1 CASE: ACADEMY OF ART AND DESIGN IN BERGEN (KHIB) (LEAN) PROCESSPLANNING in the DESIGN PHASE IGLC 2014 JUNE 23rd
2 OR: HOW TO HANDLE AN ELEPHANT
3 KHIB: SOME FACTS Projectstart and designcompetition: Autumn 2005 Granting of final construction work fundings: June 2013 Total budget (pr. July 2013): mill. NOK (incl. VAT) Floor space (pr. July 2013): sqm Schedule: 2014: Detailled design / Demolition / Ground preparations 2015: Foundation works / Framework / Enveloping 2017: Scheduled completion Q2 OWNER - CLIENT: ARCHITECTS: DESIGNING ENGINEERS: Statsbygg Snöhetta Ramböll
4 BACKGROUND / LEAN MOTIVATION 1) Experiences from Lean Construction (ie. UiO Domus Medica, Oslo) 2) Lean construction seminars (ie. Porsche Consulting) 3) Takt - Train 4) Film-clip: 30 floors in 14 days (China) And as an objective: A very lean project.
5 KHIB PLAN Strategy - An as lean project as possible in design and construction. - Lean on all levels and in all phases. Tools - BiM - drofus (room functional database)
6 GENERAL PROJECT PRINCIPALS Transparency / Overview / Collaboration Culture for continous improvement Lean included in all contract documents Extended lean requirements for contractors Reduce, minimize or (preferably) eliminate waste Flow where possible Maximize frontloading
7 KHIB LEAN STEP BY STEP 1) Pre-Seminar Discussing and preparing a lean construction strategy. Getting to know the building. 2) Product Creation Process (w/ Porsche Consulting) Project top level overview. Mindshifting. 3) Now what..? A design train and takt..? 4) Developing and improving the lean design process «Unfamiliar territory!» 5) Extended use of lean takt planning and construction with contractors. - Contract review. - Contract handover (from design to contractors). - Frontloading (putting the puzzle together). - Lean construction. 6) Lessons learned
8 PLANNING USING LAMINATED A0-DRAWINGS
9 DRAFT 2ND FLOOR CONSTRUCTION STRATEGY
10 KHIB LEAN STEP BY STEP 1) Pre-Seminar Discussing and preparing a lean construction strategy. Getting to know the building. 2) Product Creation Process (w/ Porsche Consulting) Project top level (1) overview. Mindshifting. 3) Now what..? A design train and takt..? 4) Developing and improving the lean design process «Unfamiliar territory!» 5) Extended use of lean takt planning and construction with contractors. - Contract review. - Contract handover (from design to contractors). - Frontloading (putting the puzzle together). - Lean construction. 6) Lessons learned
11 PCP-LEAN-SEMINAR W/ PORSCHE CONSULTING
12
13 COMPLETE PROCESSMAP LEVEL 1 DEPENDENCIES & TRANSPARENCY EVERYONE ON THE SAME PAGE
14 COMPLETE PROCESSMAP LEVEL 1 STATSBYGG PHASES & MILESTONES (MAINTAINED) «LEVEL 2 & 3» PROCESSES (7) KEYPOINTS (NEW)
15 Everyone developed the PCP-level-1-map together. Everyone s «on the same page». Everyone has «the same mind». Everyone has the same objectives. WITH MINDS FULL OF A LOT OF THEORY AND EXPECTATIONS.
16 KHIB LEAN STEP BY STEP 1) Pre-Seminar Discussing and preparing a lean construction strategy. Getting to know the building. 2) Product Creation Process (w/ Porsche Consulting) Project top level overview. Mindshifting. 3) Now what..? A design train and takt..? From construction to design. 4) Developing and improving the lean design process «Unfamiliar territory!» 5) Extended use of lean takt planning and construction with contractors. - Contract review. - Contract handover (from design to contractors). - Frontloading (putting the puzzle together). - Lean construction. 6) Lessons learned
17 DESIGN TEAM OBJECTIVES Cutting the elephant into minor manageable pieces. Continous flow to BiM and physical construction. Restructure flow according to contracts and milestones. Issues/topics have appointed owners. 2-week «takt» with one 3-day big-room co-location. Continous priority (or: must-should-can). Iteration-steps: 5 fw and 1 bw (instead of 4-3). Efficiency: 80% effort & 20% time spent (instead of ).
