RAJASTHAN ELECTRICITY REGULATORY COMMISSION
|
|
|
- Lorena Hunt
- 10 years ago
- Views:
Transcription
1 RAJASTHAN ELECTRICITY REGULATORY COMMISSION In the matter of amendments in: I. RERC (Renewable Energy Obligation) Regulations, II. RERC (Renewable Energy Certificate and Renewable Purchase Obligation Compliance Framework) Regulations, Coram: Sh. Vishwanath Hiremath, Chairman Sh. S. Dhawan, Member, Sh. Vinod Pandya, Member Date of Order : The Rajasthan Electricity Regulatory Commission (RERC), in exercise of powers conferred under Section 86(1) (e) of the Electricity Act, 2003 (Act 36 of 2003) read with Section 181 of the Act, framed the following Regulations to amend Rajasthan Electricity Regulatory Commission(Renewable Energy Obligation) Regulations, 2007 and Rajasthan Electricity Regulatory Commission(Renewable Energy Certificate and Renewable Purchase Obligation Compliance Framework) Regulations, 2010: a. Rajasthan Electricity Regulatory Commission (Renewable Energy Obligation) (2nd Amendment) Regulations, b. Rajasthan Electricity Regulatory Commission (Renewable Energy Certificate and Renewable Purchase Obligation Compliance Framework) (1 st Amendment) Regulations, The draft regulations along with background note were placed on the website of the Commission. Comments from the stakeholders were also invited by the Commission through Public Notice published in the following newspapers: Times of India : Rajasthan Patrika : Rashtradoot :
2 3. The last date for submission of comments/suggestions by the stakeholders/public was The main comments and views expressed by the stakeholders as well as submissions made during the hearing, are placed at Annexure-I. 4. The hearing in the matter was held on , and the list of stakeholders who participated in the hearing is placed at Annexure-II. 5. The Commission has considered views expressed by the stakeholders through their written submission as well as during the hearing, as below. Prescribing separate Solar &Non- Solar RPO target based on capacity in term of MW / Energy consumed in units. 6. Commission observes that some objectors have supported the proposal to bifurcate overall RPO targets in Solar and Non-Solar category. However it was suggested by them that benchmark capacity for such bifurcation be kept as 5MW instead 10 MW proposed in the draft. M/S Rudraksh Energy opined that for small entity of less than 10 MW, composite RPO is justified as it may not be practicable for them to buy small quantities of power from different types of source. The Commission considers that for smaller entities to enter into PPA for purchase of small quantity of power from different sources may be difficult. Therefore commission decides not to change the benchmark capacity prescribed as 10MW for bifurcation of overall RPO into Solar and Non-Solar category in the proposed regulation. Enforcement of prescribed RPO target 7. It is not correct to say that this Commission is not enforcing RPO. The Commission is enforcing RPO. Exclusion of fossil fuel based Co-generation of power based on fossil fuel from RE Power for meeting RPO 8. The suggestion by M/s Shree Cement, Ms/ JK Lakshmi Cement, M/s JK Cement Works, M/s DCM Shriram Ltd, M/s Brila Corporation, M/s Wonder Cement, M/s Chambal Fertilizers and Chemicals Kota., M/s Ultratech Cement, M/s Hindustan Zinc, not to impose RPO on CPP and OA Consumers having Co-generation plants to the extent it is met by Co-generation, has been considered by the Commission. Accordingly the 2
3 Commission has decided not to make any amendment in RERC (Renewable Energy Obligation) Regulations, 2007 and RERC(Renewable Energy Certificate and Renewable Purchase Obligation Compliance Framework) Regulations, 2010 relating to Co-generation matter. Prescribing RPO Targets: 9. Commission observes that the RPO targets prescribed are analogous to the targets prescribed earlier for distribution licensees and therefore no change is required in the proposed regulation. Treatment for Roof Top/Land mounted solar plants in consumer premises: 10. The Commission observes that no new provision as suggested by the stakeholders is required in the regulations since any RE power produced by captive RE source for own consumption or taken through open access is considered towards fulfillment of their RPO. As regards the suggestion for metering arrangement of captive RE generation and provision of banking, the Commission observes that the issue raised are not relevant to the proposed amendment. 11. In the light of the foregoing discussion, the finalized Regulation, namely Rajasthan Electricity Regulatory Commission (Renewable Energy Obligation) (2nd Amendment) Regulations, 2014 duly authenticated, placed below, may be got published in the official Gazette. 12. Copy of this order, along with the finalized Regulation, may be sent electronically and/or by post to the State Government, CEA, concerned Utilities and other stakeholders. (Vinod Pandya) (S. Dhawan) (Vishwanath Hiremath) Member Member Chairman 3
