1 RFP 43-14: STREETCAR OPERATIONS & MAINTENANCE SERVICE CONTRACT Cincinnati Streetcar Project June 2015
2 O&M timeline March O&M RFP proposals due April-May 2015 Proposal evaluation and negotiations June 2015 City Council selects preferred method July SORTA Board approves contract award July-August 2015 O&M contractor mobilization Sept. - Dec vehicle delivery April completion of civil construction September start of passenger service
3 SORTA s objectives Competitively procure an Operations & Maintenance contractor for the streetcar using Federal procurement guidelines Use the level of service established in the FTA grant applications and funding established by City Assure the best value for the City in terms of quality and price
4 Roles City selects the method of service delivery (turn-key or management contract) SORTA conducts the procurement and awards the contract
5 The two methods All proposers were required to submit two methods: Turn-key contract contractor provides all employees; fixedprice contract. Contractor assumes financial risks for operating based on contract scope. Management contract - contractor manages operations and maintains the system for a fixed price. At an additional cost, SORTA provides certain employees (streetcar operators, facility maintenance/janitorial). Total cost of operating the streetcar would change based on several factors including negotiations with new bargaining unit. Risk is shared.
6 Strict Federal procurement process Not a simple Invitation for Bid process -- low price Request for Proposal (RFP) -- best overall value Same model SORTA uses for other O&M procurements, including Access paratransit operator Evaluation committee: SORTA and City representatives Multi-step rating process, interviews and negotiations
7 Timeline for procurement process RFP issued in January; proposals received by end of March Evaluation of proposals in April; all proposers interviewed Best and final offers requested from all firms and negotiations with top firms in May City Council selection of preferred method in June SORTA contract award in July to keep project on schedule
8 Evaluation criteria RFP evaluation criteria, in order of importance: Project approach: understanding of what is required; safety and customer service; maximizing resources, etc. Qualifications: experience of the firm and staff assigned to Cincinnati Streetcar Price: fixed price to operate and maintain Specific plans: start-up preparations and testing; operations and maintenance of the vehicles and electrical system; operating facility maintenance, etc.
9 What is being shared today The best-value pricing for the Cincinnati Streetcar operations and maintenance, based on: The selected proposal for the turn-key contract The selected proposal for the management contract Tentative costs related to SORTA-provided employees for management contract approach only Costs for City s and SORTA s respective responsibilities
10 What is being shared today For both turn-key and management contract methods: Contractor cost (fixed price) SORTA s streetcar costs, reimbursed by the City: Administration including support for Federal compliance, contract oversight, customer service, communications, etc. Direct costs including electricity to operate the streetcar, fare media, ticket vending machine maintenance, etc. City s costs
11 Additional SORTA-provided employee costs: management contract method only Estimated wages and benefits for streetcar operators and facility maintenance/janitorial employees provided by SORTA These tentative costs are based on: June 2 preliminary agreement with ATU Local 627 Comparable Metro wages and benefits Comparable work rules for Metro represented employees, which would add additional positions NOTE: There are a number of cost factors that cannot be fully known until a collective bargaining agreement is negotiated
