1 Page I of VII EXECUTIVE SUMMARY 1.1 INTRODUCTION Indian Oil is India s flagship energy major and the country s largest commercial enterprise with a turnover of Rs. 2,71,000 crore (US$ 61.3 billion) and profits of Rs. 10,221 crore (US$ 2.3billion) for the year It is also the highest ranked Indian company in the prestigious Fortune Global 500 listing at 125 th position. Indian Oil is the 20th largest petroleum refining company in the world. Indian Oil and its group companies account for 48% petroleum products market share, 40.4% refining capacity and 56% downstream sector product pipelines capacity in India. For the year , Indian Oil sold 60.7 million tonnes of petroleum products, including 1.91 million tonnes of natural gas, and exported 3.33 million tonnes of petroleum products.. More than 9000 km network of crude and product pipelines in India are owned and operated by IOCL, which have state of art, modern operation and maintenance techniques. These pipelines have been accredited with national and international certifications of repute such as ISO 14001, ISO 9002, OISD Safety Award, British Safety Council Award etc. 1.2 PROJECT DESCRIPTION The proposed project site is located at village Malom, Imphal, Manipur having latitude and longitude of 24º N and 93º E respectively. The land of the proposed POL Depot has been procured from State Government. The plot of land is approx. 36 acres along side NH 150, 8 KM from Imphal town & 2 KM away from Tulihal Airport The general topography of the area is flat and the general elevation of the site is 775 m above MSL TECHNOLOGY AND PROCESS DESCRIPTION This Depot project is proposed to be executed in two phases as under: Phase I: To receive white oils like MS (Motor Spirit), HSD (High Speed Diesel) and SKO (Superior Kerosene Oil) through tank truck by road. The depot will be fed from Tinsukia Depot and Numaligarh Refinery.The products as mentioned above would be received by road in Floating Roof Tanks (FRVT store MS) and Cone Roof Vertical Tanks (CRVTs to store HSD & SKO).
2 Page II of VII These products would be dispatched to various destined locations like retail outlets, consumer points etc by Tank Lorries(TLs) in order to cater to the needs of adjoining region.details of facilities proposed under phase I are as follows: Receipt: Product receipt will be received by road. Provision will be made for receiving MS, HSD & SKO by pipeline through independent product pipeline from pump house to tanks Storage Tanks Petroleum products like MS, SKO, and HSD are received, stored and dispatched from this installation. M/s IOCL have installed 9 Nos. of tanks for the purpose. Details of product wise tankage at POL Depot Imphal are given in Table2.1. Sr. No. Tank No. 1 Tank no. 1 2 Tank no. 2 3 Tank no. 3 Table 1.1: Tank Capacity Type Product Normal Capacity (in KLS) Class A Product Size (m) FRVT MS M Dia. 9.5 M Ht. FRVT MS M Dia. 9.5 M Ht. FRVT MS M Dia. 9.5 M Ht. Total of MS Tank no Tank no Tank no.6 11 Tank no. 7 Class B Product CRVT SKO M Dia. 11 M Ht. CRVT SKO M Dia. 11 M Ht. CRVT SKO M Dia. 11 M Ht. Total of SKO 5055 CRVT HSD M Dia M Ht. 12 Tank CRVT HSD M Dia M Ht.
3 Page III of VII no Tank no. 9 CRVT HSD M Dia M Ht. Total of HSD Tank inlet and outlets shall be provided each with 2 no. gate valves. No interconnecting catwalks would be provided for storage tanks. Provision of dyke wall for containment of spillage shall be made for all tanks. All tanks would be provided with foam pourers and hydrant system as per OISD norms Distribution Tank Lorry Filling (TLF) gantries with 8 bays with bottom loading arrangement would be provided to fill tank lorries. The loading operation is envisaged to be fully automated Pump House for TLF Operation Independent arrangement for TLF and future TLD in one pump house shall be made for loading/unloading of tank lorries along with necessary pipeline manifold Product Doping Facility Blue dye doping facilities for injection of blue dye in to SKO tanks during product receipt. MFA dosing facility at TLF loading point Fire Fighting Facilities Full fledged auto pressurized system shall be provided to cover all facilities in the depot as per OSID- 117/118 norms including water storage for fire fighting.mv Spray system & Foam system as stipulated would be provided in line with OSID norms. The water storage capacity & pumping capacity would be adequate to cover two major risks Pollution Control Facilities Provision of facilities shall be made as per latest MOEF norms and meeting State pollution Control Board Rules. Collection sumps would be provided with control valves outside each tank farm. One no. master separator at outlet point of oil/water drainage to ensure that the effluent would meet pollution control norms and oil contents not to exceed 8ppm
4 Page IV of VII level. Pipe drains would be provided for oily water from tank farms, pump house manifold area, leading to master oil water separator. Surface drainage (Storm Water) system would be independent of oil water drainage to avoid oil traces in storm water. Exhaust pipes of diesel engines as per air pollution control norms. Gravity type OWS of suitable capacity as per maximum rainfall would be provided separately for other operational areas with arrangement for lifting oil and slop tank of suitable size. Vapour recovery system. Noise level of diesel engines not exceed laid down norms by the State Pollution control Board Security Security features include access control system &security zoning. Compound wall covering entire length of boundary wall with 3 M masonary+0.6 M concertina wire fencing. 1.8 high chain link fencing for licensed area/de-licensed area demarcation. Main gate-8m wide for each lane with 1 No. 1.2 M wide wicket gate. Emergency gate: 8M wide. Entry gate at licensed area 6 M wide for each lane with electricity operated gates 2 Nos. CCTV for effective security coverage of entire depot PHASE II Details of other facilities shall be undertaken under Phase II are as follows: Tank Wagon Sliding Railway sliding having provision of full BTPN rake of 48 tank wagons shall be made with provision of unloading of MS/SKO/HSD/ATF
