The Art of the Possible Scheduling Options in SAP. Mark W. Scott Vesta Partners, LLC

Size: px
Start display at page:

Download "The Art of the Possible Scheduling Options in SAP. Mark W. Scott Vesta Partners, LLC"

Transcription

1 The Art of the Possible Scheduling Options in SAP Mark W. Scott Vesta Partners, LLC

2 The Tool and the Challenge

3 The Parts The Options The Results

4 Scheduling in SAP What I ll cover: The Parts The Options The Results

5 The Parts

6 Definitions Planning allocation of resources to a work order which could contain, materials, crews, contractors, or tools Scheduling allocating the work order into the desired time frame in which the work should occur Dispatching allocating work orders to specific work crews or individuals (hopefully based on the schedule)

7 Where does Scheduling fit into the process? Maintenance plans Commitment to an agreed set of work activities to be executed within the coming week Work requests (Maintenance Notifications) Planning Set of work orders Periodic (Weekly) Scheduling Confirm actual Work execution

8 Maintenance Scheduling Without proper scheduling, all of the benefits of good planning are lost.

9 Prerequisites to Scheduling in SAP An effective SAP planning process that defines and prioritizes work A maintenance backlog accurately represented in SAP in terms of: Work activity, labor resource estimates (number of people and man hours) and durations Material Requirements Criticality and Priority Work Categorization (e.g. Preventive, Corrective, Project, etc.) Resource group / Work Center capacity information maintained to reflect: Standard Working Times Weekly available capacity

10 Maintenance Planning Maintenance Planning is a decision making process that focuses on what needs to be completed. All well planned work orders include: Scope List of required materials Work force requirements Required permits and safety procedures Equipment needs and service Other pertinent information as appropriate

11 Task List Overview Task Lists describe the sequence of individual maintenance activities to be performed, identify the required Resources (Labor, Materials, Services, Special tools) and related procedures. Task Lists are building blocks of Maintenance Plans. Simplifies the Work Order Planning process

12 Codes To Support Work Planning User Status use to identify where in the process the order is at Maintenance Activity Type use to identify type of work System Condition use to identify operational state for required intervention Revision code options for use Define turnarounds / outages / shutdowns Apply target basic dates Tagging / Grouping Basic Work Order scheduling Priority use to identify work orders to be planned first

13 Configuration IMG - Scheduling Types Typically there are no reasons to change standard SAP Scheduling Type settings. The with Time indicator allows input of times against basic start and end dates as shown to the right

14 Scheduling Parameters Defined in configuration Control how dates are calculated Defined by Plant / Order Type

15 Scheduling Parameters Options for Date Adjustment Do you want to adjust or retain Basic Dates? Are Material Requirement dates to be driven by Order Start or Operation Start? Automatic Scheduling: switch on to ensure dates are always re-calculated when Order processed / saved Scheduling with breaks: Consider excluding breaks from Work Center operating times. This ensures clean start and finish times without SAP calculations in fractions of hours. Shift Order: Switch on to exclude confirmed actual dates and times from re-calculation of schedule e.g. if work was not completed and need to adjust schedule dates to another time in future.

16 Standard Work Center Capacity For each Work Center you establish a standard available capacity and working times that reference a specific Factory Calendar Factory Calendar defines working days / non working (including holidays) days. Breaks can be defined that are deducted from available operating time For typical routine maintenance scenarios it is recommended to exclude breaks and adjust start and finish dates to reflect normal available work time The standard capacity is applied to all the working days defined within Factory Calendar For non working days the capacity is set to zero. The working times influence how schedule dates are calculated on the Work Order Work Center Capacity = Number of Ind. Capacities * Operating Time (Operating Time is adjusted by Utilization)

17 Standard Work Center Capacity Calculation examples: Operating Time = Calculated Work Time * Utilization 10 hrs, No Breaks = 10 (10 * 1.0) * 2 = hrs, 1 hr Breaks = 9 (9 * 1.0) * 3 = 27 (9 * 0.9) * 3 = 24.3 (9 * 1.2) * 3 = 32.4

18 Defines working days & Holidays Factory Calendar

19 Intervals & Shifts In this example interval added Note: Interval operating times also impact Order date scheduling.

20 Can reference and apply shifts defined within HR Intervals & Shifts

21 Capacity Versions Can apply different Versions of available capacity on Work Order Header 9 h Schedule dates reflect defined versions. 8 h

22 Employee Assignment & Capacity Calculation Within Capacity Leveling it is possible to calculate available capacity based on individual work schedules maintained within HR Master Records. Cumulate Capacity based on employees assigned to Work Center Capacity HR assignment

23 The Options

24 Business Context Scheduling system requirements and capabilities map to multiple business environments and processes A single scheduling solution does not fit all needs Requirements Work Center Resource Leveling Manual weekly schedule / dispatch Material availability Schedule compliance KPI Relationships & constraints Critical path Budget, Cost & Schedule Earned value Employee resource leveling Resource constraints / skills Tool availability Geographical optimization Automatic assignment Service level KPI Emphasis Environment Routine Maintenance Shutdowns, Turnarounds Outages Engineering & Construction Projects Maintenance Projects Field Service Major Processes

25 SAP Leveling Capacity Evaluation Capacity Planning Table SAP Multi-Resource Scheduling (MRS) SAP Projects SAP EPC PMM Click Software PMX Prometheus The Options

26 SAP Leveling Capacity Evaluation Capacity Planning Table SAP Multi-Resource Scheduling (MRS) SAP Projects SAP EPC PMM Click Software PMX Prometheus The Options

27 Capacity Evaluation Work Center Work Center Standard Overview Change Work Order Output to Printer Export to Excel

28 The Options SAP Leveling Capacity Evaluation Capacity Planning Table SAP Multi-Resource Scheduling (MRS) SAP Projects SAP EPC Click Software PMX Prometheus

29 Capacity Planning Table Using Planning Table to create the Weekly Schedule Review work requirements against capacity Manipulate capacity & requirements Dispatch operations requirements to specific work days Recommend use of CM25 Variable Capacity Planning Table Dispatching work moves an operation onto a particular day and changes Operation system status (to DSPT). This day may or may not be the same as how it was originally planned / scheduled in the work order. Two dispatching options: Manual Finite (using a dispatch strategy).