18 DESIGN FLOW OVERVIEW CONTINOUS FLOW TO THE VIRTUAL BUILDING (BIM) AND THE PHYSICAL BUILDING TOPICS WITH ISSUSES & OWNERS
19 SLICING THE ELEPHANT: MINOR PIECES / TOPICS DEADLINE «PRODUCT»/OUTPUT ISSUES: - RESOURCES - TIME - INPUT OWNER TOPIC
20 «TAKT and TRAIN» 2-WEEK «TAKT» INCL. 3-DAYS BIG-ROOM CO-LOCATION
21 2 WEEK TAKT / WORK PROCEDURE
22 KHIB LEAN STEP BY STEP 1) Pre-Seminar Discussing and preparing a lean construction strategy. Getting to know the building. 2) Product Creation Process (w/ Porsche Consulting) Project top level overview. Mindshifting. 3) Now what..? A design train and takt..? 4) Developing and improving the lean design process «Unfamiliar territory!» 5) Extended use of lean takt planning and construction with contractors. - Contract review. - Contract handover (from design to contractors). - Frontloading (putting the puzzle together). - Lean construction. 6) Lessons learned
23 COMBINING THE LEVELS
24 LEVEL 2 PROJECT DESIGNPLAN (TOPIC OVERVIEW) «LEVELS 2 & 3» TOPICS / OWNERS / PRIORITY / STATUS MILESTONES & KEYPOINTS & BIM-DEVELOPMENT CONNECTED TO: PROCESSES AND KEYPOINTS (LEVEL 1) PROCESSES (7)
25
26 3-DAYS BIG-ROOM CO-LOCATION TOPIC OWNER 3-DAY MEETING SESSIONS BOOKING LIST TOPIC OWNER SHARING BIG ROOM
27 KHIB LEAN STEP BY STEP 1) Pre-Seminar Discussing and preparing a lean construction strategy. Getting to know the building. 2) Product Creation Process (w/ Porsche Consulting) Project top level overview. Mindshifting. 3) Now what..? A design train and takt..? 4) Developing and improving the lean design process «Unfamiliar territory!» 5) Extended use of lean takt planning and construction with contractors. - Contract review. - Contract handover (from design to contractors). - Frontloading (putting the puzzle together). - Lean construction. 6) Lessons learned
28 The lean processes in the project are ongoing. Lean takt-planning and construction are yet to come. (From 2015 onwards.) KHiB goal: The lessons so far learned in KHiB lean design, have been visualized in this presentation.
29 SUMMARY Common mindset for all parties involved in the project Common objectives and tools and agreed transparency Lean project strategy (for mindshift, construction and design) Complete and transparent project processoverview («all in») Agreeing on «minor pieces» and continous flow Assign topics with issues and owners Agree on work-procedures and managing (decision)levels Big-room transparency Putting the pieces together (BiM & construction)
30 QUESTIONS? (If time )
31 Hans Thomas Holm / Statsbygg Projectmanager with Statsbygg since Projectmanager for KHiB since June [email protected] Cell-phone: Sven Wertebach / Terramar Projectmanager with Terramar since Designmanager for KHiB since September [email protected] / [email protected] Cell-phone:
Lean Construction A New Path for the Construction Industry
Lean Construction A New Path for the Construction Industry Peter Meijnen Porsche Consulting GmbH Oslo, 20 May 2015 Source: www.fosterandpartners.com Porsche Consulting - 20 years experience in consulting
Opera house facts. Architect: Snøhetta AS. Photo: Trond Isaksen
The new Opera house facts The new opera house basks in the evening sun at the water s edge in Oslo. A total of 36 000 marble and granite slabs have been laid down to create the characteristic appearance.
