1 PROJECT MINUTES Project: New Holbrook PreK12 School Project No.: Prepared by: Joel Seeley Meeting Date: 1/14/2015 Re: CM Selection Committee Meeting Meeting No: 2 Location: Town Hall Time: 5:30 PM Distribution: Attendees, (MF) Attendees: PRESENT NAME AFFILIATION Daniel F. Moriarty PSBC Chair By phone Mike Reith PSBC ViceChair Mike Bolger HPS Director of Facilities Kent Kovacs Flansburgh Associates (FAI) Bryan LeBlanc MHT&L, Town Counsel Joel Seeley SMMA, OPM Item # Action Discussion 2.1 Record Call to Order, 5:30 pm, meeting opened. 2.2 Record A motion was made by D. Moriarty and seconded by M. Bolger to approve the 1/7/15 CM Selection Committee meeting minutes. No discussion, motion passed unanimous by those attending. 2.3 Record J. Seeley distributed and reviewed the CM NonPrice and Price Evaluation Form, attached. 2.4 J. Seeley Each Committee member discussed their preliminary review findings of the submitted Proposal packages. J. Seeley to request Gilbane Building Company to clarify the role and experience of Ms. Aleita Hall, who was listed as the Manager of Engineering in the Statement of Qualifications and is now listed as the Project Manager in the Proposal. 2.5 J. Seeley J. Seeley distributed and reviewed the draft list of questions to ask each CM Firm at the interview. J. Seeley to request each of the CM firms to respond to the following questions during their interview: 1. What do you see as the most important challenge for the project?
2 2 Holbrook Elementary Schools and JuniorSenior High School Feasibility Study 1/14/ Item # Action Discussion 2. How will you manage the impact of construction operations on the commuter traffic along South Franklin Street, as well as the onsite traffic and parking for the existing Junior/Senior High School? 3. What is your process of engaging all key stakeholders in understanding the full impact of value engineering options and decisions? 4. If the Town desires to occupy the new PreK12 School in the summer of 2017, what measures would you undertake to make this happen? The Committee to develop the final list of other questions to be asked of each CM firm, during the interview, and finalize at the next Committee meeting. 2.6 Record J. Seeley distributed and reviewed updated the CM Selection Timeline, attached. 2.7 J. Seeley J. Seeley distributed and reviewed the draft analysis of each CM firm s Price Proposal, attached. Each Committee member to review. J. Seeley to request Turner Construction Company to clarify the General Liability Insurance as listed in the Price Proposal Form GC, Section C.4. J. Seeley to provide an analysis of each CM firm s Construction Staffing Plan and forward to the Committee prior to next meeting. 2.8 Record Next Meeting: January 21, 2015 at 5:30 pm at the Town Hall. 2.9 Record A Motion was made by M. Bolger and seconded by D. Moriarty to adjourn the meeting. No discussion, voted unanimously. Attachments: Agenda, CM Selection Timeline, CM Evaluation Form, Draft CM Questions, draft analysis of CM s Price Proposal The information herein reflects the understanding reached. Please contact the author if you have any questions or are not in agreement with these Project Minutes. JGS/sat/P:\2013\13006\04MEETINGS\4.3 Mtg_Notes\CM Selection Committee\2015_14January_Cmselectioncommittee\Cmselectioncommitteemeeting_14January2015FINAL.Docx
3 PROJECT MEETING SIGNIN SHEET Project: New Holbrook PreK12 School, Holbrook, MA Project No.: Prepared by: Joel Seeley Meeting Date: 1/14/2015 Re: CM Selection Committee Meeting Meeting No: 2 Location: Town Hall Inspector s Conference Room Time: 5:30pm Distribution: Attendees, (MF) SIGNATURE ATTENDEES AFFILIATION Daniel F. Moriarty inspection@holbrookmassachusetts.us PSBC Chair Mike Reith Rmike66@comcast.net PSBC ViceChair Mike Bolger mbolger@holbrook.k12.ma.us HPS Facilities Director Kent Kovacs kkovacs@faiarchitects.com Flansburgh Associates Bryan LeBlanc bleblanc@mhtl.com Town Counsel, Murphy, Hesse, Toomey & Lehane, LLP Joel Seeley Jseeley@smma.com SMMA, OPM p:\2013\13006\04meetings\4.3 mtg_notes\cm selection committee\2015_14january_cmselectioncommittee\cmselectioncommitteemeetingsigninsheet_14january2015.docx
4 AGENDA Project: New Holbrook PreK12 School, Holbrook, MA Project No.: Re: CM Selection Committee Location: Town Hall Inspector s Conference Room Meeting Date: 1/14/2015 Prepared by: Joel G. Seeley Meeting Time: 5:30 PM Distribution: Attendees (MF) 1. Call to Order 2. Approval of Minutes 3. Preliminary Evaluation of Proposals 4. Review Questions for Interviews 5. Adjourn JGS/sat/P:\2013\13006\04MEETINGS\4.2 Agendas\CM Selection Committee\2015_14January_Cmselectioncommittee\Agenda_14January2015.Doc
5 PROJECT MANAGEMENT Holbrook PK12 School October 30, 2014 Updated: January 14, 2015 Construction Manager Selection Timeline August 28, 2014 October 3 November 4 November 11 Submit Application to Inspector General Notice to Proceed with CM at Risk from Inspector General Proposition 21/2 Ballot Vote Submit Request for Qualifications (RFQ) Advertisement to: 1. Central Register (CR) 2. Local Newspaper November 19 RFQ Advertisement Noticed in: 1. Central Register (CR) 2. Local Newspaper November 25 November 25 November 26 November 26 December 3 December 3 17 December 10 December 17 December 18 January 7, 2015 January 9 January 14 January 21 January 24 February 4 February 4 18 February 18 Informational Meeting at Jr./Sr. High School and Tour 3:30 PM Review Draft CM RFP at Jr./Sr. High School 5:30pm CM RFQ Letter of Interest Due Deadline for CM Submission of Questions CM Qualification Packages Due Evaluate RFQs to Prequalify CM Firms to Receive RFP Qualifications Preliminary Review Meeting / Final Review of RFP at Town Hall 5:30pm Qualifications Final Review / Shortlist / Final Review of RFP Documents at Town Hall 5:30pm Distribute RFP to Prequalified CM Firms Review Draft Evaluation forms; Schedule Interviews CM Proposal Packages Due Preliminary Evaluation of Proposals, Finalize Questions for Interviews Evaluation of Proposals CM Interviews, Rank CM Firms Prequalification Committee CM Recommendation at PSBC Meeting Finalize General Conditions, Fee and Contract Terms with Selected CM Firm CM attend PSBC Meeting p:\2013\13006\10bid\cm selection schedule14january2015.doc
6
7 CM AT RISK PROPOSAL EVALUATION NEW HOLBROOK PREK12 SCHOOL, HOLBROOK, MASSACHUSETTS PROJECT MANAGEMENT COMBINED EVALUATION SCORES NON PRICE AND PRICE PROPOSAL Consigli Construction Company Non Price Proposal Rating Gilbane Building Company Turner Construction Company Consigli Construction Company Price Proposal Rating Gilbane Building Company Turner Construction Company Signature Date Comments Page 1 of 10
8
9 PROJECT MANAGEMENT CM AT RISK PROPOSAL EVALUATION NEW HOLBROOK PREK12 SCHOOL, HOLBROOK, MASSACHUSETTS CM AT RISK SELECTION RFP PHASE CM Company Name Evaluator's Name Consigli Construction Company Instructions: CM Selection Committee Members should begin with their review of the NonPrice Proposal and complete the NonPrice Proposal Evaluation. Open and review the Price Proposal and complete the Price Proposal Evaluation Matrix below only after completing the NonPrice Evaluation. Upon Completion of the Price Proposal Evaluation, sign and date both forms. Section #1: Verify that all Non Price Proposal Submission Documents have been submitted. Section #2: Verify that all Price Proposal Submission Documents have been submitted. Section #3: Enter evaluation rating. Section #1: Required Documents to be in the Non Price Proposal Submission Request for Proposal Response Form (Form A) Informational Sheet (Form B) Affidavit of Compliance (Form C) Certificate of Tax Compliance (Form D) Affidavit of Prevailing Wage Compliance (Form E) Certificate of Eligibility DCAM s Update Statement Bond Commitment Letter Project Experience on Comparable Projects Management Plan Staffing Plan Resumes Job Skill Narrative Self Performing Work Legal Proceedings Compliance of Labor/OSHA Compliance (Form F) Certificate of NonCollusion (Form G) Certificate of Interest Certification (Form H) Certificate of Compliance with M.G.L. C.151B (Form I) Certificate of NonDebarment (Form J) Certificate of Corporate Responder (Form K) Section #2: Required Documents to be in the Price Proposal Submission Form GC Price Proposal Form GC Section B: Schedule of CM Costs Preconstruction Phase Form GC Section C: Schedule of CM Costs Construction Phase * Items (/not ) confirmed by SMMA Page 2 of 10
