1 C -INF eraf - lucture & OPER lforrnation Requir Outline Description of the Treatment Process at Kiicioon WWTP 8 Agglomeration - Drawing No Co n se nt o f c Fo op r i yr ns ig pe ht ct ow ion ne pu r r rp eq os ui es re o d nl fo y. ra ny ot he ru se. - Drawing No EPA Export :14:29:45
2 OUTLINE DESCRIPTION OF THE TREATMENT PROCESS FOR KILCLOON WASTE WATER TREATMENT PLANT AND AGGLOMERATION 1.0 INTRODUCTION As discussed in Section 6.10 of this application, a new wastewater treatment plant (WWTP) is currently under construction to serve the Kilcloon Agglomeration. The anticipated completion date for this project is September In addition, provision of a new sewerage network to serve the Kilcloon Agglomeration has now reached completion. The following sections describe the processes at the new wastewater treatment plant (for which a Part Viil planning application has been prepared and approved). ) 2.0 EXISTING PLANT Given the relatively small catchment. Kilcloon agglomeration is not serviced by a local authority sewerage system at present. Individual septic tanks currently provide a means of waste water treatment for the agglomeration. 3.0 PROPOSED PLANT (programmed commissioning date - September 2009) The new waste water treatment plant is being constructed on a green-field site located in the townland of Kilgraigue. The new plant will provide effluent treatment to Urban Waste Water treatment standards. The units being provided in the new plant will include: lnlet Pump Sump lnlet works Storm water holding tank Extended aeration treatment unit Tertiary treatment unit Final effluent chamber Sludge recycle pump set Sludge holding tank Control house lnlet Works The inlet works will provide screening of the incoming waste water via 1 nr. automatic spiral screen (6mm stainless steel screen equipped with compaction unit and auto cleaning device), with a bypass manual 25mm bar screen for scheduled downtime of the former. The preliminary treatment will entail the removal of plastics and rags from the waste stream. EPA Export :14:29:45
3 Screened waste water will exit the inlet works and flow towards the inlet pump station. Inlet Pump Sump The inlet pump wet sump consists of a chamber with a 2.0m X 2.0m plan area, containing 2 No. submersible pumps for forward feed of incoming untreated waste water to the process plant. This inlet sump also comprises an ovefflow facility, which will direct storm water to the storm water holding tank. This storm water overflow will cut-in at a level of 3.03m above the sump base. Storm water return will also occur at this pump sump. Storm water holding tank Storm water control is being provided such that 14.7m31hr will flow forward towards the process plant. Flows in excess of 3DWF will be diverted to the storm water holding tank. Storm water will be returned to the inlet pumping station when storm conditions abate, however, during extreme wet weather conditions and in the event that storm water holding tank capacity has been exceeded, there will be a facility for excess storm water to bypass the works. The storm water holding tank has a capacity in the order of 79m3. Secondary Treatment A Compact Aeration Unit (CAU), incorporating a central clarifier unit surrounded by an oxidation ditch will provide biological treatment and settlement to the incoming screened waste water. Waste water will be pumped to the aeration portion (oxidation ditch) of the concentric tank. The CAU has an approximate combined capacity of 222m3 (aeration capacity: 162m3, clarifier capacity: 60m3) with dimensions as follows: Inner Diameter : rn Outer Diameter : 10.6m Liquid Depth of aeration unit : 3.2m Liquid Depth of Clarifier : varies 2.85m to 4.0m A fine bubble diffused air aeration system is being installed in the oxidation ditch base to maintain dissolved oxygen at sufficient levels during the aeration phase. Aerated mixed liquor will flow from the oxidation ditch to the central section of the clarifier via an overflow weir to a GRP diffuser drum. Settled sludge will fall to a base of the clarifiers, while clarified liquid will overtop the clarifier's inner wall, via a stainless steel peripheral weir. The weir will be fitted with a scum draw off device. Final effluent, on exiting the clarifier (via the peripheral weir), will flow forward by gravity to a tertiary microscreen chamber. Settled sludge will be removed from the base of the clarifie~ via a 150mm diameter sludge draw off pipe to a picket fence thickener. EPA Export :14:29:45