4 Annexure-I Summary of Main suggestions/comments received from Stakeholders and submissions made during hearing, on Proposed amendment in:- I. RERC (Renewable Energy Obligation) Regulations, II. RERC (Renewable Energy Certificate and Renewable Purchase Obligation Compliance Framework) Regulations, Obj. Stakeholders Suggestion/ Comments No. 1 Rudraksh Energy Supported the proposed RPO targets and Source wise (Solar & Non Solar) bifurcation of targets for capacity 10 MW & above to ensure balanced development of various RE sources, however suggested that effective monitoring of compliance of RPO by Nodal Agency is essential. During hearing suggested that quarterly report on compliance of RPO by Obligated Entities be placed on its website by the Nodal Agency. 2 Ms. Navin RPO targets must be 20% as we are facing climate change Verma, Jodhpur. problem. In Rajasthan Solar potential is enormous and even 1% is not tapped so far. 3 M/s Surya Chamball Power 4 S. Shanti Prasad, Jaipur. The solar power generated by roof top or land mounted Solar PV Plants setup by Industrial units for their own use may be approved by Commission for fulfillment of RPO. As per prescribed RPO targets for FY 14-15, a 10 MW consumer with LF of 60 % will require solar plant of 390 KW capacity. This capacity may increase to 650 kw for FY There cannot be exact matching of solar generation with consumer load at all instants. The Commission may consider specifying that such inadvertent injection (say up to 10% of plant capacity) will be deemed to be banked. He also suggested two systems for metering of such solar power into the grid. 5 Sh. Jitendra singh, Jaipur. While prescribing the RPO targets, the Commission has exempted CPP & OA consumers below 10 MW from meeting Solar RPO separately. This is discriminatory. The Commission should link RPO with consumption in units and not capacity as kw. Since REC is available in term of energy i.e. one REC of every1000 kwh, a CPP consuming 70,000 kwh in a year at 1.5% RPO will need 1050 kwh of RE power. He can buy one REC. Therefore it would be fare to exempt OA and CPP consumers upto 70,000 kwh consumption rather than below 10 MW. The APTEL at para 35(4) of order in appeal no. 92 of 2013 and IA no. 151 of 2013 stated that The State Commission can specify RPO/SPO on the total consumption of distribution licensee and not selectively and directly on some categories of consumers of the distribution licensee order is 4
5 6 The Rajasthan Textiles Mills Association, Jaipur. 7 Indian Wind Power Association. 8 REConnect Energy Solutions Pvt. 9 M/s Shri Cement discriminatory to some categories of consumers. The Commission should consider specifying exemption limit of units instead of 10 MW RTMA has already challenged the order of Hon ble High Court on applicability of RPO in Rajasthan on CPP and OA consumers and the matter in pending in Hon ble Supreme Court. Since 97% of power is being handled by the Discoms, therefore it is not going to make a substantial difference for promotion or RE, if CPPs are exempted. However without prejudice to their stand in court, they submit following suggestion: I. Solar power is still at developing stage and costlier, as such buying of solar power/solar REC will be an additional burden on CPP/OA consumers. II. Co-Generation and WHR power is recognized as Renewable Power, and as such the same should be allowed for fulfillment of RPO. III. The RPO proposed are quite high. The Commission should not amend the regulation till Supreme Court gives judgment. During hearing the Association representative submitted that their members are drawing the power from Power Exchange. this power may be combination of Hydel or Wind or others sources. More ever their members have installed their own Wind generators and thus meeting the combined RPO. There is already significant delay in implementation of RPO Regulations of 2007 &2010 by Obligated Entities. The Commission may specify time line of 30 days for State Agency to Complete the work of identification, data compilation & monitoring. The delay in implementation of RPO mandate has contributed to increase in REC inventory. Therefore, in case of default, the Commission may invoke the default provisions for effective enforcement. The proposed change in regulation for separate Solar obligation for capacity of 10 MW is in-consistent with practice followed by other States. Further as given in background note, Solar installations in State have under gone sea-change. Appropriate Solar RPO and its strict compliance will facilitate its development. A significant majority of CPP & OA Consumers are below 10 Mw. They should also be tied up with Solar RPO. We have installed waste heat recovery power plant by investing huge amount to fulfill RPO as per existing provision, therefore proposed change have serious implication on us. The change is proposed taking reliance on judgment of APTEL The judgment of APTEL is to be understood in perspective and context of question framed which is relevant to Discoms. The said order has not dealt with position w.r.t. co-generation of CPP/OA consumers. 5
6 This remains unchanged. The Supreme Court follows the doctrine of prospective overruling (Referred Judgments in AP Tourism Development Corporation Vs Pampa Hotels, (2010) SSCC425 and Ashok Kumar Gupta Vs. State of U.P. (1997) 5SCC 201. RPO proposed is high. Be kept at par with other States. It was further submitted that Commission should either amend the definition carving out an exception for captive power plants/open access consumers fulfilling as Renewable Purchase obligation through cogeneration like Chattisgarh ERC and MERC. Waste Heat Recovery Power Generation in Cement Industry qualifies to be categorized as environmentally benign and needs to be given preference. The principle has been accepted by CERC in Statement of Reasons of RE Tariff Regulations, As per harmonious construction cogeneration can still be a valid manner/instrument to fulfill RPO for obligated entities such as OA and CPPs. As per national Tariff Policy, Solar RPO will go upto 0.25% by the end of and further upto 3% by However, Commission has proposed to impose an obligation of 1.5% in , which is extremely high and one of the highest in the country in comparison to all other states. Cost of Solar power as well as the Solar REC is extremely high. It may be clarified whether benchmark capacity of 10 MW to determine applicability of total RPO of Solar and Non Solar RPO shall be determined on the basis of total consumption, place of consumption, generation or open access consumption unit. 10 M/s JK Lakshmi Cement During hearing submitted that they have their own WHR system. The section 86(1)(e) has mandated for the Commission to promote co-generation and generation of electricity from renewable sources of energy. They have also referred to the earlier decisions of APTEL. In case of M/s Centuary, M/s Emami, M/s Hindalco etc. and contended that these decision are unchanged and the decision in Lloyds Metal case is in respect of distribution licensees relating to purchase of power from fossil fuel based co-generation with preferential tariff. We have installed waste heat recovery power plant by investing huge amount to fulfill RPO as per existing provision, therefore proposed change have serious implication on us. Why this facility be denied to the CPP s after so many years.. The change is proposed taking reliance on judgment of APTEL The judgment of APTEL is to be understood in perspective and context of question framed which is relevant to Discoms. The said order has not dealt with position w.r.t. co-generation of CPP/OA consumers. 6
7 This remains unchanged. Our limited request is that electricity produced from our Co-generation through waste heat recovery mechanism should continue to be treated towards RPO as in the past. During hearing Sh. P.N. Bhandari submitted that the commission has multi-faceted jobs i.e. promotion of RE, protection of Consumers interest and also the healthy growth of CPP etc. The Electricity Act under section 2(12) defines co-generation of Electricity without any distinction of fuel and 86(1)(e) requires Commissions to promote both co-generation as well as generation of RE sources. Therefore a balance has to be made by the Commission. 11 M/s JK Cement Works As above 12 M/s DCM Shriram As above 13 M/s Birla Corporation As above 14 M/s Wonder Cement As above 15 M/s Chambal Fertilizers As above and Chemicals Kota. 16 M/s Ultratech Cement As above 17 M/s Hindustan Zinc As above 18 Rajasthan Discoms 19 Sh. Rajeev Kothari, Jaipur 20 ReNew Power Ventures Pvt. As per Judgment of APTEL electricity produced from fossil fuel based co-generation is not considered as RE, but cogeneration from other sources may come under RE. Therefore it is proposed that instead of deleting the words and includes co-generation from the regulation, only the energy produced from fossil fuel should be excluded from the aforesaid regulations Rajasthan Discoms be permitted to meet RPO in term of Solar & Non-Solar like CPP s as against Wind, Biomass &Solar State Agency has not lived up to the role &responsibility assigned resulting in very lax attitude by CPP s. The Commission should lay strict performance standards for State Agency (i) Capacity of 5 MW and above be specified for bifurcation as Solar & Non Solar (ii) Support exclusion of co-generation from RE purchase. (iii) Regarding deletion of provision of RE surcharge we propose that Regulation 5 of RERC (Renewable Energy Obligation) Regulations, 2007 be replaced by following words- consequences of default in fulfilling the prescribed RPO shall be dealt in accordance with RERC (Renewal Energy Certificate and renewable Purchase Obligation compliance framework ) Regulation, 2010 as amended from time to time (iv) Need for strict enforcement of RPO compliance: 7
8 21 Rajasthan Renewable Energy Corporation (RREC) Sought clarification regarding applicability on CPP/OA consumers having Standby DG sets of kva with power factor varying from 0.8 to 1.0, which result output of less than 1 MW or more than 1 MW OA consumers draw power for short periods with variation in MW capacity. Whether the obligation to be considered as per their actual maximum drawl of power or capacity indicated in NOC. The solar and non-solar RPO be kept similar on capacity of 1 MW and above. 8
9 Annexure-II Rajasthan Electricity Regulatory Commission List of Stakeholders who participated in the hearing held on Sh. M.G. Ramachandran, Advocate., Shree Cement 2. Sh. D.S. Agarwal, Consultant, Rudraksh Energy. 3. Sh. V.K. Gupta, Cunsultant, Rudraksh Energy. 4. Sh. Vinay Mehta, Jt. Vice President, DCM shriram 5. Sh. Vinoo Mehta, Vice President, DCM Shriram 6. Sh. S S Khandelwal, Company secretary Shree Cement 7. Sh. Amar jit Singh, GM Shree Cement 8. Sh. Jaideep Charan, Asst. Manager, DCM shriram 9. Sh. N.K. Bahedia, Dy.Cord.(commercial) RSWM 10. Sh. S.K. Gupta Secretary RTMA 11. Sh. Rajesh Mathur, SE(RA), JVVNL. 12. Sh. S.T. Hussain, AEn JVVNL. 13. Sh. S.K. Goyal, TM, RREC. 14. Sh. Arijit Banerjee, AM, Global Energy. 15. Sh. N.K. Sharma, Consultant, RREC. 16. Sh. R.C.Menon, Associate. Manager,HZL. 17. Sh. P.N. Bhandari, Adv.HZL&others. 18. Sh. S.K. Baswal, GM, RREC. 19. Sh.A.K. Sharma, T.M, RREC. 9