12 Turn-key contract method Based on service plan in FTA grant and O&M Agreement Contractor s price proposal (fixed) SORTA costs paid by City (fixed) City s additional costs for services/ administration* Electric and other direct costs Total projected cost City funding Startup $1,100,000 $1,100,000 $1,100,000 Year 1 $3,269,921 $261,594 $257,234 $248,386 $4,037,135 $4,200,000 Year 2 $3,308,166 $264,653 $264,951 $253,168 $4,090,938 $4,284,000 Year 3 $3,478,734 $278,299 $272,900 $258,053 $4,287,985 $4,369,680 Year 4 $3,616,542 $289,323 $281,087 $263,043 $4,449,996 $4,457,074 Year 5 $3,701,930 $296,154 $289,519 $268,143 $4,555,746 $4,546,215 Total, Year 1-5 $17,375,293 $1,390,023 $1,365,690 $1,290,792 $21,421,800 $21,856,969 Option Year 1 $3,736,259 $298,901 $298,205 $273,353 $4,606,718 $4,637,139 Option Year 2 $3,861,183 $308,895 $307,151 $278,677 $4,755,906 $4,729,882 Option Year 3 $3,972,753 $317,820 $316,365 $284,118 $4,891,057 $4,824,480 Option Year 4 $4,096,655 $327,732 $325,856 $289,679 $5,039,922 $4,920,969 Option Year 5 $4,191,127 $335,290 $335,632 $295,361 $5,157,410 $5,019,389 Total, OY 1-5 $19,857,977 $1,588,638 $1,583,209 $1,421,189 $24,451,014 $24,131,859 Grand Total $38,333,271 $2,978,662 $2,948,900 $2,711,981 $46,972,813 $47,088,828 *Not yet finalized
13 Management contract method Based on service plan in FTA grant and O&M Agreement Contractor s price proposal (fixed) SORTA-provided labor costs* SORTA costs paid by City City s additional costs for services/ administration** Electric and other direct costs Total projected cost City funding Startup $950,000 $323,216 $1,273,216 $1,100,000 Year 1 $2,531,750 $1,365,578 $311,786 $257,234 $248,386 $4,714,734 $4,200,000 Year 2 $2,537,284 $1,404,922 $315,376 $264,951 $253,168 $4,775,701 $4,284,000 Year 3 $2,679,399 $1,446,731 $330,090 $272,900 $258,053 $4,987,172 $4,369,680 Year 4 $2,800,774 $1,491,230 $343,360 $281,087 $263,043 $5,179,495 $4,457,074 Year 5 $2,878,227 $1,538,666 $353,351 $289,519 $268,143 $5,327,907 $4,546,215 Total, Year 1-5 $13,427,434 $7,247,127 $1,653,965 $1,365,690 $1,290,792 $24,985,008 $21,856,969 Option Year 1 $2,893,299 $1,589,311 $358,609 $298,205 $273,353 $5,412,777 $4,637,139 Option Year 2 $2,973,407 $1,643,461 $369,350 $307,151 $278,677 $5,572,047 $4,729,882 Option Year 3 $3,043,532 $1,701,446 $379,598 $316,365 $284,118 $5,725,060 $4,824,480 Option Year 4 $3,124,554 $1,763,624 $391,054 $325,856 $289,679 $5,894,767 $4,920,969 Option Year 5 $3,205,990 $1,830,392 $402,911 $335,632 $295,361 $6,070,286 $5,019,389 Total, OY 1-5 $15,240,783 $8,528,234 $1,901,521 $1,583,209 $1,421,189 $28,674,936 $24,131,859 Grand Total $29,618,217 $16,098,576 $3,555,486 $2,948,900 $2,711,981 $54,933,160 $47,088,828 *Will change based on negotiations with new bargaining unit, training costs, etc. ** Not yet finalized
14 Comparison of best value proposals Based on service plan in FTA grant and O&M Agreement Total Streetcar Pricing City funding Turn-key Management contract Difference between contract methods Startup $ 1,100,000 $ 1,100,000 $ 1,273,216 $ (173,216) Year 1 4,200,000 $ 4,037,135 $ 4,714,734 $ (677,599) Year 2 4,284,000 4,090,938 4,775,701 (684,763) Year 3 4,369,680 4,287,985 4,987,172 (699,187) Year 4 4,457,074 4,449,996 5,179,495 (729,499) Year 5 4,546,215 4,555,746 5,327,907 (772,161) Total, Year 1-5 $ 21,856,969 $ 21,421,800 $ 24,985,008 $ (3,563,209) Option Year 1 4,637,139 4,606,718 5,412,777 (806,059) Option Year 2 4,729,882 4,755,906 5,572,047 (816,140) Option Year 3 4,824,480 4,891,057 5,725,060 (834,003) Option Year 4 4,920,969 5,039,922 5,894,767 (854,845) Option Year 5 5,019,389 5,157,410 6,070,286 (912,876) Total, OY ,131,859 $ 24,451,014 $ 28,674,936 $ (4,223,922) Grand Total $ 47,088,828 $ 46,972,813 $ 54,933,160 $ (7,960,347)
15 City Council policy guidance In response to City of Cincinnati motion # : SORTA requests that City Council provide guidance regarding the preferred method by the end of June: - Turn-key contract - Management contract Contract must be awarded by SORTA in July 2015 to meet deadlines related to first vehicle delivery in September. Delays will add cost to the project.
