centre experts. Advanced power protection for data centres

Data centre experts. Advanced power protection for data centres Data centre experts Advanced power protection for data centres A robust power protection strategy is critical to successful data centre operations. Uninterruptible Power Supplies Limited (UPSL), a Kohler

More information

2011 Australia Excellence Awards Datacenter Services Provider of the Year

2011 Australia Excellence Awards Datacenter Services Provider of the Year 2011 2011 Australia Excellence Awards Datacenter Services Provider of the Year 2011 Frost & Sullivan 1 We Accelerate Growth Frost & Sullivan s Global Research Platform Frost & Sullivan is in its 50th year

More information

THE ROI FROM SOFTWARE-AS-A- SERVICE (SAAS)

THE ROI FROM SOFTWARE-AS-A- SERVICE (SAAS) THE ROI FROM SOFTWARE-AS-A- SERVICE (SAAS) How Cloud-based solutions can provide significant ROI. REPORT David Snelson / V3 / Nov 2011 Waer Systems Limited 2013 1 AN OVERVIEW Software-as-a-Service, or

More information

Disaster Recovery for Business-Critical Applications. Your business. Back in business. Real-time DR solutions you can rely upon when all else fails

Disaster Recovery for Business-Critical Applications. Your business. Back in business. Real-time DR solutions you can rely upon when all else fails Disaster Recovery for Business-Critical Applications Your business. Back in business. Real-time DR solutions you can rely upon when all else fails Disaster Recovery for Business-Critical Applications Your

More information

Smart Data Center Solutions

Smart Data Center Solutions Smart Data Center Solutions New Data Center Challenges Require New Solutions Data Center Architecture. Inside and Out. Data centers are mission-critical facilities. A silo-based approach to designing,

More information

SEVEN REASONS TO CONSIDER ERP IN THE CLOUD SPECIAL REPORT SERIES ERP IN 2014 AND BEYOND

SEVEN REASONS TO CONSIDER ERP IN THE CLOUD SPECIAL REPORT SERIES ERP IN 2014 AND BEYOND SEVEN REASONS TO CONSIDER ERP IN THE CLOUD SPECIAL REPORT SERIES ERP IN 2014 AND BEYOND CONTENTS INTRODUCTION 3 TRY BEFORE YOU BUY 4 TAKE ADVANTAGE OF THE MOST ADVANCED TECHNOLOGY 6 GENERATE MEASURABLE

More information

Can Cloud Database PaaS Solutions Replace In-House Systems?

Can Cloud Database PaaS Solutions Replace In-House Systems? Can Cloud Database PaaS Solutions Replace In-House Systems? Abstract: With the advent of Platform-as-a-Service as a viable alternative to traditional database solutions, there is a great deal of interest

More information

Get Significant Application Quality Improvement Without Major Investment. Performance driven. Quality assured.

Get Significant Application Quality Improvement Without Major Investment. Performance driven. Quality assured. Testing Platform-as-a-Service Get Significant Application Quality Improvement Without Major Investment. Performance driven. Quality assured. TPaaS a complete testing service, on demand, using the Capgemini

More information

WORLD CLASS, GLOBALLY CERTIFIED, HIGH AVAILABILITY DATA CENTRE INTELLICENTRE 2 MACQUARIE PARK, SYDNEY

WORLD CLASS, GLOBALLY CERTIFIED, HIGH AVAILABILITY DATA CENTRE INTELLICENTRE 2 MACQUARIE PARK, SYDNEY WORLD CLASS, GLOBALLY CERTIFIED, HIGH AVAILABILITY DATA CENTRE INTELLICENTRE 2 MACQUARIE PARK, SYDNEY A NEW GENERATION OF DATA CENTRE SOLUTIONS AUSTRALIA S FIRST SHOWCASE TIER III CERTIFIED DATA CENTRE

More information

The NREN s core activities are in providing network and associated services to its user community that usually comprises:

The NREN s core activities are in providing network and associated services to its user community that usually comprises: 3 NREN and its Users The NREN s core activities are in providing network and associated services to its user community that usually comprises: Higher education institutions and possibly other levels of

More information

Datacentre Studley. Dedicated managed environment for mission critical services. Six Degrees Group www.6dg.co.uk

Datacentre Studley. Dedicated managed environment for mission critical services. Six Degrees Group www.6dg.co.uk Dedicated managed environment for mission critical services www.6dg.co.uk Our datacentres are the core of our business. At we own and manage 30,000 square feet of highly available, geographically diverse

More information

TELEPHONY BE A PRIORITY FOR YOUR BUSINESS?