30 Capacity Planning Table With Finite setting the system will look at the work center s remaining available capacity and apply the work based on defined rules. With Manual the Planner/Scheduler controls: The specific date and time an operation is scheduled to a work center Loading of available capacity Pooled Capacity Requirements Dispatch Strategy Dispatch strategy Monday Tuesday Wednesday Thursday Friday

31 Getting to Planning Table Can navigate between IW37N and Planning Table using selection to determine Orders to be included. Call up Planning Board directly Select by Work Center Can refine selection further e.g. Revision Recommend finalizing schedule using direct access to ensure all requirements accounted for

32 Tabular Planning Table Overview Capacity details available / scheduled Work List details Define weekly schedule by assigning (Dispatching) work Adjust dates within table to balance resources with work requirements View work requirements by period

33 Tabular Planning Table Resource Section of Planning Table Initial View Remaining Available Capacity (Hrs) % ge Capacity Dispatched Click to change view Changed View Periods start at today Daily Available Capacity of Work Center (Hrs) Hours Dispatched (Scheduled) Backlog Orders show today Requirements not yet Dispatched Hrs & % ge of Capacity

34 Tabular Planning Table Views For weekly schedule recommend daily view Weekly or Monthly views can be used for longer term planning/scheduling Week Month

35 Graphical Version

36 SAP Leveling Capacity Evaluation Capacity Planning Table SAP Multi-Resource Scheduling (MRS) SAP Projects SAP EPC PMM Click Software PMX Prometheus The Options

37 Multi Resource Scheduling (MRS) Overview Scenarios Plant Maintenance Field Service Workshop Planning Project Staffing Integration SAP ERP Plant Maintenance / Customer Service (PM/CS) SAP ERP Project System (PS) Collaboration Projects (cprojects) SAP Customer Service Management (CRM) Solution Strengths MRS runs fully integrated as Add-On to the SAP ERP system leveraging the existing infrastructure Strong bi-directional integration with SAP HR Flexible resource planning scenarios from manual planning up to automated and optimized planning High scalability High configurability

38 Process Overview Scheduling on work center level with MRS optional Identification of demand Create Order / Network Scheduling on work center level Scheduling of human resources and tools Order confirmation and completion ERP Plant Maintenance (EAM) Maintenance plan Notifications Order ERP Project System (PS) Project Definition Project Structure Network Multi Resource Scheduling (MRS) Intuitive to use graphical planning board Capacity overview of work centers Employee availability SAP

39 MRS Scenario Overview Resources Demands Preventative maintenance scheduled work order Online Adobe Form Line operator shutdown People Tools Plant Maintenance/ Service Order Project System Network Counter based work order Qualifications Availability Planning and Scheduling Work Order Form Online notification Pager Capacity Management Graphical Planning Board SAP 2008

40 Key Functions Skill Management Integration with SAP HR Enhanced MRS qualifications Integration with HR Time Management Bi-directional interface with SAP HR (absences, attendances, substitutions) Capacity Management Scheduling and Dispatching on work center level Work load at group level Planned and unplanned orders Employee availability (Planned working time, absences, attendances) Graphical Planning Board Powerful SAP GUI based Planning Board Lean Web UI based Planning Board Optimizer Optimizer engine creates daily schedule based on cost parameters Integration with Geographical Information System (GIS) Visualization of travel time Display of map Search for nearest technician Integration with mobile devices Information of technicians about assignments Status tracking of assignments SAP 2008

41 Dispatching Scenarios with MRS Low Volume High Volume SAP 2008 High Volume Manual Planning The resource planner manually creates assignments (e.g. via Drag&Drop) in the MRS Graphical Planning Board Supported by Alert Monitor Selected important features Qualification Matching Simultaneous Planning of tool resources Display of clocking data (actual data) Capacitive Planning Teams Resource Selection Identical to Manual Planning but resource planner can select resources based on different criteria (partner roles, resource planning node, qualification) Automatic Planning Several functions support the resource planner Automatic scheduling based on availability and qualification in addition partner role) Utilization based automatic scheduling Intelligent Shifting Optimization An optimization engine proposes an optimized schedule (travel times, SLA dates etc.)

42 Order and Operation list Demo: Schedulers Workplace

43 Detailed work list Demo: Schedulers Workplace

44 Demo: Schedulers Workplace Messages

45 Demo: Schedulers Workplace Work Space

46 Work Center View (Demand view) Demand Gantt Work Center Gantt Work Center Capacity Alert Monitor

47 Functional Overview Demand Gantt Work Center Gantt Work Center Capacity Alert Monitor

48 Functional Overview Demand Gantt Work Center Gantt Work Center Capacity Alert Monitor

49 Functional Overview Demand Gantt Work Center Gantt Work Center Capacity Alert Monitor

50 MRS (Multi-Resource Scheduling) Resource View Planning Board Order & Operation List Detailed Work List Messages / Alerts

51 MRS Overview Assign Work Drag & Drop or Manual entry

52 MRS Overview Time Allocation Insert a Time Allocation

53 MRS Overview Create Teams Group people into temporary team

54 MRS Overview - Reports

55 MRS 900 Additional shutdown functionality Enhanced relationship handling Automatic capacity leveling Integration of production data

56 SAP Leveling Capacity Evaluation Capacity Planning Table SAP Multi-Resource Scheduling (MRS) SAP Projects SAP EPC PMM Click Software PMX Prometheus The Options

57 Use of SAP Project Systems Can enhance scheduling capability through use of PS Planning board Project environment - Shutdowns / Turnarounds

58 Creating a Project and Associating WBS Elements The first step is to create a project and create/assign WBS element values to the project. The Project Builder transaction (CJ20N) is of great use in creating both the Project and the WBS elements.

59 Creating the Networks Create Networks and assign to WBS Elements.

60 Networks / Activities The network/activity relationship is remarkably similar to the order/operation relationship.

61 Network finer points (continued) There are durations, relationships, intervals. If the network is linked to another, then its dates will move when the master network reschedules. Note: each activity within a network can be assigned a different WBS element if different from the parent.

62 Rescheduling the Project Have the option of rescheduling network only, networks and orders, or just orders. Pulls off the basic start date of the master network and then reassigns basic and scheduled start dates of all orders. Transaction gives warning messages for orders unable to schedule and why.

63 Linking Maintenance Orders to Networks Once this link is made, the order schedule and basic dates will mirror the networks activity dates. Additionally, the order will begin showing up in PS networks as a network object as well. Note: Network assignment are made at the order level and not the operation level. It is imperative that the planning of the order operations is sound because moving individual operations is not possible.

