CAPITAL PROGRAMS COMMITTEE. Enterprise Asset Management (EAM) Status Update. March 2014

Size: px
Start display at page:

Download "CAPITAL PROGRAMS COMMITTEE. Enterprise Asset Management (EAM) Status Update. March 2014"

Transcription

1 CAPITAL PROGRAMS COMMITTEE Enterprise Asset Management (EAM) Status Update March

2 EAM Project Objectives The EAM project was intended to achieve the following objectives: Provide asset tracking, condition assessments and replacement capabilities for METRO s assets; Replace existing work order systems for bus fleet maintenance, rail fleet maintenance and facilities maintenance; Provide State of Good Repair (SOGR) reporting. 2

3 Current State of EAM Project Through the Business Process Assessment (BPA) phase of the project, the stakeholders began questioning Trapeze on how certain processes were going to be accomplished and the following was learned: The Trapeze system would not be able to replace all of the functionality of the SAP work order system, leaving a significant delta of capability for the affected departments Trapeze s solution to the above problem was to continue with the SAP work order system and create several interfaces to duplicate data in both systems with the Trapeze application as the user s front-end interface This solution would mean many interfaces, with the final count at approximately 25, which is an extraordinary amount of interfaces and increases METRO s risk of having dependable data This solution would also mean that METRO would have to maintain, troubleshoot and regularly upgrade the original SAP work order system as well as the new Trapeze EAM system, along with 25 interfaces 3

4 Timeline October 2011 FTA grant awarded to METRO for SOGR program April 2012 METRO Board authorized contract with Trapeze for EAM system September 2012 Project began January Business Process Assessment (BPA) presented to METRO for review and approval January 2013 August Multiple meetings were held with stakeholders to review the specifics of the proposed processes October 2013 Project transitioned to IT and detailed meetings were held in an effort to resolve stakeholder process concerns November Trapeze proposed that SAP work order system stay in place with interfaces to their product to resolve some of the process concerns December 2013 to Present IT and Stakeholders discussed METRO s options going forward 4

5 Three Go-Forward Scenarios Scenario 1 Continue current EAM project with Trapeze Significant impact to business Throwing good money after bad Two systems to maintain instead of one 25 interfaces to maintain Difficult to upgrade in the future Scenario 2 Continue with Rail portion of EAM only Not viable. Such a significant scope modification would require a new procurement Scenario 3 SAP solution for SOGR and all work order functions Continue with SAP work order system for bus maintenance; bring in Rail and Facilities Maintenance Implement new user interface to provide mobile field work capability for SOGR Implement and build Business Intelligence (BI) for SOGR reporting 5

6 Recommend Scenario 3 - SAP solution for SOGR and all work order functions Elect to take off-ramp with Trapeze and terminate the contract Receive refund of software licenses Pay final BPA milestone payment Implement SAP solution for all SOGR and work order needs for Bus, Rail & Facilities Maintenance 6

7 Grant Expenditures and Sunk Costs Grant Grant Budget Actual Grant Draw Comments Hardware acquisition $80,000 $0 Software acquisition $2,630,000 $760,511 Project Management (labor) $502,000 $609,126 $3,212,000 $1,369,637 Estimated Sunk Costs Total costs to be written off initially $1,568,044 Reimbursement of license fees -$765,641 Reimburseable to METRO per the contract "off ramp" Payment of BPA milestone $257,397 Payable to Trapeze per the contract "off ramp" Other costs TBD $1,059,800 Does not include other costs that could arise 7

8 Next Steps Proceed with Trapeze contract termination Prepare scope and proceed with procurement for SAP SOGR solution implementation 8

Business Case for the New Electronic Payments Program

Business Case for the New Electronic Payments Program Finance & Administration Committee Information Item IV-A June 9, 2011 Business Case for the New Electronic Payments Program Page 102 of 253 Washington Metropolitan Area Transit Authority Board Action/Information

More information

Asset Management Systems Information

Asset Management Systems Information Asset Management Systems Information Required to Maintain Service Delivery and Asset State Of Good Repair Willem Ebersöhn Ph.D. Vice president Encada. LLC. Valerie Marcolongo President Encada. LLC. 4/18/2012

More information

SAN MATEO COUNTY OFFICE OF EDUCATION CLASS TITLE: ADMINISTRATOR, INFORMATION TECHNOLOGY SERVICES

SAN MATEO COUNTY OFFICE OF EDUCATION CLASS TITLE: ADMINISTRATOR, INFORMATION TECHNOLOGY SERVICES SAN MATEO COUNTY OFFICE OF EDUCATION CLASS TITLE: ADMINISTRATOR, INFORMATION TECHNOLOGY SERVICES BASIC FUNCTION: Under the direction of the Associate Superintendent, Fiscal & Operational Services, plan,

More information

FD-101. Electronic Commodity Ordering System (ECOS) & Web Based Supply Chain Management (WBSCM) Todd Griffith FDD Systems Branch May 2008

FD-101. Electronic Commodity Ordering System (ECOS) & Web Based Supply Chain Management (WBSCM) Todd Griffith FDD Systems Branch May 2008 FD-101 Electronic Commodity Ordering System (ECOS) & Web Based Supply Chain Management (WBSCM) Todd Griffith FDD Systems Branch May 2008 Overview ECOS Update 2007 Accomplishments 2008 Accomplishments &

More information

CLASS SPECIFICATION. Business Intelligence Supervisor

CLASS SPECIFICATION. Business Intelligence Supervisor San Diego Unified Port District Class Code: B843-UE08 CLASS SPECIFICATION FLSA Status: EEOC Job Category: Classified: Union Representation: Exempt Professionals No Unrepresented GENERAL PURPOSE Under general

More information

Module: Sharepoint Administrator

Module: Sharepoint Administrator Module: Sharepoint Administrator Mode: Classroom Duration: 40 hours This course teaches IT Professionals to design and deploy Microsoft SharePoint 2010. Course Outline: Module 1: Designing a Logical Architecture

More information

Audit of the Management of Projects within Employment and Social Development Canada

Audit of the Management of Projects within Employment and Social Development Canada Unclassified Internal Audit Services Branch Audit of the Management of Projects within Employment and Social Development Canada February 2014 SP-607-03-14E Internal Audit Services Branch (IASB) You can

More information

Building Your Strategic Business Case for HR Technology. Speaker: Kristie Evans Managing Principal HR Project Manager PM Instructor

Building Your Strategic Business Case for HR Technology. Speaker: Kristie Evans Managing Principal HR Project Manager PM Instructor Building Your Strategic Business Case for HR Technology Speaker: Kristie Evans Managing Principal HR Project Manager PM Instructor Agenda Today s Goals HR Value Outcomes Break 10 am Methodologies Business

More information

This bulletin addresses multiple steps that should be taken to address both scenarios. Labor reimbursement is available to authorized dealers.

This bulletin addresses multiple steps that should be taken to address both scenarios. Labor reimbursement is available to authorized dealers. SOLUTIONS SUPPORT DIVISION Bulletin Number 7829 Date: 02/16/11 From: SSD Subject: Printer Lock-up, Intermittent Printing, Copying, Faxing bizhub C35: 016 Two tendencies of certain bizhub C35 MFPs have

More information

SHARED SERVICES CAPITAL - CORNERSTONE

SHARED SERVICES CAPITAL - CORNERSTONE Filed: May, 0 EB-0-00 Exhibit D Schedule Page of SHARED SERVICES CAPITAL - CORNERSTONE.0 OVERVIEW The Cornerstone Project is part of the overall information technology ( IT ) strategy to replace several

More information

Switching from a PTA to a PTO Questions and Answers

Switching from a PTA to a PTO Questions and Answers Switching from a PTA to a PTO Questions and Answers Aren t we required to have a PTA? No. There are no Fulton County School System requirements that a school have a PTA, PTO or any kind of parent organization.

More information

FREQUENTLY ASKED QUESTIONS ABOUT ACCOUNTS PAYABLE WHEN DOES THE STATE OF MARYLAND PAY MY VENDORS?

FREQUENTLY ASKED QUESTIONS ABOUT ACCOUNTS PAYABLE WHEN DOES THE STATE OF MARYLAND PAY MY VENDORS? FREQUENTLY ASKED QUESTIONS ABOUT ACCOUNTS PAYABLE WHEN DOES THE STATE OF MARYLAND PAY MY VENDORS? The state attempts to pay all vendors within 30 days of the Service Date. This is defined as the later

More information

WORLD BANK WORLD BANK

WORLD BANK WORLD BANK XV. Financial Planning Public Transport Planning and Reform: An Introduction Public Transport Financial Planning Systematic approach that helps produce a financially sustainable program for implementing

More information

A Comprehensive Approach to Master Data Management Testing

A Comprehensive Approach to Master Data Management Testing A Comprehensive Approach to Master Data Management Testing Abstract Testing plays an important role in the SDLC of any Software Product. Testing is vital in Data Warehousing Projects because of the criticality

More information

-1- PSEG-LI Update of LIPA SGIP Full Docw-NYISO reqmts above 10 MW 10-27-14

-1- PSEG-LI Update of LIPA SGIP Full Docw-NYISO reqmts above 10 MW 10-27-14 PSEG-Long Island Smart Grid Small Generator Interconnection Procedures for New Distributed Resources 20 MW or Less Connected in Parallel with LIPA s Radial Distribution Systems -1- PSEG-LI Update of LIPA

More information

Mobility Management Project Development Process. NCPTA Conference April 7, 2014

Mobility Management Project Development Process. NCPTA Conference April 7, 2014 Mobility Management Project Development Process NCPTA Conference April 7, 2014 Project Background Funding: NCDOT FTA Section 5310 grant for $198,000 Period of Performance: December 2011- September 2013

More information

Appendix D. Minimum Requirements For Developmental Resources. For

Appendix D. Minimum Requirements For Developmental Resources. For z Appendix D Minimum For Developmental Resources For 2016 Request For Proposals For Long-Term Renewable Generation Resources For Entergy Louisiana, LLC Entergy Services, Inc. June 8, 2016 MINIMUM REQUIREMENTS

More information

Transit Asset Management MBTA Initiatives

Transit Asset Management MBTA Initiatives Transit Asset Management MBTA Initiatives Standing Committee on Audit and Finance March 3, 2015 1 Agenda TAM overview MAP 21 requirements MBTA TAM initiatives: Asset Management Plan Decision Support Tool

More information

Key Criteria for Choosing an Enterprise Asset Management System

Key Criteria for Choosing an Enterprise Asset Management System Key Criteria for Choosing an Enterprise Asset Management System February, 2013 E-ISG Asset Intelligence, LLC 3500 Boston Street Suite 316 Baltimore, MD 21224 Phone: 866.845.2416 Website: www.e-isg.com

More information

Transportation Management

Transportation Management TRANSPORTATION PERSPECTIVES: Establishing the Best Long-term Strategy for Your Company Flexible Deployment Options for an Expanding Market The range of sourcing options available today provides great flexibility

More information

SAP ERP Upgrade Checklist Project Preparation

SAP ERP Upgrade Checklist Project Preparation A SAP ERP Upgrade Checklist Project Preparation Upgrade Project Phase Project Preparation Definition From the project perspective the project preparation phase includes: Learning about the new functionality

More information

Office of the Auditor General. Audit of Accounts Payable. Tabled at Audit Committee November 26, 2015

Office of the Auditor General. Audit of Accounts Payable. Tabled at Audit Committee November 26, 2015 Office of the Auditor General Audit of Accounts Payable Tabled at Audit Committee November 26, 2015 This page has been intentionally left blank Contents Executive Summary... 2 Introduction... 2 Background...

More information

Chapter 8: Fundamentals of Capital Budgeting

Chapter 8: Fundamentals of Capital Budgeting Chapter 8: Fundamentals of Capital Budgeting-1 Chapter 8: Fundamentals of Capital Budgeting Big Picture: To value a project, we must first estimate its cash flows. Note: most managers estimate a project

More information

FISCAL YEAR 2014 SOLICITATION FOR PROPOSALS FOR FEDERAL JOB ACCESS AND REVERSE COMMUTE AND NEW FREEDOM PROGRAM FUNDS EVALUATION CRITERIA

FISCAL YEAR 2014 SOLICITATION FOR PROPOSALS FOR FEDERAL JOB ACCESS AND REVERSE COMMUTE AND NEW FREEDOM PROGRAM FUNDS EVALUATION CRITERIA FISCAL YEAR 2014 SOLICITATION FOR PROPOSALS FOR FEDERAL JOB ACCESS AND REVERSE COMMUTE AND NEW FREEDOM PROGRAM FUNDS EVALUATION CRITERIA Los Angeles County Metropolitan Transportation Authority (LACMTA)

More information

ORACLE PROJECT PLANNING AND CONTROL

ORACLE PROJECT PLANNING AND CONTROL ORACLE PROJECT PLANNING AND CONTROL (Formerly Oracle Project Management) KEY FEATURES COLLABORATIVE PROJECT PLANNING Define a project work breakdown structure to align plans to execution Coordinate financial

More information

Request for Project Approval

Request for Project Approval Date Issued: 04/13/2016 Page #: 1 of 5 1.0 POLICY OVERVIEW 1.1. This policy establishes uniform practices and procedures to be followed for authorizing ITD software projects. 1.2. LAUSD s Information Technology

More information

SAP BOBJ. Participants will gain the detailed knowledge necessary to design a dashboard that can be used to facilitate the decision making process.

SAP BOBJ. Participants will gain the detailed knowledge necessary to design a dashboard that can be used to facilitate the decision making process. SAP BOBJ 1. BOX310 SAP Business Objects Dashboards 4.0: Core Participants will gain the detailed knowledge necessary to design a dashboard that can be used to facilitate the decision making process. Participants

More information

RFP 43-14: STREETCAR OPERATIONS & MAINTENANCE SERVICE CONTRACT. Cincinnati Streetcar Project June 2015

RFP 43-14: STREETCAR OPERATIONS & MAINTENANCE SERVICE CONTRACT. Cincinnati Streetcar Project June 2015 RFP 43-14: STREETCAR OPERATIONS & MAINTENANCE SERVICE CONTRACT Cincinnati Streetcar Project June 2015 O&M timeline March 2015 - O&M RFP proposals due April-May 2015 Proposal evaluation and negotiations

More information

Telecommunications Systems Manager I (Supervisor) Essential Task Rating Results

Telecommunications Systems Manager I (Supervisor) Essential Task Rating Results Telecommunications Systems Manager I (Supervisor) Essential Task Rating Results 1 2 3 4 5 6 7 8 9 10 11 12 13 Supervise activities and direct personnel in the implementation of various departmental programs

More information

*HB0380S03* H.B. 380 3rd Sub. (Cherry) LEGISLATIVE GENERAL COUNSEL Approved for Filing: C.J. Dupont 03-09-16 7:25 PM

*HB0380S03* H.B. 380 3rd Sub. (Cherry) LEGISLATIVE GENERAL COUNSEL Approved for Filing: C.J. Dupont 03-09-16 7:25 PM LEGISLATIVE GENERAL COUNSEL Approved for Filing: C.J. Dupont 03-09-16 7:25 PM H.B. 380 3rd Sub. (Cherry) Senator Kevin T. Van Tassell proposes the following substitute bill: 1 UTAH COMMUNICATIONS AUTHORITY

More information

Insert Client Name Request for Proposal for Security Risk Assessment Services Consulting

Insert Client Name Request for Proposal for Security Risk Assessment Services Consulting Insert Client Name Request for Proposal for Security Risk Assessment Services Consulting Release Date: Closing Date: SUBMIT THE PROPOSAL TO: Insert Name Insert Title Insert Email or Physical Address Table

More information

The Financial Planning Analysis and Reporting System (FPARS) Project: Implementation Status Update

The Financial Planning Analysis and Reporting System (FPARS) Project: Implementation Status Update STAFF REPORT ACTION REQUIRED The Financial Planning Analysis and Reporting System (FPARS) Project: Implementation Status Update Date: March 24, 2014 To: From: Wards: Reference Number: Government Management

More information

Office of Budget and Financial Planning

Office of Budget and Financial Planning The Office of Budget and Financial Planning (OBFP) is a professional service organization in the Institute s financial administration area. The mission of the office is to provide value added integrated

More information

City of Lynchburg. Information Technology Strategic Plan FY16 FY18

City of Lynchburg. Information Technology Strategic Plan FY16 FY18 City of Lynchburg Information Technology Strategic Plan FY18 August, 2015 1 FY18 I. BACKGROUND and OVERVIEW Every three years, the City of Lynchburg s Information Technology Department (IT) spearheads

More information

Getting Started with Business Intelligence

Getting Started with Business Intelligence Getting Started with Business Intelligence Tips and Tools to Ensure Success 153 Kearny St., San Francisco, CA [email protected] (866) 940-1496 Introduction Identifying and selecting a Business Intelligence

More information

Information Technology Project Management (ITPM)

Information Technology Project Management (ITPM) FUNCTIONAL AREA 10 Project Management (ITPM) Incumbents in this functional area direct information technology system solution and/or improvement projects for cost, time, scope, risk, and quality. They

More information

Schedule A Support and Maintenance Agreement

Schedule A Support and Maintenance Agreement Page 1 of 5 During the Term and upon SSN s acceptance of an executed Order Form that specifies the Customer s designated support plan for the applicable Software (the Covered Services ), SSN shall provide

More information

ATTACHMENT II - WRITTEN PROPOSAL RESPONSE AND GUIDELINES

ATTACHMENT II - WRITTEN PROPOSAL RESPONSE AND GUIDELINES ATTACHMENT II - WRITTEN PROPOSAL RESPONSE AND GUIDELINES RFP#CON2014-18 Attachments I through VI from the Response Teams will be evaluated and scored (1000 points total) in accordance with the criteria

More information

-25 A-se =, zai,*,:.-.a -322-295;

-25 A-se =, zai,*,:.-.a -322-295; Los Angeles County Service Authority for Freeway Emergencies %'a- 6' B d,-a 2. *&a, -j 1-a -25 A-se =, zai,*,:.-.a -322-295; I SAFE BOARD MEETING JUNE 28,2012 SUBJECT: ACTION: ADOPT THE FISCAL YEAR 201

More information

STATE OF MONTANA MONTANA DEPARTMENT OF TRANSPORTATION JOB PROFILE Update Formal Review

STATE OF MONTANA MONTANA DEPARTMENT OF TRANSPORTATION JOB PROFILE Update Formal Review STATE OF MONTANA MONTANA DEPARTMENT OF TRANSPORTATION JOB PROFILE Update Formal Review 6/3/2013 Date Submitted SECTION I - Identification Working Title: Multimodal Planning Bureau Chief Department: Transportation

More information

POSITION QUALIFICATIONS. Minimum Experience (Yrs)

POSITION QUALIFICATIONS. Minimum Experience (Yrs) POSITION QUALIFICATIONS Core Labor Category Skill Minimum Education Minimum Experience (Yrs) Labor Category Description Technical Manager, Principal Bachelors Degree 12 Technical Manager, Senior Bachelors

More information

Laura J. Zale. Southeastern Pennsylvania Transportation Authority. Transportation Research Board 10 th Conference on Transportation Asset Management

Laura J. Zale. Southeastern Pennsylvania Transportation Authority. Transportation Research Board 10 th Conference on Transportation Asset Management Laura J. Zale Southeastern Pennsylvania Transportation Authority Transportation Research Board 10 th Conference on Transportation Asset Management April 28, 2014 Presentation Outline Transit asset management

More information

Designing a Microsoft SharePoint 2010 Infrastructure

Designing a Microsoft SharePoint 2010 Infrastructure Designing a Microsoft SharePoint 2010 Infrastructure Course Details Course Code: Duration: Notes: 10231B 5 days This course syllabus should be used to determine whether the course is appropriate for the

More information

Playing The Project Management Game

Playing The Project Management Game Playing The Project Management Game Tools and Techniques to Win the Game Dean Athanassiades, PMP Nancy Stetson, PMP Version 2003-12-02 (c) Dean Athanassiades 2003 1 Presenters Dean Athanassiades, PMP Philips

More information

Now that you have a fleet management system, what should you do with it?

Now that you have a fleet management system, what should you do with it? Now that you have a fleet management system, what should you do with it? By Brad Kelley Overview Typical fleet system use Understanding where your data lives Reporting Key Performance Indicators (KPI)

More information

Optimizing the Source to Contract Process to Maximize and Lock in Savings Patrick Eckhert Cardinal Health Head of Indirect Procurement

Optimizing the Source to Contract Process to Maximize and Lock in Savings Patrick Eckhert Cardinal Health Head of Indirect Procurement Optimizing the Source to Contract Process to Maximize and Lock in Savings Patrick Eckhert Cardinal Health Head of Indirect Procurement Program Goals and Overview Goal Share our strategy and approach for

More information

FTA OVERSIGHT PROGRAMS

FTA OVERSIGHT PROGRAMS U.S. Department of Transportation Federal Transit Administration FTA OVERSIGHT PROGRAMS FTA Region IV 2008 Conference 1 Session Outline Annual Grantee Assessment Oversight Activities Reviews (General,

More information

THOMAS G. DAY SENIOR VICE PRESIDENT, INTELLIGENT MAIL AND ADDRESS QUALITY PRITHA N. MEHRA VICE PRESIDENT, BUSINESS MAIL ENTRY AND PAYMENT TECHNOLOGIES

THOMAS G. DAY SENIOR VICE PRESIDENT, INTELLIGENT MAIL AND ADDRESS QUALITY PRITHA N. MEHRA VICE PRESIDENT, BUSINESS MAIL ENTRY AND PAYMENT TECHNOLOGIES March 31, 2009 THOMAS G. DAY SENIOR VICE PRESIDENT, INTELLIGENT MAIL AND ADDRESS QUALITY PRITHA N. MEHRA VICE PRESIDENT, BUSINESS MAIL ENTRY AND PAYMENT TECHNOLOGIES GEORGE W. WRIGHT VICE PRESIDENT, INFORMATION

More information

Accountable Plan. The Watson CPA Group

Accountable Plan. The Watson CPA Group Accountable Plan The Plan Included in this Accountable Plan packet is a sample plan for adoption into your company s corporate governance and a sample reimbursement worksheet for business expenses. If

More information

114CSR61 WEST VIRGINIA LEGISLATIVE RULE INSURANCE COMMISSIONER SERIES 61 CREDIT PERSONAL PROPERTY INSURANCE

114CSR61 WEST VIRGINIA LEGISLATIVE RULE INSURANCE COMMISSIONER SERIES 61 CREDIT PERSONAL PROPERTY INSURANCE 114CSR61 WEST VIRGINIA LEGISLATIVE RULE INSURANCE COMMISSIONER SERIES 61 CREDIT PERSONAL PROPERTY INSURANCE Section 114-61-1. General. 114-61-2. Definitions. 114-61-3. Amount, Term and Coverage of Credit

More information

Request for Expressions of Interest IT System Consultant

Request for Expressions of Interest IT System Consultant Election Commission Secretariat Preparation of Electoral Roll with Photographs and Facilitating the Issuance of National Identity Card Project Islamic Foundation Building Agargaon, Dhaka. No. PERP&FINIDC/Ops/048/2011/2608

More information

SEATAC FUEL FACILITIES LLC

SEATAC FUEL FACILITIES LLC SEATAC FUEL FACILITIES LLC 2015 ANNUAL REPORT Pursuant to the requirements of the Company Continuing Disclosure Agreement dated as of May 22, 2013 (the "Disclosure Agreement") executed by SEATAC FUEL FACILITIES

More information

Mayor Savage and Members of Halifax Regional Council. Amanda Whitewood, Director, Finance & ICT

Mayor Savage and Members of Halifax Regional Council. Amanda Whitewood, Director, Finance & ICT REVISED Jan 14/16 (Slide 15 only) P.O. Box 1749 Halifax, Nova Scotia B3J 3A5 Canada Item No. 6 Committee of the Whole January 13, 2016 TO: SUBMITTED BY: Mayor Savage and Members of Halifax Regional Council

More information

HOW TO GET MORE OUT OF ORACLE AGILE PLM

HOW TO GET MORE OUT OF ORACLE AGILE PLM HOW TO GET MORE OUT OF ORACLE AGILE PLM Presented by Domain Systems, Inc. Or email [email protected] WHO IS DOMAIN SYSTEMS? Most Experienced Longest Standing Agile Only Focus End to End Implementation

More information

Intranet Buyers Workbook

Intranet Buyers Workbook Intranet Buyers Workbook A clear path to a new intranet Trying to select a new intranet? This easy guide leads you through the 10 key steps in a straightforward but thorough evaluation and purchase process.

More information

PROPOSAL XXX INFRASTRUCTURE MIGRATION PROJECT (RFP 20XX.XX.XX)

PROPOSAL XXX INFRASTRUCTURE MIGRATION PROJECT (RFP 20XX.XX.XX) PROPOSAL XXX INFRASTRUCTURE MIGRATION PROJECT (RFP 20XX.XX.XX) PREPARED FOR: CLIENT Address City, Province / State, Index Contact: Name, Title PREPARED BY: VIMEX TECHNOLOGIES 604-126 West 3 rd Street North

More information

PAYMENT FOR WORKS, GOODS AND SERVICES FINANCIAL PROCEDURE 11

PAYMENT FOR WORKS, GOODS AND SERVICES FINANCIAL PROCEDURE 11 CHIEF FINANCE OFFICER PAYMENT FOR WORKS, GOODS AND SERVICES FINANCIAL PROCEDURE 11 OWNER: HEAD OF FINANCIAL CONTROL Version 2.0 September 2014 FINANCIAL PROCEDURE PAYING FOR WORKS, GOODS AND SERVICES CONTENTS

More information

Program Summary. Criterion 1: Importance to University Mission / Operations. Importance to Mission

Program Summary. Criterion 1: Importance to University Mission / Operations. Importance to Mission Program Summary DoIT supports and provides the infrastructure and custom development for NIU s core financial systems: PeopleSoft Financial Management (PS- FMS) provides financial information to over 200

More information

FINAL AUDIT REPORT WITH RECOMMENDATIONS Internal Operations No. 08-005

FINAL AUDIT REPORT WITH RECOMMENDATIONS Internal Operations No. 08-005 FINAL AUDIT REPORT WITH RECOMMENDATIONS Internal Operations No. 08-005 SUBJECT: Review of Trapeze, the Bus Rail DATE: March 25, 2008 Scheduling and Dispatch System FROM: TO: IG/OIG Helen Lew /s/ GMGR John

More information

PLANNING FOR YOUR PROJECT

PLANNING FOR YOUR PROJECT PLANNING FOR YOUR PROJECT This tool kit has been designed to provide an introduction to planning. It will help you to think about the reasons behind why you should plan, what to plan and the variations

More information

ITS Projects Systems Engineering Process Compliance Checklist

ITS Projects Systems Engineering Process Compliance Checklist ITS Projects Systems Engineering Process Compliance Checklist FHWA Final Rule (23 CFR 940) This checklist is to be completed by the MDOT or LPA Project Management Staff. Please refer to the accompanying

More information

This policy is supplemented by the Purchasing Card User's Manual that gives detailed PCard operating and processing procedures.

This policy is supplemented by the Purchasing Card User's Manual that gives detailed PCard operating and processing procedures. Procedure No. 31.604 Purchasing Card (PCard) Policy Date Issued: 9/9/04 Date Effective: 9/9/04 Issued By: Finance & Administration Division Purpose: The Clarion University Purchasing Card (PCard) Program

More information

ENGINEERING ADMISSIONS GUIDE

ENGINEERING ADMISSIONS GUIDE 2016-2017 ENGINEERING ADMISSIONS GUIDE 105 APPLICANTS Thank you for your application to the Faculty of Applied Science & Engineering at the University of Toronto. THE APPLICATION CYCLE AT A GLANCE 1 ACCESS

More information

NEGOTIATION: A PERSPECTIVE ON HOW TO IMPROVE THE NEGOTIATION PROCESS AS A TEAM - WHAT S BAD AND HOW TO FIX IT

NEGOTIATION: A PERSPECTIVE ON HOW TO IMPROVE THE NEGOTIATION PROCESS AS A TEAM - WHAT S BAD AND HOW TO FIX IT NEGOTIATION: A PERSPECTIVE ON HOW TO IMPROVE THE NEGOTIATION PROCESS AS A TEAM - WHAT S BAD AND HOW TO FIX IT by Yolanda Delgadillo Personnel Analyst II City of Lynwood INTRODUCTION Most government agencies

More information