5 Page V of VII Tank Wagon Pump House Provision of pump house along with required pumps and pipelines manifold shall be made for unloading of products from tank wagon siding to our storage tanks.atf will be directly pumped to Aviation Felling Station Storage tanks from TWD pump house. (Situated away from depot) Fire Fighting System Full fledged auto pressurized shall be provided to cover all facilities in the siding, tank farm and decanting pump house as per OISD-117/118 norms. 1.3 BASELINE ENVIRONMENTAL STATUS The area around the proposed pipeline, where the project activities will take place has been surveyed for physical features and existing environmental scenario. The area was surveyed around the proposed POL Depot at Village Malom, Imphal. The field survey has been done for summer season during March 2011 to May The climatic condition during the study period is presented in report for all the stations where the modification is proposed. The pre-dominant wind direction in the region is W and SW. The calm situation prevailed for 21.10% of the time. The temperature varies from C to C, whereas, the relative humidity varies from 47% to 76 %. Total rainfall recorded during the study period was 263 mm. The ambient air quality is well within the limits as per the National Ambient Air Quality Standards in all the monitoring stations. The value of RPM varies from 26 to 41, SO 2 7 to 14 and NOx 8 to 18. All the results are reported in microgram per cubic meter (µg/m 3 ). The values of THC varies from 1.3 to 3.7 mg/m 3. The land use around the project site is pre-dominantly semi-arable. The sand, silt and clay varied from 22 67%, 21-73% and 2-12% respectively indicating that soil is Sand Silt. The soil moisture varied from %, while bulk density varied between 1.40 to ph varies from 4.03 to 5.11 indicating slightly acidic that indicated to hinder the growth of agriculture crops. The conductivity varies from 160 to 460 µmhos/cm. The average concentration of nitrogen, phosphorus and potassium in the soil samples varied from 1.02 to 3.74 mg/100gm, to mg/100gm and 0.1 mg/100gm respectively. The organic matter content of soil varied from 1.15 to 3.95%. The average sodium absorption ration was 0.4, which is much below the value 9 where after the permeability of soil is affected. The ecological study of the area has been conducted within 15 km radius of the project site in order to understand the existing status of flora and fauna to generate baseline information and evaluate the possible impacts on biological environment. It has been assessed that the impact on local flora and fauna will be negligible due to the proposed project.
6 Page VI of VII The socio-economic conditions are presented in the report. The impact on socioeconomic environment as some direct or indirect employment will be generated during the construction and operation phases. 1.4 ANTICIPATED ENVIRONMENT IMPACTS AND ENVIRONMENT MANAGEMENT PLAN The potential impacts of the proposed pipeline have been limited to the proposed depot at Imphal. The land has been procured from state govt and no displacement of people is involved. No social issues are required to be addressed, as there is no rehabilitation and resettlement. The impact on soil quality is induced/ short term in nature, and can be avoided by applying good construction practices to reduce the impact, if any, on soils to a great extent. Adequate measures need to be worked out for minimizing the loss of soils, by way of storage of topsoil and then again laying it back after the completion of the construction of depot. Impacts on ambient air would mainly be due to dust emissions and movement of vehicles. However these impacts would be short-term in nature. Impacts on ambient air during operational phase would be due to emissions from DG set stacks and vehicles which will be very negligible and would be nullified by provision of scrubber and acoustic enclosure. The detailed environmental management plan has been presented in the main report. IOCL make sure that all the statutory norms, emissions norms for air, water, and noise shall be maintained during the construction and operation phases and in line with the EMP. 1.5 ENVIRONMENTAL MONITORING PROGRAMME It is imperative that the IOCL should set up regular monitoring locations to assess the environmental health in the post period. A post study monitoring programme is important as it provides useful information on the following aspects. It helps to verify the predictions on environmental impacts presented in this study. It helps to indicate warnings of the development of any alarming environmental situations, and thus, provides opportunities for adopting appropriate control measures in advance.
7 Page VII of VII 1.6 PROJECT BENEFITS The project will be improved supply position of the petroleum products in Manipur state, which is vital for economic growth as well as improving the quality of life. The improved petroleum supply will have strong logistical support for delivering the products to customers at better quality and better price. Availability of product in vicinity of demand location with safe operation will be beneficial to public at large. Establishment of large developmental projects improve the availability of the physical infrastructures like approach roads, drainage, communication and transportation facilities etc. The project will provide employment potential under unskilled, semi-skilled and skilled categories, so the direct employment opportunities would be generated.