10 RAJASTHAN ELECTRICITY REGULATORY COMMISSION NOTIFICATION Jaipur, May 2014 No. RERC/Secy/Regulation- In exercise of the powers conferred under Section 86(1)(e) read with section 181 the Electricity Act, 2003 and all powers enabling it in this behalf the Rajasthan Electricity Regulatory Commission after previous publication, makes the following Regulations, to amend Rajasthan Electricity Regulatory Commission (Renewable Energy Obligation) Regulations, 2007,namely: 1. Short title and commencement (1) These regulations shall be called the Rajasthan Electricity Regulatory Commission (Renewable Energy Obligation)(2nd Amendment) Regulations, (2) These Regulations shall come into force from date of publication in the Official Gazette. 2. Amendment in regulation 2: The existing regulation 2 Definitions shall be replaced as under: 2 Definitions (1) In these regulations unless the context otherwise requires ; I. Captive power plants or CPP shall have the same meaning as assigned in RERC (CPP) Regulations II. Renewable Energy or RE shall have meaning as assigned in RERC (Terms and Conditions for Determination of Tariff) Regulation, 2004 as amended from time to time & shall include cogeneration. (2) All words & expressions appearing in these regulations shall bear the same meaning assigned to them in the following order: (I) The RERC (CPP) Regulations, 2010 (II) The RERC (Terms and Conditions for Open Access) Regulation 2004 (III) The Electricity Act,
11 3 Amendment in regulation 4: The table in existing sub regulations 4(2) shall be replaced by the following: (A)CPP &OA Consumers with total capacity of 10 MW & above: S.No Year Obligation expressed as percentage of energy consumption (%) Non- Solar Solar Total (B) CPP & OA Consumers with capacity of 1MW and above, but less than10 MW: S. No. Year Obligation expressed as percentage of energy consumption (%) By order (G.K. Sharma) Secretary 11
S. No. Year Obligation expressed as percentage of energy consumption (%) 1 2011-12 6.00 2 2012-13 7.10 3 2013-14 8.20
Background paper for prescribing Renewable Purchase Obligation (RPO) for Captive consumption of CPP & open access consumers in the State for the period ending March, 2017 and related amendment in regulations:
RAJASTHAN ELECTRICITY REGULATORY COMMISSION JAIPUR
RAJASTHAN ELECTRICITY REGULATORY COMMISSION JAIPUR NOTIFICATION 23 rd December, 2010 No.RERC/Secy/Reg. 82 : In exercise of powers conferred under sections 61, 66, 86(1)(e) and 181 of the Electricity Act,
DRAFT MODEL REGULATIONS for STATE ELECTRICITY REGULATORY COMMISSION UNDER SETION 86 (1) (e) OF THE ACT. No. Dated: October, 2009 NOTIFICATION (DRAFT)
DRAFT MODEL REGULATIONS for STATE ELECTRICITY REGULATORY COMMISSION UNDER SETION 86 (1) (e) OF THE ACT No. Dated: October, 2009 NOTIFICATION (DRAFT) In exercise of powers conferred under sections 61, 66,
DELHI ELECTRICITY REGULATORY COMMISSION
DELHI ELECTRICITY REGULATORY COMMISSION DELHI ELECTRICITY REGULATORY COMMISSION (RENEWABLE PURCHASE OBLIGATION AND RENEWABLE ENERGY CERTIFICATE FRAMEWORK IMPLEMENTATION) REGULATIONS, 2011 No. Dated:. NOTIFICATION
Analysis of state-wise RPO Regulation across India
The Renewable Purchase Obligations (RPO) has been the major driving force in India to promote the renewable energy sector. But the State Electricity Regulatory Commissions (SERCs) have defined their respective
Renewable Purchase Obligation (RPO) / Renewable Energy Certificates (REC) Advisory and Trading
Renewable Purchase Obligation (RPO) / Renewable Energy Certificates (REC) Advisory and Trading Target Clients v Renewable Energy Generators in India v RPO mandated entities in India v Investors seeking
DRAFT REGULATIONS FOR ANDHRA PRADESH ELECTRICITY REGULATORY COMMISSION UNDER SECTION 86(1)(e) OF THE ACT NOTIFICATION
DRAFT REGULATIONS FOR ANDHRA PRADESH ELECTRICITY REGULATORY COMMISSION UNDER SECTION 86(1)(e) OF THE ACT No. Dated: -12-2011 NOTIFICATION In exercise of powers conferred under sections 61, 66, 86(1)(e)
ANDHRA PRADESH ELECTRICITY REGULATORY COMMISSION
ANDHRA PRADESH ELECTRICITY REGULATORY COMMISSION RENEWABLE POWER PURCHASE OBLIGATION (COMPLIANCE BY PURCHASE OF RENEWABLE ENERGY / RENEWABLE ENERGY CERTIFICATES) REGULATIONS, 2012 Regulation No. 1 of 2012
KERALA STATE ELECTRICITY REGULATORY COMMISSION
KERALA STATE ELECTRICITY REGULATORY COMMISSION Notification No. 2096/KSERC/CT/2014 Dated, Thiruvananthapuram 10 th June 2014. In exercise of the powers conferred under sections 66, 86 (1) (e) and 181 of
Renewable Energy Certificate Mechanism for India. ABPS Infrastructure Advisory. Background
Renewable Energy Certificate Mechanism for India Background ABPS Infrastructure Advisory India is abundantly gifted with a variety of renewable energy (RE) sources. However, not all states are endowed
PUNJAB STATE ELECTRICITY REGULATORY COMMISSION SCO NO. 220-221, SECTOR 34-A, CHANDIGARH
PUNJAB STATE ELECTRICITY REGULATORY COMMISSION SCO NO. 220-221, SECTOR 34-A, CHANDIGARH Petition No. 52 of 2013 Date of Order: 14.11.2013 In the matter of: Petition under Section 86 (1) (b) and 86 (1)
G.O.MS.No. 8 Dated 12.02.2015 Read the following:-
GOVERNMENT OF ANDHRA PRADESH ABSTRACT ENERGY, INFRASTRUCTURE & INVESTMENT DEPARTMENT - Development of Solar Power in Andhra Pradesh Andhra Pradesh Solar Power Policy, 2015 Orders Issued. ------------------------------------------------------------------------------------------------------------