16 Questions & discussion
City of Cincinnati Streetcar Project
City of Cincinnati Streetcar Project Project Analysis December 18, 2013 kpmg.com Table of Contents Section Slides Scope of Work 2 Approach 3 Exclusions 4 Executive Summary 5 Budget Summary 6 Design Vendor:
Task Order Manager. Project Planning, Engineering, Architecture service contract with experience in passenger rail or other modes, and
a) Offerors shall provide resumes for their Key Personnel, as identified below. The page count for each resume shall not exceed three (3) pages. Preferred professional qualifications of key personnel are
Request for Proposals
City of Sonora Request for Proposals City of Sonora Microenterprise Technical Assistance Program Lead Technical Assistance Consultant City of Sonora Community Development Department 94 N. Washington Street
Tel: (617) 727-4050 Fax: (617) 727-5363. OWNER S PROJECT MANAGER GUIDELINES M.G.L. c. 149, 44A1/2
The Commonwealth of Massachusetts Executive Office for Administration and Finance Division of Capital Asset Management One Ashburton Place Boston, Massachusetts 02108 Tel: (617) 727-4050 Fax: (617) 727-5363
PROCUREMENT GUIDE: SELECTING A CONTRACTOR/PROJECT DEVELOPER
PROCUREMENT GUIDE: SELECTING A CONTRACTOR/PROJECT DEVELOPER 1. Overview CHP project development and implementation are similar to many central plant construction projects or comprehensive energy conservation
English. Trapeze Rail System. www.trapezegroup.com
English Trapeze Rail System www.trapezegroup.com Trapeze Rail System Enabling future railway, tram and metro transport The worldwide growth in demand for travel and increasing competition between all modes
KANSAS CITY AREA TRANSPORTATION AUTHORITY ADDENDUM #1 TO RFP #13-7028-30
KANSAS CITY AREA TRANSPORTATION AUTHORITY ADDENDUM #1 TO RFP #13-7028-30 FOR A CONSULTANT TO PROVIDE TRIP SCHEDULING AND QUALITY ASSURANCES FOR KCATA S PARATRANSIT OPERATIONS NOVEMBER 5, 2013 The information
Department Of Human Services. Medical Assistance Transportation Program. Request for Information (RFI)
Department Of Human Services Medical Assistance Transportation Program Request for Information (RFI) Date: October 21, 2015 Table of Contents PART 1: GENERAL INFORMATION... 3 1.1 Purpose of this Request
Seeking Residential Rehabilitation Cost Estimating and Monitoring Services Neighborhood Housing Services of Orange County, NSP Program.
Seeking Residential Rehabilitation Cost Estimating and Monitoring Services Neighborhood Housing Services of Orange County, NSP Program. Response Due on or before, 11:00 AM November 30 th, 2011 Invitation:
NEWBURGH ENLARGED CITY SCHOOL DISTRIST NEWBURGH, NEW YORK REQUEST FOR PROPOSAL ARCHITECTURE SERVICES 2015 2016
NEWBURGH ENLARGED CITY SCHOOL DISTRIST NEWBURGH, NEW YORK REQUEST FOR PROPOSAL ARCHITECTURE SERVICES 2015 2016 Notice is hereby given that the Board of Education of the Newburgh Enlarged City School District,
FTA OVERSIGHT PROGRAMS
U.S. Department of Transportation Federal Transit Administration FTA OVERSIGHT PROGRAMS FTA Region IV 2008 Conference 1 Session Outline Annual Grantee Assessment Oversight Activities Reviews (General,
Open Payment System Request for Proposals
Finance, Administration and Oversight Committee Action Item III-E May 14, 2009 Open Payment System Request for Proposals Washington Metropolitan Area Transit Authority Board Action/Information Summary
Request for Proposals July 13, 2015
Maintenance and Skilled Trades Division Request for Proposals July 13, 2015 District Wide Pavement Assessment The East Bay Regional Park District ( District ) is soliciting proposals from consultants to
REQUEST FOR PROPOSAL (RFP) FORM. Enter title here. Invitation to Bid. Utica College invites you to submit a proposal to brief description.
REQUEST FOR PROPOSAL (RFP) FORM TITLE: Enter title here I. GENERAL INFORMATION Invitation to Bid. Utica College invites you to submit a proposal to brief description. If a contract results from this RFP,
REQUEST FOR PROPOSAL CONSTRUCTION MANAGEMENT SERVICES PIERSON ELEMENTARY REPLACEMENT SCHOOL PROJECT NO. 164519
REQUEST FOR PROPOSAL CONSTRUCTION MANAGEMENT SERVICES FOR PIERSON ELEMENTARY REPLACEMENT SCHOOL PROJECT NO. 164519 School Board of Volusia County Florida Facilities Services 3750 Olson Drive, Daytona Beach
Questions and Answers
Questions and Answers 1. Can pictures be inserted in the Request for Qualifications package? Do they count toward the number of pages submitted? A. Yes, you can insert photos as long as the total page
Government Contracting 101 PART 2. Text File. Welcome to SBA s training program, Government Contracting 101, Part 2.
Slide 1 Government Contracting 101 Part 2 How the Government Buys SBA U.S. Small Business Administration November 2011 Government Contracting 101 PART 2 Text File Welcome to SBA s training program, Government
Vendor Performance Evaluation
Vendor Performance Evaluation Canadian Public Procurement Council Oct. 27-29, 2014 Agenda 1) Objectives and 2) Evaluation 3) Evaluation Templates and 4) Use of Vendor Score 2 13:00 14:00 1 Objectives and
Procurement Processes and Tools
Methods of Procurement Purchasing Activities Procurement Processes and Tools There are different methods of procurement, which are utilized to acquire goods or services. There are many factors which determine
Overview. Scope of Work
Overview The University of Texas System Request for Proposal to Develop and Execute an Online Marketing Strategy for the Office of Technology Commercialization RFP#OTC12022015 In this Request for Proposal
Request for Consulting Services For the Preparation of an International Marketing Strategy EXECUTIVE SUMMARY
Request for Consulting Services For the Preparation of an International Marketing Strategy EXECUTIVE SUMMARY The City of Abbotsford, Economic Development Department, is seeking a consultant to develop
REQUEST FOR LETTERS OF INTEREST Community Based Grants Fiscal Agent Services
REQUEST FOR LETTERS OF INTEREST Community Based Grants Fiscal Agent Services Announcement Date: Monday, October 5, 2015 Deadline: Friday, October 16, 2015-4:00PM Total Funding Available: Year 1- up to
September 2005 Report No. 06-009
An Audit Report on The Health and Human Services Commission s Consolidation of Administrative Support Functions Report No. 06-009 John Keel, CPA State Auditor An Audit Report on The Health and Human Services
REQUEST for PROPOSALS. Scheduling and Dispatch Software. City of Ionia Dial-A-Ride (IDART) 251 E. Adams Street Ionia, Michigan 48846.
