Renewable Energy Certificate Mechanism for India. ABPS Infrastructure Advisory. Background

Size: px
Start display at page:

Download "Renewable Energy Certificate Mechanism for India. ABPS Infrastructure Advisory. Background"

Transcription

1 Renewable Energy Certificate Mechanism for India Background ABPS Infrastructure Advisory India is abundantly gifted with a variety of renewable energy (RE) sources. However, not all states are endowed with the same level of renewable energy sources. While some states have very high renewable energy potential, some have very little renewable energy potential. The Electricity Act 2003 (EA 2003) stimulated the development of RE based power generation by mandating that State Electricity Regulatory Commissions (SERCs) be responsible for promoting the harnessing of RE generation within the state. Under the EA 2003, the SERCs set targets for distribution companies and obligated entities to purchase a certain percentage (Renewable Purchase Obligation), of its total power requirement from renewable energy sources. The existing legal framework, under the EA 2003, puts the responsibility for promotion of renewable energy on SERCs. As a result, the regulations developed by the SERCs differ from each other on many counts. Further, the RPO regulations of one state do not recognize purchase of renewable energy generated in another state as an eligible RE source, for the purpose of fulfillment of the RPO target by Obligated Entities in that state. The RE rich states cannot sell their surplus RE based generation to the states which do not have sufficient RE generation to fulfill their RPO. Consequently, the states with lower RE sources have to keep their RPO target at lower levels. In addition, the unit cost of the RE based nonfirm power is higher than the conventional power sources. As a result, while RE rich states have no motivation to produce RE based power more than that required to fulfill the RPO demand within the state, RE scarce states are not able to procure RE generation from other states. Initiatives for Development of the REC Mechanism On June 30, 2008, the Hon ble Prime Minister of India announced the National Action Plan for Climate Change (NAPCC) which envisaged several measures to address climate change issues. The NAPCC states that increasing the share of renewable energy in the total electricity consumption of the country is one of the important measures that can combat climate change. The NAPCC has set the Dynamic Minimum Renewable Purchase Standard (DMRPS) at 5% for FY against the current level of approx 3.5%. Further, the NAPCC envisages that such targets will increase by 1% over the next 10 years; which would translate to approximately 15% of the renewable energy generation in the total energy mix of India by This would require a quantum jump in deployment of renewable energy across the country. Strong policy measures and a proactive regulatory framework and innovative financing instruments would be required, if the desired penetration level of renewable energy is to be achieved. One such policy instrument prescribed in the NAPCC is the Renewable Energy Certificate (REC) Mechanism, which would enable a large number of stakeholders to purchase renewable energy in a cost effective manner. In consideration of this recommendation of the NAPCC for the promotion of renewable energy, the Ministry of New and Renewable Energy (MNRE) had initiated a study to develop a Conceptual Framework for the Proposed REC Mechanism in India. The Conceptual Framework Report has proposed its recommendations on the Operational and Institutional Framework for the REC Mechanism in India. Along with the MNRE, the Central Electricity Regulatory Commission (CERC) and the Forum of Regulators (FOR) have also been engaged in evolving the Conceptual Framework for Development of the REC Mechanism in India. The Central Electricity Regulatory Commission (CERC) is currently seized with addressing further implementation aspects. On January 18, 2010 it notified its regulations, outlining the terms and conditions for recognition and issuance of renewable energy certificates. Implementation of these regulations will enable obligated entities to meet their RPO target through RECs which may have been generated in

2 other states. In addition to this, an expert committee has also been formed to enable successful implementation of the REC Mechanism in India. For a nation-wide implementation of the REC framework, it is essential that uniform policies are adopted at the state level, in consonance with the national level regulatory framework formulated by the CERC. In this regard, the Model Regulations for State Commissions have already been evolved by the Forum of Regulators (FOR). However, such Model Regulations need to be notified by respective state commissions, after undertaking the due regulatory process. Key Drivers for REC Mechanism in India The Renewable Energy Certificate (REC) mechanism seeks to address the mismatch between availability of RE sources and the requirement of the obligated entities to meet their renewable purchase obligation across states. So far, inter-state exchanges of renewable energy was constrained due to the fact that such transactions are governed by inter-state open access regulations and the regional energy accounting framework, which necessitates scheduling of power. Some of the RE sources, such as biomass power or bagasse based co-generation, can be scheduled and inter-state open access transactions, based on such firm RE sources, have taken place in the past. However, inter-state exchanges of power, based on non-firm RE sources, such as wind energy, solar power, small hydel power, etc., was constrained. Besides, the cost of open access wheeling, under long term arrangements, was prohibitive for such nonfirm RE sources, due to the inherently lower capacity utilization factors. The REC mechanism addresses these constraining factors as the certificate is issued for the energy generated at the point of injection into the grid. Thus, it is envisaged that the REC mechanism shall facilitate the emergence of a large number of cross-border RE transactions, based on non-firm RE sources, while at the same time, enhancing the volume of cross-border RE transactions based on firm RE sources as well. While effective implementation of inter-state transactions would be the primary objective of the REC mechanism in India, some other objectives identified are: Reducing costs for RE transactions Increasing flexibility for participants to choose the participant in RE transactions Overcoming geographical constraints to harness available RE sources Effective implementing of RPO regulations in all Indian states Creating competition among different RE technologies Developing an all encompassing incentive mechanism Reducing risks for local distribution licensees Concept of the REC Mechanism While, conceptually, the operational framework is similar to REC mechanisms implemented in other parts of the world, it has been customized to comply with India s existing legal and regulatory framework. The REC Mechanism in India shall deem the purchase of an REC as the purchase of power generated from RE sources. In the proposed mechanism, the RE generator will be selling two independent and exclusive products from the same quantum of RE generation. These products will be electricity and its associated environmental attributes in the form of RE Certificates.

3 In the proposed mechanism, one REC will be issued to the RE generator for every MWh of electrical energy fed into the grid. The RE generator may sell electricity to the distribution company, at the regulated price equivalent to the pooled cost of power purchased by the Utility from all sources, excluding RE sources and its RECs, to Obligated Entities at the market price through the exchange mechanism, in a transparent manner. The RE generator may sell his RE certificates, only through the power exchange, to such Obligated Entities who have to meet their RPO target. The purchase of RECs will be deemed as purchases of power generated from renewable sources and, accordingly, will be allowed for compliance with the RPO target. The REC mechanism will enable obligated entities in a state to procure RECs generated from any of the states in India and surrender the same to satisfy its RPO target. Operational Framework and Processes In January 2010, the CERC notified its Regulations outlining the Terms and Conditions for recognition and issuance of Renewable Energy Certificates. The salient features of the regulations are mentioned below: There will be a Central Level Agency, to be designated by the Central Commission, for registration of RE generators participating in the scheme. The RE generators will have two options either to sell the renewable energy, at preferential tariffs fixed by the concerned electricity regulatory commission, or to sell the electricity generation and environmental attributes associated with RE generation separately. On choosing the second option, the environmental attributes can be exchanged in the form of an REC. The price of electricity component would be equivalent to the weighted average of the power purchase cost of the distribution company, including short-term power purchases, but excluding renewable power purchase costs. There shall be two categories of certificates, viz., solar certificates issued to eligible entities for generation of electricity based on solar as renewable energy source; and non-solar certificates issued to eligible entities for generation of electricity based on renewable energy sources other than solar. The solar certificate shall be sold to the obligated entities to enable them to meet their renewable purchase obligation for solar, and non-solar certificate shall be sold to the obligated entities to enable them to meet their obligation for purchase from renewable energy sources other than solar. The Central Agency will issue the REC to RE generators.