64 Overview and reporting in PS Networks (CN41)

65 More on Project Info Systems (CN41) Graphics Network Diagram These charts show durations, relationships, float and critical path (red) for the networks

66 More on Project Info Systems (CN41) Graphics This is a Gantt view of the same network diagram.

67 SAP Leveling Capacity Evaluation Capacity Planning Table SAP Multi-Resource Scheduling (MRS) SAP Projects SAP EPC PMM Click Software PMX Prometheus The Options

68 Scheduling in an External Scheduling Tool Utilization of known scheduling tools Improved communication with contractor/business partners Primavera MS Project

69 Interfaces An external scheduling tool always needs an interface to SAP Integration is usually expensive Primavera Interfaces SAP PPM EPC Enterprise Project Connection Oracle Inspire Pipeline Maxavera Microsoft Project Interfaces SAP PPM EPC Enterprise Project Connection Vesta PMM (simple, cost effective)

70 Enabling Real-Time Master Scheduling

71 Execution Planning Plant Maintenance Scenario Primavera P6/MS Project Creation of work orders work order data is available as activities Scheduling dates are updated in SAP Dates are determined by scheduling and leveling Planned cost is calculated Planned cost is visible Confirmations are entered on Activity level Work progress is visible on activity level Actual Cost calculation performed Actual cost is visible on activity level, and allows Budget/Plan/Actual comparison and EVA calculation Primavera

72 Some questions you should answer first Do you understand your requirements? Are you aware of what is available within SAP? What scenario do you want to optimize? Regular maintenance Shutdown/turnaround/outage maintenance What is the number of work orders you schedule? Do you already use project management methodologies and/or systems in your organization?

73 SAP Leveling Capacity Evaluation Capacity Planning Table SAP Multi-Resource Scheduling (MRS) SAP Projects SAP EPC PMM Click Software PMX Prometheus The Options

74 Challenges Customers want to use MS Project to re-arrange their SAP work order operations Customers want a nimble and inexpensive way to integrate the two systems Work planning in SAP requires time and effort to track and manage the number of work orders processed

75 PMM Data Flow Data Flow: Work order data Updated Dates, Work Centers, Personnel, etc. MS Project filled with Tasks Work assignment

76 Benefits Reduce time to assign and optimize PM Work Leverage MS Project knowledge Display charts of PM work in MS Project Create confirmations from MS Project Easy to configure Download SAP Work Centers and Personnel into MS Project to make assignments

77 Vesta PMM in MS Project MS Project 2007 MS Project 2010

78 Specify selection criteria

79 Progress Bar With Cancel (during load)

80 Re-align activities in MS Project

81 Work order data is updated in SAP

82 SAP Leveling Capacity Evaluation Capacity Planning Table SAP Multi-Resource Scheduling (MRS) SAP Projects SAP EPC PMM Click Software PMX Prometheus The Options

83 Why SAP partnered with ClickSoftware? SAP customers and prospects are asking specifically for workforce optimization The SAP-ClickSoftware combined offering addresses an acute need for Utility and Telecommunication companies The SAP-ClickSoftware offering provides a best-of-breed solution to the market Proven and Certified integration across more than 20 customers The Return on Investment (ROI) of the combined solution is extremely compelling Recommended Solution if Optimization and Travel Times are required

84 Customer Call Centre Example: Complete Service Optimization from SAP & Click Software SAP CRM SAP ERP ClickPlan ClickForecast ClickSchedule ClickAnalyze Mobile Apps MAU/MAM Contractor Dispatcher Field Worker

85 Video Service Task Scheduled to Start in Appointment Window

86 SAP Leveling Capacity Evaluation Capacity Planning Table SAP Multi-Resource Scheduling (MRS) SAP Projects SAP EPC PMM Click Software PMX Prometheus The Options

87 BAPI s and RFC s IT Overview The Vesta Integration is developed as a Microsoft Excel Add-In It uses standard SAP BAPI s to interface with SAP The add-on honors all SAP and Microsoft security mechanisms SAP MS Excel Vesta Integration Add-on

88 SAP Screens Selected Operation Note the current Work Center and lack of assigned person Note the current Start date

89 Vesta PMX Excel Add-In Toolbar The tool is distributed as an Excel Add-In and can be found on the Data ribbon Toolbar contains four primary buttons: Load data from SAP Save changes made back into SAP Open SAP transaction IW32 Open SAP transaction IW41

90 Vesta PMX Selection Screen Press the Load From SAP button to produce the Selection Screen Customizable Selection screen

91 Vesta PMX Result Screen

92 Vesta PMX Pre-populated Work Centers All Work Centers used by the Planning Plant are loaded and populated in dropdown box All Employees for each Work Center are also populated in a dropdown box

93 Clicking on a date field opens up a calendar selection form. Vesta PMX Date change

94 Make changes to Work Center, Employee and Start Date/Time Vesta PMX Changes Press the Save To SAP button to save this data back into SAP

95 SAP results after changes Changed Work Center and assigned Employee Changed Start and Finish dates Can also update: Confirmation data User status data

96 SAP Leveling Capacity Evaluation Capacity Planning Table SAP Multi-Resource Scheduling (MRS) SAP Projects SAP EPC PMM Click Software PMX Prometheus The Options

97 Enhanced graphical planning board with flexible settings Drag and Drop functionality for operations Collapse/expand work orders Single/mass work order rescheduling Maintain / Create Relationships & Floats Configurable bar color coding Critical path display Calculate / display capacity using HR Master records Full drill down and update: Orders and Operations Work Center Capacity Flexible Order / Operations layouts Link to Materials Availability report Extensive Selection Criteria Scheduling Modes real time / simulation Orders and operations can be dispatched and de-allocated Auto leveling to resource capacity GWOS Key Features

98 GWOS Graphical Work Order Scheduler Work Order / Operations Details Planning Board Work Center Details Availability / Assigned

99 GWOS Graphical Work Order Scheduler

100 GWOS Graphical Work Order Scheduler

101 GWOS Graphical Work Order Scheduler

102 GWOS Graphical Work Order Scheduler

103 GWOS Graphical Work Order Scheduler

104 GWOS Graphical Work Order Scheduler

105 GWOS Graphical Work Order Scheduler

106 The Results

107 Scheduling Options Options Routine Shutdowns E+C Projects Field Service SAP Leveling SAP MRS $$ SAP Projects SAP EPC with Primavera $$ PMM $ Click Software $$$ PMX $ Prometheus GWOS $$ GPSS

108 Benefits of Scheduling Good Maintenance is Expensive - Bad Maintenance Costs Even More Production Longer working hours Run harder to make up Sub-contract Carry extra Inventory Redundant Equipment Maintenance Longer working hours Work harder to make up Subcontract Labor allocations Overtime Week-end and Shift work

109

110 THANK YOU FOR PARTICIPATING Please provide feedback on this session by completing a short survey via the event mobile application. SESSION CODE: 2601 For ongoing education on this area of focus, visit

SAP Multiresource Scheduling Solution Brief. Aug / 2015

SAP Multiresource Scheduling Solution Brief. Aug / 2015 SAP Multiresource Scheduling Solution Brief Aug / 2015 Introduction SAP Multiresource Scheduling Functionality, Integration and Technology as enabler SAP Multiresource Scheduling is the resource management