REQUEST for PROPOSALS Scheduling and Dispatch Software City of Ionia Dial-A-Ride (IDART) 251 E. Adams Street Ionia, Michigan 48846 Proposals Due: November 18, 2013 12:00 p.m. Table of Contents PART I Instructions
MCR Health Services Inc. Request for Proposal For Air Conditioning Unit Replacement Authorized Vendor
MCR Health Services Inc. Request for Proposal For Air Conditioning Unit Replacement Authorized Vendor Background Information: Manatee County Rural Health Services (MCR Health Services) is a private, not
REQUEST FOR PROPOSAL. Audio Visual Services
REQUEST FOR PROPOSAL The Mid-Ohio Regional Planning Commission (MORPC) is requesting statements of qualification from interested and qualified firms to provide audio visual services to be completed for
City of Kenmore, Washington
City of Kenmore, Washington Financial Management Software System Request for Proposals Issued: November 2, 2015 Date Due: December 4, 2015 Time Due: 5:00 p.m. Pacific Standard Time Page 1 of 10 1. Introduction
REQUEST FOR PROPOSAL (RFP) FOR SCHEDULING, DISPATCHING, AUTOMATION SOFTWARE AND HARDWARE
ISSUED BY: REQUEST FOR PROPOSAL (RFP) FOR SCHEDULING, DISPATCHING, AUTOMATION SOFTWARE AND HARDWARE LIMA ALLEN COUNTY REGIONAL TRANSIT AUTHORITY 200 EAST HIGH STREET, 1 C LIMA, OH 45801 Telephone: 419.222.2782
REQUEST FOR PROPOSAL CONSTRUCTION MANAGEMENT SERVICES PINE TRAIL ELEMENTARY HVAC, CEILING & LIGHTING PROJECT NO. 164514
REQUEST FOR PROPOSAL CONSTRUCTION MANAGEMENT SERVICES FOR PINE TRAIL ELEMENTARY HVAC, CEILING & LIGHTING PROJECT NO. 164514 Contact: Mr. Tom Brown, Senior Construction Project Manager Facilities Services,
Information event for consulting companies on 27 September 2010 at GTZ (now GIZ) Open questions Notes Suggestions
Information event for consulting companies on 27 September 2010 at GTZ (now GIZ) Open questions Notes Suggestions 1.- Would it be possible to issue information on award of contracts in advance of submitting
St. Cloud Metro Bus Charter Policy
St. Cloud Metro Bus Charter Policy I. St. Cloud Metro Bus Charter Policy In accordance with Federal regulation, St. Cloud Metro Bus is allowed to operate certain community based charter services excepted
Owner s Procurement Forum
Washington Metropolitan Area Transit Authority Construction Management Association of America National Capitol Chapter Owner s Committee Owner s Procurement Forum February 24, 2015 OVERVIEW of WMATA INFRASTRUCTURE:
REQUEST FOR PROPOSALS. For FINANCIAL ADVISORY SERVICES
REQUEST FOR PROPOSALS For FINANCIAL ADVISORY SERVICES Request for Proposals Issued: July 30, 2012 Deadline for Submittal of Proposals: August 17, 2012 Request for Proposals for Financial Advisory Services
STATE OF NEW HAMPSHIRE 2013-EG-03 REQUEST FOR PROPOSALS PLAN MANAGEMENT CONSULTANTS
STATE OF NEW HAMPSHIRE 2013-EG-03 REQUEST FOR PROPOSALS PLAN MANAGEMENT CONSULTANTS INTRODUCTION The New Hampshire Insurance Department (NHID) is requesting proposals for contractors to provide plan management
NORTH COLONIE CENTRAL SCHOOL DISTRICT 91 FIDDLERS LANE LATHAM, NEW YORK 12110-5349 INVITATION FOR CONSTRUCTION MANAGEMENT PROPOSALS
NORTH COLONIE CENTRAL SCHOOL DISTRICT 91 FIDDLERS LANE LATHAM, NEW YORK 12110-5349 INVITATION FOR CONSTRUCTION MANAGEMENT PROPOSALS The North Colonie Central School District invites your firm to submit
REQUEST FOR PROPOSAL Mobile Tours (Website) Development