4 The value of an REC will be equivalent to 1 MWh of electricity injected into the grid from renewable energy sources. The REC will be exchanged only in the Power Exchanges approved by the CERC within the band of a floor price and a forbearance (ceiling) price, to be determined by the CERC from time to time. The distribution companies, the open access consumer, and the Captive Power Plants (CPPs) will have the option of purchasing RECs to meet their Renewable Purchase Obligations (RPOs). Pertinently, renewable purchase obligation is the obligation mandated by the State Electricity Regulatory Commission (SERC), under the Act, to purchase a minimum level of renewable energy out of the total consumption in the area of a distribution licensee. There will also be compliance auditors to ensure compliance with the requirement of fulfilling the REC obligations by the participants of the scheme. The schematic depicted in the figure below represents a flow diagram for various processes involved in the operation of the REC mechanism. The numbers indicate the chronological sequence of seven identified key processes. The operational framework depicted above does not envisage any major modification to the existing arrangements for renewable energy procurements. The proposed framework entails the appointment of an agency, at the national level, to facilitate the registration of eligible RE generators, issuance of RECs, and maintenance of a record of the procurement of RECs by Obligated Entities. The identified seven key processes can be elaborated as under: Step 1: Electricity Generation and Feeding to the Grid

5 The electricity generated in an RE project is injected into the grid. This electricity is consumed in real time by load prevalent in the system, which in turn is accounted against the consumption by entities which had a contract with that particular RE project. The metering of the quantum of electricity injected into the grid and energy accounting will be done by the State Load Despatch Centre (SLDC). Step 2: Application for issuance of REC The RE Generator will apply to the REC Issuance Registry (i.e. the Central Agency) to issue the RE certificates equivalent to the amount of electricity injected into the grid and as certified by the SLDC. Step 3A: Confirmation of Electricity Generation The Central Agency and SLDC shall establish a procedure for exchange of information about actual electricity generated by the registered RE projects on a regular basis. The SLDC shall submit the report of the energy accounts of RE projects to the Central Agency, as per established procedures, on a regular basis. Step 3B: RE Generator Accreditation and Registration The state agency shall provide its report to the Central Agency for accreditation and for recommending the RE project for registration. The RE projects will have to be accredited with the state agency and will also have to be registered with the Central Agency. Step 4: Creation and Issuance of RECs Referring to the generation report submitted by the SLDC and the state agency, the REC Registry will create and issue an appropriate number of RECs to the concerned RE Generator (Eligible Entity). Step 5: REC Sale by RE Generator (Eligible Entity) Once the RECs are issued to the RE Generator (Eligible Entity), sale/purchase of RECs amongst various RE generators and obligated entities will be undertaken only through the power exchange that is operational under the guidance of the CERC. Step 6: Surrender/Redeeming of RECs The obligated entities can procure the RECs over the exchange platform and need to surrender the RECs to the SERCs to meet their RPS obligation. This will facilitate a convenient and effective mechanism for ensuring RPO compliance by the obligated entities. The REC Registry shall maintain a record of RECs issued and RECs received for redemption, on a regular basis. Step 7: Compliance Reporting It is envisaged that the Central Commission, in consultation with the National level Registry (i.e. Central Agency), may appoint, from time to time, Compliance Auditors to inquire into and report on the compliance of REC Regulations by the person applying for registration, or on the compliance by the renewable energy generators in regard to the eligibility of the Certificates and all matters connected thereto. As depicted from the schematic in the figure above, the State Load Despatch Centres (SLDCs) and the proposed new institutions, such as the National Level REC Registry and Compliance Auditors, will play a pivotal role in the day-to-day operation of the REC mechanism. The success of the proposed REC mechanism will depend on adoption of the precise definition of the roles and responsibilities of these

6 institutions, adoption of the appropriate governance structures, and capacity building to undertake defined roles and responsibilities. Design Features of the REC Mechanism Eligible RE Sources and Technologies Renewable energy sources are: small hydro, wind, biomass, bio-fuel cogeneration, urban or municipal waste, solar including its integration with the combined cycle, and such other sources as recognized and approved by MNRE. Further, there shall be two categories of RECs, one for generation based on solar technology and another for all other (non-solar) RE technologies. Eligible RE Generator (Eligible Entities) Considering the current status of infrastructure availability, it will be appropriate to focus and give priority to grid-interactive RE technologies only and, based on the status after a few years, the off-grid RE technologies may be included. This will enable the development of grid-interactive RE technologies up to commercial maturity and then such mature technologies can easily be transferred to the off-grid RE projects. Therefore, it is proposed that grid connected RE projects, of 250 kw and above, shall be eligible. The FOR Task Force has also concurred with this suggestion and has recommended that grid connected renewable energy generators, of at least 250 kw, should be allowed to participate in the REC Mechanism. Existing RE projects have already been covered under the particular tariff and regulatory regime. Further, the long term contracts for the same are already put in place. Hence, it will not be appropriate to compel existing RE projects to be part of the REC mechanism at this stage. Therefore, it is suggested that existing projects may be allowed to participate in the REC scheme after the expiry of their existing PPA. Accordingly, all grid connected generating companies, which have obtained accreditation from state agencies and which do not have power purchase agreements to sell electricity at a preferential tariff, determined by the appropriate commission, to the distribution licensee of the area in which the generating company is located, at a price not exceeding the pooled cost of power purchase of such distribution licensees, or to any other licensee or open access consumer, at a mutually agreed price, or through the power exchange at market determined prices, shall be eligible for receiving renewable energy certificates. Obligated Entities Entities such as distribution licensees, captive and open access consumers, as may be mandated by State Electricity Regulatory Commission to fulfill the Renewable Purchase Obligation, shall be considered Obligated Entities. REC Issuing Authority A national level REC Registry has been proposed to be created and the CERC may formulate the rules for creation of such a national level entity in accordance with the harmonized policies, to be developed by FOR, for operation of the REC mechanism at the national level. The Central Agency, as directed by the Central Electricity Regulatory Commission, shall issue the REC upon ascertaining the corresponding generation/energy accounting for the accredited RE generating stations. Creation and redemption of RECs In the Indian context, it is proposed that RECs will be issued for the RE generation injected into the grid and duly accounted in the Energy Accounting System, as per the Indian Electricity Grid Code or the State

7 Grid Code. It is envisaged that the RECs shall be issued only in electronic form to avoid issues in paperwork and also in view of the fact that the security/verification protocols, etc., can be easily implemented in cases where RECs are issued in such electronic forms. RECs shall be redeemed when they are presented to the common REC Registry for redemption by the owner of the RECs or when the shelf life of the RECs expires. Whether redeemed specifically or expired due to expiry of life, the owner of the RECs shall be allowed to account these RECs for compliance with the RPO. Sale/Purchase of REC Power exchanges are expected to provide a platform for sale and purchase of RECs. While any trading platform could be used for exchange of RECs, at this point of time there is no clarity about the volume and liquidity in the market. It is envisaged that the CERC, in consultation with the FOR, would undertake the assessment of the market, liquidity requirements, costs involved in setting up of the market, and the necessary fee structure. Accordingly, it is proposed that the sale and purchase of RECs will only be through a power exchange operating under the guidelines issued by the Central Electricity Regulatory Commission. Denomination of RE Certificates The RECs are proposed to be denominated in energy (MWh) terms in order to be consistent with RPO percentage obligations, to be specified in energy terms. With the proposed denomination in energy terms, SERCs can continue to specify the RPO target as a percentage of energy consumption, which can easily be converted into the equivalent number of RECs required for achieving the RPO target. Form of RE Certificate The proposed REC needs to contain all the information, such as: Unique Certificate Number; Name of the Issuing Body; Generator Identity; Type of Generation Technology; Installed Capacity of the Generator; Location of the Generator; and Signature of the Authorized person, in its electronic form. In addition, information about the date of issuance of certificate and validity of the certificate may also be provided on the proposed RE Certificate. Enforcement Mechanism In the event of default i.e. non-fulfillment of RPO, the obligated entity has to deposit an amount determined by the State Electricity Regulatory Commission into a separate fund maintained by the obligated entity itself. This fund will be partly utilized for purchase of the certificate and partly for development of the transmission Infrastructure, upon approval by the respective SERC. Issuance of RE Certificates The eligible entities shall apply to the Central Agency for issuance of certificates within three months after the corresponding generation from eligible renewable energy projects has been injected into the grid. The Certificates shall be issued by the Central Agency within fifteen days from the date of application by the eligible entities on the basis of units of electricity generated and injected into the grid. Pricing of Certificate The CERC shall determine the price band, i.e., the upper limit (forbearance price) and the lower limit (floor price) within which REC transactions can be undertaken over the Power Exchange. This price will be determined by the Central Electricity Regulatory Commission from time to time. The determination of floor price and forbearance price would be guided by several factors, such as variation in cost of generation for different RE sources across states, variation in the pooled power purchase cost of utilities