A strategy for use of BIM during the assets life cycle & case study from the New Østfold Hospital
A strategy for use of BIM during the assets life cycle & case study from the New Østfold Hospital EuHPN Seminar - Building Information Modelling (BIM) for Healthcare TNO, Leiden (NL), 17.04.2014 Birger
THE MASTER S DEGREE IN DESIGN PROGRAMME DESCRIPTION Adopted by the Board of KHiB on 27 October 2011
THE MASTER S DEGREE IN DESIGN PROGRAMME DESCRIPTION Adopted by the Board of KHiB on 27 October 2011 1. THE PROFILE AND OBJECTIVES OF THE STUDY PROGRAMME The goal of the Department of Design is to educate
South East of Process Main Building / 1F. North East of Process Main Building / 1F. At 14:05 April 16, 2011. Sample not collected
At 14:05 April 16, 2011 At 13:55 April 16, 2011 At 14:20 April 16, 2011 ND ND 3.6E-01 ND ND 3.6E-01 1.3E-01 9.1E-02 5.0E-01 ND 3.7E-02 4.5E-01 ND ND 2.2E-02 ND 3.3E-02 4.5E-01 At 11:37 April 17, 2011 At
Building the Asset Information Model
Building the Asset Information Model BIM: Let s Get Started Contractors Survey https://www.surveymonkey.com/s/nfbbim Hypothesis: Government as a client can derive significant improvements in cost, value
How To Design A Bim Project
BIM Virtual Construction & Integrated Project Delivery Randy LaNear BIM Manager Barnhart - Heery Synonyms & Related Terms Integrated Practice Integrated Project Delivery Virtual Building (Environment)
Time is Money! Multi Project Management and Takt Oriented Sequencing
Time is Money! Multi Project Management and Takt Oriented Sequencing Klaus Broichhausen Project results of the Schuh group as well as studies and benchmarks of the Laboratory for Machine Tools and Production
NokiaSiemens and Agile Development by Petri Haapio JAOO 2008
NokiaSiemens and Agile Development by Petri Haapio JAOO 2008 DISCLAIMER! This presentation is based on my views and my opinion. This is not the view of the company and also others have experienced the
Project Portfolio Management Information System
Project Portfolio Management Information System Highlights It provides a single point of access to proposal and project information. It streamlines proposal preparation during all important tendering phases
Master Project Manager
EARLY BIRD DISCOUNT ALL DELEGATES WILL GET FREE TABLE PC BOOK & PAY NOW! Book Before 31st May 2015 and Save USD 200 = PAY USD 2,650 After 31st MAY 2015 USD 2,850 By attending this practical and informative
l e a n software development What Lean Brings to Agile
software development Beyond the Low Hanging Fruit What Lean Brings to Agile [email protected] Mary Poppendieck www.poppendieck.com Lean in a Nutshell 1. System Thinking Customers don t want software.
Case study background Intensive Big Room
The Use of Modified PPC Measurement in Design Management MSc student at TUT, J.T. Juntunen, Fira Oy, Vantaa Prof A. Kiviniemi, University of Liverpool, Liverpool MSc. O. Alhava, CTO, Fira Oy, Vantaa Abstract
Postgraduate education in clinical pharmacy from specialisation led by professional organisations to an academic degree within the Bologna framework
Postgraduate education in clinical pharmacy from specialisation led by professional organisations to an academic degree within the Bologna framework Professor Espen Molden School of Pharmacy, University
Agile Expansion to China. Armin M. Hoffmann @ Oracle Retail CrossTalk, Washington DC, 2011-06-22
Agile Expansion to China Armin M. Hoffmann @ Oracle Retail CrossTalk, Washington DC, 2011-06-22 2 CONTENTS Media-Saturn worldwide Challenge Approach Solution Success factors, challenges & lessons learnt
Saving Troubled Projects
Saving Troubled Projects 2012 Instructor and Developer Mark Waldof Mark Waldof Consulting Retired Lockheed Martin University of Minnesota Instructor CCE Business Improvements Consultant Project Management
Enquiry 2014 15 Ref 034
2014 12 03 Request for Quotation: Design, Printing and Supply of the Buffelsdraai Information Booklet and Brochure for the Environmental Planning and Climate Protection Department 1. Background Enquiry
Building Information Modelling and collaborative construction
Building Information Modelling and collaborative construction How technology is transforming construction For today s CEO in the construction industry, the drive for faster, more efficient delivery of
Institute for Technology and Management in Construction. Jürgen Kirsch. University of Karlsruhe (TH), Germany. contact: [email protected].