REQUEST FOR PROPOSAL Mobile Tours (Website) Development Contents Introduction... 1 Proposal Submission Guidelines... 2 Executive Summary... 3 The Opportunity... 3 Objective... 3 Reports to: Director of
SOLICITATION NO.: DHCF-HCOA-2009-P-0001 RESPONSES TO SUBMITTED QUESTIONS
Department of Health Care Finance Government of the District of Columbia Office of Contracts and Compliance 825 North Capitol Street NE, Suite 5135 Washington, DC 20002 Phone: 202-442-5988 SOLICITATION
REQUEST FOR PROPOSAL FOR CONSTRUCTION MANAGEMENT SERVICES. Part I: Proposal Information
REQUEST FOR PROPOSAL FOR CONSTRUCTION MANAGEMENT SERVICES Part I: Proposal Information A. General Information The Berwick Area School District is soliciting proposals for construction management services
Chicago Transit Authority Open Standards Fare System Overview. David Faust Chicago Transit Authority Senior Project Manager Chicago, IL
Chicago Transit Authority Open Standards Fare System Overview David Faust Chicago Transit Authority Senior Project Manager Chicago, IL KEY OBJECTIVES Greater customer convenience Private financing of equipment
Food Service Facts Table of Contents
Food Service Facts Table of Contents 14. Food Service Management Companies Considerations in Deciding Whether to Contract for Food Service Management... 14-1 Management... 14-1 Quality... 14-2 Costs...
2010-2011 GRAND JURY REPORT
Background 2010-2011 GRAND JURY REPORT Riverside County Indigent Defense Contract The roots of the modern right to counsel for the defendant who cannot afford to pay a private lawyer can be found more
10/30/2015. Procurement Under the New Requirements. Why This Session Is Needed. Lesson Overview & Module Objectives. Changes to conflict of interest
Requirements Procurement under the New Requirements 1 1 Why This Session Is Needed New provisions in Uniform Guidance Changes to conflict of interest requirements in Uniform Guidance Distinctions between
REQUEST FOR PROPOSALS for EMPLOYEE BENEFITS BROKER/ CONSULTING SERVICES
Kansas City, Kansas Housing Authority 1124 North Ninth Street Kansas City, KS 66101-2197 (913) 281-3300 FAX (913) 279-3428 REQUEST FOR PROPOSALS for EMPLOYEE BENEFITS BROKER/ CONSULTING SERVICES Date RFP
REQUEST FOR PROPOSALS FOR A PROGRAM EVALUATOR TO EVALUATE LSC S MIDWEST LEGAL DISASTER COORDINATION PROJECT OCTOBER 28, 2015
LEGAL SERVICES CORPORATION REQUEST FOR PROPOSALS FOR A PROGRAM EVALUATOR TO EVALUATE LSC S MIDWEST LEGAL DISASTER COORDINATION PROJECT OCTOBER 28, 2015 Page 1 of 8 INTRODUCTION The Legal Services Corporation
CTAA - SAFETY AND SECURITY OFFICER PROGRAM (CSSO)
CTAA - SAFETY AND SECURITY OFFICER PROGRAM (CSSO) 1 Training Agenda: Morning Session-Day 1: Introduction Leadership and Administration Transit Operations Afternoon Session-Day 1: Maintenance and Technology
City of Long Beach. Request For Information Number TS14-043. For Financial Management and Human Resources Software Solution
City of Long Beach Request For Information Number TS14-043 For Financial Management and Human Resources Software Solution Release Date: March 17, 2014 Due Date: March 31, 2014 by 11:00 a.m. Pacific Time
Desired Qualifications
Request for Proposals for Professional Consulting Services to develop a Foreign Trade Zone Project Marketing and Business Development Plan I. Introduction and Purpose The Grand Forks Regional Airport Authority
Slide 3 WIOA Implementation The Workforce Innovation and Opportunity Act not only changes how we do business, but also who does that business.