4 Nutrient Removal Phosphate removal, in the form of ferric sulphate application will be practiced at the proposed plant. Tertiary Treatment The treatment process will include a microscreen unit as a form of tertiary treatment. This form of treatment will comprise a mechanically operated microscreen, installed to screen final effluent down to 50um. The microscreen will include a self-cleaning device, which will operate on a predetermined headloss. The membrane can be replaced as required for maintenance. Screenings will be returned to the Sludge Holding Tank. Continuous flow monitoring of the treated effluent will occur post microscreening. (A v-notch weir is being installed for the purposes of flow measurement) Proposed Outfall Arrangement The final effluent will exit the works in a 225mm diameter gravity pipeline, which will discharge directly to a stream tributary of the Rye Water. Excess storm water, which may on occasion bypass the works, will combine with the treated effluent downstream of the treatment process in this gravity pipeline and will then co- discharge directly to the stream. Sludge Handling Sludge handling facilities will be provided at Kilcloon in the form of a 3.5m diameter sludge holding tank I picket fence thickener. Thickened sludge will be collected and transported to either Castletown Tara or Navan WWTPs for dewatering. Supernatant drawn from the top of the thickener will be returned to the secondary aeration unit via the sludge recycle pump station. Control Building A new Control Building is being provided at the site to include a toilet, store and control room. Proposed Odour and Noise Control It is a contract requirement that the Kilcloon Waste Water Treatment Plant will comply with the European Communities (Waste Water Treatment) (Prevention of Odours and Noise), Regulations, (S.I. No. 787 of 2005). EPA Export :14:29:45
5 WWTP SlTE BOUNDARY INLET WORKS - SLUDGE RECYCLING PUMP I SLUDGE HOLDING TANK - TANK Cli& MEATH COUNTY COUNCIL Pml'd: KILCLOON WASTE WATER TERTIARY TREATMENT DISCHARGE APPLICATION LICENCE me: PLANT PROCESS SlTE PLAN,(SECTION 1 ATTACHMENT C.1 ) Sds@A3: 1 : 500 Prop.nrlk PWDinMr Chsrial: M.F.G. MAY 09 EPA Export :14:29:45
6 SCREENINGS I OFF-SITE DISPOSAL RAW SCREENING INLET PUMPING MIXED LIQUOR OVERFLOW WASTE ACTIVATEC SLUDGE I TREATMENT I MlPRnSPRFFN >. IER TREATED EFFLUENT REATED EFFLUENT TO PRIMARY ISCHARGE POINT MEATH COUNTY COUNCIL DISPENSER PIDlDd KILCLOON WASTE WATER DISCHARGE LICENCE APPLICATION FERRIC I m c PLANT1 PROCESS FLOW DIAGRAM,(SECTION 1 ATTACHMENT Cl), / STORMWATER ( HOLDING TANH D EXCESS STORMWATER OVERFLOW LINE P,ep.,a(bl; ChSXod: o.,o: R.K M.H. MAY W PmWlli-r M.F.G. TREATMENT WORKS SI EPA Export :14:29:45
7 se Co n f c Fo op r i yr ns ig pe ht ct ow ion ne pu r r rp eq os ui es re o d nl fo y. ra ny nt o se. ru he ot INF STR PEF EPA Export :14:29:46
8 OUTLINE DESCRIPTION OF OUTFALL DESIGN AND CONSTRUCTION 1.0 PRIMARY DISCHARGE POINTS EXISTING PRIMARY DISCHARGE No existing primary discharge points on Kilcloon Sewerage Scheme PROPOSE Location: Receiving Water: Originates: Invert Level: iy DISCHARGE PSWl - Kilgraigue T.D.. Kilcloon, County Meath E, N Discharge to stream tributary of the Rye Water River (Liffey Catchment) Final treated effluent from newly constructed Kilcloon WWTP 67.31m.O.D Pipe Size: 225mm diameter gravity pipeline from WWTP (shared with PSW2 - Design Criteria: Construction Detail: proposed storm water overflow) Continuous flow of treated effluent from WWTP 225mm diameter concrete pipe discharging to headwall EPA Export :14:29:46
9 2.0 SECONDARY DISCHARGE POINTS A site visit was undertaken by TOBlN Consulting Engineers in March I April 2009 during which the study area was examined, however no secondary discharges were identified. There are no secondary discharge points from Kilcloon WWTP and sewerage network, EPA Export :14:29:46
10 3.0 STORM WATER OVERFLOW DISCHARGE POINTS EXISTING STORM WATER OVERFLOW DISCHARGE No existing storm water ovefflow discharge points on Kilcloon Sewerage Scheme PROPOSED STORM WATER OVERFLOW DISCHARGE Location: Receiving Water: Originates: Invert Level: Pipe Size: Design Criteria: Construction Detail: PSW2 - Kilgraigue T.D., Kilcloon, County Meath E, N Discharge to stream tributary of the Rye Water R~ver (Liffey Catchment) Storm water overflows from storm water holding tank at newly constructed Kilcloon WWTP 67.31m.0.D Proposed 225mm d~ameter gravity pipeline from WWTP (shared w~th PSWl -proposed primary d~scharge point) Storm water control will then be provided such that 3DWF will flow forward from the inlet works. Flows in excess of 3DWF w~ll be d~verted to the proposed storm water holding tank. Storm water will be returned to the inlet works when storm conditions abate, however, during extreme wet weather conditions and in the event that storm water holding tank capacity has been filled, there will be a facility for excess storm water to bypass the works. The proposed storm water holding tank will have a capacity in the order of 162m3approximately. 225mm diameter concrete pipe discharging to headwall EPA Export :14:29:46