Production System Design A holistic production system in construction Element»quality and workflow stability«jürgen Kirsch Institute for Technology and University of Karlsruhe (TH), Germany contact: [email protected]
Machining Operations- Cycle Time
Machining Operations- Cycle Time Module 8.2 Tamboura Gaskins, LFM 06 Sean Holly, LFM 06 Mentor: Professor Tim Gutowski Professor and Associate Head of Mechanical Engineering, MIT Brian Bowers, LFM 03 Presentation
Charging for Pre-Application Advice. Guidance Note London Borough of Newham. March 2015
Charging for Pre-Application Advice Guidance Note London Borough of Newham March 2015 This guidance note provides information regarding the Council s preapplication advice service and the relevant charges.
LEAN PRODUCT DEVELOPMENT AT CATHEDRAL HILL HOSPITAL PROJECT
LEAN PRODUCT DEVELOPMENT AT CATHEDRAL HILL HOSPITAL PROJECT ABSTRACT Baris Lostuvali 1, Thais da C. L. Alves 2, Ralf-Uwe Modrich 3 The Cathedral Hill Hospital (CHH) project is a 1.2 million square feet
Leaning a Training Process for a Leading Irish Retail Bank
Lean Financial Services Value Stream Mapping Leaning a Training Process for a Leading Irish Retail Bank Lean Financial Services Value Stream Mapping Gerry Silke Lean Financial Services Consultant Leading
BIM An Introduction. 16 th April 2012 Engineers Ireland
BIM An Introduction 16 th April 2012 Engineers Ireland Agenda Brian Lahiff - Introduction James Duggan - Civil John Casey - Structural Michael Downey - MEP BIM An Introduction Brian Lahiff Thomas Garland
Certificate in Building Information Modelling (BIM) - Project Management
Certificate in Building Information Modelling (BIM) - Project Management Duration: 6 Months Distance Learning Programme Language: English RICS Member: 895.00 + VAT Non RICS Member 995.00 + VAT Course Summary
Single Sourcing as Enabler for SAP Clients
Single Sourcing as Enabler for SAP Clients Gert Keuschnigg IBM Business Consulting Services Vienna, April 2005 Table Of Contents Initial Situations at Clients and Goals of Single Sourcing Approaches of
ASSET INFORMATION REQUIREMENTS
ASSET INFORMATION REQUIREMENTS for SuperKTP - Development for Atarii* Developments Ltd *Atarii is the name given to the client team as represented by BIM4SME as part of the #SuperKTP Rev Description Date:
Synergy: Building Information Modeling and
: Building Information Modeling and Assoc. Professor Rafael Sacks BIM Handbook Symposium Georgia Tech Atlanta, GA, 13 th March 2008 Introduction Both and BIM are deep process changes, in thinking and in
The RIBA Journal. Media Information 2015
The RIBA Journal Media Information 2015 Extreme spec 3D pointcloud scanning minus the GPS 09 Doors, windows and ironmongery Hospitalhof, Stuttgart 12 Analysis: Healthcare Are architects being left in the
Collaboration is Key for the Future of Architecture
Collaboration is Key for the Future of Architecture MBMO Architects Case Study Sydney Adventist Hospital (San), Wahroonga MBMO Architects www.mbmo.com.au MBMO Architects, one of Sydney s leading studios,
PDSA Special Report. You Can Develop Software Successfully
PDSA Special Report You Can Develop Software Successfully Almost everyone in business today has tried to develop custom software at one time or another. 74% of these projects (according to a recent study
PROGRAMME MANAGEMENT AND BUSINESS PLANNING