8 across states, expected renewable energy capacity addition, and renewable purchase obligation targets set by different state commissions. It is important to ensure a threshold level of revenue certainty through the floor price in order to instill confidence amongst investors, lenders, and project developers, at least during the initial stage of introduction. Whereas, the forbearance price is necessary to avoid price volatility, else it may defeat the very purpose of facilitating RPO compliance by Obligated Entities through the REC mechanism. The Regulations also envisage introduction of the floor price and forbearance (or ceiling) price, separately for solar RECs and non-solar RECs Shelf Life of Certificates The RECs shall remain valid for 365 days from the date of issue of such certificates. Timeline for implementation It is proposed to introduce the REC mechanism with effect from April 1, Summary The RE certificates issued to eligible entities shall be a valid instrument for fulfilling the renewable purchase obligation of obligated entities, i.e. distribution licensees, captive consumers, and open access consumers. With the introduction of the REC Mechanism, the RE generators will be eligible to sell their RE certificates, which have been issued to them as per the energy they have injected into the grid, within or outside the state. The REC Mechanism will provide the RE generator a wider platform to sell his certificates to suitable buyers. Similarly, it will also provide obligated entities with multiple options for meeting their RPO targets and complying with their obligations under the RPO regime. One of the important elements for success of the REC scheme would be the commitment, at the state level, to fix RPO targets by keeping in view the current national target of 5% with an increasing trajectory, as envisaged in the National Action Plan on Climate Change (NAPCC), so that there is a sufficient demand for RECs; which in turn would fuel growth of RE capacity addition, irrespective of location. The FOR has initiated a study to develop a framework for setting the RPO trajectory across states. Besides, limitations under the present RPO Regulations in many states, such as lack of an adequate enforcement mechanism, and the scope of Obligated Entities to include open access and captive consumption, also needs to be addressed.

9 For further details, visit and contact at

Renewable Energy. and Renewal Energy Certificates in Indian Context

Renewable Energy. and Renewal Energy Certificates in Indian Context Renewable Energy and Renewal Energy Certificates in Indian Context With the increasing demand of energy and growing depletion of resources for energy generation, a global movement towards production of

More information

DELHI ELECTRICITY REGULATORY COMMISSION

DELHI ELECTRICITY REGULATORY COMMISSION DELHI ELECTRICITY REGULATORY COMMISSION DELHI ELECTRICITY REGULATORY COMMISSION (RENEWABLE PURCHASE OBLIGATION AND RENEWABLE ENERGY CERTIFICATE FRAMEWORK IMPLEMENTATION) REGULATIONS, 2011 No. Dated:. NOTIFICATION

More information

Report On Development of Conceptual Framework For Renewable Energy Certificate Mechanism for India

Report On Development of Conceptual Framework For Renewable Energy Certificate Mechanism for India Report On Development of Conceptual Framework For Renewable Energy Certificate Mechanism for India Submitted to Ministry of New and Renewable Energy (Government of India) Prepared by ABPS Infrastructure

More information

RAJASTHAN ELECTRICITY REGULATORY COMMISSION JAIPUR

RAJASTHAN ELECTRICITY REGULATORY COMMISSION JAIPUR RAJASTHAN ELECTRICITY REGULATORY COMMISSION JAIPUR NOTIFICATION 23 rd December, 2010 No.RERC/Secy/Reg. 82 : In exercise of powers conferred under sections 61, 66, 86(1)(e) and 181 of the Electricity Act,

More information

CENTRAL ELECTRICITY REGULATORY COMMISSION NEW DELHI. No. L-1/12/2010-CERC Dated: 14 th January, 2010 NOTIFICATION

CENTRAL ELECTRICITY REGULATORY COMMISSION NEW DELHI. No. L-1/12/2010-CERC Dated: 14 th January, 2010 NOTIFICATION CENTRAL ELECTRICITY REGULATORY COMMISSION NEW DELHI No. L-1/12/2010-CERC Dated: 14 th January, 2010 NOTIFICATION In exercise of powers conferred under sub-section (1) of Section 178 and Section 66 read

More information

Renewable Energy Certificate Mechanism

Renewable Energy Certificate Mechanism Opportunities in Financing Renewable Energy Projects focusing on FiT and RECs Balawant Joshi Director, balawant@gmail.com, balawant.joshi@abpsinfra.com In this presentation.. Investment Potential for Renewable

More information

DRAFT REGULATIONS FOR ANDHRA PRADESH ELECTRICITY REGULATORY COMMISSION UNDER SECTION 86(1)(e) OF THE ACT NOTIFICATION

DRAFT REGULATIONS FOR ANDHRA PRADESH ELECTRICITY REGULATORY COMMISSION UNDER SECTION 86(1)(e) OF THE ACT NOTIFICATION DRAFT REGULATIONS FOR ANDHRA PRADESH ELECTRICITY REGULATORY COMMISSION UNDER SECTION 86(1)(e) OF THE ACT No. Dated: -12-2011 NOTIFICATION In exercise of powers conferred under sections 61, 66, 86(1)(e)

More information

Renewable Energy Certificate Mechanism in India

Renewable Energy Certificate Mechanism in India 16th NATIONAL POWER SYSTEMS CONFERENCE, 15th-17th DECEMBER, 2010 92 Renewable Energy Certificate Mechanism in India S.K.Soonee, CEO*, Minaxi Garg, DGM #, and Satya Prakash, Engineer # Abstract India has

More information

DRAFT MODEL REGULATIONS for STATE ELECTRICITY REGULATORY COMMISSION UNDER SETION 86 (1) (e) OF THE ACT. No. Dated: October, 2009 NOTIFICATION (DRAFT)

DRAFT MODEL REGULATIONS for STATE ELECTRICITY REGULATORY COMMISSION UNDER SETION 86 (1) (e) OF THE ACT. No. Dated: October, 2009 NOTIFICATION (DRAFT) DRAFT MODEL REGULATIONS for STATE ELECTRICITY REGULATORY COMMISSION UNDER SETION 86 (1) (e) OF THE ACT No. Dated: October, 2009 NOTIFICATION (DRAFT) In exercise of powers conferred under sections 61, 66,

More information

ANDHRA PRADESH ELECTRICITY REGULATORY COMMISSION

ANDHRA PRADESH ELECTRICITY REGULATORY COMMISSION ANDHRA PRADESH ELECTRICITY REGULATORY COMMISSION RENEWABLE POWER PURCHASE OBLIGATION (COMPLIANCE BY PURCHASE OF RENEWABLE ENERGY / RENEWABLE ENERGY CERTIFICATES) REGULATIONS, 2012 Regulation No. 1 of 2012

More information

Analysis of state-wise RPO Regulation across India

Analysis of state-wise RPO Regulation across India The Renewable Purchase Obligations (RPO) has been the major driving force in India to promote the renewable energy sector. But the State Electricity Regulatory Commissions (SERCs) have defined their respective

More information

PROCEDURE FOR ISSUANCE OF RENEWABLE ENERGY CERTIFICATE TO THE ELIGIBLE ENTITY BY CENTRAL AGENCY

PROCEDURE FOR ISSUANCE OF RENEWABLE ENERGY CERTIFICATE TO THE ELIGIBLE ENTITY BY CENTRAL AGENCY PROCEDURE FOR ISSUANCE OF RENEWABLE ENERGY CERTIFICATE TO THE ELIGIBLE ENTITY BY CENTRAL AGENCY 1. OBJECTIVE 1.1. This procedure shall provide guidance to the entities to implement Renewable Energy Certificate

More information

DRAFT KERALA STATE ELECTRICITY REGULATORY COMMISSION, NOTICE. No. 442/CT/2014/KSERC Dated, Thiruvananthapuram 31 st March, 2015

DRAFT KERALA STATE ELECTRICITY REGULATORY COMMISSION, NOTICE. No. 442/CT/2014/KSERC Dated, Thiruvananthapuram 31 st March, 2015 DRAFT 31.3.2015 KERALA STATE ELECTRICITY REGULATORY COMMISSION, NOTICE 442/CT/2014/KSERC Dated, Thiruvananthapuram 31 st March, 2015 The Kerala State Electricity Regulatory Commission hereby publishes

More information

REPORT ON DEVELOPMENT OF REC FRAMEWORK IN INDIA PRICING OF RENEWABLE ENERGY AND RENEWABLE ENERGY CERTIFICATES

REPORT ON DEVELOPMENT OF REC FRAMEWORK IN INDIA PRICING OF RENEWABLE ENERGY AND RENEWABLE ENERGY CERTIFICATES 1 REC MECHANISM REPORT ON DEVELOPMENT OF REC FRAMEWORK IN INDIA PRICING OF RENEWABLE ENERGY AND RENEWABLE ENERGY CERTIFICATES Submitted by : Anand Parmar 2 REC MECHANISM Introduction: India has sustained

More information

Renewable Purchase Obligation (RPO) / Renewable Energy Certificates (REC) Advisory and Trading

Renewable Purchase Obligation (RPO) / Renewable Energy Certificates (REC) Advisory and Trading Renewable Purchase Obligation (RPO) / Renewable Energy Certificates (REC) Advisory and Trading Target Clients v Renewable Energy Generators in India v RPO mandated entities in India v Investors seeking

More information

In Focus. India s Renewable Energy Certificate Market

In Focus. India s Renewable Energy Certificate Market 2011 1 India s Renewable Energy Certificate Market In Focus India s Renewable Energy Certificate Market Carbon Credit Capital LLC 561 Broadway New York, NY 10012 Tel: 212-925-5697 (Main Office) www.carboncreditcapital.com

More information

TAMIL NADU ELECTRICITY REGULATORY COMMISSION. Notification No. TNERC/RPO/ 19/1 dated 07-12-2010

TAMIL NADU ELECTRICITY REGULATORY COMMISSION. Notification No. TNERC/RPO/ 19/1 dated 07-12-2010 TAMIL NADU ELECTRICITY REGULATORY COMMISSION Notification No. TNERC/RPO/ 19/1 dated 07-12-2010 In exercise of powers conferred by section 181 of the Electricity Act, 2003 (Central Act 36 of 2003) read

More information

S. No. Year Obligation expressed as percentage of energy consumption (%) 1 2011-12 6.00 2 2012-13 7.10 3 2013-14 8.20

S. No. Year Obligation expressed as percentage of energy consumption (%) 1 2011-12 6.00 2 2012-13 7.10 3 2013-14 8.20 Background paper for prescribing Renewable Purchase Obligation (RPO) for Captive consumption of CPP & open access consumers in the State for the period ending March, 2017 and related amendment in regulations:

More information

Renewable Energy Certificate (REC) - A Key Step for the Growth of Renewable Energy in India

Renewable Energy Certificate (REC) - A Key Step for the Growth of Renewable Energy in India Brochure More information from http://www.researchandmarkets.com/reports/1532074/ Renewable Energy Certificate (REC) - A Key Step for the Growth of Renewable Energy in India Description: Renewable Energy

More information

Karnataka Electricity Regulatory Commission. Discussion note on

Karnataka Electricity Regulatory Commission. Discussion note on Karnataka Electricity Regulatory Commission Discussion note on Draft KERC (Forecasting, Scheduling, Deviation settlement and related matters for Wind and Solar Generation sources) Regulations, 2015. 1.0.

More information

PROCEDURE FOR ACCREDITATION OF RENEWABLE ENERGY GENERATION PROJECT FOR RENEWABLE ENERGY CERTIFICATE BY STATE AGENCY

PROCEDURE FOR ACCREDITATION OF RENEWABLE ENERGY GENERATION PROJECT FOR RENEWABLE ENERGY CERTIFICATE BY STATE AGENCY PROCEDURE FOR ACCREDITATION OF RENEWABLE ENERGY GENERATION PROJECT FOR RENEWABLE ENERGY CERTIFICATE BY STATE AGENCY 1 Objective (1) This procedure shall provide guidance to the entities to implement Renewable

More information

Tamil Nadu WiNd ENErgy ProfilE

Tamil Nadu WiNd ENErgy ProfilE Tamil Nadu WiNd ENErgy ProfilE Wind energy in Tamil Nadu has witnessed tremendous growth propelling the State to the number one position in India in terms of renewables. However the challenge that remains

More information

KERALA STATE ELECTRICITY REGULATORY COMMISSION

KERALA STATE ELECTRICITY REGULATORY COMMISSION KERALA STATE ELECTRICITY REGULATORY COMMISSION Notification No. 2096/KSERC/CT/2014 Dated, Thiruvananthapuram 10 th June 2014. In exercise of the powers conferred under sections 66, 86 (1) (e) and 181 of

More information

PROCEDURE FOR ACCREDITATION OF RENEWABLE ENERGY GENERATION PROJECT FOR RENEWABLE ENERGY CERTIFICATE BY STATE AGENCY

PROCEDURE FOR ACCREDITATION OF RENEWABLE ENERGY GENERATION PROJECT FOR RENEWABLE ENERGY CERTIFICATE BY STATE AGENCY PROCEDURE FOR ACCREDITATION OF RENEWABLE ENERGY GENERATION PROJECT FOR RENEWABLE ENERGY CERTIFICATE BY STATE AGENCY 1. OBJECTIVE : 1.1. This procedure shall provide guidance to the entities to implement

More information

KERALA STATE ELECTRICITY REGULATORY COMMISSION THIRUVANANTHAPURAM IN THE MATTER OF

KERALA STATE ELECTRICITY REGULATORY COMMISSION THIRUVANANTHAPURAM IN THE MATTER OF KERALA STATE ELECTRICITY REGULATORY COMMISSION THIRUVANANTHAPURAM PRESENT: Shri. K.J.Mathew, Chairman Shri. C. Abdulla, Member Shri. M.P.Aiyappan, Member Petition No. CT/SOLAR JNNSM/KSERC/2010 August 4,

More information

Emerging market for Green Certificates

Emerging market for Green Certificates Emerging market for Green Certificates Dr Marianne OSTERKORN, Director of REEEP Dr Xavier LEMAIRE, SERN/REEEP CONTENT 1. What is a certificate system? 2. How certificates system works 3. What are the benefits

More information

Model Renewable Energy Wheeling Agreement under Renewable Energy Certificate (REC) scheme

Model Renewable Energy Wheeling Agreement under Renewable Energy Certificate (REC) scheme Model Renewable Energy Wheeling Agreement under Renewable Energy Certificate (REC) scheme This agreement made at on this day of two thousand between M/s. (Renewable Energy Generator name and address) hereinafter

More information

MARKET BASED INSTRUMENTS: AUSTRALIA S EXPERIENCE WITH TRADING RENEWABLE ENERGY CERTIFICATES

MARKET BASED INSTRUMENTS: AUSTRALIA S EXPERIENCE WITH TRADING RENEWABLE ENERGY CERTIFICATES Workshop on Good Practices in Policies and Measures, 8-10 October 2001, Copenhagen MARKET BASED INSTRUMENTS: AUSTRALIA S EXPERIENCE WITH TRADING RENEWABLE ENERGY CERTIFICATES Gwen Andrews Australia Chief

More information

Concern about climate change and concerted international action to reduce greenhouse gas emissions are powerful new drivers for renewable energy.

Concern about climate change and concerted international action to reduce greenhouse gas emissions are powerful new drivers for renewable energy. Title: AUSTRALIA S RENEWABLE ENERGY CERTIFICATE SYSTEM Authors: David Rossiter and Karla Wass 1 Office of the Renewable Energy Regulator Kings Avenue, Barton ACT 2600, Australia GPO Box 621, Canberra ACT

More information

CERC (Terms and Conditions for Tariff determination from Renewable Energy Sources) Regulations, 2009

CERC (Terms and Conditions for Tariff determination from Renewable Energy Sources) Regulations, 2009 CERC (Terms and Conditions for Tariff determination from Renewable Statement of Objects and Reasons 1. Introduction 1.1 The Electricity Act, 2003 (hereinafter referred to as the Act ) under Section 79

More information

Abstract. Key words: REC Mechanism, ROC-UK, Policy- Regulatory Intervention, Solar and Wind,

Abstract. Key words: REC Mechanism, ROC-UK, Policy- Regulatory Intervention, Solar and Wind, Promotion of Wind and Solar Energy through Renewable Energy Certificate System: Lessons from Renewable Obligation Certificate, United Kingdom experience for India Sushanta K Chatterjee a1, 2 Prasoom Dwivedi

More information

Solar City Master Plan - Executive Summary

Solar City Master Plan - Executive Summary Solar City Master Plan - Executive Summary Meeting the growing energy demand is one of the biggest challenges that the world is facing today. Rising population and depleting fossil fuel resources are compelling

More information

PUNJAB STATE ELECTRICITY REGULATORY COMMISSION SCO 220-221, SECTOR 34-A, CHANDIGARH. Petition No.26 of 2010 (Suo Motu) Date of Order: 7.7.

PUNJAB STATE ELECTRICITY REGULATORY COMMISSION SCO 220-221, SECTOR 34-A, CHANDIGARH. Petition No.26 of 2010 (Suo Motu) Date of Order: 7.7. PUNJAB STATE ELECTRICITY REGULATORY COMMISSION SCO 220-221, SECTOR 34-A, CHANDIGARH Petition No.26 of 2010 (Suo Motu) Date of Order: 7.7.2010 In the matter of : Determination of generic levellised generation

More information

MINISTRY OF ENERGY FEED-IN-TARIFFS POLICY ON WIND, BIOMASS, SMALL-HYDRO, GEOTHERMAL, BIOGAS AND SOLAR RESOURCE GENERATED ELECTRICITY

MINISTRY OF ENERGY FEED-IN-TARIFFS POLICY ON WIND, BIOMASS, SMALL-HYDRO, GEOTHERMAL, BIOGAS AND SOLAR RESOURCE GENERATED ELECTRICITY MINISTRY OF ENERGY FEED-IN-TARIFFS POLICY ON WIND, BIOMASS, SMALL-HYDRO, GEOTHERMAL, BIOGAS AND SOLAR RESOURCE GENERATED ELECTRICITY Initial Issue: March 2008 1 st Revision: January 2010 2 nd Revision:

More information

Indian Experiences on Promoting Renewable Energy DR SUSHANTA K CHATTERJEE JOINT CHIEF (REGULATORY AFFAIRS) CENTRAL ELECTRICITY REGULATORY COMMISSION

Indian Experiences on Promoting Renewable Energy DR SUSHANTA K CHATTERJEE JOINT CHIEF (REGULATORY AFFAIRS) CENTRAL ELECTRICITY REGULATORY COMMISSION Indian Experiences on Promoting Renewable Energy DR SUSHANTA K CHATTERJEE JOINT CHIEF (REGULATORY AFFAIRS) CENTRAL ELECTRICITY REGULATORY COMMISSION Introduction Clean energy promotion in India Focus on

More information

REC QUESTIONS & ANSWERS

REC QUESTIONS & ANSWERS REC QUESTIONS & ANSWERS Q: What is a REC? A: A Renewable Energy Certificate (REC), also known as a Green Tag, Renewable Energy Credit, or Tradable Renewable Energy Certificate (TREC), is a tradable environmental

More information

G.O.MS.No. 8 Dated 12.02.2015 Read the following:-

G.O.MS.No. 8 Dated 12.02.2015 Read the following:- GOVERNMENT OF ANDHRA PRADESH ABSTRACT ENERGY, INFRASTRUCTURE & INVESTMENT DEPARTMENT - Development of Solar Power in Andhra Pradesh Andhra Pradesh Solar Power Policy, 2015 Orders Issued. ------------------------------------------------------------------------------------------------------------

More information

Comments on Draft Deviation Settlement Mechanism and related matters Regulations, 2013

Comments on Draft Deviation Settlement Mechanism and related matters Regulations, 2013 Comments on Draft Deviation Settlement Mechanism and related matters Regulations, 2013 Dr. Anoop Singh Associate Professor Department of Industrial and Management Engineering, Indian Institute of Technology

More information

F. No. 66/185/2016 -WE Ministry of New & Renewable Energy

F. No. 66/185/2016 -WE Ministry of New & Renewable Energy F. No. 66/185/2016 -WE Ministry of New & Renewable Energy India has set an ambitious target of reaching 175 GW of installed capacity from renewable energy sources including 100 GW from solar and 60 GW

More information

Green Power Accounting Workshop: Concept Note For discussion during Green Power Accounting Workshop in Mexico City, May 13th 2011

Green Power Accounting Workshop: Concept Note For discussion during Green Power Accounting Workshop in Mexico City, May 13th 2011 Introduction As more companies and government organizations prepare greenhouse gas (GHG) inventories that reflect the emissions directly and indirectly associated with their operations, they increasingly

More information

Financing Energy Efficiency and Renewable Energy through the India Renewable Energy Development Agency

Financing Energy Efficiency and Renewable Energy through the India Renewable Energy Development Agency RENEWABLE ENERGY INDUSTRIAL ENERGY EFFICIENCY BUILDING ENERGY EFFICIENCY Financing Energy Efficiency and Renewable Energy through the India Renewable Energy Development Agency A RANGE OF FINANCIAL SUPPORT

More information

Solar Power Policy Uttar Pradesh 2012 Suggestions to be sent to : dirupneda@rediffmail.com ho_nmk@rediffmail.com

Solar Power Policy Uttar Pradesh 2012 Suggestions to be sent to : dirupneda@rediffmail.com ho_nmk@rediffmail.com Draft ver2 Solar Power Policy Uttar Pradesh 2012 Suggestions to be sent to : dirupneda@rediffmail.com ho_nmk@rediffmail.com 1 TABLE OF CONTENTS S.No Contents Page No 1. PREAMBLE 3 2. OBJECTIVES 3 3. OPERATIVE