More information

Turnaround / Shutdown Management with SAP Enterprise Asset Management Dean Fitt

Turnaround / Shutdown Management with SAP Enterprise Asset Management Dean Fitt Turnaround / Shutdown Management with SAP Enterprise Asset Management Dean Fitt SAP AG A collaboration of: What I ll Cover SAP Enterprise Asset Management can be used to manage the whole lifecycle of a

More information

SAP MRS Multiresource Scheduling Info session - 2013. Atul Wakankar May 2013

SAP MRS Multiresource Scheduling Info session - 2013. Atul Wakankar May 2013 SAP MRS Multiresource Scheduling Info session - 2013 Atul Wakankar May 2013 MRS: Foundation for the End-to-end Scheduling Process Resource Management for various Industries and different Scenarios Oil

More information

Mastering Microsoft Project 2013

Mastering Microsoft Project 2013 Course 55054: Mastering Microsoft Project 2013 Page 1 of 9 Mastering Microsoft Project 2013 Course 55054: 2 days; Instructor-Led Introduction This two-day, instructor-led course is intended for individuals

More information

Mastering Microsoft Project 2013 Course: 55054A Course Length: 3 Days

Mastering Microsoft Project 2013 Course: 55054A Course Length: 3 Days 3 Riverchase Office Plaza Hoover, Alabama 35244 Phone: 205.989.4944 Fax: 855.317.2187 E-Mail: rwhitney@discoveritt.com Web: www.discoveritt.com Mastering Microsoft Project 2013 Course: 55054A Course Length:

More information

Mastering Microsoft Project 2010

Mastering Microsoft Project 2010 Mastering Microsoft Project 2010 Duration: 2 days Course Description This two-day instructor-led course provides students with the knowledge and skills to plan and manage projects using Microsoft Project

More information

Mastering Microsoft Project 2013

Mastering Microsoft Project 2013 This three-day, instructor-led course is intended for individuals who are interested in expanding their knowledge base and technical skills about Microsoft Project. The course begins with the basic concepts

More information

Mastering Microsoft Project 2010 50413B; 3 days, Instructor-led

Mastering Microsoft Project 2010 50413B; 3 days, Instructor-led Mastering Microsoft Project 2010 50413B; 3 days, Instructor-led Course Description This three-day instructor-led course provides students with the knowledge and skills plan and manage projects using Microsoft

More information

NE-50413B Mastering Microsoft Project 2010

NE-50413B Mastering Microsoft Project 2010 NE-50413B Mastering Microsoft Project 2010 Summary Duration Vendor 3 Days Microsoft Audience This course is intended for both novice and experienced Project Managers and project support personnel who need

More information

Software Development & Education Center. Microsoft Office 2010. (Microsoft Project 2010)

Software Development & Education Center. Microsoft Office 2010. (Microsoft Project 2010) Software Development & Education Center Microsoft Office 2010 (Microsoft Project 2010) Mastering Microsoft Project 2010 About This Course This three-day instructor-led course provides students with the

More information

Microsoft Project Professional

Microsoft Project Professional Microsoft Project Professional A 100% practical workshop to master Microsoft Project, training the main features of the application for project management. Objective Insight into the functions required

More information

Planning and Managing Projects with Microsoft Project Professional 2013

Planning and Managing Projects with Microsoft Project Professional 2013 Slides Slides Slides Steps to Enter Resource Types: 1. Click View and Resource Sheet 2. In the Type column of a resource, select Work, Material, or Cost, and press Enter on your keyboard Important

More information

User Guide QAD Field Service Scheduler

User Guide QAD Field Service Scheduler User Guide QAD Field Service Scheduler Introduction to QAD FSS All Calls Browse Gantt Chart Scheduling Tab Call Details Tab List of Engineers Tab Geography Map Tab Part Details Tab 78-0698-3.3.1 QAD Field

More information

MAXIMO SCHEDULER 7.5.1 Bouke Spoelstra

MAXIMO SCHEDULER 7.5.1 Bouke Spoelstra MAXIMO SCHEDULER 7.5.1 Bouke Spoelstra 1 Topics To Be Covered Scheduler - Our revised view of Work Management Licensing & Pricing Target Markets & Differentiators Detailed Functionality by Role Key Contacts

More information

Maximo Scheduler Update

Maximo Scheduler Update Anthony Honaker, Maximo Product Strategy Maximo Scheduler Update 2012 IBM Corporation 2009 IBM Corporation Please note: IBM s statements regarding its plans, directions, and intent are subject to change

More information

INTRODUCTION 5 COLLABORATION RIBBON 5 SELECT THE UPDATING METHOD 6 MAKE YOUR PROJECT COLLABORATIVE 8 PROCESSING RECEIVED TASK UPDATES 9

INTRODUCTION 5 COLLABORATION RIBBON 5 SELECT THE UPDATING METHOD 6 MAKE YOUR PROJECT COLLABORATIVE 8 PROCESSING RECEIVED TASK UPDATES 9 Contents Contents INTRODUCTION 5 COLLABORATION RIBBON 5 SELECT THE UPDATING METHOD 6 MAKE YOUR PROJECT COLLABORATIVE 8 PROCESSING RECEIVED TASK UPDATES 9 IMPORT UPDATES 12 CUSTOM TEXT FIELDS MAPPING 13

More information

OVERVIEW. Microsoft Project terms and definitions

OVERVIEW. Microsoft Project terms and definitions PROJECT 2003 DISCLAIMER: This reference guide is meant for experienced Microsoft Project users. It provides a list of quick tips and shortcuts for familiar features. This guide does NOT replace training

More information

Resource Dashboard. Portfolio and Project Management. A PLM Consulting Solution. Public

Resource Dashboard. Portfolio and Project Management. A PLM Consulting Solution. Public Portfolio and Project Management A PLM Consulting Solution The PPM Consulting Solution allows you to manage you resources efficiently. It shows business partner availability, role demand and staffing,

More information

www.fieldez.com FieldEZ for Oil and Gas

www.fieldez.com FieldEZ for Oil and Gas www.fieldez.com FieldEZ for Oil and Gas Overview Operating in a truly dynamic environment that includes fluctuating energy prices, strict government regulations and environmental pressures while balancing

More information

USER CONVERSION P3, SURETRAK AND MICROSOFT PROJECT ASTA POWERPROJECT PAUL E HARRIS EASTWOOD HARRIS

USER CONVERSION P3, SURETRAK AND MICROSOFT PROJECT ASTA POWERPROJECT PAUL E HARRIS EASTWOOD HARRIS P.O. Box 4032 EASTWOOD HARRIS PTY LTD Tel 61 (0)4 1118 7701 Doncaster Heights ACN 085 065 872 Fax 61 (0)3 9846 7700 Victoria 3109 Project Management Systems Email: harrispe@eh.com.au Australia Software