ADA Compliant Transcript WIOA: Implementing Change October 20-23, 2015 Title Slide Role of Board Members in WIOA Implementation Presenters are Michelle Ball, Assistant Bureau Chief, Employment and Training
GENERAL CONTRACTOR / CONSTRUCTION MANAGER SERVICES
REQUEST FOR QUALIFICATIONS GENERAL CONTRACTOR / CONSTRUCTION MANAGER SERVICES NEW DINING HALL MONTANA STATE UNIVERSITY Bozeman, Montana PPA NO. 15-0103 Campus Planning, Design & Construction Plew Building
Consolidated I&T Data Centre - P3 Canada Fund
STAFF REPORT ACTION REQUIRED Consolidated I&T Data Centre - P3 Canada Fund Date: January 16, 2012 To: From: Wards: Reference Number: Government Management Committee Deputy City Manager & Chief Financial
REQUEST FOR PROPOSALS FOR TELEPHONE SYSTEM ADMINISTRATIVE AND SUPPORT SERVICES
REQUEST FOR PROPOSALS FOR TELEPHONE SYSTEM ADMINISTRATIVE AND SUPPORT SERVICES LEGISLATIVE COUNCIL SERVICE 411 STATE CAPITOL SANTA FE, NEW MEXICO 87501 (505) 986-4600 ISSUE DATE: June 19, 2015 NOTICE The
Metro Met..,.u... T,...,...,...,
~ ""... c,., Metro Met..,.u... T,...,...,..., One Gateway Plaza Los Angeles, CA 90012-2952 213.922.2ooo Tel metro. net 37 EXECUTIVE MANAGEMENT COMMITTEE MARCH 20,2014 SUBJECT: ACTION: INNOVATIVE WAYS TO
North Carolina Department of Public Instruction School Nutrition Services
North Carolina Department of Public Instruction School Nutrition Services Procedures for Contracting with Food Service Management Companies (FSMC) (Effective April 1, 2004) Outsourcing the nonprofit School
Car Service with App and Dispatch Options Program Concept Paper June 15, 2016
The City of New York Department for the Aging 2 Lafayette Street New York, New York 10007 A. Purpose Car Service with App and Dispatch Options Program Concept Paper June 15, 2016 This concept paper is
ATLANTA PUBLIC SCHOOLS
Procurement Services 130 Trinity Avenue, S.W. 5 th Floor Atlanta, Georgia 30303 Request for Qualifications For October 31, 2007 Solicitation Number: 112607-01 Due Date: November 26, 2007 ADVERTISEMENT
Time-and-Materials and Labor-Hour Contracts The New Policies
Time-and-Materials and Labor-Hour Contracts The New Policies Overview: Time-and-materials and labor-hour (T&M/LH) contracts are the least preferred contract types, but they may play an important role in
Description: Publication Date: 9/21/2015. Closing Date/Time: Open Until Contracted
Description: The New River Valley Regional Jail Authority (NRVRJA) values and appreciates the contributions and efforts of its employees. Toward this end, the NRVRJA is committed to providing a supportive,
Experience and Qualifications of PROCESS PLANTS CORPORATION
Experience and Qualifications of PROCESS PLANTS CORPORATION Table of Contents Section 1. Project Services pg 3-20 Engineering Services Project management Design engineering Design management Construction
Request for Qualifications for Disaster Debris Monitoring
Request for Qualifications for Disaster Debris Monitoring Franklin County invites qualified firms to respond to this request for qualifications (RFQ) by providing their qualifications and experience for
CITY OF BELL REQUEST FOR PROPOSAL FOR Spanish Translation and Interpretation Services
CITY OF BELL REQUEST FOR PROPOSAL FOR Spanish Translation and Interpretation Services SUBMITTAL: One (1) original must be received on or before 2:00 p.m., March 18, 2015 Addressed to: Angela Bustamante,
Request for Qualifications (Design-Build Contract) State of Ohio Standard Forms and Documents
Request for Qualifications (Design-Build Contract) State of Ohio Standard Forms and Documents Administration of Project: Local Higher Education Project Name Campus Elevator Upgrades Response Deadline 9/03/13
C. H. Guernsey & Company 5555 North Grand Boulevard Oklahoma City, OK 73112 www.guernsey.us
U.S. GENERAL SERVICES ADMINISTRATION (GSA) FEDERAL SUPPLY SERVICES (FSS) 00CORP CONSOLIDATED SCHEDULE INCLUDING MISSION ORIENTED BUSINESS INTEGRATED SERVICES (MOBIS) & ENVIRONMENTAL SERVICES (ES) CONTRACT
TOWN OF OVID, SENECA COUNTY, NEW YORK REQUEST FOR PROPOSALS
TOWN OF OVID, SENECA COUNTY, NEW YORK REQUEST FOR PROPOSALS FOR PROFESSIONAL CONSULTING SERVICES ESTABLISH/REVISE THE TOWN S COMPREHENSIVE PLAN The Town Board of the Town of Ovid, Seneca County, of New
Nothing in this job description restricts management s right to assign or reassign duties and responsibilities to this job at any time.
S23671, page 1 Nothing in this job description restricts management s right to assign or reassign duties and responsibilities to this job at any time. DUTIES Serves as a Construction Project Cost Estimator
Policy Number: 3-804 Policy Name: Professional Services and Construction Services Procurement
Page 1 3-804 Professional Services and Construction A. Project Delivery Methods 1. A university may procure design services, construction and construction services, as applicable, under any of the following
Memorandum. Date: 11.27.13 RE: Citizens Advisory Committee December 4, 2013
Memorandum Date: 11.27.13 RE: Citizens Advisory Committee December 4, 2013 To: From: Subject: Summary Citizens Advisory Committee Cynthia Fong Deputy Director for Finance and Administration ACTION Adopt
Testimony of Dennis Anosike, Chief Financial Officer Washington Metropolitan Area Transit Authority
Testimony of Dennis Anosike, Chief Financial Officer Washington Metropolitan Area Transit Authority Before a joint hearing of the Subcommittee on Transportation and Public Assets and the Subcommittee on
Invitation for Bid. For. Bank Courier Services
Invitation for Bid For Bank Courier Services Solicitation # 2015 BC Sealed bids are due March 23, 2015 Manatee County Rural Health Services Administration Attn: Sam Love, Procurement Manager 700 8 th Avenue
MANAGEMENT 3 PROCUREMENT AND CONTRACTOR. Purpose
3 PROCUREMENT AND CONTRACTOR MANAGEMENT Purpose The purpose of Procurement and Contractor Management is to provide basic information and direction regarding procuring commodities or services within New
State of Rhode Island Department of Administration / Division of Purchases ADDENDUM # 4 RFP # 7479367
State of Rhode Island Department of Administration / Division of Purchases One Capitol Hill, Providence, Rhode Island 02908-5855 Tel: (401) 574-8100 Fax: (401) 574-8387 Solicitation Information July 23,
The State of Oregon. Department of Procurement Services Issues the Following
The State of Oregon Department of Procurement Services Issues the Following Request for Information (RFI) # DASPS-2346-15 For The Oregon Enterprise-wide Human Resource Information System Project Single
City of Moreno Valley Date Council Approved March 13, 2007 Date Effective April 6, 2007 CLASS SPECIFICATION Senior Electrical Engineer, P.E.
City of Moreno Valley Date Council Approved March 13, 2007 Date Effective April 6, 2007 CLASS SPECIFICATION Senior Electrical Engineer, P.E. GENERAL PURPOSE Under direction, manages, oversees, evaluates,
Insert Client Name Request for Proposal for Security Risk Assessment Services Consulting
Insert Client Name Request for Proposal for Security Risk Assessment Services Consulting Release Date: Closing Date: SUBMIT THE PROPOSAL TO: Insert Name Insert Title Insert Email or Physical Address Table
RFP SB01-PO1516 Taos Regional Landfill Data Collection and Point of Sale System Page 1
Town of Taos Request for Proposal (RFP) Taos Regional Landfill Data Collection and Point of Sale System September 21, 2015 SB01-PO15-16 1.0 PROJECT DESCRIPTION 1.1 Taos Regional Landfill Board is seeking