10 PROJECT MANAGEMENT CM AT RISK PROPOSAL EVALUATION NEW HOLBROOK PREK12 SCHOOL, HOLBROOK, MASSACHUSETTS Section #3: Evaluators Rankings CM AT RISK SELECTION RFP PHASE Instructions: Please place a check mark in the box which best represents the materials submitted in the Non Price Proposal and tally the corresponding numbers below. Upon completion please sign and date. CM COMPANY NAME: Consigli Construction Company 1. Management Team Is the Management Team especially superintendent and project manager knowledgeable and qualified to meet the project goals? Yes the Management Team meet all of the above Yes the Management Team meet most of the above No the Management Team does not meet any of the above 2. Management Plan Does the Management Plan for the project, describe in detail the firm s proposed approach to meeting the project goals, including schedule and phasing management, budget management, quality management goals and maintaining safety? Yes the Management Plan includes all of the above Yes the Management Plan includes most of the above No the Management Plan does not include any of the above 3. Project Plan PreConstruction Does the Offeror's plan illustrate the understanding of the activities required during preconstruction and demonstrate the ability to coordinate and perform those activities including design review, phasing and scheduling, cash flow chart, value engineering, constructability, cost control, and subcontractor bid packages. Yes the PreConstruction Plan fully illustrates all of the above Yes the PreConstruction Plan fully illustrates most of the above No the PreConstruction Plan fully illustrates none of the above 4. Project Plan Construction Does the Offeror's plan illustrate a clear management structure and methodology for project management, logistics, phasing and sequencing of the Work? Does the Offeror have project specific program for quality assurance and quality control. Has the Offeror described how they will comply with requirements for schedule development, cost loading, resource loading, monthly schedule updates, periodic community meetings, and weekly project meeting review of the look ahead schedule? Yes the Construction Plan includes all of the above Yes the Construction Plan includes most of the above No the Construction Plan includes none of the above Page 3 of 10
11 PROJECT MANAGEMENT CM AT RISK PROPOSAL EVALUATION NEW HOLBROOK PREK12 SCHOOL, HOLBROOK, MASSACHUSETTS 5. Schedule CM AT RISK SELECTION RFP PHASE Did the Offeror submit its proposed Preliminary Project Schedule. Is this schedule clearly explained and advantageous for this project timeline? Yes the Schedule is and advantageous for this project Yes the Schedule is and mostly advantageous for this project No the Schedule is not and nonadvantageous for this project 6. Comparable Experience Is the Offeror s experience similar in scope, size and budget to this project. Does the Offeror s experience includes projects on occupied sites? Yes the Comparable Experience includes all of the above Yes the Comparable Experience includes most of the above No the Comparable Experience includes none of the above 7. Litigation Does the Offeror s history of litigation indicate a culture of collaboration and teamwork between Owner, Designer and Subcontractors? Yes the history of Litigation indicates all of the above Yes the history of Litigation indicates most of the above No the history of Litigation does not indicate the above 8. Financial Capacity Does the Offeror's financial capacity support their ability to undertake this project? Yes the Financial Capacity indicates all of the above Yes the Financial Capacity indicates most of the above No the Financial Capacity does not indicate the above 9. Safety History Does the Offeror s Safety History support their approach to this project? Yes the Safety History includes all of the above Yes the Safety History includes most of the above No the Safety History includes none of the above. TOTAL (#19 ABOVE) Signature Date Page 4 of 10
12
13 PROJECT MANAGEMENT CM AT RISK PROPOSAL EVALUATION NEW HOLBROOK PREK12 SCHOOL, HOLBROOK, MASSACHUSETTS CM AT RISK SELECTION RFP PHASE CM Company Name Evaluator's Name Gilbane Building Company Instructions: CM Selection Committee Members should begin with their review of the NonPrice Proposal and complete the NonPrice Proposal Evaluation. Open and review the Price Proposal and complete the Price Proposal Evaluation Matrix below only after completing the NonPrice Evaluation. Upon Completion of the Price Proposal Evaluation, sign and date both forms. Section #1: Verify that all Non Price Proposal Submission Documents have been submitted. Section #2: Verify that all Price Proposal Submission Documents have been submitted. Section #3: Enter evaluation rating. Section #1: Required Documents to be in the Non Price Proposal Submission Request for Proposal Response Form (Form A) Informational Sheet (Form B) Affidavit of Compliance (Form C) Certificate of Tax Compliance (Form D) Affidavit of Prevailing Wage Compliance (Form E) Certificate of Eligibility DCAM s Update Statement Bond Commitment Letter Project Experience on Comparable Projects Management Plan Staffing Plan Resumes Job Skill Narrative Self Performing Work Legal Proceedings Compliance of Labor/OSHA Compliance (Form F) Certificate of NonCollusion (Form G) Certificate of Interest Certification (Form H) Certificate of Compliance with M.G.L. C.151B (Form I) Certificate of NonDebarment (Form J) Certificate of Corporate Responder (Form K) Section #2: Required Documents to be in the Price Proposal Submission Form GC Price Proposal Form GC Section B: Schedule of CM Costs Preconstruction Phase Form GC Section C: Schedule of CM Costs Construction Phase * Items (/not ) confirmed by SMMA Page 5 of 10
14 PROJECT MANAGEMENT CM AT RISK PROPOSAL EVALUATION NEW HOLBROOK PREK12 SCHOOL, HOLBROOK, MASSACHUSETTS Section #3: Evaluators Rankings CM AT RISK SELECTION RFP PHASE Instructions: Please place a check mark in the box which best represents the materials submitted in the Non Price Proposal and tally the corresponding numbers below. Upon completion please sign and date. CM COMPANY NAME: Gilbane Building Company 1. Management Team Is the Management Team especially superintendent and project manager knowledgeable and qualified to meet the project goals? Yes the Management Team meet all of the above Yes the Management Team meet most of the above No the Management Team does not meet any of the above 2. Management Plan Does the Management Plan for the project, describe in detail the firm s proposed approach to meeting the project goals, including schedule and phasing management, budget management, quality management goals and maintaining safety? Yes the Management Plan includes all of the above Yes the Management Plan includes most of the above No the Management Plan does not include any of the above 3. Project Plan PreConstruction Does the Offeror's plan illustrate the understanding of the activities required during preconstruction and demonstrate the ability to coordinate and perform those activities including design review, phasing and scheduling, cash flow chart, value engineering, constructability, cost control, and subcontractor bid packages. Yes the PreConstruction Plan fully illustrates all of the above Yes the PreConstruction Plan fully illustrates most of the above No the PreConstruction Plan fully illustrates none of the above 4. Project Plan Construction Does the Offeror's plan illustrate a clear management structure and methodology for project management, logistics, phasing and sequencing of the Work? Does the Offeror have project specific program for quality assurance and quality control. Has the Offeror described how they will comply with requirements for schedule development, cost loading, resource loading, monthly schedule updates, periodic community meetings, and weekly project meeting review of the look ahead schedule? Yes the Construction Plan includes all of the above Yes the Construction Plan includes most of the above No the Construction Plan includes none of the above Page 6 of 10