PROGRAMME MANAGEMENT AND BUSINESS PLANNING This paper describes what lessons were learned from the programme management and business planning which was done to support the operation of the Help Scheme
CALL FOR TENDERS TO DEVELOP A NEW WEBSITE FOR THE EUROPEAN CYCLISTS FEDERATION
CALL FOR TENDERS TO DEVELOP A NEW WEBSITE FOR THE EUROPEAN CYCLISTS FEDERATION www.ecf.com JUNE 2015 ECF Gratefully acknowledges financial support from the European Commission Introduction and goals:
Norsk Tipping AS. Responsible Gambling Platform. Helsinki, 11. september 2014. Bjørn Helge Hoffmann Chief Adviser Responsible Gaming
Norsk Tippings Responsible Gambling Platform Helsinki, 11. september 2014 Bjørn Helge Hoffmann Chief Adviser Responsible Gaming 17.09.2014 Norsk Tipping AS Agenda Brief introduction to Norsk Tipping Responsible
Building Construction and BIM in Japan
Building Construction and BIM in Japan Japan Federation of Construction Contractors, Research and Development Committee Technical Research Section Chairman Obayashi Corporation, Technical Research Institute
HULLEY & KIRKWOOD CONSULTING ENGINEERS LIMITED BIM PROJECT EXECUTION PLAN FOR [PROJECT TITLE] Date
HULLEY & KIRKWOOD CONSULTING ENGINEERS LIMITED BIM PROJECT EXECUTION PLAN FOR [PROJECT TITLE] Head Office Watermark Business Park 305 Govan Road Glasgow G51 2SE (t): 0141 332 5466 (f): 0870 928 1028 (e):
BIM Strategy for NHSScotland
BIM Strategy for NHSScotland Professor Bimal Kumar and Graham Hayne GCU BIM Partnership School of Engineering and Built Environment Glasgow Caledonian University Agenda Introduction to BIM GCU BIM Partnership
Bjørn Kjos (CEO) Oslo, 27. April 2006 Norwegian Air Shuttle ASA
Norwegian (NAS) Q1 2006 Bjørn Kjos (CEO) Oslo, 27. April 2006 Norwegian Air Shuttle ASA Strong revenue growth in Q1 539 MNOK in revenue in Q1 2006 Revenue growth of 69 % since Q1 2005 Revenue MNOK 600
The Agile Manifesto is based on 12 principles:
The Agile Manifesto is based on 12 principles: Customer satisfaction by rapid delivery of a useful product solution Welcome changing requirements, even late in development Working products are delivered
BIM: Transitioning the Industry through Education. Adam Matthews Education Lead UK Government BIM Task Group
BIM: Transitioning the Industry through Education Adam Matthews Education Lead UK Government BIM Task Group 2.32 Government will require fully collaborative 3D BIM (with all project and asset information,
LEGAL PROJECT MANAGEMENT
LEGAL PROJECT MANAGEMENT Cost management of litigation is becoming a focus of legislators in both Australia and the UK, in an attempt to streamline litigation and ensure costs are proportionate. The Civil
BIM BASICS AIRAH PRESENTATION SERIES. Mark Jacobson National BIM Operations Manager AE Smith & Son
BIM BASICS AIRAH PRESENTATION SERIES Mark Jacobson National BIM Operations Manager AE Smith & Son Presentation Content What will be covered Common terms and software utilised A basic overview of BIM workflows
BIM Best Practice to Cut Capital and Operational Expenditure: Maximizing Business Value. Professor Mustafa Alshawi
BIM Best Practice to Cut Capital and Operational Expenditure: Maximizing Business Value Professor Mustafa Alshawi Improving Project Performance Current Project Portfolio 1.83 B UAED ($500M) Award Winning
The role will require the management of consultancy and in-house teams in the successful execution of the estates strategy.