More information

VIP & Mobile Maintenance. Kim Boger AECI Eric Stern Juan Collados

VIP & Mobile Maintenance. Kim Boger AECI Eric Stern Juan Collados VIP & Mobile Maintenance Kim Boger AECI Eric Stern Juan Collados VIP Overview VIP supports effective daily maintenance scheduling. Maintenance labor can be a significant input cost especially in older

More information

Oracle Primavera P6 Enterprise Project Portfolio management Overview Programme Reference # 201A

Oracle Primavera P6 Enterprise Project Portfolio management Overview Programme Reference # 201A Oracle Primavera P6 Enterprise Project Portfolio management Overview Programme Reference # 201A Programme Description: Dedicated one full day training module in a structured and professional manner to

More information

Scheduling Document Creation

Scheduling Document Creation Scheduling Document Creation What is a Schedule in epm? Schedules The epm Schedule application is an integral part of the Portfolio Management suite of applications. Start and end dates for each summary

More information

PERCEPTION PERT-PAC Using Microsoft Project 2000

PERCEPTION PERT-PAC Using Microsoft Project 2000 PERCEPTION PERT-PAC Using Microsoft Project 2000 to Plan & Schedule A Training Tutorial (Sample Hull Block Construction) 1 This training tutorial outlines the basic features of the Microsoft Project 2000

More information

IST 195 Lab 12 Introduction to Microsoft Project

IST 195 Lab 12 Introduction to Microsoft Project IST 195 Lab 12 Introduction to Microsoft Project Microsoft Project is a project management software program developed and sold by Microsoft which is designed to assist project managers in developing plans,

More information

QAD Enterprise Asset Management BI Metrics Demonstration Guide. May 2015 BI 3.11

QAD Enterprise Asset Management BI Metrics Demonstration Guide. May 2015 BI 3.11 QAD Enterprise Asset Management BI Metrics Demonstration Guide May 2015 BI 3.11 Overview This demonstration focuses on one aspect of QAD Enterprise Asset Management Business Intelligence Metrics and shows

More information

Scheduling Software User s Guide

Scheduling Software User s Guide Scheduling Software User s Guide Revision 1.12 Copyright notice VisualTime is a trademark of Visualtime Corporation. Microsoft Outlook, Active Directory, SQL Server and Exchange are trademarks of Microsoft

More information

Microsoft Project Server 2010 Project Manager s Guide for Project Web App

Microsoft Project Server 2010 Project Manager s Guide for Project Web App Microsoft Project Server 2010 Project Manager s Guide for Project Web App Copyright This document is provided as-is. Information and views expressed in this document, including URL and other Internet Web

More information

Stephanie Smith Inside Sales Brittenford Systems. Cynthia West VP, Sales and Marketing Project Insight

Stephanie Smith Inside Sales Brittenford Systems. Cynthia West VP, Sales and Marketing Project Insight Stephanie Smith Inside Sales Brittenford Systems Cynthia West VP, Sales and Marketing Project Insight Natalie Solomon Divney Project and Portfolio Management Consultant ERP/Financial Management Enterprise

More information

ARTEMIS VIEWS ADVANCED PLANNING. With ProjectView

ARTEMIS VIEWS ADVANCED PLANNING. With ProjectView ARTEMIS VIEWS ADVANCED PLANNING With ProjectView ADVANCED PLANNING Advanced Planning is a powerful role-based project and resource management application. Designed for project managers, project planners

More information

Microsoft Project 2013 Guide to Task and Resource Planning

Microsoft Project 2013 Guide to Task and Resource Planning Starting a Project The Microsoft Project 2013 Start screen Double click Blank Project, select a Recent project, or click Open Other Projects to work on a saved project stored on disk or on SkyDrive. To

More information

How project management software can smooth the way

How project management software can smooth the way How project management software can smooth the way By Michael V. Brown New Standard Institute The most demanding call on maintenance resources comes when a plant or facility is shut down for an extended

More information

How To Increase Employee Productivity And Increase Wrench Time At An Oil Refinery

How To Increase Employee Productivity And Increase Wrench Time At An Oil Refinery Employee Productivity Improvement Strategies In Oil Refinery Environments Automated Workforce Management Helps Reduce Maintenance Backlogs, Increase Safety Compliance and Improve Profitability CONTENTS

More information

Lehnert Computer Services

Lehnert Computer Services Article for MPA ezine March, 2007 Ellen Lehnert, PMP - Lehnert Computer Services www.lehnertcs.com RE: Project Progress Comparison Question: Every month I am required to produce a report that shows the

More information

Absoft White Paper Managing maintenance in upstream oil and gas: Which software is best?

Absoft White Paper Managing maintenance in upstream oil and gas: Which software is best? Absoft White Paper Managing maintenance in upstream oil and gas: Which software is best? Geoff Taggart Absoft Limited Achilles JQS Qualified Registered Absoft White Paper Managing maintenance in upstream

More information

PROJECT MANAGEMENT IN PRIMAVERA P6 WEB ACCESS REL 7

PROJECT MANAGEMENT IN PRIMAVERA P6 WEB ACCESS REL 7 PROJECT MANAGEMENT IN PRIMAVERA P6 WEB ACCESS REL 7 Duration: 03 days INTRODUCTION This course provides hands-on training for Primavera s web-based solution. Participants will create a project, add activities

More information

Oracle s Primavera P6 Enterprise Project Portfolio Management

Oracle s Primavera P6 Enterprise Project Portfolio Management Oracle s Primavera P6 Enterprise Project Portfolio Management Oracle s Primavera P6 Enterprise Project Portfolio Management is the most powerful, robust and easy-to-use solution for prioritizing, planning,

More information

Stefan Glatzmaier, Michael Sokollek. Project Portfolio Management with SAP. RPM and cprojects. Bonn Boston

Stefan Glatzmaier, Michael Sokollek. Project Portfolio Management with SAP. RPM and cprojects. Bonn Boston Stefan Glatzmaier, Michael Sokollek Project Portfolio Management with SAP RPM and cprojects Bonn Boston Contents Acknowledgements... 9 Introduction... 11 1 Overview of Project Portfolio Management with

More information

Module A2 Item Activities, Gantt Chart and Utilization Sheet

Module A2 Item Activities, Gantt Chart and Utilization Sheet Module A2 Item Activities, Gantt Chart and Utilization Sheet A2.1 Project item activities A2.2 Gantt chart A2.3 Utilization sheet 1 Module 1. Project item activities, Gantt Chart & Utilization Sheet Contents...

More information

1... Overview of Project Portfolio Management with SAP... 15 1.1... Requirements Scenario for Project Portfolio Management... 15...