More information

Uttar Pradesh Rooftop Solar Photovoltaic Power Plant Policy, 2014

Uttar Pradesh Rooftop Solar Photovoltaic Power Plant Policy, 2014 Uttar Pradesh Rooftop Solar Photovoltaic Power Plant Policy, 2014 Table of Contents 1- PREAMBLE - 1 2- OBJECTIVES - 1 3- OPERATIVE PERIOD - 1 4- IMPLEMENTATION PLAN - 2 5- ELIGIBLE ENTITIES - 2 6- TARGETS

More information

THE INDIAN MARKET FOR RENEWABLE ENERGY THE 100 GW SOLAR INITIATIVE

THE INDIAN MARKET FOR RENEWABLE ENERGY THE 100 GW SOLAR INITIATIVE THE INDIAN MARKET FOR RENEWABLE ENERGY THE 100 GW SOLAR INITIATIVE PRESENTATION BY : MR KESHAV PRASAD MEMBER, DELEGATION OF THE CONFEDERATION OF INDIAN INDUSTRY (CII) & CHIEF OPERATING OFFICER, IL&FS ENERGY

More information

CENTRAL ELECTRICITY REGULATORY COMMISSION NEW DELHI NOTIFICATION. No. L-1/(3)/2009-CERC Dated the 7 th August 2009

CENTRAL ELECTRICITY REGULATORY COMMISSION NEW DELHI NOTIFICATION. No. L-1/(3)/2009-CERC Dated the 7 th August 2009 CENTRAL ELECTRICITY REGULATORY COMMISSION NEW DELHI NOTIFICATION No. L-1/(3)/2009-CERC Dated the 7 th August 2009 In exercise of powers conferred by section 178 of the Electricity Act, 2003 and all other

More information

Electricity Generation from Renewable Energy in Sri Lanka: Future Directions

Electricity Generation from Renewable Energy in Sri Lanka: Future Directions Electricity Generation from Renewable Energy in Sri Lanka: Future Directions Presented by M.M.C. Ferdinando, Secretary, Ministry of Power and Energy R.J. Gunawardana, Additional General Manager (Transmission),

More information

Solar Power Plants FAQs

Solar Power Plants FAQs Solar Power Plants FAQs Solar Power industry in India is gaining more and more prominence with each passing day. The domestic/off-grid industry is picking up speed too. Owing to the queries we are receiving

More information

THE GOVERNMENT THE FEDERAL REPUBLIC OF NIGERIA

THE GOVERNMENT THE FEDERAL REPUBLIC OF NIGERIA THE GOVERNMENT OF THE FEDERAL REPUBLIC OF NIGERIA ----------------------------------------------------------------------- THE NATIONAL GAS SUPPLY AND PRICING POLICY -----------------------------------------------------------------------

More information

KERALA STATE ELECTRICITY REGULATORY COMMISSION

KERALA STATE ELECTRICITY REGULATORY COMMISSION KERALA STATE ELECTRICITY REGULATORY COMMISSION Dated 24 th January 2014 NOTICE Notice is hereby given that Kerala State Electricity Regulatory Commission has published the Draft Kerala State Electricity

More information

Opportunities for the Georgian Hydropower industry to benefit from Directive 2009/28EC of the European Parliament

Opportunities for the Georgian Hydropower industry to benefit from Directive 2009/28EC of the European Parliament Promotion hidroenergetikasi Project investiciebis (HIPP) Opportunities for the Georgian Hydropower industry to benefit from Directive 2009/28EC of the European Parliament What Europe wants to do Comply

More information

Government of Jharkhand Department of Energy. Notification

Government of Jharkhand Department of Energy. Notification Draft Jharkhand State Solar Power Policy 2015 Government of Jharkhand Department of Energy Notification No. ------ Date:./2015 Preamble: In order to reduce the dependence on fossil fuel based generation,

More information

Existing Wind Power Policies and Incentives

Existing Wind Power Policies and Incentives Existing Wind Power Policies and Incentives Consultation on National Wind Energy Mission January 9, 2014 New Delhi Wind Power Progress (in MW) Potential (at 80 m) : 1,02,000 Achievement so far : 20,150

More information

Procedure for Nominating Renewable Energy Credit Offsets

Procedure for Nominating Renewable Energy Credit Offsets Procedure for Nominating Renewable Energy Credit Offsets A. Nominations for renewable energy credit offsets shall be made jointly by the generating facility owner and the intended recipients of the offsets.

More information

Environment and energy briefing from Burges Salmon published in the March 2014 issue of The In-House Lawyer:

Environment and energy briefing from Burges Salmon published in the March 2014 issue of The In-House Lawyer: Environment and energy briefing from Burges Salmon published in the March 2014 issue of The In-House Lawyer: Electricity market reform: an update on contracts for difference Electricity market reform:

More information

Economics, Regulation, and Implementation Strategy for Renewable Energy Certificates in India

Economics, Regulation, and Implementation Strategy for Renewable Energy Certificates in India 3 Economics, Regulation, and Implementation Strategy for Renewable Energy Certificates in India Anoop Singh Introduction Renewable energy sources (RES) have been promoted through a number of policies including

More information

ELECTRICITY MARKET ACT

ELECTRICITY MARKET ACT 1 NB: Unofficial translation Ministry of Trade and Industry, Finland ELECTRICITY MARKET ACT (386/1995; amendments up to 1172/2004 included) In accordance with a decision by Parliament, the following is

More information

Application for accreditation of a power station

Application for accreditation of a power station Application for accreditation of a power station FORM CER-RET-PS V6.1 13/07/2015 under the Renewable Energy (Electricity) Act 2000 Office use only minated person for the power station Power station name

More information

Methodology for Solar Power Projects

Methodology for Solar Power Projects Annexure E Methodology for Solar Power Projects This methodology is applicable to the solar power projects included in the composite policy for new and renewable (non-conventional energy sources) power

More information

Electricity in Egypt

Electricity in Egypt T: (+20) 2 3760 4592 F: (+20) 2 3760 4593 A: 16 Hussein Wassef Street, Messaha Square Dokki, Giza, Egypt 12311 www.ide.com.eg Electricity in Egypt Policy and Regulatory Reform November 2015 Electricity

More information

Renewable Energy Certificates

Renewable Energy Certificates EPA s Green Power Partnership Renewable Energy Certificates Last updated: July 2008 U.S. Environmental Protection Agency 1200 Pennsylvania Ave, NW (Mail Code 6202J) Washington, DC 20460 www.epa.gov/greenpower

More information

Consultative Paper on Comprehensive Tariff Order on Solar Power. (Comments/Suggestions are invited on or before 31.08.2013)

Consultative Paper on Comprehensive Tariff Order on Solar Power. (Comments/Suggestions are invited on or before 31.08.2013) TAMIL NADU ELECTRICITY REGULATORY COMMISSION Consultative Paper on Comprehensive Tariff Order on Solar Power (Comments/Suggestions are invited on or before 31.08.2013) 1. Introduction 1.1 The importance

More information

To assist you with getting started with the SRECs program, find enclosed a copy of the following:

To assist you with getting started with the SRECs program, find enclosed a copy of the following: [Current Date] Dear New Jersey Solar System Owner: New Jersey s Renewable Portfolio Standard (RPS) requires electricity suppliers to secure a portion of their electricity from solar facilities connected