KERALA STATE ELECTRICITY REGULATORY COMMISSION THIRUVANANTHAPURAM IN THE MATTER OF
KERALA STATE ELECTRICITY REGULATORY COMMISSION THIRUVANANTHAPURAM PRESENT: Shri. K.J.Mathew, Chairman Shri. C. Abdulla, Member Shri. M.P.Aiyappan, Member Petition No. CT/SOLAR JNNSM/KSERC/2010 August 4,
DRAFT KERALA STATE ELECTRICITY REGULATORY COMMISSION, NOTICE. No. 442/CT/2014/KSERC Dated, Thiruvananthapuram 31 st March, 2015
DRAFT 31.3.2015 KERALA STATE ELECTRICITY REGULATORY COMMISSION, NOTICE 442/CT/2014/KSERC Dated, Thiruvananthapuram 31 st March, 2015 The Kerala State Electricity Regulatory Commission hereby publishes
RAJASTHAN ELECTRICITY REGULATORY COMMISSION, JAIPUR Petition No. RERC 456/14, 457/14, 458/14, 442/14, 444/14 & 447/14
RAJASTHAN ELECTRICITY REGULATORY COMMISSION, JAIPUR Petition No. RERC 456/14, 457/14, 458/14, 442/14, 444/14 & 447/14 In the matter of Determination of Annual Revenue Requirement (ARR) & Retail Supply
BEFORE THE HARYANA ELECTRICITY REGULATORY COMMISSION BAYS NO. 33-36, SECTOR 4, PANCHKULA-134112 - HARYANA
BEFORE THE HARYANA ELECTRICITY REGULATORY COMMISSION BAYS NO. 33-36, SECTOR 4, PANCHKULA-134112 - HARYANA Quorum: Case No. HERC/PRO-51 of 2014 Date of hearing: 22.07.2014 Date of order : 22.07.2014 Shri
PROCEDURE FOR ACCREDITATION OF RENEWABLE ENERGY GENERATION PROJECT FOR RENEWABLE ENERGY CERTIFICATE BY STATE AGENCY
PROCEDURE FOR ACCREDITATION OF RENEWABLE ENERGY GENERATION PROJECT FOR RENEWABLE ENERGY CERTIFICATE BY STATE AGENCY 1. OBJECTIVE : 1.1. This procedure shall provide guidance to the entities to implement
KERALA STATE ELECTRICITY REGULATORY COMMISSION
KERALA STATE ELECTRICITY REGULATORY COMMISSION Dated 24 th January 2014 NOTICE Notice is hereby given that Kerala State Electricity Regulatory Commission has published the Draft Kerala State Electricity
Uttar Pradesh Rooftop Solar Photovoltaic Power Plant Policy, 2014
Uttar Pradesh Rooftop Solar Photovoltaic Power Plant Policy, 2014 Table of Contents 1- PREAMBLE - 1 2- OBJECTIVES - 1 3- OPERATIVE PERIOD - 1 4- IMPLEMENTATION PLAN - 2 5- ELIGIBLE ENTITIES - 2 6- TARGETS
Determination of cost of power generation for Dongamahua captive power plant of Jindal Steel & Power Ltd. from FY 2011-12 till FY 2015-16.
Chhattisgarh State Electricity Regulatory Commission Irrigation Colony, Shanti Nagar, Raipur - 492 001 (C.G.) Ph.0771-4048788, Fax: 4073553 www.cserc.gov.in, e-mail: [email protected] Petition No. 47
PUNJAB STATE ELECTRICITY REGULATORY COMMISSION SCO 220-221, SECTOR 34-A, CHANDIGARH. Petition No.26 of 2010 (Suo Motu) Date of Order: 7.7.
PUNJAB STATE ELECTRICITY REGULATORY COMMISSION SCO 220-221, SECTOR 34-A, CHANDIGARH Petition No.26 of 2010 (Suo Motu) Date of Order: 7.7.2010 In the matter of : Determination of generic levellised generation
PROCEDURE FOR ACCREDITATION OF RENEWABLE ENERGY GENERATION PROJECT FOR RENEWABLE ENERGY CERTIFICATE BY STATE AGENCY
PROCEDURE FOR ACCREDITATION OF RENEWABLE ENERGY GENERATION PROJECT FOR RENEWABLE ENERGY CERTIFICATE BY STATE AGENCY 1 Objective (1) This procedure shall provide guidance to the entities to implement Renewable
TAMIL NADU ELECTRICITY REGULATORY COMMISSION. Notification No. TNERC/RPO/ 19/1 dated 07-12-2010
TAMIL NADU ELECTRICITY REGULATORY COMMISSION Notification No. TNERC/RPO/ 19/1 dated 07-12-2010 In exercise of powers conferred by section 181 of the Electricity Act, 2003 (Central Act 36 of 2003) read
Solar Power Policy Uttar Pradesh 2012 Suggestions to be sent to : [email protected] [email protected]
Draft ver2 Solar Power Policy Uttar Pradesh 2012 Suggestions to be sent to : [email protected] [email protected] 1 TABLE OF CONTENTS S.No Contents Page No 1. PREAMBLE 3 2. OBJECTIVES 3 3. OPERATIVE
MAHARASHTRA ELECTRICITY REGULATORY COMMISSION, MUMBAI
MAHARASHTRA ELECTRICITY REGULATORY COMMISSION, MUMBAI Draft Maharashtra Electricity Regulatory Commission (Net Metering for Rooftop Solar Systems) Regulations, 2015 Electricity Act, 2003 No. MERC / Legal
Model Renewable Energy Wheeling Agreement under Renewable Energy Certificate (REC) scheme
Model Renewable Energy Wheeling Agreement under Renewable Energy Certificate (REC) scheme This agreement made at on this day of two thousand between M/s. (Renewable Energy Generator name and address) hereinafter
CENTRAL ELECTRICITY REGULATORY COMMISSION NEW DELHI. Petition No. 266/SM/2012
CENTRAL ELECTRICITY REGULATORY COMMISSION NEW DELHI Petition No. 266/SM/2012 Coram: Dr. Pramod Deo, Chairperson Shri S. Jayaraman, Member Shri V.S. Verma, Member Shri M. Deena Dayalan, Member Date of Hearing:
KARNATAKA ELECTRICITY REGULATORY COMMISSION No.9/2, 6 th & 7 th Floor, Mahalaxmi Chambers, M.G. Road, Bangalore-560 001
KARNATAKA ELECTRICITY REGULATORY COMMISSION No.9/2, 6 th & 7 th Floor, Mahalaxmi Chambers, M.G. Road, Bangalore-560 001 Present: Shri M.R.Sreenivasa Murthy Chairman Shri Vishvanath Hiremath Shri K. Srinivasa
Success in Scaling-up Solar Energy in Rajasthan, India
Success in Scaling-up Solar Energy in Rajasthan, India Shreemat Pandey Principal Secretary to Chief Minister Rajasthan, India 1. Introduction Solar power is attractive because it is abundant and offers
Solar Power Plants FAQs
Solar Power Plants FAQs Solar Power industry in India is gaining more and more prominence with each passing day. The domestic/off-grid industry is picking up speed too. Owing to the queries we are receiving