Senior Project Manager Job Description Reference: 102014/51 Job Title: Senior Project Manager Purpose of Role: The University is committed to providing an environment conducive to high quality teaching
Importance of Construction Management in Project Execution
Importance of Construction Management in Project Execution ARC Twelfth India Forum, Bangalore 10-11 July, 2014 Industry in Transition: The Information Driven Enterprise in a Connected World Rainer Lamping
The Basic Principles Of TEAMWORK
The Basic Principles Of TEAMWORK We re All In This Together Team Training The Value of Teamwork Traits of High-Performance Teams Develop Your Team s Success Factors Ideas for Team Roles SMART Goal Setting
Construction automation and productivity - Industry perspective
Construction automation and productivity - Industry perspective Vice President R&D, Ilkka Romo Skanska Oy 22.1.2013 1 22.1.2013 Ilkka Romo Skanska in short One of the world s leading companies in construction
05 SEP MORE FROM HANS VAN HEESWIJK ARCHITECTS MORE MUSEUM. Rieteiland House / Hans van Heeswijk Architects Selected Projects
SELECTED PROJECTS ArchDaily Broadcasting Van Bookmark Gogh this picture! Museum / Hans van Heeswijk Architects 05 SEP 2015 Projects Built Projects Selected Projects Museum Extension Amsterdam The Netherlands
The Role of the BIM Coordinator
The Role of the BIM Coordinator The objectives of this webinar are to: Introduce and define the role of Information Manager Introduce and define the emerging role and responsibilities of the BIM Coordinator.
Mature Agile with a twist of CMMI
Mature Agile with a twist of CMMI Carsten Ruseng Jakobsen Systematic Software Engineering [email protected] Kent Aaron Johnson AgileDigm, Incorporated [email protected] Abstract Systematic is
Every Student I Every Day I Every Possibility
For the Facilities Master Plan March 4, 2015 1 Introduction This has been prepared to describe a proposed process to be implemented in order to develop comprehensive Facility Master Plans for all schools
MASTER S DEGREE IN FINE ART PROGRAMME DESCRIPTION Adopted by the Board of KHiB on 27 October 2011
MASTER S DEGREE IN FINE ART PROGRAMME DESCRIPTION Adopted by the Board of KHiB on 27 October 2011 1. THE PROFILE AND OBJECTIVES OF THE STUDY PROGRAMME The Master s programme in Fine Art is an interdisciplinary
Centre for Entrepreneurship. Master of Science in. Innovation and. graduate
Centre for Entrepreneurship Master of Science in Innovation and Entrepreneurship graduate Prospectus WELCOME WELCOME Contents The University of Oslo Students currently studying at the Centre for Entrepreneurship
EGLC Conference 2015. Incentive System to Support Collaboration in Public Construction Projects
EGLC Conference 2015 Incentive System to Support Collaboration in Public Construction Projects Annett Schöttle 19. March 2015 INSTITUTE FOR TECHNOLOGY AND MANAGEMENT IN CONSTRUCTION, DEPARTMENT OF CIVIL
Project Management Handbook 2014. "To Understand the Causes of Things"
Management Handbook 2014 "To Understand the Causes of Things" AMENDMENT RECORD This document has been issued and amended as follows: - Isu. Rev. Reason for Issue / revision Date Issued to Team Stakeholders
Industry Solutions Construction Project Collaboration and Document Control Solutions for the Construction Sector
Industry Solutions Project Collaboration and Document Control Solutions for the Sector Industry Solutions McLaren Software Setting Standards New Opportunities, New Challenges Whether it be architects,
Hospice UK. Conference 2015. The Largest Annual Hospice Conference in the UK Sponsorship, Exhibition and Branding Opportunities
Hospice UK Conference 2015 The Largest Annual Hospice Conference in the UK Sponsorship, Exhibition and Branding Opportunities November 10-12 ACC, Liverpool We are delighted to offer you the opportunity
The European Renewable Energy Directive and international Trade. Laurent Javaudin Delegation of the European Commission to the U.S.