TELEPHONY BE A PRIORITY FOR YOUR BUSINESS? WHY SHOULD HOSTED TELEPHONY BE A PRIORITY FOR YOUR BUSINESS? An Insight For Business Leaders 01 INTRODUCTION There is much talk about hosted or cloud-based telephony and the rapid adoption of this new

More information

The sky s the limit: How medium-sized businesses can capitalise on the cloud to propel business growth. A white paper by Pegasus Software

The sky s the limit: How medium-sized businesses can capitalise on the cloud to propel business growth. A white paper by Pegasus Software The sky s the limit: How medium-sized businesses can capitalise on the cloud to propel business growth A white paper by Pegasus Software Cloud: a definition The term Cloud Computing refers to software,

More information

IT Services. Capita Private Cloud. Cloud potential unleashed

IT Services. Capita Private Cloud. Cloud potential unleashed IT Services Capita Private Cloud Cloud potential unleashed Cloud computing at its best Cloud is fast becoming an integral part of every IT strategy. It reduces cost and complexity, whilst bringing freedom,

More information

LDeX Group. Colocation Solutions for High Expectations

LDeX Group. Colocation Solutions for High Expectations LDeX Group Colocation Solutions for High Expectations LDeX1 Units 8 10 The Oxgate Centre, Oxgate Lane, London, NW2 7JA +44 (0)845 370 3510 sales@ldexgroup.co.uk www.ldexgroup.co.uk 5 M VA LDeX1 delivers

More information

Green ICT Strategy 2010-2014

Green ICT Strategy 2010-2014 Department of Transformation Information & Communication Technology Author: Quentin McPhee - Lead for Green ICT Date: February 2010 Version: 00_05 Green ICT Strategy 2010-2014 Table of Contents 1.Summary...2

More information

Who moved my cloud? Part I: Introduction to Private, Public and Hybrid clouds and smooth migration

Who moved my cloud? Part I: Introduction to Private, Public and Hybrid clouds and smooth migration Who moved my cloud? Part I: Introduction to Private, Public and Hybrid clouds and smooth migration Part I of an ebook series of cloud infrastructure and platform fundamentals not to be avoided when preparing

More information

Specialist Cloud Services Lot 4 Cloud Printing and Imaging Consultancy Services

Specialist Cloud Services Lot 4 Cloud Printing and Imaging Consultancy Services Specialist Cloud Services Lot 4 Cloud Printing and Imaging Consultancy Services Page 1 1 Contents 1 Contents... 2 2 Transcend360 Introduction... 3 3 Service overview... 4 3.1 Service introduction... 4

More information

How To Understand Cloud Computing

How To Understand Cloud Computing TOP 10 CLOUD MYTHS DEBUNKED Navigating to the Cloud - Maximize Operational Efficiencies and Minimize by Avoiding Common Cloud Myths WHITE PAPER Contents 1. EXECUTIVE SUMMARY 2. INTRODUCTION Top Market

More information

Reducing Storage TCO With Private Cloud Storage

Reducing Storage TCO With Private Cloud Storage Prepared by: Colm Keegan, Senior Analyst Prepared: October 2014 With the burgeoning growth of data, many legacy storage systems simply struggle to keep the total cost of ownership (TCO) in check. This

More information

Get Significant Application Quality Improvement without Major Investment Performance driven. Quality assured.

Get Significant Application Quality Improvement without Major Investment Performance driven. Quality assured. Testing Platform-as-aService Get Significant Application Quality Improvement without Major Investment Performance driven. Quality assured. TPaaS providing testing on demand, using the Capgemini Cloud Application

More information

Why prioritise cloud telephony for your business?

Why prioritise cloud telephony for your business? Why prioritise cloud telephony for your business? Your insight to getting into The Cloud A 360 Solutions White Paper Overview There is much talk about hosted or cloud-based telephony and the rapid adoption

More information

software license management is becoming an important issue for hosting resellers and Microsoft solution providers.

software license management is becoming an important issue for hosting resellers and Microsoft solution providers. Crayon becomes a preferred partner for the distribution of Microsoft Cloud Technology Things to remember... Crayon, consultant and world leader in software asset management for businesses, holds the highest

More information

Integrated Data Center Infrastructure Optimizes Power, Space and Cooling While Reducing Complexity

Integrated Data Center Infrastructure Optimizes Power, Space and Cooling While Reducing Complexity white paper 1 Integrated Data Center Infrastructure Optimizes Power, Space and Cooling While Reducing Complexity THE GROWING COMPLEXITY OF THE DATA CENTER makes it difficult to find and retain people with

More information

Intensive Hosting. Intensive Hosting Overview. Why Intensive Hosting?

Intensive Hosting. Intensive Hosting Overview. Why Intensive Hosting? Rackspace is the world s leader in hosting. We deliver websites, web-based IT systems, and computing as a service. Our rapid growth is the result of our commitment to serving our customers, known as Fanatical

More information

Colt Colocation Services. 2010 Colt Technology Services Group Limited. All rights reserved.

Colt Colocation Services. 2010 Colt Technology Services Group Limited. All rights reserved. Colt Colocation Services 2010 Colt Technology Services Group Limited. All rights reserved. Award winning Colt Data Centre Solutions 2012: Modular Data Centre Solution of the year winner at 5 th Datacentre

More information

MAXIMIZING YOUR DATA CENTER INFRASTRUCTURE: CENTRALIZED MANAGEMENT AND WIRE-FREE ENVIRONMENTAL MONITORING

MAXIMIZING YOUR DATA CENTER INFRASTRUCTURE: CENTRALIZED MANAGEMENT AND WIRE-FREE ENVIRONMENTAL MONITORING MAXIMIZING YOUR DATA CENTER INFRASTRUCTURE: CENTRALIZED MANAGEMENT AND WIRE-FREE Chris C. Gaskins Vice President of Product Development RF Code, Inc. AUGUST 2010 Shawn Griggs Director of Product Management

More information

The trusted technology partner in the Public Sector

The trusted technology partner in the Public Sector The trusted technology partner in the Public Sector www.exponential-e.com/public-sector About Exponential-e Market Leaders in Technical Innovation GovConnect: The Exponential-e public sector service portfolio

More information

BBC Technology Strategy

BBC Technology Strategy BBC Technology Strategy Issued: January 2010 For more information contact: Spencer.piggott@bbc.co.uk Copyright 2010 BBC All Rights Reserved TECHNOLOGY STRATEGY Introduction This paper defines the BBC s

More information

Colocation Selection Guide. Workspace Technology Ltd

Colocation Selection Guide. Workspace Technology Ltd Colocation Selection Guide Workspace Technology Ltd Technology House 5 Emmanuel Court Reddicroft Sutton Coldfield West Midlands B72 1TJ Tel 0121 354 4894 Fax 0121 354 6447 www.workspace-technology.com

More information

Session 2. The economics of Cloud Computing

Session 2. The economics of Cloud Computing Session 2. The economics of Cloud Computing Cloud computing is the next step in the on-going evolution of Information Technology. From a technical standpoint, very little that currently is done on cloud

More information

Essential NCPI Management Requirements for Next Generation Data Centers

Essential NCPI Management Requirements for Next Generation Data Centers Essential NCPI Requirements for Next Generation Data Centers By Ted Ives White Paper #14 1 Executive Summary The management of physical infrastructure in data centers can no longer be considered independently

More information

VoIP in the Enterprise

VoIP in the Enterprise VoIP in the Enterprise Date: March. 2005 Author: Sonia Hanson Version: 1.1 1 1 Background Voice over IP In the late 1990s Voice over IP (VoIP) was seen as a disruptive new technology that had the potential

More information

Creating the dynamic data center of the future, now

Creating the dynamic data center of the future, now Integrating data center expansion with IT growth Lower your cost I Reduce your risk I Enable your business Modular Solutions Whitepaper May 2012 Dave Whitcomb/RTKL Creating the dynamic data center of the

More information

Data Center Refresh: Build or Buy?

Data Center Refresh: Build or Buy? Data Center Refresh: Build or Buy? In-house data centers vs. colocation, managed services and cloud computing: 5 questions to consider Presented by Cosentry, the trusted Midwest provider of Managed and

More information

Low Carbon Data Centres without compromise

Low Carbon Data Centres without compromise Low Carbon Data Centres without compromise Thursday 16 th September 2010 Pip Squire, Engineering & Project Director delivered by: Ark Continuity - Continuously Delivering high integrity data centres Introduction

More information

Juniper Networks QFabric: Scaling for the Modern Data Center

Juniper Networks QFabric: Scaling for the Modern Data Center Juniper Networks QFabric: Scaling for the Modern Data Center Executive Summary The modern data center has undergone a series of changes that have significantly impacted business operations. Applications

More information

Sovereign. The made to measure data centre

Sovereign. The made to measure data centre Sovereign D ATA C O N N E C T The made to measure data centre Prime Location Within touching distance of everything that s important. 2 Your Customer-Centric Data Centre For the vast majority of organisations