11 EPA Export :14:29:46
12 WWTP SITE BOUNDARY PROPOSED PRIMARY DISCHARGE PROPOSED STORMWATER OVERFLOW MEATH COUNTY COUNCIL we. KILCLOON WASTE WATER DISCHARGE LICENCE APPLICATION rm 'ROPOSED PRIMARY DISCHARGE POINT (PSWI) 8 PROPOSED itormwater OVERFLOW (PSWZ) COlrSTRLCTlON 8 DESlGh ( SECTION I ATTACHMENT C.2 )/ ',cp.ndw Ch.r*d. OdS R.K. M.H. MAY 09 'miodoulra. M F.G. EPA Export :14:29:46
Type of Sewer Systems. Solomon Seyoum
Type of Sewer Systems Solomon Seyoum 0 Learning objectives Upon completion of this lecture, the participants will be able to differentiate between types of sewer systems and discuss different aspects of
More informationCambridge Wastewater Treatment Facility
Cambridge Wastewater Treatment Facility Emergency Situations If you have a water or sewer emergency that relates to the City s utility system call the Public Works office at 763-689-1800 on normal working
More informationThe City of Boulder 75 th Street Wastewater Treatment Facility
The City of Boulder 75 th Street Wastewater Treatment Facility Wastewater Collection and Treatment The Foundation of Public Health Wastewater Collection Boulder s wastewater collection system, also known
More informationDescription of the Water Conserv II Facility
Description of the Water Conserv II Facility Introduction The Water Conserv II (WCII) Water Reclamation Facility provides service to a majority of the southwest section of Orlando. The WCII facility has
More informationWASTE WATER TREATMENT SYSTEM (OPERATING MANUALS )
Page 1 of 76 1.0 PURPOSE The purpose of the Wastewater Treatment System is to remove contaminates from plant wastewater so that it may be sent to the Final Plant Effluent Tank and eventually discharged
More informationSewerage Management System for Reduction of River Pollution
Sewerage Management System for Reduction of River Pollution Peter Hartwig Germany Content page: 1 Introduction 1 2 Total emissions 3 3 Discharge from the wastewater treatment plants 4 4 Discharge from
More informationSEPTIC TANKS FOR THE COLLECTION & SETTLEMENT OF DOMESTIC SEWAGE
SEPTIC TANKS FOR THE COLLECTION & SETTLEMENT OF DOMESTIC SEWAGE Let us help! Free professional site visit with friendly support and advice. helpingyou@klargester.com to make the right decision or call
More informationWilliam E. Dunn Water Reclamation Facility. Facility Overview & Information
William E. Dunn Water Reclamation Facility Facility Overview & Information General Area Served: Plant History Facility Highlights Northern Pinellas County St. Joseph Sound to East Lake Road (E/W) Tampa
More informationWWTP RETROFIT. Smith & Loveless Inc. www.smithandloveless.com. Also in this issue: Do You Have Emergency Backup? Aging Clarifiers Retrofit to Like New
Winter 2010 Issue #04-06-759 Rehabilitate your aging infrastructure quickly and increase your treatment capacity. Also in this issue: Do You Have Emergency Backup? Aging Clarifiers Retrofit to Like New
More informationAfter the Flush. Safe disposal of our wastewater is a valued and complex, not-for-profit municipal service.
After the Flush Published: July 14, 2011 Sewage or wastewater is something we rarely think or talk about. The wastewater from our toilets, showers, washing machines and dishwashers quickly departs our
More informationAdvanced Wastewater Treatment and Disposal Systems. Water and Wastewater Utility Operation and
Advanced Wastewater Treatment and Disposal Systems Water and Wastewater Utility Operation and Management for Tribes Preliminary Treatment Primary Treatment Secondary Treatment Tertiary Treatment Disinfection
More informationEngineers Edge, LLC PDH & Professional Training
510 N. Crosslane Rd. Monroe, Georgia 30656 (770) 266-6915 fax (678) 643-1758 Engineers Edge, LLC PDH & Professional Training Copyright, All Rights Reserved Engineers Edge, LLC An Introduction to Advanced
More informationTABLE OF CONTENTS EXECUTIVE SUMMARY...1 1.0 DESCRIPTION OF EXISTING CONDITIONS... 1-1. 1.1 Population... 1-1. 1.2 Wastewater Flows...
TABLE OF CONTENTS EXECUTIVE SUMMARY...1 1.0 DESCRIPTION OF EXISTING CONDITIONS... 1-1 1.1 Population... 1-1 1.2 Wastewater Flows... 1-1 1.3 Existing Wastewater Facilities... 1-2 1.3.1 City of Celina...