The European Renewable Energy Directive and international Trade Laurent Javaudin Delegation of the European Commission to the U.S. The European Union 27 Member States 490 million people 2 Outline The Present:
Overview of the features that provide the highest return on your investment in Tour de Force
ROI Summary Overview of the features that provide the highest return on your investment in Tour de Force Tour de Force provides many areas of functionality that will help automate your sales organization
Top 3 Reasons To Outsource Product Development By Ralph Paul Director of Product Engineering MPR Product Development
Top 3 Reasons To Outsource Product Development By Ralph Paul Director of Product Engineering MPR Product Development Copyright 2014 MPR Associates, Inc. All Rights Reserved In today s environment, almost
BACHELOR S DEGREE IN FINE ART PROGRAMME DESCRIPTION Adopted by the Board of KHiB on 27 October 2011
BACHELOR S DEGREE IN FINE ART PROGRAMME DESCRIPTION Adopted by the Board of KHiB on 27 October 2011 1. THE PROFILE AND OBJECTIVES OF THE STUDY PROGRAMME The Bachelor s programme in Fine Art is a study
Learning to see True Cost
Learning to see True Cost Working Paper n 13 Projet Lean Entreprise, TELECOM ParisTech Michael Ballé 1, ESG Consultants et TELECOM ParisTech This text is a working paper. Please do not cite, reproduce
The Strategic Deployment of Lean Construction
The Strategic Deployment of Lean Construction Presentation to LCI-Finland 2 nd December 2015 A 120bn Estate to be Operated, Maintained and renewed 18,000 structures, 34,000 drainage assets 4 million vehicles
China Center for Operations Excellence
China Center for Operations Excellence McKinsey China Leadership Institute A McKinsey Capability Center An innovative and lasting capability building program using the Beijing model factory set up jointly
Building Integrated Photovoltaic (BIPV)
Building Integrated Photovoltaic (BIPV) Jan-Willem Tolkamp, International Account Manager BIPV Solar power on buildings' conference, 20th October 2010 see it. feel it Index 1. From PV to BIPV 2. The BIPV
Asset Management Strategy (2013-2017) Doing things Differently A New Approach for a sustainable future
Asset Management Strategy (2013-2017) A New Approach for a sustainable future Contents Introduction... 2 The Asset Management Vision, Policy Statement & Strategic Themes... 5 Part B The Asset Management
Preparing for a Trade Show: How to Market your Company Effectively. Piers Bocock
Preparing for a Trade Show: How to Market your Company Effectively Piers Bocock Workshop Agenda Introductions and expectations Purpose of this seminar The importance of marketing Trade shows as a marketing
APPENDIX A (CFO/263/09) Merseyside Fire & Rescue Service ICT Outsourcing Procurement Support. Final Report
Merseyside Fire & Rescue Service ICT Outsourcing Procurement Support Final Report Version 1.1 Oct 2009 Contents 1. Executive Summary...3 2. Context and Background...3 3. Deliverables and Value Added...
Document Commentary. AIA Document C191 2009, Standard Form Multi-Party Agreement for Integrated Project Delivery
Document AIA Document C191 2009, Standard Form Multi-Party Agreement for Integrated Project Delivery INTRODUCTION Current practice in the construction industry promotes inefficiency when the key project
IMPLEMENTING LEAN SIX SIGMA: A CASE STUDY IN CONCRETE PANEL PRODUCTION
IMPLEMENTING LEAN SIX SIGMA: A CASE STUDY IN CONCRETE PANEL PRODUCTION Celep Oguz 1, Yong-Woo Kim 2, John Hutchison 3, and Seungheon Han 4 ABSTRACT Lean Six Sigma method is recognized widely and has been
CPIx on Line. Pre-Contract Building Information Modelling (BIM) Execution Plan (BEP) Project Name: Project Address: Project Number: Date:
CPIx on Line Pre-Contract Building Information Modelling (BIM) Execution Plan (BEP) Project Name: Project Address: Project Number: Date: Document No: Date: April 2013 Revision: v2.0 Status: For review
Financing Public Transport
Financing Public Transport Oslo s long term funding commitment Viajeo PLUS, Rio de Janeiro, March 23rd 2015 Hanne Bertnes Norli, Development director, Ruter As Ruter: PT Authority for the Norwegian Capital
PERFORMANCE MANAGEMENT Planning & Goal Setting
PERFORMANCE MANAGEMENT Planning & Goal Setting To whom much is given, much is expected. Leadership Development Series Summer 2011 Areas We Will Cover Today 1. Discuss our collective lessons and learnings
Lessons all can learn from Lean Car Dealers
Lessons all can learn from Lean Car Dealers Lean Enterprise Australia Summit, Melbourne David Brunt February 26 th & 27 th 2008 1 Lean Enterprise Academy Objectives To introduce a practical & systematic