More information

DRAFT OF THE GOA STATE GOVERNMENT POLICY TOWARDS RENEWABLE, SOLAR ENERGY AND ENERGY CONSERVATION- GOA 2014

DRAFT OF THE GOA STATE GOVERNMENT POLICY TOWARDS RENEWABLE, SOLAR ENERGY AND ENERGY CONSERVATION- GOA 2014 DRAFT OF THE GOA STATE GOVERNMENT POLICY TOWARDS RENEWABLE, SOLAR ENERGY AND ENERGY CONSERVATION- GOA 2014 Drafted by Goa Energy Development Agency (GEDA) team for the approval by the State Govt. of Goa

More information

WORKING PAPER. India: Implementing incentives focused on energy. Anuradha R.V., Sumiti Yadava (Clarus Law Associates)

WORKING PAPER. India: Implementing incentives focused on energy. Anuradha R.V., Sumiti Yadava (Clarus Law Associates) WORKING PAPER N 06/12 april 2012 CliMate India: Implementing incentives focused on energy Anuradha R.V., Sumiti Yadava (Clarus Law Associates) www.iddri.org Challenges for climate policy and governance

More information

INDONESIA S COUNTRY REPORT ENCOURAGING CLEAN ENERGY INITIATIVE

INDONESIA S COUNTRY REPORT ENCOURAGING CLEAN ENERGY INITIATIVE DEWAN PERWAKILAN RAKYAT REPUBLIK INDONESIA INDONESIA S COUNTRY REPORT ENCOURAGING CLEAN ENERGY INITIATIVE As part of the international community, Indonesia shares its concern on the environment and development

More information

I M P L E M E N TAT I O N O F T H E R E N E WA B L E E N E R GY C E R T I F I CAT E ( R EC) F RA M E WO R K I N I N D I A

I M P L E M E N TAT I O N O F T H E R E N E WA B L E E N E R GY C E R T I F I CAT E ( R EC) F RA M E WO R K I N I N D I A I M P L E M E N TAT I O N O F T H E R E N E WA B L E E N E R GY C E R T I F I CAT E ( R EC) F RA M E WO R K I N I N D I A S H O R T-T E R M S O L U T I O N S ACKNOWLEDGEMENTS We acknowledge the support

More information

Draft Jharkhand State Solar Power Policy 2015

Draft Jharkhand State Solar Power Policy 2015 Draft Jharkhand State Solar Power Policy 2015 Government of Jharkhand Department of Energy Notification No. ------ Date:./2015 Preamble: In order to reduce the dependence on fossil fuel based generation,

More information

DRAFT ORDER (SUO-MOTU)

DRAFT ORDER (SUO-MOTU) Before the MAHARASHTRA ELECTRICITY REGULATORY COMMISSION 13 th Floor, Centre No.1, World Trade Centre, Cuffe Parade, Mumbai- 400 005 Tel: 22163964/65/69 Fax: 22163976 E-mail: mercindia@mercindia.org.in

More information

National Electricity Policy 03-Feb-2005

National Electricity Policy 03-Feb-2005 National Electricity Policy 03-Feb-2005 Under the provisions of section 3(1) of the Electricity Act, 2003, the Central Government is required to prepare the National Electricity Policy for development

More information

AN OVERVIEW OF INDIA S ENERGY SECTOR

AN OVERVIEW OF INDIA S ENERGY SECTOR AN OVERVIEW OF INDIA S ENERGY SECTOR India is the world s eleventh largest economy by nominal GDP and fourth largest by Purchasing Power Parity. The eleventh five year plan of India s Planning Commission

More information

Electricity Exchanges in South Asia The Indian Energy Exchange Model

Electricity Exchanges in South Asia The Indian Energy Exchange Model Electricity Exchanges in South Asia The Indian Energy Exchange Model 18 Mar 14 Rajesh K Mediratta Director (BD) rajesh.mediratta@iexindia.com www.iexindia.com In this presentation Overview - Indian Market

More information

Regulatory Briefing. Capital Markets Day. 17 October 2013

Regulatory Briefing. Capital Markets Day. 17 October 2013 Regulatory Briefing Capital Markets Day 17 October 2013 Agenda Andrew Koss Director of Strategy Damien Speight Head Trader Renewables Obligation Contracts for Difference Levy Control Framework Capacity

More information

Delhi Solar Energy Policy, 2015

Delhi Solar Energy Policy, 2015 DRAFT VERSION FOR PUBLIC COMMENT Delhi Solar Energy Policy, 2015 GOVERNMENT OF NCT OF DELHI DELHI SECTRETARIAT, I.P. ESTATE, NEW DELHI- 110002 10 September 2015 NOTIFICATION The Government of NCT of Delhi

More information

REQUEST FOR PROPOSALS

REQUEST FOR PROPOSALS REQUEST FOR PROPOSALS RENEWABLE ENERGY CERTIFICATES SOURCED FROM RENEWABLE RESOURCES CERTIFIED BY THE CALIFORNIA ENERGY COMMISSION February 18, 2015 1.0 Introduction of Pittsburg Power Company dba Island

More information

Support Information for Solar Power Generation Regulation of JERC & Suggestive Power Purchase Agreement.

Support Information for Solar Power Generation Regulation of JERC & Suggestive Power Purchase Agreement. Support Information for Solar Power Generation Regulation of JERC & Suggestive Power Purchase Agreement. Technical and interconnection requirements The Project Developers shall adhere to the National &

More information

QUALIFICATIONS REQUIREMENTS FOR INVESTORS TO PARTICIPATE IN FEED-IN TARIFF SCHEME

QUALIFICATIONS REQUIREMENTS FOR INVESTORS TO PARTICIPATE IN FEED-IN TARIFF SCHEME Ministry of Electricity and Renewable Energy Egyptian Electricity Holding Company Egyptian Electricity Transmission Company QUALIFICATIONS REQUIREMENTS FOR INVESTORS TO PARTICIPATE IN FEED-IN TARIFF SCHEME

More information

Greenhouse Gas Offsets and Renewable Energy Certificates: Distinct Commodities in an Evolving Market The Climate Trust

Greenhouse Gas Offsets and Renewable Energy Certificates: Distinct Commodities in an Evolving Market The Climate Trust Greenhouse Gas Offsets and Renewable Energy Certificates: Distinct Commodities in an Evolving Market The Climate Trust Introduction The framework for future climate policy is emerging in the United States

More information

Methodology for Merit Order Dispatch. Version 1.0

Methodology for Merit Order Dispatch. Version 1.0 Methodology for Merit Order Dispatch Version 1.0 25 th April 2011 TABLE OF CONTENTS 1. OBJECTIVES... 1 2. ROADMAP FOR IMPLEMENTATION... 1 3. DEFINITIONS... 3 4. OPERATIONS PLANNING... 3 4.1. General Considerations...