More informationWASTEWATER TREATMENT OBJECTIVES
WASTEWATER TREATMENT OBJECTIVES The student will do the following: 1. Define wastewater and list components of wastewater. 2. Describe the function of a wastewater treatment plant. 3. Create a wastewater
More informationPRODUCT SELECTOR Pollution Control, Pumping and Rainwater Harvesting Systems
PRODUCT SELECTOR Pollution Control, Pumping and Rainwater Harvesting Systems PACKAGE SEWAGE TREATMENT SYSTEM Clearwater treatment plants are ideal for single houses and employ the well proven aerobic biological
More informationOasis Clearwater ENVIRONMENTAL SYSTEMS WASTEWATER TREATMENT ENGINEERS
Oasis Clearwater ENVIRONMENTAL SYSTEMS WASTEWATER TREATMENT ENGINEERS The evolution continues in decentralised wastewater technology... The Process Decentralised wastewater treatment systems are defined
More informationTackling London s Sewer Overflows
Thames Tideway Tunnel Thames Water Utilities Limited Application for Development Consent Application Reference Number: WWO10001 Tackling London s Sewer Overflows Doc Ref: 8.2.5 Solutions Working Group
More informationHigh-Rate Retention Treatment Facility for CSO Control in Windsor Riverfront East
High-Rate Retention Treatment Facility for CSO Control in Windsor Riverfront East Jian Li, Ph.D., P.Eng., PE Senior Environmental Engineer Stantec Consulting Ltd. Water & Wastewater Treatment BMP Forum
More informationPhosphorus Removal. Wastewater Treatment
Phosphorus Removal In Wastewater Treatment by Derek Shires (512) 940-2393 Derek.Shires@ett-inc.com Why do we care? Eutrophication of surface water - Especially reservoirs Maximum agronomic uptake - Limiting
More informationCHAPTER 10-2. Section 1 Inventory of Existing Sanitary Sewer Collection and Treatment Facilities
CHAPTER 10-2 SEWAGE COLLECTION AND TREATMENT FACILITIES Section 1 Inventory of Existing Sanitary Sewer Collection and Treatment Facilities 1.1 SANITARY SEWER COLLECTION SYSTEM The City of Washougal operates
More informationHYDROVEX. CSO, SSO and Stormwater Management Specialist Products and Services for North America
HYDROVEX CSO, SSO and Stormwater Management Specialist Products and Services for North America A long tradition in excellence John Meunier Inc. has been serving North American municipalities and industries
More informationChapter 8: Common Treatment Facilities, Programs, Operational Improvements and Policies for the Recommended Plan
Chapter 8: Common Treatment Facilities, Programs, Operational Improvements and Policies for the Recommended Plan 8.1 Introduction The purpose of this chapter is to document the variety of treatment-related
More informationBay Park Sewage Treatment Plant Super Storm Sandy Recovery
County of Nassau Department of Public Works Bay Park Sewage Treatment Plant Super Storm Sandy Recovery Edward P. Mangano County Executive Shila Shah-Gavnoudias, P.E. Commissioner of Public Works Bay Park
More informationWastewater Treatment System Rehabilitation Project
Wastewater Treatment System Rehabilitation Project An overview The City of Shelton, WA / January 2010 Before After SHELTON WASTEWATER TREATMENT IMPROVMENTS PROJECT Enabled by extensive grant-funding, loans
More informationOutlet stabilization structure
Overview of Sedimentation and Erosion Control Practices Practice no. 6.41 Outlet stabilization structure Erosion at the outlet of channels, culverts, and other structures is common, and can cause structural
More informationAnn Arbor Wastewater Treatment Plant Facilities Renovations Project September 2015
Ann Arbor Wastewater Treatment Plant Facilities Renovations Project September 2015 The Facilities Master Plan was completed in 2004 and identified the need for improvements to the City of Ann Arbor s Wastewater
More informationWastewater Nutrient Removal
Wastewater Nutrient Removal An overview of phosphorus and nitrogen removal strategies Presented by: William E. Brown, P.E. Peter C. Atherton, P.E. Why are nutrients an issue in the environment? Stimulates
More informationCHAPTER 8 UPGRADING EXISTING TREATMENT FACILITIES
CHAPTER 8 UPGRADING EXISTING TREATMENT FACILITIES 8-1. General. Upgrading of wastewater treatment plants may be required to handle increased hydraulic and organic loadings to meet existing effluent quality
More informationSEPTIC SYSTEMS. 1. Building sewer connects the building plumbing to the septic tank.