BHARAT PETROLEUM CORPORATION LIMITED
TERMS OF REFERENCE (TOR) FOR CARRYING OUT ENVIRONMENT IMPACT ASSESSMENT (EIA) FOR BPCL- KOCHI REFINERY MS BLOCK PROJECT AT KOCHI, KERALA PROPONENT: BHARAT PETROLEUM CORPORATION LIMITED 1.0 INTRODUCTION
Environmental Management Plan
Environmental Management Plan ENVIRONMENTAL MANAGEMENT PLAN An Environmental Management Plan is prepared for construction phase, post construction phase (commissioning & operation) and for post project
TERMS OF REFERENCE FOR SCOPING OF EIA STUDY
TERMS OF REFERENCE FOR SCOPING OF EIA STUDY Ours project is a proposed large scale unit and categorized as 5(h)-B as per the EIA notification 2006 of MoEFCC, New Delhi and subsequent amendments. Looking
The Terms of reference (ToR) for conducting Rapid EIA study for the proposed project is described below:
Proposed Terms of Reference for EIA Study Objective: In order to identify the environmental impacts due to construction and operation of the proposed project and associated facilities, a study will be
TERMS OF REFERENCE FOR THE RAPID EIA STUDY
TERMS OF REFERENCE FOR THE RAPID EIA STUDY 1 SUMMARY OF EIA METHODOLOGY STEP I : SCOPING OF THE ASSESSMENT Own with prevailing regulatory setting and criteria Identification of Environmental Assessment
2x800 MW Thermal Power Project Near Village Paraspani, Tehsil Pathargama, Godda- District By Adani Power (Jharkhand) Limited
(IV) Proposed Terms of Reference for EIA Studies Project Category Project Proponent Location Paraspani Thermal Power Plant (2x800 MW) Coal based Thermal Power Project A [1(d) Thermal Power Plant 500 MW]
Prepared and Submitted by
Technical Feasibility Study Report of Proposed Sulfuric Acid and Phosphoric Acid Unloading Facilities, Acid Storage Tanks at the existing Wharf and Acid Transfer Pipeline Falling within the CRZ area &
How To Conduct An Environmental Impact Assessment
Proposed Terms of Reference for EIA studies 1. Introduction The proposed expansion of Bulk Drugs & Intermediates manufacturing unit by M/s. Sri Krishna Pharmaceuticals Limited (Unit V). is located at Plot
Proposed Terms of Reference for EIA studies
1 Proposed Terms of Reference for EIA studies Base line data collection will be collected for the Post-Monsoon season 2016 (September to November 2016) in study area and 10 kms radius from project site.
Final Environmental Impact Assessment of Smt. Singam Bhavani Laterite Mining ADDITIONAL STUDIES
ADDITIONAL STUDIES 7.0 DISASTER MANAGEMENT PLAN It is presumed that the proposed mining process would be designed and engineered with all possible safety measures and standard code of practices. In spite
ENVIRONMENTAL MANAGEMENT PLAN. Nilaya Hills/ Heights Promoted by M/s RBS Developers (Group Housing & Commercial Building Project)
ENVIRONMENTAL MANAGEMENT PLAN Of Nilaya Hills/ Heights Promoted by M/s RBS Developers (Group Housing & Commercial Building Project) at Khasra Nos. 1353Min,1354Min,1355, 1356, 1358, 1357, 1587 Ka, 1587Kha,
Fuel Treatment and Conditioning Systems
RULES FOR CLASSIFICATION OF Ships PART 6 CHAPTER 14 NEWBUILDINGS SPECIAL EQUIPMENT AND SYSTEMS ADDITIONAL CLASS Fuel Treatment and Conditioning Systems JULY 2006 This chapter has been amended since the
Explosion of a gasoline vapour cloud formed in a hydrocarbon loaded effluents storage tank 10 December 1999 Arquata Scrivia Italy
Explosion of a gasoline vapour cloud formed in a hydrocarbon loaded effluents storage tank 10 December 1999 Arquata Scrivia Italy UVCE Storage tank Hydrocarbons Steam coil Corrosion Steam Instrumentation
SUFFOLK COUNTY DEPARTMENT OF HEALTH SERVICES TOXIC/HAZARDOUS MATERIAL TRANSFER FACILITY DESIGN GUIDELINES
SUFFOLK COUNTY DEPARTMENT OF HEALTH SERVICES TOXIC/HAZARDOUS MATERIAL TRANSFER FACILITY DESIGN GUIDELINES 1.0 GENERAL 1.1 Article 12 of the Suffolk County Sanitary Code requires that toxic/hazardous material
M/s SANGHVI GRUHA NIRMAN PVT. LTD. PROPOSED. REDEVELOPMENT OF BUILDING (JANKI BHAVAN) At
M/s SANGHVI GRUHA NIRMAN PVT. LTD. PROPOSED REDEVELOPMENT OF BUILDING (JANKI BHAVAN) At Final Plot No. 1274, situated at T.P.S. IV, Mahim, Hatiskar Marg, Prabhadevi, Mumbai 400 025. EXECUTIVE SUMMARY PREPARED
PROPOSED TERMS OF REFERENCE
PROPOSED TERMS OF REFERENCE ABOUT THE PROJECT: Rampura Marble Mine (ML No.- 420/91) is proposed by M/s Continental Minerals Pvt. Ltd. The Mine Lease area consists of 3.0 ha, which is located at Khasra