More information

Global Headquarters: 5 Speen Street Framingham, MA 01701 USA P.508.872.8200 F.508.935.4015 www.idc.com

Global Headquarters: 5 Speen Street Framingham, MA 01701 USA P.508.872.8200 F.508.935.4015 www.idc.com WHITE PAPER Solutions for the Datacenter's Thermal Challenges Sponsored by: IBM and Intel Jed Scaramella January 2007 Matthew Eastwood IDC OPINION Global Headquarters: 5 Speen Street Framingham, MA 01701

More information

IBM Cloud Managed Infrastructure Services for New Zealand Government

IBM Cloud Managed Infrastructure Services for New Zealand Government IBM Cloud Managed Infrastructure Services for New Zealand Government An agile cloud infrastructure designed to provide quick access to a security- rich, enterprise- class virtual server environment. 2

More information

The Elephant in the Room is Lost Capacity

The Elephant in the Room is Lost Capacity The Elephant in the Room is Lost Capacity How your short term drivers erode your long term goals Executive Summary In the world of economics, short-termism, the policy of concentrating on short-term profit

More information

Stacked in your favour... Advanced network infrastructure engineered to give your business value, service and innovation

Stacked in your favour... Advanced network infrastructure engineered to give your business value, service and innovation Vodacom Infrastructure Solutions Stacked in your favour... Advanced network infrastructure engineered to give your business value, service and innovation Vodacom Infrastructure Solutions Build your business

More information

Get Significant Application Quality Improvement without Major Investment Performance driven. Quality assured.

Get Significant Application Quality Improvement without Major Investment Performance driven. Quality assured. Testing Platform-as-a-Service Get Significant Application Quality Improvement without Major Investment Performance driven. Quality assured. Testing the way we do it Application testing can get expensive.

More information

EXECUTIVE REPORT. Build vs Buy: Key Steps to Overcome Capital Constraints in the Data Center

EXECUTIVE REPORT. Build vs Buy: Key Steps to Overcome Capital Constraints in the Data Center EXECUTIVE REPORT Build vs Buy: Key Steps to Overcome Capital Constraints in the Data Center Overview Data center industry trends are changing the way businesses spend money and invest in IT initiatives.

More information

Whitepaper. The ABC of Private Clouds. A viable option or another cloud gimmick?

Whitepaper. The ABC of Private Clouds. A viable option or another cloud gimmick? Whitepaper The ABC of Private Clouds A viable option or another cloud gimmick? Although many organizations have adopted the cloud and are reaping the benefits of a cloud computing platform, there are still

More information

Colocation and Cloud Hosting Solutions. Build a strong and efficient physical infrastructure that delivers service reliability and profitability

Colocation and Cloud Hosting Solutions. Build a strong and efficient physical infrastructure that delivers service reliability and profitability Colocation and Cloud Hosting Solutions Build a strong and efficient physical infrastructure that delivers service reliability and profitability 2 Dependability and Deployment Speed that Improves Your Bottom

More information

CLOUD AND CARRIER- NEUTRALITY IN A COLOCATION DATA CENTRE

CLOUD AND CARRIER- NEUTRALITY IN A COLOCATION DATA CENTRE CLOUD AND CARRIER- NEUTRALITY IN A COLOCATION DATA CENTRE What it is, why it matters, and what it means for the future By Kevin Dean CMO, Interxion INTRODUCTION IT consumerisation, mobility, social media,

More information

Data Center Solutions

Data Center Solutions Data Center Solutions New Data Center Challenges Require New Solutions Data Center Architecture. Inside and Out. Data centers are mission-critical facilities. A silo-based approach to designing, deploying

More information

Your Data Centre provider

Your Data Centre provider Your Data Centre provider About VIRTUS VIRTUS Data Centres, the UK s fastest growing data centre provider, owns, designs, builds and operates the country s most efficient and flexible data centres. VIRTUS

More information

Bringing the Cloud into Focus. A Whitepaper by CMIT Solutions and Cadence Management Advisors

Bringing the Cloud into Focus. A Whitepaper by CMIT Solutions and Cadence Management Advisors Bringing the Cloud into Focus A Whitepaper by CMIT Solutions and Cadence Management Advisors Table Of Contents Introduction: What is The Cloud?.............................. 1 The Cloud Benefits.......................................

More information

Scalable. Affordable. Flexible. Fast.

Scalable. Affordable. Flexible. Fast. Modular Data Center Solutions Scalable. Affordable. Flexible. Fast. Build the data center you need today with the flexibility to meet tomorrow s challenges The only constant in business is change. Fluctuations

More information