SEPTIC SYSTEMS Who Has A Septic System? Approximately 30 percent of Connecticut s population is served by on-site subsurface sewage disposal systems (a.k.a. septic systems). This means a large percentage
More informationDID YOU KNOW... THE IMPACT OF ON-SITE SEWAGE SYSTEMS AND ILLICIT DISCHARGES ON THE ROUGE RIVER
DID YOU KNOW... THE IMPAT OF ON-SITE SEWAGE SYSTEMS AND ILLIIT DISHARGES ON THE ROUGE RIVER by Barry Johnson, P.E., M.S., amp Dresser & McKee and Dean Tuomari, Wayne ounty Department of Environment The
More informationOn Site Treatment Systems
On Site Treatment Systems Introduction In cases where houses require to be located in the countryside,(i.e. where no sewerage is available),it is necessary to provide a specific on-site treatment system
More informationAdvanced Wastewater Treatment Process
7 th Workshop on Greenhouse Gas Inventories in Asia Possibly Co-benefit? Advanced Wastewater Treatment Process Tomonori ISHIGAKI Dept. of Environmental Solution Technology Ryukoku University, Japan Introductory
More informationCity of Charlottetown Wastewater Treatment Expansion & Upgrading
City of Charlottetown Wastewater Treatment Expansion & Upgrading Background As Canada s smallest provincial capital, the City of the Charlottetown has a population of approximately 34,000 residents and
More informationACTIFLO Process For Wet Weather and Wastewater Treatment
ACTIFLO Process For Wet Weather and Wastewater Treatment ACTIFLO Microsand Ballasted Clarification Process ACTIFLO is a high rate, compact process developed by Veolia Solutions & Technologies. The process
More informationExperts Review of Aerobic Treatment Unit Operation and Maintenance. Bruce Lesikar Texas AgriLife Extension Service
Experts Review of Aerobic Treatment Unit Operation and Maintenance Bruce Lesikar Texas AgriLife Extension Service Overview Overview of Aerobic Treatment Units Installing for accessibility to system components
More informationGreater Dublin Strategic Drainage Study Regional Drainage Policies - Volume 2 New Development
7 SPECIFICATIONS There is currently no Irish specification for construction of drainage works, or water supply works. There are several publications that give guidance on drainage works, such as the Building
More informationTechnical Feasibility of a Wet Weather Flow Treatment Facility
Wastewater Master Plan DWSD Project No. CS-1314 Technical Feasibility of a Wet Weather Flow Treatment Facility Technical Memorandum Original Date: August 9, 2001 Revision Date: September 2003 Author: Tetra
More informationEnvironmental Science 101 Waste. Fall 2012. Lecture Outline: Terms You Should Know: Learning Objectives: Reading Assignment: Chlorinated.
Environmental Science 101 Waste Fall 2012 1 Lecture Outline: 17. SEWAGE DISPOSAL A. Sewage Handling B. Raw Sewage C. Wastewater Treatment Steps D. Individual Septic Systems E. Taking Stock Learning Objectives:
More informationRULE 8-8 - ORGANIC COMPOUNDS - WASTEWATER COLLECTION AND SEPARATION SYSTEMS
BAY AREA AIR QUALITY MANAGEMENT DISTRICT RULE 8-8 - ORGANIC COMPOUNDS - WASTEWATER COLLECTION AND SEPARATION SYSTEMS (ADOPTED: January 17, 1979) (AMENDED: November 1, 1989; October 6, 1993; June 15, 1994;
More informationKansas City s Overflow Control Program
Kansas City s Overflow Control Program Kansas City Water Services Water Wastewater Stormwater 2 Water Services Department 1000 Positions 835 Employees 3 Utilities FY 13/14 Budget = $307 million Water Wastewater
More informationOWNER S MANUAL MODEL NUMBERS M-6-A M-8-A M-1050-A M-1200-A M-2000-A
OWNER S MANUAL MODEL NUMBERS M-6-A M-8-A M-1050-A M-1200-A M-2000-A Consolidated Treatment Systems, Inc. 1501 Commerce Center Drive Franklin, OH 45005 Tel: 937-746-2727 Fax: 937-746-1446 www.consolidatedtreatment.com
More informationCOD/BOD 5 Reduction with ROTAMAT Fine and Micro Screens
COD/BOD 5 Reduction with ROTAMAT Fine and Micro Screens Removal of particulate material from wastewater Eco-efficient use of capital Water pollution control through maximum COD/BOD 5 reduction Service
More informationSewage: Collection, Treatment & Disposal
Ohio EPA State of Ohio Environmental Protection Agency Sewage: Collection, Treatment & Disposal Where Public Sewers Are Not Available 1993 Edition Table of Contents Administration... 1 Laws and Rules for
More informationCHAPTER 11 STORM DRAINAGE
CHAPTER 11 STORM DRAINAGE SECTION 11 GENERAL 11.1 Scope. The provisions of this chapter shall govern the materials, design, construction and installation of storm drainage. 11.2 Where required. All roofs,
More informationA HOMEOWNERS GUIDE ON-SITE SEWAGE MANAGEMENT SYSTEMS
GEORGIA DEPARTMENT OF HUMAN RESOURCES ENVIRONMENTAL HEALTH SECTION A HOMEOWNERS GUIDE TO ON-SITE SEWAGE MANAGEMENT SYSTEMS March 12, 2002 WHAT IS AN ON-SITE SEWAGE MANAGEMENT SYSTEM An on-site sewage management
More informationLouisiana Administrative Code Title 51 Part XIII. Sewage Disposal
Louisiana Administrative Code Title 51 Part XIII. Sewage Disposal Regulations Regarding Septic Tank Installations with Field Beds/Absorption Trenches For Individual Residential Installations Chapter 3.
More informationModule 16: The Activated Sludge Process - Part II Instructor Guide Answer Key
Unit 1 Process Control Strategies Exercise Module 16: The Activated Sludge Process - Part II Instructor Guide Answer Key 1. What are the six key monitoring points within the activated sludge process? Ans:
More informationCWD BALDWIN PLANT NEW RESIDUALS HANDLING SYSTEM
CWD BALDWIN PLANT NEW RESIDUALS HANDLING SYSTEM OTCO Water Workshop March, 2011 Frank Woyma Plant Manager Nick Pizzi Vice-President EE&T ENVIRONMENTAL ENGINEERING & TECHNOLOGY, INC. Objectives Review the
More informationALL YOU NEED TO KNOW...