ENVIRONMENT MANAGEMENT PLAN
ENVIRONMENT MANAGEMENT PLAN 1 [Type the company name] ENVIRONMENT MANAGEMENT PLAN LIMESTONE (BUILDING) 1.0. INTRODUCTION: The proposed M/s. Building Lime Stone Mine of Shree Jitubhai Parbatbhai Chudashma
ENVIRONMENT MANAGEMENT PLAN
ENVIRONMENT MANAGEMENT PLAN Page 33 ENVIRONMENT MANAGEMENT PLAN BLACK TRAP 1.0. INTRODUCTION: The proposed M/s. Black Trap Mine of Govindbhai Karshanbhai Ram area at near Vill.Chuldi, Tal.Malia-Hatina,
EnVirOnMEnT ManaGEMEnT PLan. FOr. M/S. LiME STOnE MinE OF. Dhirajlal Panchanbhai Vachhani. area. PrOPOSEd PrOdUCTiOn:-36000 TPa
EnVirOnMEnT ManaGEMEnT PLan FOr M/S. LiME STOnE MinE OF dhirajlal PanChhanBhai VaChhani area (SUrVEY no.49 PaiKi, ViLL.Unadari, TaL.Una, dis.junagadh) PrOPOSEd PrOdUCTiOn:-36000 TPa PrOJECT COST: - 15
ENVIRONMENT MANAGEMENT PLAN
ENVIRONMENT MANAGEMENT PLAN LIMESTONE 1. INTRODUCTION: The proposed Bagdhara Limestone area, near Village- Bagdhara, Taluka- Jamjodhpur and District-Jamnagar, Gujarat has been granted to Dipakkumar Anantray
ENVIRONMENT MANAGEMENT PLAN
ENVIRONMENT MANAGEMENT PLAN ENVIrONMENT MaNaGEMENT plan 1. INTRODUCTION: Shri Ratilal Ravji Solanki have a Blacktrap mining lease project for an area of 1.00.00 Ha located on Survey no. 984 paiki, Village:
Refining of Crude Oil - Process
Introduction: The process of producing valuable Petroleum Products from Crude Oil is termed as Oil Refining. Refining is a complex engineering application which involves both Physical and Chemical processes
Element D Services Plumbing
Medical Vacuum and Gas PART 1 - GENERAL 1.01 OVERVIEW A. This section addresses medical vacuum, waste anesthetic gas disposal, compressed air, oxygen, nitrous oxide, nitrogen and carbon dioxide systems.
The Ministry of Environment and Forest says No Discharge from Red Mud Pond in Lanjigarh
The Ministry of Environment and Forest says No Discharge from Red Mud Pond in Lanjigarh In response to allegations raised by certain groups claiming leakage from the Red Mud Pond at the Alumina refinery
Pre- FEASIBILITY REPORT
Pre- FEASIBILITY REPORT In Respect Of JHILIMINDA SAND BED OVER 20.30 ACRES OR 8.215 HA IN VILLAGE JHILIMINDA, ATTABIRA TAHASIL OF BARGARH DISTRICT, ODISHA (For the Financial Year-2015-16 to 2019-20) Prepared
Fire & Explosion Risks in Service Stations
Fire & Explosion Risks in Service Stations Petrol Vapour Petrol gives off highly flammable vapour even at very low temperatures. Because of the flammability of petrol vapours, service stations carry a
ENVIRONMENT MANAGEMENT PLAN
6. REHABILITATION AND RESETTLEMENT (R & R) PLAN Since the project is private land, there is no reserves forest or protected forest land within the applied area. There is no human settlements within the
PROPOSED TERMS OF REFERENCE
Annexure-IV PROPOSED TERMS OF REFERENCE 1.0 Proposed Scope of Work for EIA Study The components of the EIA study include: Detailed description of all elements of the project activities (existing and proposed
ENVIRONMENTAL CODE OF PRACTICE FOR CONCRETE BATCH PLANT & ROCK WASHING OPERATIONS
ENVIRONMENTAL CODE OF PRACTICE FOR CONCRETE BATCH PLANT & ROCK WASHING OPERATIONS PREPARED BY: DEPARTMENT OF ENVIRONMENT AND LANDS INDUSTRIAL ENVIRONMENTAL ENGINEERING DIVISION APRIL 16, 1992 - TABLE OF
PROPOSED TOR FOR EIA STUDY
JAWAHARPUR VIDYUT UTPADAN NIGAM LIMITED 2x660 MW JAWAHARPUR THERMAL POWER PROJECT JAWAHARPUR, DISTRICT ETAH, UTTAR PRADESH PROPOSED TOR FOR EIA STUDY SEPTEMBER- 2015 DESEIN PRIVATE LIMITED CONSULTING ENGINEERS
WERRIS CREEK COAL PRP U1: MONITORING RESULTS WHEEL GENERATED DUST
Report WERRIS CREEK COAL PRP U1: MONITORING RESULTS WHEEL GENERATED DUST WERRIS CREEK COAL PTY LTD Job ID. 07487c 29 July 2014 PROJECT NAME: Werris Creek Coal PRP U1: Monitoring Results Wheel Generated
(IV) Proposed Terms of Reference for EIA Studies
ENVIRONMENT CLERNCE FOR EXPNSION OF 1X600 MW SUPER CRITICL THERML POWER PLNT BY DDITION 2X800 MW UNIT (PHSE II) IN RIGRH DISTRICT IN CHHTTISGRH STTE (IV) Proposed Terms of Reference for EI Studies Project
Pre- FEASIBILITY REPORT
Pre- FEASIBILITY REPORT In Respect Of SRIPURA SAND BED-BOVER 35.25 ACRES OR 14.265 HA IN VILLAGE SRIPURA, JHARSUGUDA TAHASIL OF JHARSUGUDA DISTRICT, ODISHA (For the Financial Year-2015-16 to 2019-20) Prepared