Existing Wind Power Policies and Incentives
Existing Wind Power Policies and Incentives Consultation on National Wind Energy Mission January 9, 2014 New Delhi Wind Power Progress (in MW) Potential (at 80 m) : 1,02,000 Achievement so far : 20,150
Appellate Tribunal for Electricity (Appellate Jurisdiction) APPEAL No. 297 of 2013
Dated: 23 rd April, 2015 Appellate Tribunal for Electricity (Appellate Jurisdiction) APPEAL No. 297 of 2013 Present: Hon ble Mr. Rakesh Nath, Technical Member Hon ble Mr. Justice Surendra Kumar, Judicial
( Extract from Haryana Government Gazette, dated the 6 th December,2005) HARYANA GOVERNMENT
( Extract from Haryana Government Gazette, dated the 6 th December,2005) HARYANA GOVERNMENT RENEWABLE ENERGY DEPARTMENT NOTIFICATION The 23 rd November, 2005 POLICY FOR PROMOTING GENERATION OF ELECTRICITY
Case No. 100 of 2014. Smt. Chandra Iyengar, Chairperson Shri Vijay L. Sonavane, Member ORDER (SUO-MOTU)
Before the MAHARASHTRA ELECTRICITY REGULATORY COMMISSION 13 th Floor, Centre No.1, World Trade Centre, Cuffe Parade, Mumbai- 400 005 Tel: 22163964/65/69 Fax: 22163976 E-mail: [email protected] Website:
Tamil Nadu WiNd ENErgy ProfilE
Tamil Nadu WiNd ENErgy ProfilE Wind energy in Tamil Nadu has witnessed tremendous growth propelling the State to the number one position in India in terms of renewables. However the challenge that remains
Renewable Energy Certificate Mechanism
Opportunities in Financing Renewable Energy Projects focusing on FiT and RECs Balawant Joshi Director, [email protected], [email protected] In this presentation.. Investment Potential for Renewable
Indian Experiences on Promoting Renewable Energy DR SUSHANTA K CHATTERJEE JOINT CHIEF (REGULATORY AFFAIRS) CENTRAL ELECTRICITY REGULATORY COMMISSION
Indian Experiences on Promoting Renewable Energy DR SUSHANTA K CHATTERJEE JOINT CHIEF (REGULATORY AFFAIRS) CENTRAL ELECTRICITY REGULATORY COMMISSION Introduction Clean energy promotion in India Focus on
Section 4-Tariff proposals and approved tariff
18. Tariff proposals Section 4-Tariff proposals and approved tariff As discussed in the foregoing paragraphs, even after taking the effect of improved Transmission & Distribution Losses, allowing of interest
AN OVERVIEW OF INDIA S ENERGY SECTOR
AN OVERVIEW OF INDIA S ENERGY SECTOR India is the world s eleventh largest economy by nominal GDP and fourth largest by Purchasing Power Parity. The eleventh five year plan of India s Planning Commission
PROCEDURE FOR ISSUANCE OF RENEWABLE ENERGY CERTIFICATE TO THE ELIGIBLE ENTITY BY CENTRAL AGENCY
PROCEDURE FOR ISSUANCE OF RENEWABLE ENERGY CERTIFICATE TO THE ELIGIBLE ENTITY BY CENTRAL AGENCY 1. OBJECTIVE 1.1. This procedure shall provide guidance to the entities to implement Renewable Energy Certificate
DRAFT OF THE GOA STATE GOVERNMENT POLICY TOWARDS RENEWABLE, SOLAR ENERGY AND ENERGY CONSERVATION- GOA 2014
DRAFT OF THE GOA STATE GOVERNMENT POLICY TOWARDS RENEWABLE, SOLAR ENERGY AND ENERGY CONSERVATION- GOA 2014 Drafted by Goa Energy Development Agency (GEDA) team for the approval by the State Govt. of Goa
Draft Jharkhand State Solar Power Policy 2015
Draft Jharkhand State Solar Power Policy 2015 Government of Jharkhand Department of Energy Notification No. ------ Date:./2015 Preamble: In order to reduce the dependence on fossil fuel based generation,
Delhi Solar Energy Policy, 2015
DRAFT VERSION FOR PUBLIC COMMENT Delhi Solar Energy Policy, 2015 GOVERNMENT OF NCT OF DELHI DELHI SECTRETARIAT, I.P. ESTATE, NEW DELHI- 110002 10 September 2015 NOTIFICATION The Government of NCT of Delhi
In Focus. India s Renewable Energy Certificate Market
2011 1 India s Renewable Energy Certificate Market In Focus India s Renewable Energy Certificate Market Carbon Credit Capital LLC 561 Broadway New York, NY 10012 Tel: 212-925-5697 (Main Office) www.carboncreditcapital.com
New Delhi, the 20 th November, 2002
GOVERNMENT OF INDIA MINISTRY OF PETROLEUM AND NATURAL GAS NOTIFICATION New Delhi, the 20 th November, 2002 GUIDELINES FOR LAYING PETROLEUM PRODUCT PIPELINES F.No.P-20012/5/99-PP The Government of India
Solar City Master Plan - Executive Summary
Solar City Master Plan - Executive Summary Meeting the growing energy demand is one of the biggest challenges that the world is facing today. Rising population and depleting fossil fuel resources are compelling
all that you want to know About Rajasthan Solar Energy
all that you want to know bout Rajasthan Solar Energy Policy, 2014 General 01 Registration Land Timelines Fee & Charges 06 08 11 13 all that you want to know bout Rajasthan Solar Energy Policy, 2014 Rajasthan
THE AMENDED RENEWABLE ENERGY SOURCES ACT 2014 (EEG 2014)
THE AMENDED RENEWABLE ENERGY SOURCES ACT 2014 (EEG 2014) 18.08.2014 Energy Regulatory & Governmental Affairs The Amended Renewable Energy Sources Act 2014 (EEG 2014) With the most recent amendment of the
Tamil Nadu Electricity Regulatory Commission
1 Tamil Nadu Electricity Regulatory Commission No 19A, Rukmini Lakshmipathy Salai, Egmore, Chennai - 600 008. Phone:044-28411376, Website:http://www.tnerc.tn.nic.in/ Public Notice 1. The Tamil Nadu Generation
Karnataka Electricity Regulatory Commission. Discussion note on
Karnataka Electricity Regulatory Commission Discussion note on Draft KERC (Forecasting, Scheduling, Deviation settlement and related matters for Wind and Solar Generation sources) Regulations, 2015. 1.0.