15 PROJECT MANAGEMENT CM AT RISK PROPOSAL EVALUATION NEW HOLBROOK PREK12 SCHOOL, HOLBROOK, MASSACHUSETTS 5. Schedule CM AT RISK SELECTION RFP PHASE Did the Offeror submit its proposed Preliminary Project Schedule. Is this schedule clearly explained and advantageous for this project timeline? Yes the Schedule is and advantageous for this project Yes the Schedule is and mostly advantageous for this project No the Schedule is not and nonadvantageous for this project 6. Comparable Experience Is the Offeror s experience similar in scope, size and budget to this project. Does the Offeror s experience includes projects on occupied sites? Yes the Comparable Experience includes all of the above Yes the Comparable Experience includes most of the above No the Comparable Experience includes none of the above 7. Litigation Does the Offeror s history of litigation indicate a culture of collaboration and teamwork between Owner, Designer and Subcontractors? Yes the history of Litigation indicates all of the above Yes the history of Litigation indicates most of the above No the history of Litigation does not indicate the above 8. Financial Capacity Does the Offeror's financial capacity support their ability to undertake this project? Yes the Financial Capacity indicates all of the above Yes the Financial Capacity indicates most of the above No the Financial Capacity does not indicate the above 9. Safety History Does the Offeror s Safety History support their approach to this project? Yes the Safety History includes all of the above Yes the Safety History includes most of the above No the Safety History includes none of the above. TOTAL (#19 ABOVE) Signature Date Page 7 of 10
16
17 PROJECT MANAGEMENT CM AT RISK PROPOSAL EVALUATION NEW HOLBROOK PREK12 SCHOOL, HOLBROOK, MASSACHUSETTS CM AT RISK SELECTION RFP PHASE CM Company Name Evaluator's Name Turner Construction Company Instructions: CM Selection Committee Members should begin with their review of the NonPrice Proposal and complete the NonPrice Proposal Evaluation. Open and review the Price Proposal and complete the Price Proposal Evaluation Matrix below only after completing the NonPrice Evaluation. Upon Completion of the Price Proposal Evaluation, sign and date both forms. Section #1: Verify that all Non Price Proposal Submission Documents have been submitted. Section #2: Verify that all Price Proposal Submission Documents have been submitted. Section #3: Enter evaluation rating. Section #1: Required Documents to be in the Non Price Proposal Submission Request for Proposal Response Form (Form A) Informational Sheet (Form B) Affidavit of Compliance (Form C) Certificate of Tax Compliance (Form D) Affidavit of Prevailing Wage Compliance (Form E) Certificate of Eligibility DCAM s Update Statement Bond Commitment Letter Project Experience on Comparable Projects Management Plan Staffing Plan Resumes Job Skill Narrative Self Performing Work Legal Proceedings Compliance of Labor/OSHA Compliance (Form F) Certificate of NonCollusion (Form G) Certificate of Interest Certification (Form H) Certificate of Compliance with M.G.L. C.151B (Form I) Certificate of NonDebarment (Form J) Certificate of Corporate Responder (Form K) Section #2: Required Documents to be in the Price Proposal Submission Form GC Price Proposal Form GC Section B: Schedule of CM Costs Preconstruction Phase Form GC Section C: Schedule of CM Costs Construction Phase * Items (/not ) confirmed by SMMA Page 8 of 10
18 PROJECT MANAGEMENT CM AT RISK PROPOSAL EVALUATION NEW HOLBROOK PREK12 SCHOOL, HOLBROOK, MASSACHUSETTS Section #3: Evaluators Rankings CM AT RISK SELECTION RFP PHASE Instructions: Please place a check mark in the box which best represents the materials submitted in the Non Price Proposal and tally the corresponding numbers below. Upon completion please sign and date. CM COMPANY NAME: Turner Construction Company 1. Management Team Is the Management Team especially superintendent and project manager knowledgeable and qualified to meet the project goals? Yes the Management Team meet all of the above Yes the Management Team meet most of the above No the Management Team does not meet any of the above 2. Management Plan Does the Management Plan for the project, describe in detail the firm s proposed approach to meeting the project goals, including schedule and phasing management, budget management, quality management goals and maintaining safety? Yes the Management Plan includes all of the above Yes the Management Plan includes most of the above No the Management Plan does not include any of the above 3. Project Plan PreConstruction Does the Offeror's plan illustrate the understanding of the activities required during preconstruction and demonstrate the ability to coordinate and perform those activities including design review, phasing and scheduling, cash flow chart, value engineering, constructability, cost control, and subcontractor bid packages. Yes the PreConstruction Plan fully illustrates all of the above Yes the PreConstruction Plan fully illustrates most of the above No the PreConstruction Plan fully illustrates none of the above 4. Project Plan Construction Does the Offeror's plan illustrate a clear management structure and methodology for project management, logistics, phasing and sequencing of the Work? Does the Offeror have project specific program for quality assurance and quality control. Has the Offeror described how they will comply with requirements for schedule development, cost loading, resource loading, monthly schedule updates, periodic community meetings, and weekly project meeting review of the look ahead schedule? Yes the Construction Plan includes all of the above Yes the Construction Plan includes most of the above No the Construction Plan includes none of the above Page 9 of 10
19 PROJECT MANAGEMENT CM AT RISK PROPOSAL EVALUATION NEW HOLBROOK PREK12 SCHOOL, HOLBROOK, MASSACHUSETTS 5. Schedule CM AT RISK SELECTION RFP PHASE Did the Offeror submit its proposed Preliminary Project Schedule. Is this schedule clearly explained and advantageous for this project timeline? Yes the Schedule is and advantageous for this project Yes the Schedule is and mostly advantageous for this project No the Schedule is not and nonadvantageous for this project 6. Comparable Experience Is the Offeror s experience similar in scope, size and budget to this project. Does the Offeror s experience includes projects on occupied sites? Yes the Comparable Experience includes all of the above Yes the Comparable Experience includes most of the above No the Comparable Experience includes none of the above 7. Litigation Does the Offeror s history of litigation indicate a culture of collaboration and teamwork between Owner, Designer and Subcontractors? Yes the history of Litigation indicates all of the above Yes the history of Litigation indicates most of the above No the history of Litigation does not indicate the above 8. Financial Capacity Does the Offeror's financial capacity support their ability to undertake this project? Yes the Financial Capacity indicates all of the above Yes the Financial Capacity indicates most of the above No the Financial Capacity does not indicate the above 9. Safety History Does the Offeror s Safety History support their approach to this project? Yes the Safety History includes all of the above Yes the Safety History includes most of the above No the Safety History includes none of the above. TOTAL (#19 ABOVE) Signature Date Page 10 of 10