ALL YOU NEED TO KNOW... What do you know about your septic tank system? For the purposes of this booklet, a septic tank system refers to any kind of on-site sewage management system including traditional
More informationA Property Owner s Guide
The Operation and Maintenance of Domestic and Commercial Sewers A Property Owner s Guide KILDARE LOCAL AUTHORITIES WATER SERVICES DEPARTMENT TABLE OF CONTENTS Introduction 1. Why should I care? 2. What
More informationDESCRIPTION OF STORMWATER STRUCTURAL CONTROLS IN MS4 PERMITS
DESCRIPTION OF STORMWATER STRUCTURAL CONTROLS IN MS4 PERMITS Phase I MS4 permits require continuous updating of the stormwater system inventory owned and operated by the MS4. They also include inspection
More informationHUBER Vacuum Rotation Membrane VRM Bioreactor
HUBER Vacuum Rotation Membrane VRM Bioreactor VRM The rotating plate membrane for clean water applications. The future-oriented solution designed for the ever increasing requirements in wastewater treatment
More information5. TREATMENT FACILITIES
5. TREATMENT FACILITIES 5.1. Background... 1 5.2. Nine Springs Wastewater Treatment Plant... 1 5.2.1. Liquid Treatment Facilities... 3 5.2.2. Biosolids Disposal Facilities... 6 5.2.3. Operation and Maintenance
More informationBiological Drain Maintenance Systems
Biological Drain Maintenance Systems 2007 NCH Corporation HISTORY OF DRAINS MODERN SEWAGE SYSTEM Septic tanks were introduced; effluent water was largely untreated causing pollution of streams and rivers.
More informationSeptic System. Responsibility! Is Your. You should know that:
Southwest Florida Water Management District Septic System Your Is Your Responsibility! PIPE SEPTIC TANK DRAIN FIELD SOIL You should know that: As a homeowner you re responsible for maintaining your septic
More informationExample Calculations Evaluation for Fine Bubble Aeration System. Red Valve Company, Inc. 700 NORTH BELL AVENUE CARNEGIE, PA 15106-0548
Revision Date 6/10/02 9:52 Red Valve Company, Inc. 700 NORTH BELL AVENUE CARNEGIE, PA 15106-0548 PHONE (412) 279-0044 FAX (412) 279-5410 Red Valve Representative Sample Air Diffuser Calcs.xls Input Data
More informationBiological wastewater treatment plants of BIOGEST
Biological wastewater treatment plants of BIOGEST by: Thorsten ten Neuerer and Markus Batschauer from: BIOGEST AG, Taunusstein The so-called batch technology represents a particularly interesting and effective
More informationE nv i ro n m e nta l. Biotec 5-7. Sustainable, Reliable, Affordable
E nv i ro n m e nta l Biotec 5-7 Package Sewage Treatment for Residential, Business & Leisure Applications Sustainable, Reliable, Affordable ENTEC BIOTEC 5-7 FROM KINGSPAN ENVIRONMENTAL Package Sewage
More informationFlorida Department of Environmental Protection
Florida Department of Environmental Protection Background Mobile vehicle and equipment washing involves washing at a location where vehicles are based (such as a trucking company, warehouse, bus station,
More informationAsset Management Answering the 5 Core Questions
Asset Management Answering the 5 Core Questions by Timothy Taber, PE Barton & Loguidice Page 1 Drivers Asset Management Case Study 1. What is the current state of my assets? 2. What is my required sustainable
More informationCHAPTER 11 STORM DRAINAGE
CHAPTER STORM DRAINAGE SECTION PC 0 GENERAL 0. Scope. The provisions of this chapter shall govern the materials, design, construction and installation of storm drainage. Storm water discharge shall be
More informationMAP KEYS GLOSSARY FOR THE DRAINAGE AND WATER REPORT
Record MAP KEYS GLOSSARY FOR THE DRAINAGE AND WATER REPORT Abandoned Gravity Private Combined Gravity Private Foul Gravity Private Surface Water Gravity Public Combined Gravity Public Foul Gravity Public
More informationIndiana State Department of Health Construction Guidelines for Gravity and Flood-Dose Trench Onsite Systems
Indiana State Department of Health Construction Guidelines for Gravity and Flood-Dose Trench Onsite Systems The septic tank-absorption field sewage treatment system is composed of two major elements; the
More informationTerms of Reference. Aqaba Water and Wastewater Utility Asset Valuation
Technical Support for Procurement and Project Management and Private Sector Participation to the Ministry of Water and Irrigation, Water Authority of Jordan and the Jordan Valley Authority Support for
More informationComposting and Wastewater Treatment Facilities in İzmir
Die Festwoche der Abfallwirtschaft und Altlasten der TU Dresden: 26.-30. September 2005 1. Fachtagung Perspektiven von Deponien Stilllegung und Nachnutzung nach 2005 am 26.-27. September 2005 2. Mischen
More informationWASTE WATER Solutions
Huber Technology is a leading supplier of stainless steel waste water treatment equipment. Our extensive experience enables us to offer high quality solutions for all your waste water treatment needs for
More informationaquateam Aquateam - Norwegian Water Technology Centre A/S Report no: 02-051 Project no: O-02033 Project manager: Dr. Bjørn Rusten.