1... Overview of Project Portfolio Management with SAP... 15 1.1... Requirements Scenario for Project Portfolio Management... 15... 1... Overview of Project Portfolio Management with SAP... 15 1.1... Requirements Scenario for Project Portfolio Management... 15... Project Initialization 1... 15... Project Planning 2... 17... Resource

More information

Oracle s Primavera Project Portfolio Management Technology Overview and Vision Sept 2011

Oracle s Primavera Project Portfolio Management Technology Overview and Vision Sept 2011 Oracle s Primavera Project Portfolio Management Technology Overview and Vision Sept 2011 Dick Faris Senior Vice President, Primavera GBU Safe Harbor Statement The following is intended

More information

WHAT IS IT? WHO IS IT FOR? WHY?

WHAT IS IT? WHO IS IT FOR? WHY? WHAT IS IT? Zoho Creator is an online platform that allows you to build custom applications for any business need, all by yourself. together - just the application you need. To make it work the way you

More information

Microsoft Project 2013

Microsoft Project 2013 CALIFORNIA STATE UNIVERSITY, LOS ANGELES INFORMATION TECHNOLOGY SERVICES Microsoft Project 2013 Summer 2014, Version 1.0 Table of Contents Introduction...2 Overview of the User Interface...2 Creating a

More information

Administration. Welcome to the Eastwood Harris Pty Ltd MICROSOFT PROJECT 2010 AND PMBOK GUIDE FOURTH EDITION training course presented by

Administration. Welcome to the Eastwood Harris Pty Ltd MICROSOFT PROJECT 2010 AND PMBOK GUIDE FOURTH EDITION training course presented by Welcome to the Eastwood Harris Pty Ltd MICROSOFT PROJECT 2010 AND PMBOK GUIDE FOURTH EDITION training course presented by Paul E Harris Administration Evacuation Timings, meals and facilities Mobile phones

More information

Microsoft Outlook 2013 Workshop

Microsoft Outlook 2013 Workshop Microsoft Outlook 2013 Workshop Course objectives: Manage correspondence and contacts efficiently Use the calendar effectively for appointments, meetings and events Customise Outlook settings View and

More information

Infor LN Service User Guide for Service Scheduler Workbench

Infor LN Service User Guide for Service Scheduler Workbench Infor LN Service User Guide for Service Scheduler Workbench Copyright 2015 Infor Important Notices The material contained in this publication (including any supplementary information) constitutes and contains

More information

LONG INTERNATIONAL. Long International, Inc. 10029 Whistling Elk Drive Littleton, CO 80127-6109 (303) 972-2443 Fax: (303) 972-6980

LONG INTERNATIONAL. Long International, Inc. 10029 Whistling Elk Drive Littleton, CO 80127-6109 (303) 972-2443 Fax: (303) 972-6980 LONG INTERNATIONAL Long International, Inc. 10029 Whistling Elk Drive Littleton, CO 80127-6109 (303) 972-2443 Fax: (303) 972-6980 www.long-intl.com Scott M. Francis, P.E., PSP Table of Contents 1. INTRODUCTION...

More information

CDC UNIFIED PROCESS JOB AID

CDC UNIFIED PROCESS JOB AID Purpose The purpose of this document is to provide guidance on the practice of using Microsoft Project and to describe the practice overview, requirements, best practices, activities, and key terms related

More information

Managing Projects. With. MinuteMan Project Management Software

Managing Projects. With. MinuteMan Project Management Software Managing Projects With MinuteMan Project Management Software Copyright 2011 by MinuteMan Systems Introduction This is a brief introduction to the use of Project Management Software to help you organize

More information

Release Notes Assistance PSA 2015 Summer Release

Release Notes Assistance PSA 2015 Summer Release Release Notes Assistance PSA 2015 Summer Release (August 2015) Advanced Opportunity Management The Microsoft Dynamics CRM Opportunity functionality has been extended with Assistance PSA functionality.

More information

Enhanced Time Entry for. Step-by-Step

Enhanced Time Entry for. Step-by-Step Enhanced Time Entry for Table of Contents CAT2 Step-by-Step Introduction... 3 Document Conventions... 3 Italicized Text... 3 Procedures and Bold/Italicized Text... 3 Graphic Conventions... 3 Training Materials

More information

Steven Wood Software, 2 Harksome Hill, West Hunsbury Northampton. NN4 9YF. United Kingdom

Steven Wood Software, 2 Harksome Hill, West Hunsbury Northampton. NN4 9YF. United Kingdom The Time Location Chart originates from a project management system known as Line of Balance or Elemental Trend Analysis, which is used on projects which are repetitive and require strict trade sequencing,

More information

Microsoft Project 70-178 Exam Study Guide

Microsoft Project 70-178 Exam Study Guide Microsoft Project 70-178 Exam Study Guide Prepared by The Versatile Company for MPUG. www.versatilecompany.com The Versatile Company, 2012. About this Study Guide This guide was developed based upon the

More information

ORACLE PROJECT MANAGEMENT

ORACLE PROJECT MANAGEMENT ORACLE PROJECT MANAGEMENT KEY FEATURES Oracle Project Management provides project managers the WORK MANAGEMENT Define the workplan and associated resources; publish and maintain versions View your schedule,

More information

Microsoft Outlook 2013 Part 1: Introduction to Outlook

Microsoft Outlook 2013 Part 1: Introduction to Outlook CALIFORNIA STATE UNIVERSITY, LOS ANGELES INFORMATION TECHNOLOGY SERVICES Microsoft Outlook 2013 Part 1: Introduction to Outlook Fall 2014, Version 1.0 Table of Contents Introduction...3 Starting Outlook...3

More information

What s New in Version 12

What s New in Version 12 What s New in Version 12 New Service Agreement Scheduling tab design makes scheduling much easier. Brand new List Views report capability that opens the door for new searching and reporting in ESC. Dispatch

More information

Time & Attendance Supervisor Basics for ADP Workforce Now. Automatic Data Processing, LLC ES Canada

Time & Attendance Supervisor Basics for ADP Workforce Now. Automatic Data Processing, LLC ES Canada Time & Attendance Supervisor Basics for ADP Workforce Now Automatic Data Processing, LLC ES Canada ADP s Trademarks The ADP Logo, ADP, ADP Workforce Now and IN THE BUSINESS OF YOUR SUCCESS are registered

More information

Time & Attendance Manager Basics

Time & Attendance Manager Basics Time & Attendance Manager Basics Handout Manual V03261272136EZ18CMB2 2012 ADP, Inc. ADP s Trademarks The ADP Logo, ADP Workforce Now, and ezlabormanager are registered trademarks of ADP, Inc. In the Business

More information

Microsoft Project 2007 Level 2: Working with Resources and Managing a Project

Microsoft Project 2007 Level 2: Working with Resources and Managing a Project Microsoft Project 2007 Level 2: Working with Resources and Managing a Project By Robin Peers Robin Peers, 2008 ABOUT THIS CLASS In Microsoft Project 2007 Level 1: Creating Project Tasks, the focus was