20
21 PROJECT MANAGEMENT CM AT RISK PROPOSAL EVALUATION NEW HOLBROOK PREK12 SCHOOL, HOLBROOK, MASSACHUSETTS PRICE PROPOSAL EVALUATION Instructions: After reviewing the NonPrice Proposal and completing the NonPrice Evaluation, please open and review the Price Proposal and complete the Price Proposal Evaluation Matrix below. Evaluators will need only one copy of this form to evaluate all 3 CMs as spaces have been provided. 1 = Least Advantageous, 2 = Advantageous, 3 = Most Advantageous SECTION 1 SECTION 2 SECTION 4 RFP Description Consigli Gilbane Turner Preconstruction Services Evaluation of Preconstruction Staff: Does the Preconstruction Phase personnel listed, their roles, and % of time allocated toward the job provide the level of service required? Construction General Conditions Does the CM show they can provide the adequate amount of full time staff members to support the project through Construction? Insurance and Bonds Evaluation of Insurance: Which of the insurance rates listed in C.4 favors the project? Evaluation of Bonds: Which of the Bond rates listed in C.4 favors the project? CM Fee Which of the fee costs favor the project? TOTALS Signature Date Page 1 of 1
22
23 PROJECT MANAGEMENT CM AT RISK PROPOSAL EVALUATION NEW HOLBROOK PREK12 SCHOOL, HOLBROOK, MASSACHUSETTS RFP INTERVIEW CONSTRUCTION MANAGER QUESTIONS 1 = Least Advantageous, 2 = Advantageous, 3 = Most Advantageous Response Rating Panel Questions Consigli Gilbane Turner 1 Tell us about your similar projects and how they relate to our project. 2 Tell us how your staff's experience will benefit the project. 3 What did you see as the most important projectrelated issues? 4 How can your team be assigned to our project if they are on other projects right now? 5 How will you ensure quality in your construction? 6 Tell us how you closed a LEED project without losing points. 7 DRAFT How will you handle onsite traffic and parking concerns from the staff and the public? 8 How will you handle commuter traffic concerns? 9 How do you ensure that there will be no interruption to education in the existing Junior/Senior High School? 10 Give us some good examples of Value Engineering for a project like ours. Page 1 of 2
24 PROJECT MANAGEMENT CM AT RISK PROPOSAL EVALUATION NEW HOLBROOK PREK12 SCHOOL, HOLBROOK, MASSACHUSETTS RFP INTERVIEW CONSTRUCTION MANAGER QUESTIONS 1 = Least Advantageous, 2 = Advantageous, 3 = Most Advantageous Response Rating Panel Questions Consigli Gilbane Turner 11 Tell us of what you think would be opportunities for savings. 12 What do you see as the biggest challenge on this job? 13 What makes you different from the other firms? 14 How do you manage a nonperforming subcontractor? TOTALS Signature Date DRAFT Page 2 of 2
25 CM AT RISK PROPOSAL EVALUATION NEW HOLBROOK PREK12 SCHOOL, HOLBROOK, MASSACHUSETTS PROJECT MANAGEMENT CM Price Proposal Analysis Summary PFA Budget Consigli Gilbane Turner PreConstruction Services Code PreConstruction Services B.1 $ 193,500 $ 180,000 $ 144,181 Subtotal $ 600,000 $ 193,500 $ 180,000 $ 144,181 Construction Project Management Labor C.1 $ 2,336,300 $ 307,945 $ 2,251,096 Field Supervisory Labor C.2 $ 1,608,360 $ 3,087,377 $ 1,850,631 Subtotal $ 3,944,660 $ 3,395,322 $ 4,101,727 Consultant Labor C.3 $ $ $ P&P Bonds C.4 $ 600,420 $ 655,757 $ 665,246 Insurance C.4 $ 1,088,856 $ 807,234 $ 2,943,281 Subtotal $ 1,689,276 $ 1,462,991 $ 3,608,527 Trailers, Supplies etc. C.5 $ 276,500 $ 228,730 $ 854,602 Additional Costs C.6 $ $ 97,500 $ Subtotal $ 276,500 $ 326,230 $ 854,602 Cost of Work Items C.7 $ $ $ Subtotal C.8 $ 4,995,422 $ 5,910,436 $ 5,184,543 $ 8,564,856 CM Fee CM Fee $ 1,604,800 $ 1,725,031 $ 1,805,401 Subtotal $ 1,616,292 $ 1,604,800 $ 1,725,031 $ 1,805,401 Total $ 7,211,714 $ 7,708,736 $ 7,089,574 $ 10,514,438
26 CM AT RISK PROPOSAL EVALUATION NEW HOLBROOK PREK12 SCHOOL, HOLBROOK, MASSACHUSETTS PROJECT MANAGEMENT CM Price Proposal Analysis Construction Labor Consigli Gilbane Turner Construction Project Management Labor C.1 Principal in Charge $ $ 60,407 $ Project Executive $ 212,160 $ 189,910 $ 242,791 OnSite Project Executive $ 425,174 Senior Project Manager $ $ $ 753,720 Project Manager $ 721,600 $ 486,600 $ Asst. Project Manager $ 590,400 $ $ Project Engineer $ 557,600 $ 314,441 $ 578,636 Asst. Project Engineer $ $ 10,546 $ Office Engineer $ 245,779 Quality Manager LEED Coordinator $ 13,260 $ $ Project Accountant $ 53,040 $ 150,866 $ 117,802 Engineering/Administrative Assistant $ 24,960 $ $ 140,495 Cost Control Engineer $ $ 36,764 $ 114,178 CORI Management/Badge Coordinator $ $ $ Scheduler $ 34,320 $ 37,259 $ 66,649 BIM $ 37,440 $ w/ MEP Coord Information Technology $ 20,000 $ $ 46,215 Purchasing Agent $ 52,800 $ 29,688 $ 190,610 Purchasing Assistant $ 27,775 Accounts Payable $ 12,476 Compliance/Outreach Officer $ 18,720 Regulatory $ 12,361 List Consultant Costs $ $ $ Subtotal $ 2,336,300 $ 2,040,046 $ 2,251,096 Field Supervisory Labor C.2 General Superintendent $ 26,520 $ 491,507 $ 495,484 Superintendent $ 780,000 $ 312,704 $ Asst. Superintendent $ $ $ 375,986 Asst. Superintendent $ 530,400 $ $ 270,710 Internal Envelope Review $ 13,000 MEP Coordinator / Commissioning Assistant $ 162,240 $ 323,035 $ 382,915 Field Engineer $ $ cost of work Asst. Field Engineer $ cost of work Safety Engineer $ 34,320 $ 73,004 $ 325,537 CORI Implementation above w/ Admin Assist Quality Manager $ 74,880 $ 7,665 Intern $ 134,361 Subtotal $ 1,608,360 $ 1,355,276 $ 1,850,632 Total $ 3,944,660 $ 3,395,322 $ 4,101,728
27 CM AT RISK PROPOSAL EVALUATION NEW HOLBROOK PREK12 SCHOOL, HOLBROOK, MASSACHUSETTS PROJECT MANAGEMENT CM Price Proposal Analysis Additional General Conditions Consigli Gilbane Turner Construction Trailers, Supplies Etc. C.5 Town of Holbrook, OPM and Architect Temporary Office Trailers (minimum 12x60 with $ 27,000 $ 8,250 $ 62,680 Town of Holbrook, OPM and Architect Telephone, high speed internet line and wireless internet connection and Usage Charges (including long distance) $ 14,400 $ 18,630 $ 17,000 Town of Holbrook, OPM and Architect Office $ 5,000 $ 3,000 $ 4,500 Cleaning of Town of Holbrook and Architect $ $ 5,000 cost of work CM Temporary Office Trailers $ 36,000 $ 20,000 $ 154,040 CM Telephone and Internet Service, Equipment and Usage Charges (including long distance) $ 14,400 $ 13,000 $ 66,498 CM Office Furniture $ 5,000 $ 4,000 $ 9,896 Cleaning of CM Trailers $ $ 12,500 cost of work Travel, Meals, etc $ $ 5,000 $ 40,120 LEEDS Supervision and Assistance Implementation (Field) w/ staff labor w/ staff labor w/ staff labor Information Technology (I.T.) Time (Field Office) $ 54,000 $ 2,000 w/ staff labor Computers & Software $ 54,000 $ 77,100 $ 156,012 Field Office Supplies $ 18,000 $ 10,000 $ 58,230 Site Security Services $ 1,000 $ 2,000 na OnSite Storage Containers $ 1,000 $ 3,750 $ 17,000 Small Tools $ $ 12,500 $ 108,800 Safety Materials (Safety Kit) $ 7,200 $ 4,500 $ 18,000 Photos $ 1,800 $ 2,500 $ 12,750 Reprographics $ 7,200 $ 6,250 $ 108,677 Postage, Shipping, Courier Services, etc $ 18,000 $ 5,000 $ 20,400 Management of Plans, Specifications, etc $ $ 6,250 w/ project engineer Record Drawings $ 2,500 $ 5,000 w/ reprographics Punch List $ 5,000 w/ staff labor w/ staff labor Photo ID Badge Machine $ 5,000 $ 2,500 relocated Other $ $ $ $ 276,500 $ 228,730 $ 854,603 Additional General Conditions C.6 Cell Phones $ $ 27,500 $ Bottled Water $ $ 2,000 $ Expediting Travel $ $ 10,000 $ Safety Incentives $ $ 40,000 $ Drug Testing $ $ 18,000 Subtotal $ $ 97,500 $ Total $ 276,500 $ 326,230 $ 854,603
28
Tel: (617) 727-4050 Fax: (617) 727-5363. OWNER S PROJECT MANAGER GUIDELINES M.G.L. c. 149, 44A1/2
The Commonwealth of Massachusetts Executive Office for Administration and Finance Division of Capital Asset Management One Ashburton Place Boston, Massachusetts 02108 Tel: (617) 727-4050 Fax: (617) 727-5363
More informationMondays 9:00 a.m. 4:30 p.m. Tuesdays 9:00 a.m. 4:30 p.m. Wednesdays 9:00 a.m. 1:00 p.m. Thursdays 9:00 a.m. 4:30 p.m. Fridays 9:00 a.m. 4:30 p.m.
TOWN OF WEBSTER, MASSACHUSETTS REQUEST FOR QUALIFICATIONS FOR OWNER S PROJECT MANAGEMENT SERVICES FOR THE CHESTER C. CORBIN PUBLIC LIBRARY CONSTRUCTION PROJECT The Town of Webster, Massachusetts seeks
More informationCapital Projects Construction Manager At-Risk (CMR) Guaranteed Maximum Price (GMP) Best Value Selection Procedure Manual
Page 1 of 21 Connecticut Department of Administrative Services Capital Projects Construction Manager At-Risk (CMR) Guaranteed Maximum Price (GMP) Best Value Selection Procedure Manual Prepared for Capital
More informationMid Michigan Community College
Mid Michigan Community College REQUEST FOR QUALIFICATIONS FOR CONSTRUCTION MANAGEMENT/CONSTRUCTOR SERVICES PART 1 -- GENERAL INSTRUCTIONS A. PROJECT DESCRIPTION Mid Michigan Community College (the "Owner")
More informationREQUEST FOR PROPOSALS FOR CONSTRUCTION MANAGEMENT AT-RISK FOR LOGANVILLE ELEMENTARY SCHOOL (REPLACEMENT) FOR THE WALTON COUNTY SCHOOL DISTRICT
ADVERTISEMENT: REQUEST FOR PROPOSALS FOR CONSTRUCTION MANAGEMENT AT-RISK FOR LOGANVILLE ELEMENTARY SCHOOL (REPLACEMENT) FOR THE WALTON COUNTY SCHOOL DISTRICT The WALTON COUNTY SCHOOL DISTRICT will receive
More informationConstruction Management At-Risk
Oconee County Schools P.O. Box 146, 34 School Street Watkinsville, GA 30677 706-769-5130 706-769-3513 REQUEST FOR PROPOSALS ISSUE DATE: March 10, 2016 RFP REF: Construction Management At-Risk Construction
More informationCorrected Form: Revised Attachment 7B Cost Proposal Distribution Exhibits A1 and A2 Attached
ADDENDUM #1 RFP: 500 16 Design Build Maintenance & Operations Complex The following changes to the Request for Proposal and clarifications are provided based on questions received and must be added/considered
More informationREQUEST FOR QUALIFICATIONS CONSTRUCTION MANAGER / GENERAL CONTRACTOR (CM/GC SERVICES)
REQUEST FOR QUALIFICATIONS CONSTRUCTION MANAGER / GENERAL CONTRACTOR (CM/GC SERVICES) Return Completed Qualifications To: Twin Falls School District No. 411 Administrative Office 201 Main Avenue West Twin
More informationRequest for Qualifications. Owner s Project Manager. Design and Construction of a New School Facility. K~8 Charter School
Request for Qualifications Owner s Project Manager Design and Construction of a New School Facility K~8 Charter School 26 Madeira Avenue New Bedford, MA 02746 REQUEST FOR QUALIFICATIONS (RFQ) Issued: 4/16/2014
More informationRequest for Qualifications (CM at Risk Contract) State of Ohio Standard Forms and Documents
Request for Qualifications (CM at Risk Contract) Administration of Project: School District Board + OFCC Project Name Groveport Madison High School Response Deadline 10/17/2014 4:00pm local time Project
More informationConstruction Management Agency (CMa) Services Request for Qualifications Hermantown Schools ISD #700
Construction Management Agency (CMa) Services Request for Qualifications Hermantown Schools ISD #700 Response Due: February 21, 2014 4:00 PM Submit to: Brad Johnson, Superintendent Hermantown Schools ISD
More informationProposers will quote a fixed fee for this engagement as outlined in the complete RFP. Page 1 of 9
Request for Proposals For Technology Consulting Services For the creation of A Regional Emergency Communications Center ( RECC ) for The Towns of Cohasset, Hingham, Hull and Norwell, Massachusetts by the
More informationEanes Independent School District
EANES INDEPENDENT SCHOOL DISTRICT 601 Camp Craft Road Austin, Texas 78746 Request for Qualifications Construction Manager at Risk Services Eanes Independent School District Construct a District Operations
More informationExecutive Office for Administration & Finance. Request for Qualifications For Construction Management Services
Executive Office for Administration & Finance Request for Qualifications For Construction Management Services Massachusetts State Project (Project Number) (Full Project Name and Location), Massachusetts
More informationREQUEST FOR QUALIFICATIONS FOR CONSTRUCTION MANAGER-AT-RISK (CMAR)
REQUEST FOR QUALIFICATIONS FOR CONSTRUCTION MANAGER-AT-RISK (CMAR) For the Project: CITY OF KATY NEW KATY FIRE STATION #2 Issued: August 13, 2015 Katy Fire Station #2 August 13, 2015 Page 1 of 17 Request
More informationRequest for Qualifications (CM at Risk Contract) State of Ohio Standard Forms and Documents
Request for Qualifications (CM at Risk Contract) Administration of Project: Local Higher Education Project Name FAES- Student Success Center Response Deadline 03/04/2013 4:30 pm local time Project Location
More informationIndependent School District No. 1 Strive Achieve Succeed Go Beyond Lewiston, Idaho
Independent School District No. 1 Strive Achieve Succeed Go Beyond Lewiston, Idaho REQUEST FOR QUALIFICATIONS Independent School District No. 1, Lewiston, Idaho ( District ) is seeking responses from individuals
More informationCHECKLIST TO DESIGNATE AREAS OF EVALUATION FOR REQUESTS FOR PROPOSAL (RFP)
Michigan Department Of Transportation 5100B (05/13) CHECKLIST TO DESIGNATE AREAS OF EVALUATION FOR REQUESTS FOR PROPOSAL (RFP) Page 1 of 2 REQUISITION NUMBER DUE DATE TIME DUE MDOT PROJECT MANAGER JOB
More informationFOR USE WITH PPP PROJECTS 1 SAMPLE GUIDELINES FOR PRE-QUALIFICATION AND COMPETITIVE BIDDING PROCESS 2
FOR USE WITH PPP PROJECTS 1 SAMPLE GUIDELINES FOR PRE-QUALIFICATION AND COMPETITIVE BIDDING PROCESS 2 1. PRE-QUALIFICATION 1.1 The requirements for pre-qualifications will be reasonable and efficient and
More informationREQUEST FOR PROPOSALS
REQUEST FOR PROPOSALS The Town of Ayer s Department of Planning & Development seeks proposals from qualified consultants to provide the following services in the Town of Ayer: INFRASTRUCTURE PROJECT CONSULTANT
More informationGEORGETOWN PUBLIC SCHOOLS REQUEST FOR PROPOSALS. Perley Elementary School Roof Replacement Project DESIGN SERVICES
GEORGETOWN PUBLIC SCHOOLS REQUEST FOR PROPOSALS Perley Elementary School Roof Replacement Project DESIGN SERVICES The Georgetown School Committee seeks proposals for Design Services in connection with
More informationRequest for Qualifications (Design-Build Contract) State of Ohio Standard Forms and Documents
Request for Qualifications (Design-Build Contract) State of Ohio Standard Forms and Documents Administration of Project: Local Higher Education Project Name Campus Elevator Upgrades Response Deadline 9/03/13
More informationRequest of Qualification Proposal for Construction Management Services
Request of Qualification Proposal for Construction Management Services Dated June 10, 2014 Table of Contents Overview 3 Introduction 4 Scope of Construction Managers Services 4 Submission of Qualifications
More informationREQUEST FOR QUALIFICATIONS ARCHTECTURAL SERVICE FEBRUARY 20, 2015 JACKSONVILLE PUBLIC SCHOOL DISTRICT 117
Introduction The Board of Education for Jacksonville School District 117 is soliciting Statements of Interest and Qualifications pursuant to 50 ILCS 510/0.01 from qualified firms to provide comprehensive
More informationRequest for Qualifications (CM at Risk Contract) State of Ohio Standard Forms and Documents
Request for Qualifications (CM at Risk Contract) State of Ohio Standard Forms and Documents Administration of Project: School District Board + OFCC Project Name Wellington New K-8 EM/MS Response Deadline
More informationREQUEST FOR PROPOSALS CONSTRUCTION MANAGEMENT SERVICES. PASSENGER SCREENING CHECKPOINT CONSOLIDATION PROJECT PROJECT No.
REQUEST FOR PROPOSALS CONSTRUCTION MANAGEMENT SERVICES PASSENGER SCREENING CHECKPOINT CONSOLIDATION PROJECT PROJECT No. FY15-805-67 Manchester-Boston Regional Airport is soliciting Proposals from qualified
More informationNOTICE TO CM/GC Companies
NOTICE TO CM/GC Companies Facilities and Construction Management Jefferson County School District R-1 (Jeffco) is pre-qualifying Construction Manager/General Contractors for CM/GC services for a new K-6
More informationREQUEST FOR PROPOSAL CONSTRUCTION MANAGEMENT SERVICES PINE TRAIL ELEMENTARY HVAC, CEILING & LIGHTING PROJECT NO. 164514
REQUEST FOR PROPOSAL CONSTRUCTION MANAGEMENT SERVICES FOR PINE TRAIL ELEMENTARY HVAC, CEILING & LIGHTING PROJECT NO. 164514 Contact: Mr. Tom Brown, Senior Construction Project Manager Facilities Services,
More informationRequest for Qualifications (CM at Risk Contract) State of Ohio Standard Forms and Documents
Request for Qualifications (CM at Risk Contract) State of Ohio Standard Forms and Documents Administration of Project: Local Higher Education Project Name RH-Renovations Summer 2013 Response Deadline 1/03/13
More informationHoneywell Energy Services Group
Honeywell Energy Services Group Minnesota State Colleges and Universities Riverland Community College Guaranteed Energy Savings Program (GESP) Project Request for Qualifications (RFQ) Phase 3 Lighting
More informationQuestions and Answers
Questions and Answers 1. Can pictures be inserted in the Request for Qualifications package? Do they count toward the number of pages submitted? A. Yes, you can insert photos as long as the total page
More informationREQUEST FOR QUALIFICATIONS FOR CONSTRUCTION MANAGEMENT SERVICES
REQUEST FOR QUALIFICATIONS FOR CONSTRUCTION MANAGEMENT SERVICES ISSUED BY: INGLEWOOD UNIFIED SCHOOL DISTRICT Issued: November 20, 2015 Due: December 18, 2015 SCHEDULE OF EVENTS INGLEWOOD UNIFIED SCHOOL
More informationMT. SAN ANTONIO COMMUNITY COLLEGE DISTRICT
MT. SAN ANTONIO COMMUNITY COLLEGE DISTRICT REQUEST FOR QUALIFICATIONS FOR CONSTRUCTION MANAGEMENT SERVICES RFQ #3028 Submissions Due by 2:00 p.m. PST, August 20, 2015 Mt. San Antonio Community College
More informationREQUEST FOR PROPOSALS (RFP) - Construction Management Services. Germantown School District Office
REQUEST FOR PROPOSALS (RFP) - Construction Management Services From: Germantown School District Project: Germantown School District Addition & Renovations to Rockfield Elementary School N132 W18473 Rockfield
More informationREQUEST FOR QUALIFICATIONS FOR CONSTRUCTION MANAGEMENT PROFESSIONAL SERVICES. Part I: Qualifications Information
REQUEST FOR QUALIFICATIONS FOR CONSTRUCTION MANAGEMENT PROFESSIONAL SERVICES A. General Information Part I: Qualifications Information The Tacoma School District is soliciting Qualifications for onsite
More informationT34 - PUBLIC WORK IN MASSACHUSETTS, UNDERSTANDING CHAPTER 149 AND CHAPTER 149A
T34 - PUBLIC WORK IN MASSACHUSETTS, UNDERSTANDING CHAPTER 149 AND CHAPTER 149A PANELISTS: Deborah Anderson, Esq. Office of the Attorney General Laura Wernick, FAIA, REFP, LEED AP HMFH Architects, Inc.
More informationGENERAL CONTRACTOR PRE-QUALIFICATION 2014 - FOR PERIOD ENDING DEC 2017
APPLICATION for PRE QUALIFICATION GENERAL CONSTRUCTION CONTRACTORS Construction Projects up to $3,000,000 Prequalified General Contractors will be invited to submit bids for various Renovation and Construction
More informationTRAVIS UNIFIED SCHOOL DISTRICT REQUEST FOR QUALIFICATIONS CONSTRUCTION MANAGEMENT SERVICES CONSTRUCTION MANAGER MULTI-PRIME
TRAVIS UNIFIED SCHOOL DISTRICT REQUEST FOR QUALIFICATIONS CONSTRUCTION MANAGEMENT SERVICES CONSTRUCTION MANAGER MULTI-PRIME QUESTIONS PAGE 11 200.325 BONDING REQUIREMENTS Please confirm that construction
More informationTOWN OF MILLIS REQUEST FOR PROJECT MANAGEMENT SERVICES (RFS) FOR CLYDE F. BROWN ELEMENTARY SCHOOL
TOWN OF MILLIS REQUEST FOR PROJECT MANAGEMENT SERVICES (RFS) FOR CLYDE F. BROWN ELEMENTARY SCHOOL The Town of Millis is seeking the services of a qualified Owner s Project Manager as defined in Massachusetts
More informationREQUEST FOR PROPOSAL CONSTRUCTION MANAGEMENT SERVICES PIERSON ELEMENTARY REPLACEMENT SCHOOL PROJECT NO. 164519
REQUEST FOR PROPOSAL CONSTRUCTION MANAGEMENT SERVICES FOR PIERSON ELEMENTARY REPLACEMENT SCHOOL PROJECT NO. 164519 School Board of Volusia County Florida Facilities Services 3750 Olson Drive, Daytona Beach
More informationREQUEST FOR PROPOSAL TO PROVIDE CONSTRUCTION MANAGEMENT AND GENERAL CONTRACTOR SERVICES SPRINGVILLE CITY NEW AQUATICS AND ACTIVITIES CENTER
RFP #2016-02 REQUEST FOR PROPOSAL TO PROVIDE CONSTRUCTION MANAGEMENT AND GENERAL CONTRACTOR SERVICES FOR SPRINGVILLE CITY NEW AQUATICS AND ACTIVITIES CENTER RELEASE DATE: January 29, 2016 DUE DATE: February
More informationCONSTRUCTION MANAGEMENT SERVICES for the new REPLACEMENT NORTH DORCHESTER HIGH SCHOOL Dorchester County Public Schools December 9, 2015
CONSTRUCTION MANAGEMENT SERVICES for the new REPLACEMENT NORTH DORCHESTER HIGH SCHOOL Dorchester County Public Schools December 9, 2015 Dorchester County Public Schools is intending to engage the services
More informationREQUEST FOR QUALIFICATIONS (RFQ) FOR PROFESSIONAL ARCHITECTURAL/ENGINEERING AND CONSULTING SERVICES FOR Fiscal Years 2015 2018
REQUEST FOR QUALIFICATIONS (RFQ) FOR PROFESSIONAL ARCHITECTURAL/ENGINEERING AND CONSULTING SERVICES FOR Fiscal Years 2015 2018 Solicitation No.: BFZ1523 1. Mission Statement and General Information 1.1.
More informationGREENBURGH CENTRAL SCHOOL DISTRICT No. 7 REQUEST FOR PROPOSALS CONSTRUCTION MANAGEMENT SERVICES
GREENBURGH CENTRAL SCHOOL DISTRICT No. 7 REQUEST FOR PROPOSALS CONSTRUCTION MANAGEMENT SERVICES Greenburgh Central School District No. 7 ( The District ) invites proposals to perform construction management
More informationGENERAL CONTRACTOR / CONSTRUCTION MANAGER SERVICES
REQUEST FOR QUALIFICATIONS GENERAL CONTRACTOR / CONSTRUCTION MANAGER SERVICES NEW DINING HALL MONTANA STATE UNIVERSITY Bozeman, Montana PPA NO. 15-0103 Campus Planning, Design & Construction Plew Building
More informationBIDDER S DATA SHEETS (FORMS TO BE COMPLETED BY BIDDER)
BIDDER S DATA SHEETS (FORMS TO BE COMPLETED BY BIDDER) The bidder should fully complete and submit the following Bidder s. Failure to satisfactorily complete and submit the Bidder s may result in a determination
More informationThe Construction Management Delivery System An Architect s Point of View
Session 1421 The Construction Management Delivery System An Architect s Point of View Daniel Davis, AIA University of Hartford Abstract There are at least three different building project delivery systems
More informationRequest for Qualifications (CM at Risk Contract) State of Ohio Standard Forms and Documents
Request for Qualifications (CM at Risk Contract) State of Ohio Standard Forms and Documents Administration of Project: Local Higher Education Project Name Shideler Hall Renovation Response Deadline 12/20/13
More informationCity of Seattle Department of Education and Early Learning
City of Seattle Department of Education and Early Learning 1 FAMILIES A ND EDUCATION LEVY ELEMENTARY SCHOOL REQUESTS FOR INVESTMENTS ( RFI) INTENT TO APPLY A PPLICATION RFI Intent to Apply Application
More informationREQUEST FOR PROPOSAL FOR CONSTRUCTION MANAGEMENT SERVICES. Part I: Proposal Information
REQUEST FOR PROPOSAL FOR CONSTRUCTION MANAGEMENT SERVICES Part I: Proposal Information A. General Information The Berwick Area School District is soliciting proposals for construction management services
More informationResidential Builders New Application
State of Arkansas CONTRACTORS LICENSING BOARD Residential Builders New Application $100.00 Filing Fee - NON-REFUNDABLE MAIL TO: CONTRACTORS LICENSING BOARD 4100 RICHARDS ROAD NORTH LITTLE ROCK, ARKANSAS
More informationCREOL EXPANSION PHASE II UCF-581 Architect/Engineer (A/E) and Construction Manager (CM) Project Fact Sheet
CREOL EXPANSION PHASE II UCF-581 Architect/Engineer (A/E) and Construction Manager (CM) Project Fact Sheet PROJECT DESCRIPTION The project consists of the design and construction of an expansion to the
More informationNotes. Score. 1 Basic Services 1.1. A few instances; could have been more proactive
Jacobs Contract performance Tracking spreadsheet = Excellent 2 = Meets performance standards 1 = Improvement needed 0= Unsatisfactory Report for the time period: Annual report 210 Total average score 2.86
More informationAttachment A. Application for Prequalification. General Contractors, Trade Subcontractors and Related Construction Service Providers.
Attachment A Application for Prequalification of General Contractors, Trade Subcontractors and Related Construction Service Providers Pre-Qualification Form 03.14.16 Page 1 of 15 Application for Pre-Qualification:
More informationTOWN OF MILFORD REQUEST FOR QUALIFICATIONS DESIGNER SERVICES FOR LIBRARY ROOF REPLACEMENT
TOWN OF MILFORD REQUEST FOR QUALIFICATIONS DESIGNER SERVICES FOR LIBRARY ROOF REPLACEMENT The Milford Board of Library Trustees, as the Awarding Authority, invites the submission of qualifications by responsible
More informationPart II - Submission Requirements
Part II - Submission Requirements The online virtual school vendor shall be held to have read the Request for Proposals document that includes the public notice, instructions to bidders, and specifications.
More informationDesigning and Constructing Public Facilities
Designing and Constructing Public Facilities Legal Requirements Recommended Practices Sources of Assistance Commonwealth of Massachusetts Office of the Inspector General Gregory W. Sullivan Inspector General
More informationCOAST COMMUNITY COLLEGE DISTRICT REQUEST FOR PROPOSALS #2013 FOR
COAST COMMUNITY COLLEGE DISTRICT REQUEST FOR PROPOSALS #2013 FOR CONSTRUCTION MANAGEMENT SERVICES FOR ORANGE COAST COLLEGE BUSINESS, MATH, COMPUTING CENTER December 14, 2012 PROPOSALS DUE: By 4 p.m. -
More informationRequest for Proposal for Construction Management Services
Request for Proposal for Construction Management Services Moorhead Area Public Schools is soliciting Construction Management Agent of the Owner (CMa) proposals for the construction of a new K-4 elementary
More informationIDALIA SCHOOL DISTRICT RJ-3 REQUEST FOR QUALIFICATIONS (RFQ) CONSTRUCTION MANAGEMENT/GENERAL CONTRACTING (CM/GC) SERVICES DECEMBER 14, 2011
IDALIA SCHOOL DISTRICT RJ-3 REQUEST FOR QUALIFICATIONS (RFQ) CONSTRUCTION MANAGEMENT/GENERAL CONTRACTING (CM/GC) SERVICES DECEMBER 14, 2011 PROJECT: New PK-12 School Facility Idalia, Colorado Idalia School
More information4. Q: Is there a walkthrough for this procurement? A: No, there will not be a walkthrough for this procurement.
NYC H+H Coney Island Hospital Request for Proposals (RFP) for Construction Management Services Project # 6162 Questions & Answers Date: February 3, 2016 1. Q: Was there a sign-in sheet for the Information
More informationCOMMUNITY LIBRARY (SUNBURY) RFP for Construction Manager at Risk
Project Name: Addition to Community Library (Sunbury) Project Location: 44 Burrer Drive, Sunbury, Ohio 43074 Owner: Community Library Board of Trustees Address: 44 Burrer Drive, Sunbury, Ohio 43074 Project
More informationOBJECTIVE To establish procedures for administration of construction manager agreements, including negotiation, contracting and payments.
OP-B-11-D2 ADMINISTRATION OF CONSTRUCTION MANAGER AGREEMENTS SPECIFIC AUTHORITY Sections 240.209(3)(p), 1001.74, 1013.46, F. S. OBJECTIVE To establish procedures for administration of construction manager
More informationREQUEST FOR QUALIFICATIONS (RFQ) FOR CONSTRUCTION MANAGEMENT SERVICES
REQUEST FOR QUALIFICATIONS (RFQ) FOR CONSTRUCTION MANAGEMENT SERVICES (Construction Manager At-Risk) FOR PROJECTS IN THE CENTER UNIFIED SCHOOL DISTRICT April 7, 2005 The ( District ) is seeking Statements
More informationTown of Clarkdale Guidelines for the Non-Profit Funding Program
Town of Clarkdale Guidelines for the Non-Profit Funding Program The Clarkdale Town Council developed the Non-Profit Funding Program in order to support non-profit entities that benefit the Town of Clarkdale
More informationConstruction Management Services Delmar School District RFP No. DSD16001-CONSTR_MAN
Construction Management Services Delmar School District RFP No. DSD16001-CONSTR_MAN The Delmar School District (DSD) is seeking the professional services of a Construction Management (CM) firm for the
More information6. Q: A: No, however it is anticipated that the PM firm will need to understand FEMA and HUD CDBG compliance as part of the scope of services. 7.
HHC Program Manager Request for Proposals (RFP) for Consulting Services Project # 6161 Questions & Answers Date: October 1, 2015 1. Q: In CR#2017007 would schedule outsourcing be considered as an appropriate
More informationConstruction Management Standards of Practice
Construction Management Standards of Practice 2010 Edition Advancing Professional Construction/ Program Management Worldwide. 7926 Jones Branch Drive, Suite 800 McLean, VA 22102-3303 USA 703.356.2622 703.356.6388
More informationOffice of the Inspector General
Office of the Inspector General Commonwealth of Massachusetts Gregory W. Sullivan Inspector General Experience of Massachusetts Public Agencies with Construction Management at Risk Under M.G.L. c. 149A
More informationTown of Montreat Buncombe County, North Carolina
Town of Montreat Buncombe County, North Carolina Request for Qualifications For Professional Architectural Services In Providing Design Services for the Construction a New Montreat Town Hall January 9,
More informationFLORIDA DEPARTMENT OF TRANSPORTATION DISTRICT 2 1109 S. Marion Avenue, Mail Station 2015 Lake City, Florida 32025-5874
ADVERTISEMENT FOR LETTERS OF INTEREST FOR A DESIGN BUILD PROJECT (PROCUREMENT METHOD SHORTLISTING OF PROPOSERS WITH TECHNICAL AND PRICE EVALUATION BY ADJUSTED SCORE) PROCUREMENT NUMBER: E2N44 Financial
More informationCity of Vallejo REQUEST FOR PROPOSAL WORKERS COMPENSATION CLAIMS AUDIT
City of Vallejo REQUEST FOR PROPOSAL WORKERS COMPENSATION CLAIMS AUDIT Date original issued: September 28, 2015 Qualifications Statements due: The City of Vallejo will consider Proposals submitted in response
More informationCovance Construction Management Staffing Plan Chandler, Arizona
INTRODUCTION: This Construction Management (CM) Staffing Plan has been prepared for Covance to identify the critical organizational structure necessary to successfully complete the Chandler project according
More informationANY INVALID WILL NOT
NOTICE!! THIS IS AN OFFICIAL DOCUMENT THAT IS USED TO DETERMINE THE QUALIFICATIONS OF CONTRACTORS TO BID WITH THE AGENCY OF TRANSPORTATION FOR THE STATE OF VERMONT. ANY ALTERATIONS OF THIS DOCUMENT WILL
More information5. Whether the timely completion of the project is critical to the university s ability to repay debt service or to meet grant obligations.
OP-B-11-C2 CONSTRUCTION MANAGER SELECTION PROCESS SPECIFIC AUTHORITY Sections 1001.74(28), 1013.46, F. S. OBJECTIVE To provide guidelines for the selection of construction managers. OVERVIEW This procedure
More informationDIRECTORATE OF ESTATES & FACILITIES
DIRECTORATE OF ESTATES & FACILITIES PROCEDURE AND INFORMATION MANUAL EPM PM4 Client Representative (University Project Manager) for Capital Projects Scope of Services Document Originated: April 2006 By:
More informationRequest for Qualifications for Program Management Support Services for The Greenville-Spartanburg International Airport Terminal Improvement Program
Request for Qualifications for Program Management Support Services for The Greenville-Spartanburg International Airport Terminal Improvement Program SECTION 1 - GENERAL INFORMATION The Greenville-Spartanburg
More informationCity Of Portsmouth, New Hampshire REQUEST FOR QUALIFICATIONS # 30-10 For. Construction Management Services for the
City Of Portsmouth, New Hampshire REQUEST FOR QUALIFICATIONS # 30-10 For Construction Management Services for the Renovation and Expansion of Portsmouth Middle School INVITATION The City of Portsmouth,
More informationVENDOR QUESTIONS AND ANSWERS FOR RFP Req# 08072013 BUDGET DEVELOPMENT SOFTWARE
VENDOR QUESTIONS AND ANSWERS FOR RFP Req# 08072013 BUDGET DEVELOPMENT SOFTWARE NOTE: TO ALLOW ADEQUTE TIME TO ADDRESS AND POST EACH QUESTION IN TIME FOR THIS RFP, NO ADDITIONAL QUESTIONS WILL BE ACCEPTED
More informationTROUP COUNTY COMPREHENSIVE HIGH SCHOOL
TROUP COUNTY BOARD OF EDUCATION REQUEST FOR SEALED COMPETITIVE PROPOSALS FOR CONSTRUCTION OF: RE-FLOORING TO: TROUP COUNTY COMPREHENSIVE HIGH SCHOOL LAGRANGE, GEORGIA TROUP COUNTY SCHOOL SYSTEM LAGRANGE,
More informationREQUEST FOR QUOTES ACTUARIAL CONSULTING SERVICES - GASB 43 & 45 To Valuate the Town of Reading Retiree Medical & Life Insurance Obligation
REQUEST FOR QUOTES ACTUARIAL CONSULTING SERVICES - GASB 43 & 45 To Valuate the Town of Reading Retiree Medical & Life Insurance Obligation You are cordially invited to submit an RFQ for Actuarial Consulting
More informationEXPRESSION OF INTEREST PROVISION OF TRAINING SERVICES
The Kenya Power & Lighting Co. Ltd. EXPRESSION OF INTEREST PROVISION OF TRAINING SERVICES TENDER NO. KPLC1/5BA/42U/01/11 LIST OF CONTENTS PART I INTRODUCTION PART II SUMMARY OF THE IN-HOUSE COURSES TO
More informationCITY OF GREENFIELD, a/k/a TOWN OF GREENFIELD GREENFIELD, MASSACHUSETTS. Request for Services (RFS) Owner s Project Manager Senior Center Project
CITY OF GREENFIELD, a/k/a TOWN OF GREENFIELD GREENFIELD, MASSACHUSETTS RFP TITLE: Request for Services (RFS) Owner s Project Manager Senior Center Project RFS #: 15-20 DATE OF ISSUANCE: Monday, June 1,
More informationDesign Build Procurement Guide
Design Build Procurement Guide DESIGN BUILD PROCUREMENT GUIDE Page 1 of 29 TABLE OF CONTENTS Abbreviations... 4 Chapter 1 Design Build Introduction.. 1.1 Purpose 1.2 Authority 1.3 Scope 1.4 Background
More informationSTATUS AND RESPONSE TO ARTHUR ANDERSEN S STUDY OF. CONSTRUCTION MANAGEMENT PRACTICES ANCHORAGE SCHOOL DISTRICT Revised 8/7/00
AND RESPONSE TO ARTHUR ANDERSEN S STUDY OF CONSTRUCTION MANAGEMENT PRACTICES ANCHORAGE SCHOOL DISTRICT Revised 8/7/00 The Arthur Andersen study of construction management practices of the Anchorage School
More informationesi ning and Constructing ublic acilities
esi ning and Constructing ublic acilities.. Legal Requirements.. Recommended Practices.. Sources of Assistance Commonwealth of Massachusetts Office of the Inspector General Glenn A. Cunha Inspector General
More informationGENERAL CONTRACTOR QUALIFICATION STATEMENT PACKAGE FOR VICTOR VALLEY COMMUNITY COLLEGE
GENERAL CONTRACTOR QUALIFICATION STATEMENT PACKAGE FOR VICTOR VALLEY COMMUNITY COLLEGE ASBESTOS ABATEMENT and DEMOLITION Music Building VICTOR VALLEY COMMUNITY COLLEGE DISTRICT CONTRACTOR'S STATEMENT OF
More informationWASHINGTON COUNTY BOARD OF COUNTY COMMISSIONERS December 16, 2014 Special Meeting - Commission Board Room 1331 South Blvd., Chipley, FL 32428
316 WASHINGTON COUNTY BOARD OF COUNTY COMMISSIONERS December 16, 2014 Special Meeting - Commission Board Room 1331 South Blvd., Chipley, FL 32428 DISTRICT 1 DISTRICT 2 DISTRICT 3 DISTRICT 4 DISTRICT 5
More informationState of Rhode Island Department of Administration / Division of Purchases ADDENDUM # 4 RFP # 7479367
State of Rhode Island Department of Administration / Division of Purchases One Capitol Hill, Providence, Rhode Island 02908-5855 Tel: (401) 574-8100 Fax: (401) 574-8387 Solicitation Information July 23,
More informationREQUEST FOR PROPOSAL FOR CONSTRUCTION MANAGEMENT SERVICES
REQUEST FOR PROPOSAL FOR CONSTRUCTION MANAGEMENT SERVICES Prepared & Issued by: Middleton-Cross Plains Area School District 7106 South Avenue Middleton, Wisconsin 53562 January 9, 2012 Request for Proposal
More informationTOWN OF WEST BOYLSTON, MASSACHUSETTS REQUEST FOR PROPOSALS COMPUTER NETWORK ADMINISTRATION AND INFORMATION TECHNOLOGY TECHNICAL ASSISTANCE
TOWN OF WEST BOYLSTON, MASSACHUSETTS REQUEST FOR PROPOSALS COMPUTER NETWORK ADMINISTRATION AND INFORMATION TECHNOLOGY TECHNICAL ASSISTANCE The Town of West Boylston, acting by and through the Office of
More informationANNUAL PREQUALIFACTION APPLICATION. Interested Subcontractor:
ANNUAL PREQUALIFACTION APPLICATION Interested Subcontractor: Each Frank L. Blum Construction subcontractor that has the potential of having a contract greater than $50,000 must submit a completed Subcontractor
More informationREQUEST FOR QUALIFICATIONS: Professional Engineering Services For Water Treatment Plant Filter Replacement or Rehab
Department of Utilities 504 N. Queen Street Palestine, Texas 75801 (903)731-8423 Fax (903)723-2953 REQUEST FOR QUALIFICATIONS: Professional Engineering Services For Water Treatment Plant Filter Replacement
More informationHolbrook Public Schools New PreK-12 School
Special Town Meeting - Oct 22, 2014 Holbrook Public Schools New PreK-12 School Agenda Introductions What is the NEED for the Project? What is the Design? Were Other Options Considered? Has MSBA approved
More informationProgram/Construction Management Request for Qualifications
Solano Community College District Program/Construction Management Request for Qualifications Please note: Applicants must attend the mandatory pre-qualification conference on Friday, January 11, 2013 at
More informationPANOLA COLLEGE REQUEST FOR QUALIFICATIONS CONSTRUCTION MANAGER AT RISK (2 STEP PROCESS)
(2 STEP PROCESS) OPENING DATE: AUGUST 21, 2013 TIME: 3:00 P.M. LOCATION: Panola College Magnolia Room, Administration Bldg. 1109 West Panola Carthage, TX 75633 TELEPHONE: (903) 693-2023 Request for Qualifications
More informationSchedule A RFP Data Sheet
Schedule A to the Request for Proposals - Equipment and Supplies Template Final Version April, 2011 Schedule A RFP Data Sheet Schedule A to the Request for Proposals Equipment and Supplies Template Final
More informationBaltimore City Public Schools Construction & Revitalization Act of 2013
Baltimore City Public Schools Construction & Revitalization Act of 2013 Established a Four Agency Partnership to Implement Act Maryland Stadium Authority (MSA) Baltimore City Public Schools (City Schools)
More informationFor Construction of the Sandy Suburban Improvement District 2013 Pipeline Rehabilitation Project
DOCUMENTS For Construction of the Sandy Suburban Improvement District 2013 Pipeline Rehabilitation Project February 11, 2013 OWNER Sandy Suburban Improvement District 8855 South 700 West Sandy, UT 84070
More informationREQUEST FOR QUALIFICATIONS PROJECT / PROGRAM MANAGEMENT CONSULTANT
REQUEST FOR QUALIFICATIONS PROJECT / PROGRAM MANAGEMENT CONSULTANT DUE: January 9, 2015 @ 5:00 PM Lopez Island School District 86 School Road Lopez Island, WA 98261 Contact: Bill Evans, Superintendent
More information