Climate Change and Infrastructure Planning Ahead
Climate Change and Infrastructure Planning Ahead Climate Change and Infrastructure Planning Ahead Infrastructure the physical facilities that support our society, such as buildings, roads, railways, ports
CHAPTER 11 STORM DRAINAGE
CHAPTER STORM DRAINAGE SECTION PC 0 GENERAL 0. Scope. The provisions of this chapter shall govern the materials, design, construction and installation of storm drainage. Storm water discharge shall be
MBJ Environmental Programmes
MBJ Airports Limited Environmental Policy The following is MBJ Airports Limited s (MBJ) Environmental Policy for Sangster International Airport (SIA): Integrate environmental management measures with planning,
Civil Engineering Sector Labour-Management Health and Safety Committee
PROCEDURE FOR THE STORAGE AND HANDLING OF FUEL ON CONSTRUCTION SITES Civil Engineering Sector Labour-Management Health and Safety Committee July 2008 PROCEDURE FOR THE STORAGE AND HANDLING OF FUEL ON CONSTRUCTION
Spill Prevention, Control and Countermeasure (SPCC) Rule
Spill Prevention, Control and Countermeasure (SPCC) Rule Code of Federal Regulations Title 40 CFR Part 112 Training Guide for Oil and Fuel handlers on Farms 1 Purpose of SPCC Rule To prevent oil discharges
MAP KEYS GLOSSARY FOR THE DRAINAGE AND WATER REPORT
Record MAP KEYS GLOSSARY FOR THE DRAINAGE AND WATER REPORT Abandoned Gravity Private Combined Gravity Private Foul Gravity Private Surface Water Gravity Public Combined Gravity Public Foul Gravity Public
Section A SPCC Plan Implementation Checklist This section of the report addresses compliance with certain requirements of Federal Regulations 40 CFR 112. I. STATUS OF SPCC PLAN (40 CFR 112.3) YES NO A.
Air Eliminators and Combination Air Eliminators Strainers
Description Air Eliminators and Combination Air Eliminator Strainers are designed to provide separation, elimination and prevention of air in piping systems for a variety of installations and conditions.
Cardok Sàrl CP37 CH-1295 Tannay Switzerland Phone: 0041 22 77 66 051 [email protected]
CARDOK CARLIFT Fast access to underground garages Fast, Silent, Discreet, Design, High-Tech Installation to replace an access ramp on private property Dimensions: (Built to measure, all dimensions can
TERMS OF REFERENCE FOR THE RAPID EIA STUDY FOR SHIVKAR LIGNITE BLOCK, DIST. BARMER, RAJASTHAN
1. GENERAL TERMS OF REFERENCE FOR THE RAPID EIA STUDY FOR SHIVKAR LIGNITE BLOCK, DIST. BARMER, RAJASTHAN The main objective of the EIA study is to assess the positive and negative impacts likely to accrue
2. PRE-FEASIBILITY REPORT
2. PRE-FEASIBILITY REPORT 2.1 Executive Summary The proposed project is Building stone quarry having lease area of 0.809 ha and falls under Category- A as per EIA Notification 2006 and its amendments of
2. PRE-FEASIBILITY REPORT
2. PRE-FEASIBILITY REPORT 2.1 Executive Summary The proposed project is Building stone quarry having lease area of 1.214 ha and falls under Category- A as per EIA Notification 2006 and its amendments of
www.klmtechgroup.com TABLE OF CONTENT
Page : 1 of 36 Project Engineering Standard www.klmtechgroup.com KLM Technology #03-12 Block Aronia, Jalan Sri Perkasa 2 Taman Tampoi Utama 81200 Johor Bahru Malaysia TABLE OF CONTENT SCOPE 3 REFERENCES
Climate Change and Sri Lanka. Ajith Silva Director/ Policy and Planning Ministry of Environment and Natural Resources Sri Lanka
Climate Change and Sri Lanka Ajith Silva Director/ Policy and Planning Ministry of Environment and Natural Resources Sri Lanka Asia Total Area: 65610 Km Land Area : 62705 Km Inland water : 2905 Km 2 Coastal
Natural Resources Conservation Authority Guidelines for Secondary Containment of Hazardous Liquids stored Above-ground
Natural Resources Conservation Authority Guidelines for Secondary Containment of Hazardous Liquids stored Above-ground December 2011 Table of Contents Definition of Terms... 2 Requirements for Secondary
Indiana State Department of Health Construction Guidelines for Gravity and Flood-Dose Trench Onsite Systems
Indiana State Department of Health Construction Guidelines for Gravity and Flood-Dose Trench Onsite Systems The septic tank-absorption field sewage treatment system is composed of two major elements; the
CHAPTER 2 HYDRAULICS OF SEWERS