Feasibility study of biological wastewater treatment plants with Salsnes Filter fine mesh sieve primary treatment compared to plants without primary treatment Aquateam - Norwegian Water Technology Centre
More informationIMPACT OF CHEMICALS ADDITION IN WATER/WASTEWATER TREATMENT ON TDS CONCENTRATION AND SLUDGE GENERATION Jurek Patoczka, PhD, PE Hatch Mott MacDonald 27 Bleeker Str., Millburn, NJ 07041 (973) 912 2541 jurek.patoczka@hatchmott.com
More informationHow do storm water and wastewater networks function together with the wastewater treatment plant? Theo G. Schmitt, Kaiserslautern University (Germany)
Urban FG Siedlungswasserwirtschaft Water Management KfWInternational Conference on Efficient Use of Energy in Water Supply and Wastewater Disposal in Southeastern Europe and Turkey November 26-27, 2013
More informationPOTW PHOSPHORUS REMOVAL PROCESSES
POTW PHOSPHORUS REMOVAL PROCESSES Ohio Lake Erie Phosphorus Task Force - December 20, 2007 ROBERT M. BONNETT, PE Northeast Ohio Regional Sewer District OUTLINE SOURCES AND FORMS IN WASTEWATER TYPICAL POTW
More informationSource Water Protection Practices Bulletin Managing Sanitary Sewer Overflows and Combined Sewer Overflows to Prevent Contamination of Drinking Water
United States Office of Water EPA 916-F-01-032 Environmental Protection (4606) July 2001 Agency Source Water Protection Practices Bulletin Managing Sanitary Sewer Overflows and Combined Sewer Overflows
More informationENVIRONMENTAL IMPACT ASSESSMENT PROCESS
ENVIRONMENTAL IMPACT ASSESSMENT PROCESS PROPOSED SOLIDS REMOVAL AND TREATMENT FACILITIES UPGRADE AT THE SOUTHERN WASTE WATER TREATMENT WORKS, MEREWENT, IN THE ETHEKWINI METROPOLITAN MUNICIPALITY BACKGROUND
More informationseptic systems What is a Septic System? How does a Septic System Work?
septic systems What is a Septic System? A septic system is a private sewage treatment system. They are common in rural areas where there are no municipal sewage pipes for homes, farms, businesses or other
More informationDESIGN APPROACH. The design of skimming and pumping systems for classifying selectors must take into account three principal considerations:
Making Classifying Selectors Work for Foam Control in the Activated Sludge Process Denny Parker 1*, Steve Geary 2, Garr Jones 1, Lori McIntyre 1, Stuart Oppenheim 1, Vick Pedregon 3, Rod Pope 1, Tyler
More informationSanitary Sewer Overflow Enforcement : A National Perspective
Sanitary Sewer Overflow Enforcement : A National Perspective LOREN DENTON, CHIEF MUNICIPAL ENFORCEMENT BRANCH WATER ENFORCEMENT DIVISION U.S. ENVIRONMENTAL PROTECTION AGENCY Topics Covered 2 SSOs National
More informationCERTIFYING DRAINLAYER
No. 9198 REGISTRATION EXAMINATION, NOVEMBER 2013 CERTIFYING DRAINLAYER ANSWER SCHEDULE Plumbers, Gasfitters and Drainlayers Board, 2013. All rights reserved. No part of this publication may be reproduced
More informationHow To Improve Water Quality In East Pacificon
WATER STORIES EAST PROVIDENCE, RI We are proud to partner with East Providence on this very important project. Together we developed an innovative, sustainable solution that promotes public, economic
More informationGuidance on applying for approval of installation of a commercial onsite wastewater system
Guidance on applying for approval of installation of a commercial onsite wastewater system This factsheet is designed to assist you to complete an Application to construct or install an apparatus for the
More informationThe Sewage Plant. The Original! Fully biological. Small sewage. wastewater treatment for. new construction. & retrofitting
The Sewage Plant The Original! Fully biological wastewater treatment for new construction & retrofitting Ssb Small sewage treatment plant AQuato stabi-kom AQUATO STABI-KOM THE NEW GENERATION AMONG THE
More informationWaste Water Solutions
Waste Water Solutions Mono is a leading name in the design, manufacture and supply of progressing cavity pumps, parts, grinders, screens and packaged solutions, worldwide. We have 7 international sites
More informationTECHNICAL BULLETIN. Location of the system. Percolation tests for drainage fields. Cesspool sizing. Suggested Information notices
TECHNICAL BULLETIN Issue 1 Market leaders Whichever product is most suitable for your needs you can be assured of Klargester s quality. Klargester is an accredited company under BS EN ISO 9001 2000 quality
More informationTemporary Batch Plants
Categories EC SE TC WE NS WM Erosion Control Sediment Control Tracking Control Wind Erosion Control Non-Stormwater Management Control Waste Management and Materials Pollution Control Legend: Primary Category
More informationSt. John s Harbour Clean-Up Phase 2. Project Description
St. John s Harbour Clean-Up Phase 2 Project Description February 2003 NEWFOUNDLAND DESIGN ASSOCIATES LIMITED 1 Introduction The City of St. John s, the adjoining City of Mount Pearl and the Town of Paradise
More informationRECOMMENDED PROGRAM FOR WELL AND SEPTIC SYSTEM REAL ESTATE TRANSACTION INSPECTIONS
Contra Costa Environmental Health 2120 Diamond Blvd., Suite 200 Concord, CA 94520 Phone: (925) 692-2500 Fax: (925) 692-2504 www.cchealth.org/eh/ RECOMMENDED PROGRAM FOR WELL AND SEPTIC SYSTEM REAL ESTATE
More informationANAEROBIC/ANOXIC TANKS
PROCESS DESCRIPTION In the anaerobic/anoxic tanks, wastewater is prepared for further treatment in the biological reactors. Denitrification and luxury uptake of phosphorus take place by mixing a food source
More informationProtecting your private water supplies. The possible causes of contamination and their remediation to prevent this risk.
Protecting your private water supplies The possible causes of contamination and their remediation to prevent this risk. Contamination from a variety of sources can occur potentially at any point throughout
More informationTALLINN WATER TREATMENT AND SEWERAGE Tuuli Myllymaa
TALLINN WATER TREATMENT AND SEWERAGE Tuuli Myllymaa Tallinn is the capital of Estonia. It has approximately 450,000 inhabitants and the town area is about 150 km 2. Tallinn Water Ltd., owned by the City
More informationGrit Removal Systems Simple, low cost, effective grit removal to enhance plant performance
LAKESIDE Water Purification Since 1928 Bulletin #1603 April 2005 Grit Removal Systems Simple, low cost, effective grit removal to enhance plant performance Aeroductor Model L Grit Classifier SpiraGrit
More information4.2 Option 1 Expand Existing Lagoon System
4. WASTEWATER TREATMENT SYSTEM 4.1 of Existing Lagoons The of existing lagoon system is evaluated for future demand based on the following requirements. Existing Lagoons Anaerobic cells - Four Cells, of
More informationFlexible Microscreen Filter. Hydrotech Discfilter
Flexible Microscreen Filter Hydrotech Discfilter Hydrotech Discfilter The world s leading microscreen filter is the ideal filtration system for fine solids removal and product recovery thanks to its superior
More informationCity of East Lansing CSO Control Facility Evaluation Demonstrative Approach to Meet WQS
City of East Lansing CSO Control Facility Evaluation Demonstrative Approach to Meet WQS Jeff Johnston, East Lansing WWTP Superintendent & Tom Maxwell, P.E., Hubbell, Roth & Clark, Inc. East Lansing CSO
More informationAeration Efficiency Guide
Aeration Efficiency Guide Environmental Dynamics InTernational EDI specializes in the research, development, and application of advanced technology aeration and biological treatment solutions for municipal
More informationWater Management in Helsinki. Water supply. Mikael Sillfors
Water Management in Helsinki Mikael Sillfors Helsinki is located on the northern shore of the Gulf of Finland. The main water systems in the area are the Gulf of Finland and River Vantaa, which runs through
More informationChemistry at Work. How Chemistry is used in the Water Service
Chemistry at Work How Chemistry is used in the Water Service WATER TREATMENT Everyday, more than 100 water treatment works in Northern Ireland put approximately 680 million litres of water into the supply
More informationBIODISC HIGH PERFORMANCE SEWAGE TREATMENT PLANT FOR DOMESTIC APPLICATIONS
BIODISC HIGH PERFORMANCE SEWAGE TREATMENT PLANT FOR DOMESTIC APPLICATIONS Let us help! Free professional site visit with friendly support and advice. helpingyou@klargester.com to make the right decision
More informationSaudi Aramco Project Development
Saudi Aramco Project Development Wastewater Treatment Facilities Jeddah Refinery And Marine Area December 2007 Facilities Planning Dept. OBJECTIVE: Provide an overview of the complexities of developing
More informationMinnesota. BMI Project No. M21.037315
Wastewater Treatment Facility Plan City of Paynesville Minnesota BMI Project No. M21.037315 March 2009 TABLE OF CONTENTS EXECUTIVE SUMMARY... 1 A. GENERAL... 1 B. DESIGN PARAMETERS... 1 C. COST ESTIMATES...
More informationFlygt N-Pumps 3085, 3102 & 3127. For reliable and efficient wastewater handling
Flygt N-Pumps 3085, 3102 & 3127 For reliable and efficient wastewater handling The Concept Flygt N-Pump series Reduced pumping efficiency, high energy and maintenance costs shouldn t be a fact of life
More informationHelp protect our special places by maintaining your septic tank
Help protect our special places by maintaining your septic tank BC3136 A septic tank guide Help protect our special places Rural Auckland is a special place, but the remoteness also means that many homes
More information