More information

Draft Solar Energy Purchase Agreement (EPA) subject to approval by TNERC

Draft Solar Energy Purchase Agreement (EPA) subject to approval by TNERC Draft Solar Energy Purchase Agreement (EPA) subject to approval by TNERC This agreement made at on this day of Two thousand between M/s. (Solar Power Generator name and address) hereinafter called the

More information

Statutes in translation Please note that this translations are not official translations. The translation is furnished for information purposes only

Statutes in translation Please note that this translations are not official translations. The translation is furnished for information purposes only Statutes in translation Please note that this translations are not official translations. The translation is furnished for information purposes only and the documents are not legal documents. The texts

More information

Success in Renewables. Glossary of Terms Investment and Renewables

Success in Renewables. Glossary of Terms Investment and Renewables Success in Renewables Glossary of Terms Investment and Renewables If you re new to renewable energy or investment, then it can be a minefield of new language and terminology. What seems totally normal

More information

Certificate of Origin Renewable Energy

Certificate of Origin Renewable Energy Energy Regulatory Office Certificate of Origin Renewable Energy Partnership Activity: Energy Regulatory Office & Illinois Commerce Commission National Association of Regulatory Utility Commissioners Legal

More information

THE GREEN ELECTRCITY MARKET IN DENMARK: QUOTAS, CERTIFICATES AND INTERNATIONAL TRADE. Ole Odgaard Denmark

THE GREEN ELECTRCITY MARKET IN DENMARK: QUOTAS, CERTIFICATES AND INTERNATIONAL TRADE. Ole Odgaard Denmark Workshop on Best Practices in Policies and Measures, 11 13 April 2000, Copenhagen THE GREEN ELECTRCITY MARKET IN DENMARK: QUOTAS, CERTIFICATES AND INTERNATIONAL TRADE Ole Odgaard Denmark Abstract: The

More information

Staff Paper. April 2013

Staff Paper. April 2013 Page 1 of 17 Staff Paper Introduction of Ancillary Services in Indiann Electricity Market April 2013 CENTRAL ELECTRICITY REGULATORY COMMISSION NEW DELHI Page 2 of 17 Introduction of Ancillary Services

More information

3. Buying non-accredited green power from electricity retailer

3. Buying non-accredited green power from electricity retailer ATTACHMENT 1 Understanding Australia s Renewable Energy Market In Australia electricity customers have four options for neutralising the greenhouse emissions associated with their electricity use. These

More information

Comments of the Edison Electric Institute Net Benefits and Costs of Distributed Solar Energy and Innovative Solar Deployment Models, DOE-EERE

Comments of the Edison Electric Institute Net Benefits and Costs of Distributed Solar Energy and Innovative Solar Deployment Models, DOE-EERE Comments of the Edison Electric Institute Net Benefits and Costs of Distributed Solar Energy and Innovative Solar Deployment Models, DOE-EERE Category 2 - Innovative Solar Deployment Models Edward H. Comer,

More information

Renewable Energy Feed-in Tariff Projects Regulations

Renewable Energy Feed-in Tariff Projects Regulations for Consumer Protection and Renewable Energy Feed-in Tariff Projects Regulations Oct. 2014 EgyptERA s crew has prepared this document so as to answer all the questions related to the renewbales supporting

More information

The Policy and Market Environment for Renewable Energy Development

The Policy and Market Environment for Renewable Energy Development Gunnar Birgisson of Bracewell & Giuliani LLP Speaker 15: 1 The Policy and Market Environment for Renewable Energy Development Gunnar Birgisson March 2008 An Era for Renewables? Growth and Interest: Wind

More information

Renewable Energy Certificates & Green Power Certification. Dr. Jan Hamrin Center for Resource Solutions San Francisco, CA

Renewable Energy Certificates & Green Power Certification. Dr. Jan Hamrin Center for Resource Solutions San Francisco, CA Renewable Energy Certificates & Green Power Certification Dr. Jan Hamrin Center for Resource Solutions San Francisco, CA The Same by Any Other Name Tradable Renewable Energy Certificates Renewable Certificates

More information

Renewable Electricity and Liberalised Markets REALM. JOULE-III Project JOR3-CT98-0290 GREECE ACTION PLAN. By ICCS / NTUA K. Delkis

Renewable Electricity and Liberalised Markets REALM. JOULE-III Project JOR3-CT98-0290 GREECE ACTION PLAN. By ICCS / NTUA K. Delkis Renewable Electricity and Liberalised Markets REALM JOULE-III Project JOR3-CT98-0290 GREECE ACTION PLAN By ICCS / NTUA K. Delkis October 1999 INTRODUCTION AND BACKGROUND Background to Renewable Energy

More information

CENTRAL ELECTRICITY REGULATORY COMMISSION NEW DELHI. Petition No. 266/SM/2012

CENTRAL ELECTRICITY REGULATORY COMMISSION NEW DELHI. Petition No. 266/SM/2012 CENTRAL ELECTRICITY REGULATORY COMMISSION NEW DELHI Petition No. 266/SM/2012 Coram: Dr. Pramod Deo, Chairperson Shri S. Jayaraman, Member Shri V.S. Verma, Member Shri M. Deena Dayalan, Member Date of Hearing:

More information

RENEWABLE ENERGY DEVELOPMENT IN LITHUANIA ACHIEVEMENTS AND DRAWBACKS

RENEWABLE ENERGY DEVELOPMENT IN LITHUANIA ACHIEVEMENTS AND DRAWBACKS RENEWABLE ENERGY DEVELOPMENT IN LITHUANIA ACHIEVEMENTS AND DRAWBACKS Ieva Kuodė Ministry of Energy of the Republic of Lithuania SOLINVEST 2015-06-02 RES TARGETS BY 2020 23% the share of energy from renewable

More information

all that you want to know About Rajasthan Solar Energy

all that you want to know About Rajasthan Solar Energy all that you want to know bout Rajasthan Solar Energy Policy, 2014 General 01 Registration Land Timelines Fee & Charges 06 08 11 13 all that you want to know bout Rajasthan Solar Energy Policy, 2014 Rajasthan

More information

Japan. Nagahide Sato and Sadayuki Matsudaira. Nishimura & Asahi

Japan. Nagahide Sato and Sadayuki Matsudaira. Nishimura & Asahi Nagahide Sato and Sadayuki Matsudaira Nishimura & Asahi 1 Policy and law What is the government policy and legislative framework for the electricity sector? The electricity sector in is governed by the

More information

Regulatory Environment and Electricity Tariff Design in Nigeria. Nigerian Electricity Regulatory Commission June, 2013

Regulatory Environment and Electricity Tariff Design in Nigeria. Nigerian Electricity Regulatory Commission June, 2013 Regulatory Environment and Electricity Tariff Design in Nigeria By Nigerian Electricity Regulatory Commission June, 2013 Outline Functions of the Commission Tariff Regulation in Nigeria Methodology of

More information

Japan. Nagahide Sato and Sadayuki Matsudaira Nishimura & Asahi

Japan. Nagahide Sato and Sadayuki Matsudaira Nishimura & Asahi Nagahide Sato and Sadayuki Matsudaira Nishimura & Asahi 1 Policy and law What is the government policy and legislative framework for the electricity sector? The electricity sector in is governed by the

More information

Renewable Energy Strategy for 2020 and Regulatory Framework. Eng. Hatem Amer Egyptian Electric Regulatory and Consumer Protection Agency

Renewable Energy Strategy for 2020 and Regulatory Framework. Eng. Hatem Amer Egyptian Electric Regulatory and Consumer Protection Agency Renewable Energy Strategy for 2020 and Regulatory Framework Eng. Hatem Amer Egyptian Electric Regulatory and Consumer Protection Agency Objectives of the Agency Regulate, supervise, and control all matters

More information

Western Australian Feed-In Tariff Discussion Paper

Western Australian Feed-In Tariff Discussion Paper Western Australian Feed-In Tariff Discussion Paper OVERVIEW In September 2008, the incoming State Government announced its intention to introduce a feed-in tariff as part of the Liberal Plan for Environmental

More information

Falling Short: An Evaluation of the Indian Renewable Certificate Market

Falling Short: An Evaluation of the Indian Renewable Certificate Market Falling Short: An Evaluation of the Indian Renewable Certificate Market Climate Policy Initiative Gireesh Shrimali Sumala Tirumalachetty David Nelson December 2012 CPI-ISB Report Descriptors Sector Region

More information

RAJASTHAN ELECTRICITY REGULATORY COMMISSION

RAJASTHAN ELECTRICITY REGULATORY COMMISSION RAJASTHAN ELECTRICITY REGULATORY COMMISSION In the matter of amendments in: I. RERC (Renewable Energy Obligation) Regulations, 2007. II. RERC (Renewable Energy Certificate and Renewable Purchase Obligation

More information