CHAPTER 2 HYDRAULICS OF SEWERS SANITARY SEWERS The hydraulic design procedure for sewers requires: 1. Determination of Sewer System Type 2. Determination of Design Flow 3. Selection of Pipe Size 4. Determination
GUIDELINES FOR THE LOCATION OF STATIONARY BULK AMMONIA STORAGE FACILITIES
GUIDELINES FOR THE LOCATION OF STATIONARY BULK AMMONIA STORAGE FACILITIES In accordance with Part 1, Section 4 of the Clean Air (General) Regulations, being Alberta Statute 216/75, the Department of the
Project Details- Minor Minerals (Other Than Sand)
Project - Minor Minerals (Other Than Sand) Sr. ABOUT THE PROPOSAL 1. Name of Lease Holder M/s. KARMANBHAI JODHABHAI RABARI (Partner) 2. Location address Mr. Karmanbhai Jodhabhai Rabari Survey No- 194 Paikee,
PROJECT PROFILE ON CEMENT CONCRETE HOLLOW BLOCKS
PROJECT PROFILE ON CEMENT CONCRETE HOLLOW BLOCKS PRODUCT : Cement Concrete Hollow Blocks NIC CODE : 26959 (based on NIC 2004) PRODUCT CODE : 94459 (based on ASICC 2000) PRODUCTION CAPACITY : Quantity :
PIPELINE FUNDAMENTALS. texaspipelines.com
PIPELINE FUNDAMENTALS texaspipelines.com Texas Oil & Gas: Generating $2.6 Billion for State Revenues texaspipelines.com Texas Oil & Gas Texas produces 20% of US Domestic Oil Production 1.1 Million Barrels
RULE 8-8 - ORGANIC COMPOUNDS - WASTEWATER COLLECTION AND SEPARATION SYSTEMS
BAY AREA AIR QUALITY MANAGEMENT DISTRICT RULE 8-8 - ORGANIC COMPOUNDS - WASTEWATER COLLECTION AND SEPARATION SYSTEMS (ADOPTED: January 17, 1979) (AMENDED: November 1, 1989; October 6, 1993; June 15, 1994;
<Insert Picture Here> JD Edwards EnterpriseOne Bulk Stock Industry & Overview
JD Edwards EnterpriseOne Bulk Stock Industry & Overview 2 The following is intended to outline our general product direction. It is intended for information purposes only, and may
Bharat Petroleum Corporation Limited,
Bharat Petroleum Corporation Limited, Ennore Installation, Survey No: 1556 B Vallur village and 354/1 Athipattu village, Chennai 600081 RECEIPT, STORAGE & DISTRIBUTION OF MOTOR SPIRIT (MS), HIGH SPEED
www.klmtechgroup.com TABLE OF CONTENT
Page : 1 of 23 Rev: 01 Project Engineering Standard www.klmtechgroup.com KLM Technology #03-12 Block Aronia, Jalan Sri Perkasa 2 Taman Tampoi Utama 81200 Johor Bahru Malaysia TABLE OF CONTENT SCOPE 2 DEFINITIONS
6.0 WHOLESALE TRADE 6.1 REGIONAL MARKETS
48 6.0 WHOLESALE TRADE Delhi is the biggest consumption centre in North India. It has attained the status of a major distribution centre by virtue of its geographical location and other historical factors.
FIRE SAFETY GUIDANCE NOTE Risk Assessments for Petrol Filling Stations Required Under Fire Safety Legislation
FIRE SAFETY GUIDANCE NOTE Risk Assessments for Petrol Filling Stations Required Under Fire Safety Legislation Number: GN75 This Guidance Note provides information on the legislation relating to risk assessments
APPENDIX 4. Risk Tables
APPENDIX 4 Tables Preliminary Qualitative Criteria The qualitative risk assessment criteria have been developed to identify key risks to the environment, society, heritage and business reputation. The
Fire Safety In High Rise Building
Fire Safety In High Rise Building CLASSIFICATION OF BUILDINGS AS PER NATIONAL BUILDING CODE 1. GROUPING. Group A - Residential : Lodgings, Dwellings, Dormitories, Flats, Hotels. Group B Group C - Educational
MARYLAND AVENUE BACKUPS DURING AUGUST 31, 2014 STORM EVENT COMMUNITY OUTREACH
MARYLAND AVENUE BACKUPS DURING AUGUST 31, 2014 STORM EVENT COMMUNITY OUTREACH MARYLAND AVENUE BACKUPS COMMUNITY OUTREACH MEETING AGENDA Introductions History of PWSA Actions August 31 Storm Impacts Short
HYDRAULIC ANALYSIS OF OIL SPILL CONTROL SYSTEMS AT ELECTRICAL TRANSFORMER STATIONS
HYDRAULIC ANALYSIS OF OIL SPILL CONTROL SYSTEMS AT ELECTRICAL TRANSFORMER STATIONS JAMES LI (1) & CELIA FAN (2) (1) Department of Civil Engineering, Ryerson University, Toronto, Canada, [email protected]
DESCRIPTION OF STORMWATER STRUCTURAL CONTROLS IN MS4 PERMITS
DESCRIPTION OF STORMWATER STRUCTURAL CONTROLS IN MS4 PERMITS Phase I MS4 permits require continuous updating of the stormwater system inventory owned and operated by the MS4. They also include inspection
TERMS OF REFERENCE. BEFORE CONSTRUCTION: Sl No TOR RESPONSE 1. Legalities of the land: Is the land The Project is clear from all angles.