CENTRAL INFORMATION COMMISSION Appeal No. CIC/AT/A/2009/00422 dated 18-4-2009 Right to Information Act 2005 Section 19
CENTRAL INFORMATION COMMISSION Appeal No. CIC/AT/A/2009/00422 dated 18-4-2009 Right to Information Act 2005 Section 19 Appellant: Respondent: Shri Suraj Prakash, United India Insurance Co. Decision Announced
MAHARASHTRA ELECTRICITY REGULATORY COMMISSION
Before the MAHARASHTRA ELECTRICITY REGULATORY COMMISSION World Trade Centre, Centre No.1, 13th Floor, Cuffe Parade, Mumbai 400 005 Tel. 022 22163964/65/69 Fax 22163976 Email: [email protected]
v/s. Western India Art Litho Works Pvt. Ltd.
1 cp1096.2000 IN THE HIGH COURT OF JUDICATURE AT BOMBAY ORDINARY ORIGINAL CIVIL JURISDICTION COMPANY PETITION NO. 1096 of 2000 Solar Printing Inks v/s. Western India Art Litho Works Pvt. Ltd....Petitioner...Respondent
F. No. 66/185/2016 -WE Ministry of New & Renewable Energy
F. No. 66/185/2016 -WE Ministry of New & Renewable Energy India has set an ambitious target of reaching 175 GW of installed capacity from renewable energy sources including 100 GW from solar and 60 GW
Japan. Nagahide Sato and Sadayuki Matsudaira Nishimura & Asahi
Nagahide Sato and Sadayuki Matsudaira Nishimura & Asahi 1 Policy and law What is the government policy and legislative framework for the electricity sector? The electricity sector in is governed by the
Smart meters: Removing regulatory barriers and maintaining consumer safety for a market-led roll out of smart meters in New South Wales
Smart meters: Removing regulatory barriers and maintaining consumer safety for a market-led roll out of smart meters in New South Wales The NSW Government is committed to a voluntary, market-led roll out
TV18 Broadcast Limited
TV18 Broadcast Limited CODE FOR PREVENTION OF INSIDER TRADING [IN TERMS OF SEBI (PROHIBITION OF INSIDER TRADING) REGULATIONS, 1992 S.NO. CONTENTS PAGE NO. CHAPTER I A Introduction 1 B Objective 1 C Definitions
a) Whether there is a need to revisit the existing approach for debt: equity ratio or to continue with the existing composition?
Summary of the comments and suggestions received on Approach Paper on Terms and Conditions of Tariff Regulations for the tariff period 1.4.2014 to 31.3.2019 ( Ref No. 20/2013/CERC/Fin(Vol-I)/Tariff Reg/CERC
CENTRAL INFORMATION COMMISSION
CENTRAL INFORMATION COMMISSION (Room No.315, B Wing, August Kranti Bhawan, Bhikaji Cama Place, New Delhi 110 066) Prof. M. Sridhar Acharyulu (Madabhushi Sridhar) Information Commissioner CIC/SA/A/2015/001408
CENTRAL ELECTRICITY REGULATORY COMMISSION NEW DELHI NOTIFICATION. No. L-1/(3)/2009-CERC Dated the 7 th August 2009
CENTRAL ELECTRICITY REGULATORY COMMISSION NEW DELHI NOTIFICATION No. L-1/(3)/2009-CERC Dated the 7 th August 2009 In exercise of powers conferred by section 178 of the Electricity Act, 2003 and all other
RENEWABLE ENERGY DEVELOPMENT IN LITHUANIA ACHIEVEMENTS AND DRAWBACKS
RENEWABLE ENERGY DEVELOPMENT IN LITHUANIA ACHIEVEMENTS AND DRAWBACKS Ieva Kuodė Ministry of Energy of the Republic of Lithuania SOLINVEST 2015-06-02 RES TARGETS BY 2020 23% the share of energy from renewable
Renewable Energy in the manufacturing and tourism industry in Egypt. Regulatory Framework and market potential
Renewable Energy in the manufacturing and tourism industry in Egypt Regulatory Framework and market potential Part 1 Electricity Self-consumption 2 Egypt s Electricity Sector Figures 2013 27 GW Peak Load
National Electricity Policy 03-Feb-2005
National Electricity Policy 03-Feb-2005 Under the provisions of section 3(1) of the Electricity Act, 2003, the Central Government is required to prepare the National Electricity Policy for development
POLICY FOR IMPLEMENTATION OF SOLAR POWER BASED PROJECTS IN MADHYA PRADESH, 2012
POLICY FOR IMPLEMENTATION OF SOLAR POWER BASED PROJECTS IN MADHYA PRADESH, 2012 (1) Preamble Energy is a prime mover of the development of any economy. While conventional fuels like coal and oil have been
Sub: Scheduling and Dispatch Procedure under RERC (Intra-State ABT) Regulations, 2006.
Sub: Scheduling and Dispatch Procedure under RERC (Intra-State ABT) Regulations, 2006. 1. General a) Intra-State ABT as per RERC (Intra-State ABT) Regulations, 2006 has come into commercial operation w.e.f.
TELANGANA SOLAR POWER POLICY 2015
TELANGANA SOLAR POWER POLICY 2015 1 GLOSSARY COD CII GoTS GoI MNRE MoP NCE NOC NSM PCB PPA PV R&D REC RPPO RLDC SGST SLDC SPC SPP SPV SRP Scheduled Commercial Operations Date Confederation of Indian Industry
THE INDIAN MARKET FOR RENEWABLE ENERGY THE 100 GW SOLAR INITIATIVE
THE INDIAN MARKET FOR RENEWABLE ENERGY THE 100 GW SOLAR INITIATIVE PRESENTATION BY : MR KESHAV PRASAD MEMBER, DELEGATION OF THE CONFEDERATION OF INDIAN INDUSTRY (CII) & CHIEF OPERATING OFFICER, IL&FS ENERGY
CENTRAL INFORMATION COMMISSION Club Building (Near Post Office) Old JNU Campus, New Delhi-110067 Tel: +91-11-26105682. File No.CIC/DS/A/2011/001995/RM
CENTRAL INFORMATION COMMISSION Club Building (Near Post Office) Old JNU Campus, New Delhi-110067 Tel: +91-11-26105682 File No.CIC/DS/A/2011/001995/RM Appellant: Mr. Rakesh Kumar Gupta, New Delhi Public
UNDERSTANDING ENERGY BILLS & TARRIFS
UNDERSTANDING ENERGY BILLS & TARRIFS as part of the Energy Efficiency Information Grants Program Reading and understanding your energy and gas bills is a good first step to help you to identify where you
Standard conditions of electricity supply licence
Gas and Electricity Markets Authority ELECTRICITY ACT 1989 Standard conditions of electricity supply licence SECTION A: STANDARD CONDITIONS FOR ALL SUPPLIERS Standard conditions 1 to 6: General arrangements
Grid Connected Solar Power in India. Tarun Kapoor Joint Secretary Ministry of New and Renewable Energy Government of India
Grid Connected Solar Power in India Tarun Kapoor Joint Secretary Ministry of New and Renewable Energy Government of India Indian Power Sector (31 March 2012) Thermal Hydro Nuclear Renewable 1,31,353 MW
IN THE HIGH COURT OF DELHI AT NEW DELHI SUBJECT : RAILWAY CLAIMS TRIBUNAL ACT,1987 FAO No. 507/2011 DATE OF DECISION : 8th January, 2014
IN THE HIGH COURT OF DELHI AT NEW DELHI SUBJECT : RAILWAY CLAIMS TRIBUNAL ACT,1987 FAO No. 507/2011 DATE OF DECISION : 8th January, 2014 GURCHARAN SINGH & ORS. Through: Mr. N.K. Gupta, Advocate versus
BEFORE THE UTTAR PRADESH ELECTRICITY REGULATORY COMMISSION, LUCKNOW
BEFORE THE UTTAR PRADESH ELECTRICITY REGULATORY COMMISSION, LUCKNOW IN THE MATTER OF: Suo - Motu Proceedings on matters of 1. Provisional Billing in case of defective meters / Normative Consumption for
THE HIGH COURT OF DELHI AT NEW DELHI SUBJECT : NEGOTIABLE INSTRUMENTS ACT CRL.M.C.1640/2011 Date of Decision: 27.04.2012
THE HIGH COURT OF DELHI AT NEW DELHI SUBJECT : NEGOTIABLE INSTRUMENTS ACT CRL.M.C.1640/2011 Date of Decision: 27.04.2012 KAJAL SENGUPTA Petitioner Through: Mr.Viplav Sharma, Advocate with Ms.Nilanjana
Support Information for Solar Power Generation Regulation of JERC & Suggestive Power Purchase Agreement.
Support Information for Solar Power Generation Regulation of JERC & Suggestive Power Purchase Agreement. Technical and interconnection requirements The Project Developers shall adhere to the National &
The Narragansett Electric Company d/b/a National Grid
The Narragansett Electric Company d/b/a National Grid Rhode Island Renewable Energy Growth Program Solicitation and Enrollment Process Rules for Small-Scale Solar Projects Effective Date: April 1, 2015
No. 22/9/2009-NSM (ST) भ रत सरक र/ Government of India नव न और नव करण य ऊर म त र ऱय / Ministry of New & Renewable Energy ***** Office Memorandum
No. 22/9/2009-NSM (ST) भ रत सरक र/ Government of India नव न और नव करण य ऊर म त र ऱय / Ministry of New & Renewable Energy ***** Office Memorandum Block-14, CGO Complex, Lodhi Road, New Delhi, dated 8 th
Methodology for Solar Power Projects
Annexure E Methodology for Solar Power Projects This methodology is applicable to the solar power projects included in the composite policy for new and renewable (non-conventional energy sources) power