More information

SAP Digital CRM. Getting Started Guide. All-in-one customer engagement built for teams. Run Simple

SAP Digital CRM. Getting Started Guide. All-in-one customer engagement built for teams. Run Simple SAP Digital CRM Getting Started Guide All-in-one customer engagement built for teams Run Simple 3 Powerful Tools at Your Fingertips 4 Get Started Now Log on Choose your features Explore your home page

More information

QAD Field Service Scheduler Demonstration Guide. May 2015 EE2015

QAD Field Service Scheduler Demonstration Guide. May 2015 EE2015 QAD Field Service Scheduler Demonstration Guide May 2015 EE2015 Overview This demonstration focuses on one aspect of QAD SSM Field Service Scheduler and shows how this functionality supports the vision

More information

Construction Planning, Equipment and Methods ENGI 8749 Fall Semester, 2008 Tutorial #2 Resource Leveling using MS Project

Construction Planning, Equipment and Methods ENGI 8749 Fall Semester, 2008 Tutorial #2 Resource Leveling using MS Project Construction Planning, Equipment and Methods ENGI 8749 Fall Semester, 2008 Tutorial #2 Resource Leveling using MS Project Project Example Overview Microsoft Project, in addition to scheduling calculations,

More information

1 Start a new project

1 Start a new project Project Management Quick Reference Guide for Microsoft Project 2010 Before beginning a new project, an organization must determine whether the project fits its strategic goals. Executives should classify

More information

TOPS v3.2.1 Calendar/Scheduler User Guide. By TOPS Software, LLC Clearwater, Florida

TOPS v3.2.1 Calendar/Scheduler User Guide. By TOPS Software, LLC Clearwater, Florida TOPS v3.2.1 Calendar/Scheduler User Guide By TOPS Software, LLC Clearwater, Florida Document History Version Edition Date Document Software Trademark Copyright First Edition Second Edition 02 2007 09-2007

More information

Advanced Planning and Scheduling

Advanced Planning and Scheduling Taylor Scheduler Welcome! Taylor Scheduler is our advanced planning and production scheduling software. Its many features allow Taylor Scheduler to be able to handle just about any manufacturing scheduling

More information

Microsoft Project Server 2013

Microsoft Project Server 2013 Project Server 2013 Project Server 2013 is a flexible on-premises solution for project portfolio management (PPM) and everyday work. Team members, project participants, and business decision makers can

More information

Microsoft Access 2010 handout

Microsoft Access 2010 handout Microsoft Access 2010 handout Access 2010 is a relational database program you can use to create and manage large quantities of data. You can use Access to manage anything from a home inventory to a giant

More information

FIELDAWARE PRO. Cloud-based, made for mobile field service automation solution for small and medium-sized businesses. KEY FEATURES

FIELDAWARE PRO. Cloud-based, made for mobile field service automation solution for small and medium-sized businesses. KEY FEATURES KEY Work order management Scheduling and dispatch Customer and asset management Quotes and estimates Invoice creation Built-in business reports Cloud-based, made for mobile field service automation solution

More information

Reading Sample. Integration Scenarios with Other Project Management Tools. Contents. Index. The Author. Project Management with SAP Project System

Reading Sample. Integration Scenarios with Other Project Management Tools. Contents. Index. The Author. Project Management with SAP Project System First-hand knowledge. Reading Sample SAP Project System s innovative design allows for cross-platform usage. This is good news for companies who manage projects through different programs and software.

More information

Manufacturing. Manufacturing challenges of today and how. Navision Axapta solves them- In the current explosive economy, many

Manufacturing. Manufacturing challenges of today and how. Navision Axapta solves them- In the current explosive economy, many Manufacturing challenges of today and how Navision Axapta solves them- the solution for change; controlled by you. Manufacturing In the current explosive economy, many manufacturers are struggling to keep

More information

Customer Master Presentation - Contents

Customer Master Presentation - Contents Customer Master Presentation - Contents V4.607 Solution at a Glance Solution in Detail ESS/MSS with lanes HCM Core Services for Employee Lanes Time Management Services for Employee Lanes Travel Management

More information

Fast Track: Applications in Microsoft Dynamics CRM 2015 / CRM Online (Microsoft Training Course: F1082) - 2 days

Fast Track: Applications in Microsoft Dynamics CRM 2015 / CRM Online (Microsoft Training Course: F1082) - 2 days Fast Track: Applications in Microsoft Dynamics CRM 2015 / CRM Online (Microsoft Training Course: F1082) - 2 days TARGET AUDIENCE This course provides both an introduction to Microsoft Dynamics CRM 2015

More information

INTRODUCTION TO PROJECT MANAGEMENT AND MS PROJECT

INTRODUCTION TO PROJECT MANAGEMENT AND MS PROJECT LECTURE -01 TO PROJECT MANAGEMENT AND MS PROJECT 2 Objective LEARNING OBJECTIVES To learn Project Management Software and their Application to Civil Engineering Books Microsoft Office Project Step by Step

More information

QAD Usability Customization Demo

QAD Usability Customization Demo QAD Usability Customization Demo Overview This demonstration focuses on one aspect of QAD Enterprise Applications Customization and shows how this functionality supports the vision of the Effective Enterprise;

More information

1. INTRODUCTION...2 2. PRODUCT...2. 2.1. Installation... 2 2.2. Documentation... 2 2.3. Website... 2. 3. workbench features...2

1. INTRODUCTION...2 2. PRODUCT...2. 2.1. Installation... 2 2.2. Documentation... 2 2.3. Website... 2. 3. workbench features...2 Table of Contents 1. INTRODUCTION...2 2. PRODUCT...2 2.1. Installation... 2 2.2. Documentation... 2 2.3. Website... 2 3. workbench features...2 3.1. Project Planning... 2 3.2. Project Tracking... 3 4.

More information

Microsoft Project Activity

Microsoft Project Activity Microsoft Project Activity Purpose: The goal of this activity is to lead you through the most important data entry and formatting activities in MS Project and to provide you with the fundamental knowledge

More information

Tracking Project Progress

Tracking Project Progress L E S S O N 2 Tracking Project Progress Suggested lesson time 45-55 minutes Lesson objectives To begin tracking an active project, you will: a b c Modify the environment for tracking. You will use the

More information

Open Workbench Warrior. Beginner's Guide to Open Workbench

Open Workbench Warrior. Beginner's Guide to Open Workbench Open Workbench Warrior Beginner's Guide to Open Workbench Table of Contents Introduction...3 Open Workbench Functionality...3 Project Planning...3 Project Tracking and Management...3 Sample Project...3

More information

Reporting and Analysis Using Vivid Reports Flex

Reporting and Analysis Using Vivid Reports Flex Reporting and Analysis Using Vivid Reports Flex Presented By: Jim Lee Table of Contents Introduction... 3 Simplify... 3 Gain Insight... 3 Build Smarter... 3 Vivid Reports Flex... 4 Getting Started... 4

More information

Information Server Documentation SIMATIC. Information Server V8.0 Update 1 Information Server Documentation. Introduction 1. Web application basics 2

Information Server Documentation SIMATIC. Information Server V8.0 Update 1 Information Server Documentation. Introduction 1. Web application basics 2 Introduction 1 Web application basics 2 SIMATIC Information Server V8.0 Update 1 System Manual Office add-ins basics 3 Time specifications 4 Report templates 5 Working with the Web application 6 Working

More information

Explore commands on the ribbon Each ribbon has groups, and each group has a set of related commands.

Explore commands on the ribbon Each ribbon has groups, and each group has a set of related commands. Quick Start Guide Microsoft Project 2013 looks different from previous versions, so we created this guide to help you minimize the learning curve. Quick Access Toolbar Customize this area so your favorite

More information

CPM Scheduling with Primavera Unifier

CPM Scheduling with Primavera Unifier CPM Scheduling with Primavera Unifier Don McNatty, PSP March 26, 2014 2014 Technical Webinar Series Thank you for joining today s technical webinar Mute all call in phones are automatically muted in order

More information

Intellect Platform - The Workflow Engine Basic HelpDesk Troubleticket System - A102

Intellect Platform - The Workflow Engine Basic HelpDesk Troubleticket System - A102 Intellect Platform - The Workflow Engine Basic HelpDesk Troubleticket System - A102 Interneer, Inc. Updated on 2/22/2012 Created by Erika Keresztyen Fahey 2 Workflow - A102 - Basic HelpDesk Ticketing System

More information

CORE K-Nect Web Portal

CORE K-Nect Web Portal CORE K-Nect Web Portal Training October 2015 KIOSK Information Systems www.kiosk.com October 2015 Table of Contents Table of Contents 1 Getting Started 2 Logging In 2 Your Account Settings 3 My Profile

More information

Using Microsoft Office to Manage Projects

Using Microsoft Office to Manage Projects (or, Why You Don t Need MS Project) Using Microsoft Office to Manage Projects will explain how to use two applications in the Microsoft Office suite to document your project plan and assign and track tasks.

More information

Swedish Time & Attendance (STA)

Swedish Time & Attendance (STA) Swedish Time & Attendance (STA) Swedish Time & Attendance (STA) To Service Customer IT Consultancy Service Time & Attendance Model Fully Integration with Oracle E-Business Suite SAP or (Stand Alone ) Complete,

More information

CRM Alliance Scheduler Productsheet

CRM Alliance Scheduler Productsheet Meeting Your Challenges At CRM Alliance, we understand your need to streamline operations in the face of increased competition, increased customers demand and cost-cutting initiatives. To remain successful

More information

Providing Patch Management With N-central. Version 7.1

Providing Patch Management With N-central. Version 7.1 Providing Patch Management With N-central Version 7.1 Contents Patch Management 3 Introduction 3 Monitoring for Missing Patches 3 Setting up Patch Management in N-central 4 Adding a WSUS Server to N-central

More information

Resco CRM Guide. Get to know Resco CRM

Resco CRM Guide. Get to know Resco CRM Resco CRM Guide Get to know Resco CRM Table of Contents Introducing Resco CRM... 3 1.1. What is Resco CRM...3 1.2. Capabilities of Resco CRM... 4 1.3. Who should use Resco CRM...5 1.4. What are the main

More information

MICROSOFT PROJECT 2010 - II

MICROSOFT PROJECT 2010 - II MICROSOFT PROJECT 2010 - II Course Material This 2-day course is for intermediate and advanced users of the MS Project scheduling application who want to increase their capabilities managing projects in

More information

SELECTING PROJECT MANAGEMENT SOFTWARE

SELECTING PROJECT MANAGEMENT SOFTWARE SELECTING PROJECT MANAGEMENT SOFTWARE Information needs People at different levels within an organization have different information needs. Information should be made available to all as needed, in a standardized

More information

Project 2010. Quick Reference. The Assignment Equation. EPM Architects www.epmarchitects.com

Project 2010. Quick Reference. The Assignment Equation. EPM Architects www.epmarchitects.com The Assignment Equation The following equation controls the relationship between the Work, Duration, and Assignment Units for a task assignment: Or Or Work: The number of hours of real work effort spent

More information

Building a Reporting and Analytics System Connected Enterprise Seminar

Building a Reporting and Analytics System Connected Enterprise Seminar Manufacturing Intelligence, de stuwende kracht om in een Connected Enterprise snel accurate beslissingen te nemen om de bedrijfsprestaties te optimaliseren. Building a Reporting and Analytics System Connected

More information

Microsoft Dynamics GP. Field Service Service Call Management

Microsoft Dynamics GP. Field Service Service Call Management Microsoft Dynamics GP Field Service Service Call Management Copyright Copyright 2011 Microsoft. All rights reserved. Limitation of liability This document is provided as-is. Information and views expressed

More information

Command Spanish for Healthcare

Command Spanish for Healthcare Command Spanish for Healthcare Online Command Spanish Command Spanish is a learner-friendly language program and training class that requires NO PRIOR KNOWLEDGE OF SPANISH. Command Spanish language classes

More information

NetComplete Ethernet Performance Management. Ethernet Performance and SLA Monitoring Application

NetComplete Ethernet Performance Management. Ethernet Performance and SLA Monitoring Application NetComplete Ethernet Performance Management Ethernet Performance and SLA Monitoring Application NetComplete Service Assurance for Ethernet The Viavi NetComplete Solution for Ethernet provides an integrated,

More information

PLANNING AND SCHEDULING USING MICROSOFT PROJECT 2010 PAUL EASTWOOD HARRIS

PLANNING AND SCHEDULING USING MICROSOFT PROJECT 2010 PAUL EASTWOOD HARRIS PLANNING AND SCHEDULING USING MICROSOFT PROJECT 2010 BY PAUL EASTWOOD HARRIS Eastwood Harris Pty Ltd i Copyright 1999 2010 by Eastwood Harris Pty Ltd. No part of this publication may be reproduced or used

More information

MODEL SCHEDULING SPECIFICATION

MODEL SCHEDULING SPECIFICATION MODEL SCHEDULING SPECIFICATION Introduction (Not part of the specification) Before implementation, we recommend that your contract and this provision be reviewed and modified to ensure compatibility with

More information

Appointment Scheduler

Appointment Scheduler EZClaim Appointment Scheduler User Guide Last Update: 11/19/2008 Copyright 2008 EZClaim This page intentionally left blank Contents Contents... iii Getting Started... 5 System Requirements... 5 Installing

More information