TERMS OF REFERENCE Name of the Project: M/s Suadela Constructions Pvt. Ltd. Address: Sy.No. 321/2B(P),321/2C(P),322/1,323/1(P),323/1(P),323/3,323/4,323/5(P), 323/6,323/7,325/1(P),325/2,327,328/1,328/2(P),328/3,328/4,330,331,332/2
Format for scrutinising the Hill Station Building Applications ( Current File No. 24911/2001-HSBA) The application shall be accompanied by
Format for scrutinising the Hill Station Building Applications ( Current File No. 24911/2001-HSBA) 1 2 3 4 5 I. Tamil Nadu Districts Municipalities (Hill Stations) Building Rules 1993. Rules Required Available
CHAPTER 62-740 PETROLEUM CONTACT WATER
CHAPTER 62-740 PETROLEUM CONTACT WATER 62-740.010 Declaration of Intent (Repealed) 62-740.020 Applicability 62-740.030 Definitions 62-740.040 General 62-740.100 Management Practices for Producers of PCW
Environmental Site Inspection Checklist
Note : This form is designed for general use and may not be exhaustive. Modifications and additions may be necessary to suit individual projects and to address specific environmental issues and associated
CHAPTER 1 INTRODUCTION
CHAPTER 1 INTRODUCTION 1.1 Project Background Beta Cement Ltd, hereinafter referred to as the promoter and/or proponent, intends to construct a cement storage terminal on premises that has been reserved
Pollution Control NEW! NEW! Stormwater Attenuation Systems Sustainable Urban Drainage Solutions for Domestic & Commercial Applications. klargester.
Pollution Control NEW! NEW! Stormwater Attenuation Systems Sustainable Urban Drainage Solutions for Domestic & Commercial Applications klargester.com Stormwater Attenuation Systems Sustainable Urban Drainage
London Borough of Waltham Forest LOCAL FLOOD RISK MANAGEMENT STRATEGY. Summary Document
LOCAL FLOOD RISK MANAGEMENT STRATEGY Summary Document October 2013 Local Flood Risk Management Strategy Summary 1 Introduction 2 Partner responsibilities 3 What do we know about flooding in the borough?
Maine Department of Environmental Protection Program Guidance On Combined Sewer Overflow Facility Plans
Maine Department of Environmental Protection Program Guidance On Combined Sewer Overflow Facility Plans OVERVIEW The objective of a Combined Sewer Overflow (CSO) Facility Plan is to abate CSO discharges
MOBILE HOME LAW. Revised November 2001
MOBILE HOME LAW Revised November 2001 TABLE OF CONTENTS: SECTION 1: SECTION 2: SECTION 3: SECTION 4: SECTION 5: SECTION 6: SECTION 7: SECTION 8: SECTION 9: SECTION 10: SECTION 11: SECTION 12: INTENT DEFINITIONS
MOBILE FIRE - RESCUE DEPARTMENT FIRE CODE ADMINISTRATION
MOBILE FIRE - RESCUE DEPARTMENT FIRE CODE ADMINISTRATION Fire Pump Plan Review 2009 International Fire Code and NFPA 20 Date of Review / / BLD201 - Project Address: Project Name: Contractor s Business
Abstract. 1 Introduction. 2 Sampling locations
Air Pollution XV 363 Ambient air quality monitoring in southern Kuwait A. A. Ramadan, A. Khan & S. Al-Hajraf Coastal and Air Pollution Department, Institute for Scientific Research, Kuwait Abstract Ambient
Environmental Management Plan
Environmental Management Plan FOR BOULDER, GRAVEL AND SAND MINOR MINERAL Mine lease area: 13.20 Ha Village Mandlai Tehsil Raipur Rani, District- Panchkula and State - Haryana Category of Project: B2 Lease
Annexure-A. No additional land used. acquired for any activity of project without obtaining proper permission. v For controlling fugitive natural dust
Annexure-A Compliance Report SEAC 2010/CR.824/TC-2 Dated 02/11/2011 Reporting Date : 27/06/2014 Manufacture of alpha Pinene, Beta Pinene, Limonene and byproducts by way of backward integration at MIDC,
Environment Management Plan
Environment Management Plan FOR Mining of Sildhara Flage Stone Quarry Area-.1.50,Hectare Kh No-87 At Village- Sildhara, Tehsil Panna, Distt.Panna MR.BRIJMOHAN SINGH S/O SHRI JAI RAM SINGH RESI-VILLAGE
CONTENTS ABOUT US SALES OVERVIEW SALES PRODUCTS OTHER SERVICES OUR LOCATIONS ACCREDITATIONS RECENT PROJECTS 12 CASE STUDIES 13
CONTENTS ABOUT US 3 SALES OVERVIEW 4 SALES PRODUCTS 4 OTHER SERVICES 6 OUR LOCATIONS 10 ACCREDITATIONS 11 RECENT PROJECTS 12 CASE STUDIES 13 2 ABOUT US Power Electrics is the largest independent generator
TOR for Synthetic Organic Chemicals ToR for EIA studies in respect of the synthetic organic chemicals industry may include, but not limited to the
TOR for Synthetic Organic Chemicals ToR for EIA studies in respect of the synthetic organic chemicals industry may include, but not limited to the following: 1 Executive summary of the project giving a
The Use and Application of the Benchmarking Assessment Tool for the Recovery and Recycling of Used Lead Acid Batteries in India
The Use and Application of the Benchmarking Assessment Tool for the Recovery and Recycling of Used Lead Acid Batteries in India Brian Wilson International Lead Management Center (ILMC) In conjunction with:
SPILL PREVENTION, CONTROL AND COUNTERMEASURE PLAN
SPILL PREVENTION, CONTROL AND COUNTERMEASURE PLAN XXXX FARM (CITY OR COUNTY), MICHIGAN CONTACT (NAME), OWNER CERTIFICATION: I hereby certify that I have examined the facility, and being familiar with the
Ontario Fire Code SECTION 5.13 DIP TANKS. Illustrated Commentary. Office of the Ontario Fire Marshal
Ontario Fire Code SECTION 5.13 DIP TANKS Illustrated Commentary Office of the Ontario Fire Marshal Dip Tanks Illustrated Commentary 1 5.13.1. Location 5.13.1.1. Dip tank operations involving flammable
Homeowner s Guide Foundation Water PenetrationTips TIPS TO IDENTIFY WATER PENETRATION PROBLEMS / CRACKING BASEMENTS
Homeowner s Guide Foundation Water PenetrationTips TIPS TO IDENTIFY WATER PENETRATION PROBLEMS / CRACKING BASEMENTS MAINTAINING YOUR HOME BASEMENT FOUNDATION BY HOMEOWNER PREVENTATIVE MAINTENANCE LUX WATERPROOF
DEF Q&A. A. SCR is a technology that uses a urea based diesel exhaust fluid (DEF) and a
Selective Catalytic Reduction (SCR) Q. What is Selective Catalytic Reduction (SCR)? A. SCR is a technology that uses a urea based diesel exhaust fluid (DEF) and a catalytic converter to significantly reduce
Natural Gas and the U.S. Fertilizer Industry
Natural Gas and the U.S. Fertilizer Industry Harry Vroomen Vice President, Economic Services The Fertilizer Institute July 15, 2010 www.tfi.org Outline of Presentation Brief Intro on Fertilizer Focus on
ENVIRONMENT MANAGEMENT PLAN
1.0 INTRODUCTION ENVIRONMENT MANAGEMENT PLAN The Environment Management Plan has been developed with a view to bring down the levels of impacts during proposed mining activities In each of the areas of
Gas Detection for Refining. HA University
Gas Detection for Refining HA University Refinery Process and Detection Needs Refining i Crude Oil Final Products Coke Asphalt Waxes, Lubricating Oils and Greases Kerosene, Jet Fuel, Diesel Fuel, Home
Liquid Effluent Treatment Plant (LETP) Land Clean-Up
Liquid Effluent Treatment Plant (LETP) Land Clean-Up Frequently Asked Questions What is proposed? Magnox Ltd is proposing to remove the redundant Liquid Effluent Treatment Plant (LETP) at Harwell and to
PROPASAL FROM FOR PUBLIC LIABILITY INSURANCE (For Industrial Risks and Storage Risks)
PROPASAL FROM FOR PUBLIC LIABILITY INSURANCE (For Industrial Risks and Storage Risks) LIABILITY OF THE COMPANY DOES NOT COMMENCE UNTIL THE PROPOSAL HAS BEEN ACCEPTED AND THE PREMIUM PAID THE TERRITORIAL
Published in "Official Gazette of the Republic of Macedonia" No. 67/2004 LAW ON AMBIENT AIR QUALITY I. GENERAL PROVISIONS
Published in "Official Gazette of the Republic of Macedonia" No. 67/2004 LAW ON AMBIENT AIR QUALITY I. GENERAL PROVISIONS Article 1 Subject of regulation (1) This Law shall regulate the measures for avoidance,
OUR CONVERSATION TODAY
OUR CONVERSATION TODAY Our goal is to raise the level of awareness around the oil supply chain among key stakeholders in order to facilitate positive working relationships and more informed decision making.
PLANT LOCATION AND LAYOUT
PLANT LOCATION AND LAYOUT The Location Of The Plant Can Have A Crucial Effect On The Profitability Of A Project, And The Scope For Future Expansion. Many Factors Must Be Considered When Selecting A Suitable
Project Details- Minor Minerals (Other Than Sand)
Project - Minor Minerals (Other Than Sand) Sr. ABOUT THE PROPOSAL 1. Name of Lease Holder M/s. ABDUL MUNAF MOHAMMEDMIYA MALEK Mr.Abdul Munaf Mohammedmiya malek (Proprietor) 2. Location address OPP Block
From cow dung to biogas in Karnataka, India
From cow dung to biogas in Karnataka, India Beyond Carbon India, 2012 Project summary With the carbon offset project Kolar Biogas Project, myclimate and its local partner SKG Sangha are contributing to
CHAPTER 8 CIVIL DESIGN
CHAPTER 8 CIVIL DESIGN A. GENERAL This Chapter includes standards and design considerations for other civil engineering design in structural, drainage and utilities. Design considerations for electrical
SIX REASONS TO DRY BIOGAS To A LOW DEWPOINT BEFORE COMBUSTION IN A CHP ENGINE STEVEN SCOTT MARKET DEVELOPMENT MANAGER ALTERNATIVE ENERGIES
SIX REASONS TO DRY BIOGAS To A LOW DEWPOINT BEFORE COMBUSTION IN A CHP ENGINE STEVEN SCOTT MARKET DEVELOPMENT MANAGER ALTERNATIVE ENERGIES Filippo Turra Product Manager Cooling Technology INTRODUCTION
Suffolk County Department of Health Services. Division of Environmental Quality
Suffolk County Department of Health Services Division of Environmental Quality Guidelines For the Construction of Storage Areas for Portable Containers ~~~~ Clare B. Bradley, M.D., M.P.H. Suffolk County
Backup Fuel Oil System Decommissioning & Restoration Plan
Backup Fuel Oil System Page 1 of 19 Overview of Physical Fuel Oil System and Decommissioning Steps The fuel oil system at Milford Power consists of a number of subsystems. These include the following: