1 SUBFLOOR REQUIREMENTS KÄHRS WOOD FLOORS GB SUBFLOOR REQUIREMENTS AND UNDERFLOOR HEATING Kährs UK Ltd Unit A4 Cairo Place Endeavour Business Park 7 Penner Road, Havant Hampshire PO9 1QN Phone: Fax: [email protected]
2 SUBFLOOR REQUIREMENTS KÄHRS WOOD FLOORS 2 CONTENT GENERAL REQUIREMENTS FOR SUBFLOORS PAGE 3 A fl oor can only be as good as the subfl oor allows Humidity and temperature Curvature SPECIFIC REQUIREMENTS FOR FLOORS GLUED TO THE SUBSTRATE PAGE 5 General Adhesive used for gluing WOOD FLOORS AND UNDERFLOOR HEATING PAGE 6 Specifi c requirements for wood fl oors over underfl oor heating Choice of wood fl oor Thermal conductivity in W/(m*K) VAPOUR BARRIER/DAMP-PROOF MEMBRANE PAGE 7 Vapour barrier Damp-proof membrane IMPACT SOUND INSULATION INTERMEDIATE LAYER PAGE 7 CONCRETE FLOORS AND LEVELLED FLOORS PAGE 8 TIMBER FLOOR STRUCTURES PAGE 8 CHIPBOARD PAGE 8 PLYWOOD PAGE 8 EXISTING WOOD FLOORS PAGE 8 PVC FLOORING PAGE 8 LINOLEUM FLOORING PAGE 8 CERAMIC TILES PAGE 8 NEEDLEFELT CARPET PAGE 9 FITTED CARPET PAGE 9 LIGHTWEIGHT CONCRETE PAGE 9 EPS FOAM (EXPANDED POLYSTYRENE) PAGE 9 HDPE AIR-GAP MEMBRANES PAGE 9 AIR-GAP SUBFLOOR SYSTEM PAGE 10 SECONDARY SPACED BOARDING PAGE 10 SAND PAGE 10 PLASTERBOARD SHEETS PAGE 10 GENERAL INFORMATION ABOUT MOISTURE PAGE 11 Relative humidity Moisture protection Moisture is often the cause of a problem
3 SUBFLOOR REQUIREMENTS KÄHRS WOOD FLOORS 3 GENERAL REQUIREMENTS FOR SUBFLOORS A floor can only be as good as the subfloor allows The substrate must fulfi l a number of criteria to enable different types of wood fl oors to function for many years. The criteria are as follows: When installing, the materials, substrate and site must be heated to at least 18 C. The relative humidity in the premises must be lower than 60%. The substrate must be clean, solid and dry and provided with the necessary protection against moisture. The subfl oor must be suffi ciently level. (HusAMA98, Table 43. DC/-1 Class A and MDB.3). The EPS foam underlay must have suffi cient compression strength (RA98Hus IBF.11, HusAMA98IBF.11 or SS-EN13163). The foam sheets must comply with the necessary thickness tolerance (HusAMA98 IBF.11 or SS-EN13163). Soft, springy subfl oors must be rectifi ed. For example, carpets with a thick pile must be removed. Humidity and temperature The chapter on MD in RA states that the air s relative humidity (RH) should lie between 30 60%. If the RH is above 60% the premises must be dehumidifi ed. If it is below 30% there is a risk of concavity. The temperature must be at least 18 C. It is important for parquet fl oors that the RH of the air is maintained within the specifi ed limits. Permanent damage can occur if the RH is too high. HusAMA98 JSF states, for example, that if the size and number of gaps exceed those prescribed by AMA, it is often due to excessive humidity followed by drying out. A parquet fl oor must always be protected against moisture from the subfl oor. For protection against moisture (vapour barrier), we recommend 0.2 mm ageing-resistant PE sheeting, i.e. sheeting that meets the requirements in the current edition of SPF s Verksnorm The sheeting must be laid with an overlap of at least 200 mm. We also approve Kährs Tuplex as a vapour barrier. The underlay must always be clean and free from organic material such as wood chips, scraps of paper, etc., before the vapour barrier is installed. The organic material will otherwise cause mould when the RH under the sheeting subsequently increases. Hus AMA98 JSF.52 deals with building moisture. It specifi es 60% relative humidity (RH) as the upper limit in suspended fl oor structures (e.g. concrete) before protection against moisture in the form of a vapour barrier normally becomes necessary. Note that newly cast concrete fl oor structures are never suffi ciently dry by the time a fl oor is installed, and a vapour barrier is therefore always needed. A few months after the concrete is cast, the RH in the structural fl oor is usually <95% and moisture measurement is not normally necessary. A vapour barrier is obligatory for certain types of structural fl oors irrespective of age. HusAMA98, MD states: When installing a floor on ground-supported fl oors structural fl oors above warm or humid areas (boiler rooms, laundry rooms) above a crawl space foundation warm fl oors (underfl oor heating) lightweight concrete fl oor structures the fl oor construction MUST be provided with a vapour barrier. Lightweight concrete fl oor structures must be fi tted with a vapour barrier because of the long drying-out time. If the RH in the substrate is over 95%, a plastic sheeting vapour barrier does not give suffi cient protection against moisture. Curvature For an installed parquet fl oor to perform satisfactorily, the substrate must have a suffi ciently smooth surface. The requirements in HusA- MA98, Table 43. DC/-1, class A apply to all fl oors from Kährs. The tolerance is ± 3 mm over a measured length of 2 m, and ± 1.2 mm over a measured length of 0.25 m. Kährs also approves a tolerance of ± 2 mm over a measured length of 1 m. Equipment A straight edge should be used. Two lengths should be used, with pegs at 0.25 m and 2.0 m centres respectively. The contact area between the pegs and the substrate should be 100 mm². Kährs also approves a 1.0 m straight edge for check measurements. A wedge gauge should be used. Precision levelling is an alternative to using a straight edge. Procedure When measuring, the straight edge must be located in the most adverse position on the surface. The pegs must not be located in joints in brickwork or similarly pronounced joints. However, irregularities in construction joints in concrete or slab fl oors are also covered by the measurement requirements. The tolerance requirements in AMA are set as absolute values and must therefore be complied with at each measurement point. Measurements made in this way always result in a pass or fail. The imaginary line between the pegs contact surfaces with the substrate is used as the reference value. All measurement points along the line must then meet the stipulated requirements wherever the straigh tedge is placed. Even if the curvature requirements are met, the wood fl oor is not necessarily in constant contact with the substrate. However, the fl exing that occurs is not harmful to the board.
4 SUBFLOOR REQUIREMENTS KÄHRS WOOD FLOORS 4 Example A Situation: Measurement length = 2 m, Peg height = 10 mm Tool = Wedge gauge If the wedge gauge measurement is 7 mm, the plus value is (+) 10 7 = 3 mm. Therefore a pass. Example C Situation: As in example A Moving the straight edge to the left gives the plus value (+) = 6 mm, which is also a fail. Example B Situation: As in example A If the straight edge is moved to the right so that the pegs contact the elevated areas, the minus value is (-) = 6 mm. This is a fail because all measurement points must meet the specifi ed tolerance requirements. No value, + or -, must be greater than 3 mm. Example of measurement of curvature: Plus value Minus value A B C
5 SUBFLOOR REQUIREMENTS KÄHRS WOOD FLOORS 5 SPECIFIC REQUIREMENTS FOR FLOORS GLUED TO THE SUBSTRATE General If the fl oor material is to be glued to a concrete substrate, the surface must be strong enough to withstand a scratch test without the concrete fl aking. This also applies to fl oor surfaces fi nished with a levelling compound. If a weak surface skin remains it must be ground away, otherwise the adhesive will not bond properly. If the substrate construction means it is not possible to glue directly to it, or if a vapour barrier is required, a sheet material must be laid under the wood fl oor. Even if a sheet material is not a requirement, it may still be advisable to use it, as a surface to glue the fl oor to. The fl oor can then be stripped out easily when it needs replacing. Suitable sheet materials for this purpose are: Good quality chipboard of at least class 2 SIS , 19 mm thick. A minimum of 16 mm may be suitable provided the substrate is level. Plywood (preferably pine), at least B quality and min. 12 mm thick, driven or screwed to the substrate at 400 mm centres. Always follow the sheet manufacturer s installation instructions. Note the adhesive manufacturer s priming requirements for these substrates. The surface must also be clean and free from dust, grease and dirt. Any old adhesive residues on the substrate should normally be removed (follow the adhesive manufacturer s instructions). If the sheet manufacturer has used a mould release agent in production, adhesion can be jeopardised. To ensure a good bond, the sheets should be sanded. without joints. Floors laid in patterns must usually be glued down to perform well. Whenever the fl oor is glued down, the end joints should be staggered because this levels out the fl oor and avoids bond failure when the adhesive dries. To ensure adhesion, the fl oor can be weighted down while the adhesive dries. Adhesive used for gluing Surface-treated products to be glued to suspended concrete fl oor structures that do not exceed RH 65% must be glued using an adhesive that does not contain water, such as an MS polymer adhesive. Irregularities in the substrate must never be levelled with adhesive because this results in an uneven and inadequate bond. Use a spreader that applies the correct amount of adhesive. The adhesive manufacturer s instructions must be followed. Kährs parquet boards with Woodloc joints can be glued to the substrate. The laying wedge with pullout string used for Woodloc installation is designed so that it can also be used when gluing. For gluing to suspended concrete fl oor structures where the RH exceeds 65% read the section above and make sure that you follow the adhesive manufacturer s instructions. MS polymer adhesive does not give the same moisture protection as a vapour barrier. When a factory-fi nished fl oor that has been glued down using an MS polymer is re-lacquered, the bond between the new coat of lacquer and the factory-fi nished lacquer cannot be guaranteed. If the substrate requires an expansion joint, the same also applies to the parquet. Otherwise, very large continuous areas can be laid
6 SUBFLOOR REQUIREMENTS KÄHRS WOOD FLOORS 6 WOOD FLOORS AND UNDERFLOOR HEATING General Wood fl oors and underfl oor heating are often combined nowadays and work well together. The heating system used electrical or water is of no signifi cance to the wood fl oor. The underfl oor heating system must deliver no more than 80 W/m 2, evenly distributed. The surface temperature of the fl oor must never exceed 27 C. This applies even next to/above radiator pipes, above pipe runs and under carpets, furniture etc. In a normally insulated house, with a properly functioning underfl oor heating system, the temperature of the fl oor surface is generally 2 C higher than the room temperature. In a warm water underfl oor heating system, the fl ow temperature is usually 7 12 C higher than the fl oor s surface temperature. The installation instructions for each type of fl oor also apply to installation over underfl oor heating. This section discusses issues particular to wood fl oors over underfl oor heating. Specific requirements for wood floors over underfloor heating The fl oor construction must have a heat-distributing layer that gives a very even temperature across the entire fl oor area, in order to avoid excessive temperatures near the heat source. The entire living area must be heated. However, this does not apply to comfort heating systems, which complement the normal heating. The temperature in this case is signifi cantly lower than the permitted 27 C at the fl oor surface. The fl oor covering (including intermediate layer) should have a low thermal conductivity. It must be possible to control and limit the surface temperature very accurately. The installed fl oor s temperature must never exceed 27 C. This also applies under carpets and furniture. If the room does not have too many textile fl oorcoverings or particularly thick rugs, it is reasonable to achieve 23 C in the clear fl oor areas, giving a room temperature of approximately 21 C. The proviso, of course, is that the room has normal heating requirements, i.e., it must have normal standards of draughtproofi ng, insulation, window area, ceiling height, etc. Note that the requirement for max. 27 C also applies to pipe runs from bypass groups. A vapour barrier must be built into the fl oor construction. This should be as close to the wood fl oor as possible. It is particularly important that the vapour barrier is close to the wood fl oor if the structural fl oor is thick or heavy. Under no circumstances must the vapour barrier be on the opposite side of the structural fl oor. The wood fl oor must lie tightly to the substrate, without air gaps that may cause substantial drying of the wood. However, Kährs Activity Floor can be installed over underfl oor heating because there are no air changes to cause drying. Provided the conditions above are met, both warm water and electrical underfl oor heating systems are suitable for use with Kährs wood fl oors. Choice of wood floor All Kährs fl oors have Woodloc joints, which reduces the risk of gaps occurring. Hard Maple (Canadian Maple) and Beech multi-layer parquet expands and contracts more than other species. Underfl oor heating increases drying, which causes additional contraction. In a cold and dry climate, gaps may therefore appear between strips and between boards. Thermal conductivity in W/(m*K) Product Without intermediate layer Kährs wood fl oors 14, 15 and 20 mm 0.14 Kährs Linnea 7 mm 0.22 Underfl oor heating Radiator heating Note that thick rugs, etc., can result in damagingly high temperatures in the wood floor. Underfl oor heating gives the ideal distribution of heat within a living space.
7 SUBFLOOR REQUIREMENTS KÄHRS WOOD FLOORS 7 VAPOUR BARRIER/DAMP-PROOF MEMBRANE IMPACT SOUND INSULATION INTERMEDIATE LAYER Vapour barrier A vapour barrier must be located as close to the fl oor as the construction permits. This usually means it is placed under the intermediate layer. We recommend 0.2 mm thick polyethene (PE) sheeting that meets the requirements in the current edition of the Swedish Plastics Federation s Verksnorm 2000 as a vapour barrier. The sheeting is laid with a overlap of min. 200 mm in accordance with RA98Hus JSF.5 and JSF.52. With this overlap the joints need not be taped. Applying coats of so-called damp-proofi ng agents can never replace a vapour barrier, i.e. protect against moisture penetration. For substrates where a vapour barrier is always required, read section Humidity and temperature. When a vapour barrier is used with an intermediate layer, the sheeting must be placed under the intermediate layer. Kährs Tuplex is approved as a vapour barrier provided it is installed as instructed. In accordance with HusAMA98 JSF.512, plastic sheeting must not be used for protection against moisture if the RH in the substrate is >95%. Damp-proof membrane When installing on a fl oor surface with a RH >95%, the damp-proof membrane can sometimes be used for protection against moisture in accordance with HusAMA 98 JSF.71. Damp-proof membranes are made by a number of manufacturers, e.g. Platon and Mataki, and must be installed in accordance with the manufacturer s instructions. For maximum effectiveness, the construction must be mechanically ventilated. To achieve a quiet and pleasant fl oor to walk on, some form of intermediate layer should always be installed between the substrate and the wood fl oor. The most commonly used are polyethene foam, felt paper or Kährs Tuplex. Where an impact sound insulation rating is required, the underlying construction is crucial. For this reason we cannot provide general recommendations. However, when installing a fl oor in a typical family house (where there are no standardised requirements), Kährs Tuplex or polyethene foam is normally suffi cient. Floors that are glued down do not improve impact sound insulation. The intermediate layer is placed between the subfl oor and the wood fl oor. It must be installed edge-to-edge, i.e. with no overlaps. When an intermediate layer is used with a vapour barrier, the intermediate layer must be laid over the vapour barrier, which is then protected against abrasion and perforation. Kährs has tested a number of intermediate layers with regard to impact noise insulation. The results of these tests, carried out at the Swedish Testing and Research Institute (SP), are given below. If an impact sound reduction rating is required, please contact an acoustics specialist. Floor description Impact sound Impact sound Airborne ΔLw (db) class sound ΔRw (db) 7 mm Kährs wood fl oor + fl ooring paper L mm Kährs wood fl oor + Cellofl oor 2 mm mm Kährs wood fl oor + Cellofl oor 3 mm mm Kährs wood fl oor + Airolen 1.8 mm mm Kährs wood fl oor + Cellofl oor 2 mm mm Kährs wood fl oor + Cellofl oor 3 mm mm Kährs wood fl oor + Airolen 1.8 mm mm Kährs wood fl oor + Airolen 3.0 mm mm Kährs wood fl oor + Tuplex 18 7
8 SUBFLOOR REQUIREMENTS KÄHRS WOOD FLOORS 8 CONCRETE FLOORS AND LEVELLED FLOORS EXISTING WOOD FLOORS A vapour barrier is obligatory on ground-supported fl oors, crawl space foundations and newly cast suspended fl oor structures. Concrete fl oors that were previously not intended for parquet installation must usually be levelled because a parquet fl oor requires a smoother substrate. Floating floors: Uneven concrete fl oors must be levelled using a levelling compound. Glued-down floors: If the construction requires a vapour barrier, this must be covered with a sheet material. When the fl oor is glued to sheets and concrete subfl oors, large areas can be installed without expansion joints. When gluing, MS-polymer adhesive is not an adequate vapour barrier. TIMBER FLOOR STRUCTURES The timber fl oor structure must be suffi ciently dry (max 10% moisture content). To avoid creaking, make sure that battens and joists are level. The end joints of adjoining rows of boards must be staggered by at least 500 mm, and adjoining rows of boards must not have end joints that fall within the same section of framework. It is not necessary to locate the end joints over the battens. CHIPBOARD Chipboard sheets must be suffi ciently dry (max. 9.5% moisture content). Note that the maximum width for laying chipboard sheets may be less than for the multi-layer parquet. Glued-down floors: When installing on a solid substrate, such as ground-supported fl oors, the chipboard sheet must be at least 16 mm thick. If the construction requires a vapour barrier, this must be placed under the chipboard sheet. The sheets must not be fi xed to the substrate. If the sheet manufacturer has used a mould release agent in production, adhesion can be jeopardised. To ensure a good bond, the sheets should be sanded. PLYWOOD Plywood can be used as substrate for a glued parquet fl oor on concrete when a vapour barrier is required. The plywood sheets must be suffi ciently dry (max. 9.5% moisture content ). Glued-down floors: The plywood sheet must be at least 12 mm thick when installing on a level substrate such as a ground-supported fl oor. If the construction requires a vapour barrier, this must be placed under the plywood sheet, which must be nail-gunned or screwed to the substrate at 400 mm centres. The timber fl oor structure must be suffi ciently dry (10% moisture content). Floating floors: Multi-layer parquet is normally installed at right angles to the existing fl oor. Provided the old fl oorboards are level, the new fl oor can be installed in the same direction as the old fl oorboards. PVC FLOORING Floors that were previously not intended for parquet installation must usually be levelled because a parquet fl oor requires a smoother substrate. Floating floors: PVC fl ooring may be considered to act as a vapour barrier provided the fl ooring and any joints are sealed and intact. If an underfl oor heating system is to be installed, the PVC fl ooring must be removed, which may affect impact sound. Glued-down floors: It can be diffi cult to achieve adhesion to PVC fl ooring. There is often no information about how the fl ooring is stuck to the subfl oor or which adhesive was used. If the bond is inadequate, the PVC fl ooring may lift because it is pulled by the glued wood fl oor. It is therefore recommended that this fl ooring be removed. LINOLEUM FLOORING Floors that were previously not intended for parquet installation must usually be levelled because a parquet fl oor requires a smoother substrate. Floating floors: Linoleum fl ooring is made of organic material, so it must be removed if the construction requires a vapour barrier. If an underfl oor heating system is to be installed, the fl ooring must be removed, which may affect impact sound. Glued-down floors: It can be diffi cult to achieve adhesion to linoleum fl ooring. There is often no information on how the fl ooring is stuck to the subfl oor. If the bond is inadequate, the linoleum fl ooring may lift because it is pulled by the glued wood fl oor. It is therefore recommended that this fl ooring be removed. CERAMIC TILES Note that this type of fl oor was often used in the past because of the risk of moisture penetration from below. The need for a vapour barrier must therefore be checked carefully. Glued-down floors: Gluing directly onto ceramic tiles is not possible. If the surface is roughened (e.g. with carborundum) a solventbased adhesive can be used. Ceramic tiles are often used in humid premises and hygiene areas. The diffi culty in removing grease, particularly from the joints, in hygiene areas means gluing onto this
9 SUBFLOOR REQUIREMENTS KÄHRS WOOD FLOORS 9 substrate can be very diffi cult. For sheet materials suitable for use as a substrate, see section Specifi c requirements for fl oors glued to the substrate. Contact your adhesive supplier for more detailed information. NEEDLEFELT CARPET Remember that carpets may contain residues of organic material that can go mouldy in the presence of moisture. Floors that were previously not intended for parquet installation must usually be levelled because a parquet fl oor requires a smoother substrate. Floating floors: Floating installation is normally possible. However, the carpet must be removed if it lies on a construction that requires a vapour barrier. Generally, it is recommended that the carpet be removed. Kährs Linnea can be installed on this substrate. Glued-down floors: Gluing is not possible. Remove the carpet. If the fl oor lies on a construction that requires a vapour barrier, lay a sheet material. FITTED CARPET Remember that carpets may contain residues of organic material that can go mouldy in the presence of moisture. Floors that were previously not intended for parquet installation must usually be levelled because a parquet fl oor requires a smoother substrate. Floating installation of 15 mm multi-layer parquet: If the carpet s pile is short, a fl oating installation can be carried out on top of the carpet, otherwise the carpet must be removed. The carpet must be removed if the construction requires a vapour barrier. We generally recommend that the carpet be removed. Floating installation of Kährs Linnea: The carpet must be removed. Glued-down floors: Gluing is not possible. Remove the carpet. If the fl oor lies on a construction that requires a vapour barrier, lay a sheet material. LIGHTWEIGHT CONCRETE EPS FOAM (EXPANDED POLYSTYRENE) When applying supplementary insulation to concrete fl oor structures it is important to use EPS sheets designed for wood fl oor installation. To avoid undesirable fl exing and long-term damage, the thickness tolerance of the sheets should be ± 0.5 mm (see HusAMA98 IBF.11). Note that EPS sheets for (e.g.) ground insulation under concrete fl oor structures have a much higher thickness tolerance. This makes such sheets unsuitable. For the same reason, bowed sheets should not be used. Follow the foam manufacturer s instructions. Our instructions regarding EPS foam are: Floating installation of 15 mm wood floors in domestic rooms: EPS foam with a compressive strength of at least 150 kpa (density 30 kg/m³), in accordance with SS-EN An intermediate layer is placed between the foam and boards. Floating installation of Kährs Linnea in domestic rooms: EPS foam with a compressive strength of at least 150 kpa (density 30 kg/m 3 ), in accordance with SS-EN 13163, must be covered with sheets of load-distributing chipboard at least 10 mm thick or 6 mm tongue and groove chipboard or fi breboard. HDPE AIR-GAP MEMBRANES Air-gap membranes are signifi cantly more impervious than vapour barriers, and additional protection against moisture is not necessary. The membrane should meet the requirements in HusAMA 98 JSF.7, JSF.71 and JSF.72. A membrane is often used in environments where there is a high risk of capillary suction in concrete or poor air. This construction is therefore often combined with mechanical ventilation for maximum effect. Floating floors, 15 mm: Several options are available on the market. Follow the manufacturer s recommendations and instructions. Floating installation of Kährs Linnea in domestic rooms: Kährs Linnea can be installed on Delta FM Yellow Line and Platon Multi without a load-distributing sheet. A 10 mm load-distributing chipboard sheet must be laid on Blue Platon. Otherwise, see the manufacturer s recommendations and instructions. Floating installation of Kährs Activity Floor 30 mm: Blue Platon is one of the membranes that cannot be used as an underlay for Activity Floor. Glued-down floors: See Kährs Installation Guide. We always recommend a vapour barrier on this substrate, whatever its age. Uneven lightweight concrete fl oors must be levelled using a levelling compound. Glued-down floors: Because a vapour barrier is required, it must be covered with a sheet material to which the fl oor can be glued. The vapour barrier is laid under the boarding.
10 SUBFLOOR REQUIREMENTS KÄHRS WOOD FLOORS 10 AIR-GAP SUBFLOOR SYSTEM SAND Floating floors: When installing a subfl oor system such as Nivell or Granab, a 22 mm chipboard sheet must be screw-glued to the battens in accordance with the manufacturer s instructions. Remember that in many cases the wood fl oor must be protected with a vapour barrier. Follow the subfl oor system manufacturer s instructions regarding mechanical ventilation. Floating floors: 15 mm multi-layer parquet can be installed on a layer of sand. In accordance with HusAMA98. MDB.336, the sand must be covered with plastic sheeting laid with a min. overlap of 200 mm. The sheeting must also be turned up the walls. PLASTERBOARD SHEETS SECONDARY SPACED BOARDING This construction is often used in connection with underfl oor heating. Floating floors: 15 mm multi-layer parquet can be installed on 28 x 120 mm secondary spaced boarding, ideally at 160 mm centres. Floating floors: Plasterboard sheets can be used as a substrate for fl oating installation. Glued-down floors: Do not glue to paper-faced plasterboard sheets because it may make the paper-layer delaminate. These recommendations apply to installation on secondary spaced boarding on joists at max 600 mm centres.
11 SUBFLOOR REQUIREMENTS KÄHRS WOOD FLOORS 11 GENERAL INFORMATION ABOUT MOISTURE Moisture is a very important factor in fl oor installation and has a major impact on the end result. It is therefore important to know how moisture affects fl oors and fl oor installation and how to deal with the problem. Potential diffi culties can be avoided with a little information and the right approach. Relative humidity (RH) Defi nition: The air s capacity to absorb and hold moisture is related to the air s temperature. In winter, the outdoor temperature is normally low, resulting in a high RH. For example, if the outdoor temperature is -10 C, the air can hold a maximum of 2.14 g water/m 3 air. Taking this outdoor air in via ventilation and heating it to +20 C does not change the quantity of water. At +20 C the air can hold a maximum of g water/m 3 air. At 20º C, 2.14 g/m 3 is less water than the air can hold, which means the relative humidity is low. See the fi gure below. The diagram below shows how the RH varies during the year. The position and amplitude of the curve vary in different parts of the world. (This curve refl ects conditions in the Nordic region.) As can be seen from the graph, wood has a lag effect, so the EMC (equilibrium moisture content) curve is somewhat fl atter than for moisture in the indoor air. All porous materials, e.g. wood, tend to achieve the same relative humidity as that of the surrounding air. Wood is a hygroscopic material, which means that it swells or shrinks depending on the ambient climate. Different species of wood move to different extents. Furthermore, wood does not move uniformly. The manufacturing method gives multi-layer parquet and Linnea a cross-ply or locked construction because the various layers are at different angles. The movements are only 25 30% of the movements of solid wood. The greater the ventilation in winter, the drier the indoor air (and hence the fl oor) becomes. This also applies, of course, to mechanically ventilated buildings. The table below shows the shrinkage when fresh wood is dried to 0% moisture content: Wood is anisotropic, i.e. it has different properties in different directions, which is particularly apparent in shrinkage and swelling, for example. However, movement due to moisture cannot be entirely prevented. It is therefore important that there is a movement joint in between the fl oor and the wall and other fi xed objects when a parquet fl oor is installed fl oating. To stop the fl oor absorbing moisture before installation, it is important not to open packaging until just before installation. The boards in an unopened package have an RH corresponding to approximately 40% at 20 C. This is the annual mean indoor value in the Nordic region. In practice, wood s hygroscopic properties mean that the crosssection of a multi-layer fl oor is slightly concave in winter and slightly convex in summer. To limit concavity to an acceptable level, the relative humidity in winter should not be less than 30%. Important: Moisture levels in newly built premises are often still high when parquet fl oors are installed. To avoid damage it is important that the relative humidity during and after installation is below 60%. The fl oor boards may be permanently deformed if their relative humidity exceeds 60%. This could occur if the fl oor is installed in newly built premises with inadequate or no ventilation, e.g. during holiday periods. Ventilation is a simple way of keeping the relative humidity low when installing fl oors in newly built premises. Note that excessive airing/ ventilation in winter during normal conditions, i.e. in an occupied building, can make the RH too low. The temperature of rooms and materials must be at least 18 C. See Hus AMA98 MD. A parquet fl oor must not therefore be installed until all other trades, such as painters and tilers, have fi nished their work and the site has the correct RH. Max 17,34 g/m 3 (RH 100%) Max 2,14 g/m 3 (RH 100%) RH 10% RH 90% - 10 C + 20 C -10 C +20 C D F A J A O D Indoors EMC wood 20 C Outdoors Annual mean When drying from fresh wood to 0% moisture ratio, the shrinkage is as follows: Wood Across annual rings Along annual rings In fibre direction Volume Oak and Pine 4% 8% 0.4% 12% Beech and Alder 6% 12% 0.3% 18%
12 SUBFLOOR REQUIREMENTS KÄHRS WOOD FLOORS 12 Moisture protection Moisture protection is not normally necessary on structural fl oors where the relative humidity is below 60%. Note that newly cast structural fl oors do not meet this requirement, so moisture protection is always needed. Moisture protection prevents the diffusion of moisture (moisture migration) between different building materials in a building, and normally consists of 0.2 mm age-resistant polyethene. Installation instructions for vapour barriers and intermediate layers can be found in the section Vapour barrier/damp-proof membrane in this brochure. Moisture migration in constructions is determined by vapour pressure, which in turn depends on the temperature and moisture content. At the same RH, a material with a higher temperature has a higher vapour pressure than one that is colder. At the same temperature, a material with a higher RH has a higher vapour pressure than one with a lower RH. (Compare with ground-supported slab.) The vapour pressure in a construction will tend to even out, and therefore equalise itself between areas with higher and lower vapour pressures, which is usually from warm to cold. In certain situations the moisture migrates in the wrong direction (but still from the higher vapour pressure to the lower pressure). If this occurs in a fl oor construction such as a crawl space foundation with a pre-fi nished wood fl oor without a vapour barrier, the fl oor s surface treatment will be the fi rst impervious layer the moisture will encounter. This will cause the wood at the wood fl oor s surface to swell and eventually to be damaged. Certain constructions will load the vapour pressure, due to additional moisture, with high moisture content or relatively higher temperature. When installing on a fl oor surface with a RH >95%, the damp-proof membrane can sometimes be used for protection against moisture in accordance with HusAMA 98 JSF.71. Damp-proof membranes are made by a number of manufacturers, e.g. Platon and Mataki, and must be installed in accordance with the manufacturer s instructions. For maximum effectiveness, the construction must be mechanically ventilated. Moisture protection on the following subfl oors, whatever their age, is obligatory for the reasons given above: underfl oor heating concrete fl oor lying directly on the ground (ground-supported slab) fl oor above warm or humid area (e.g. boiler room or laundry room) structural fl oor above a ventilated crawl space foundation lightweight concrete fl oor structures
13 SUBFLOOR REQUIREMENTS KÄHRS WOOD FLOORS 13 Moisture is often the cause of a problem Complaints about wood fl oors arise most often from damage caused by the effects of high humidity followed by drying out. The humidity of a wood fl oor is directly proportional to the humidity of the surrounding air. If the air humidity is high, the wood fl oor s moisture content increases and the fl oor will expand. High air humidity can be caused by general building moisture, or more usually by building moisture in the concrete fl oor structure plus water vapour penetrating by diffusion through the structural fl oor from the ground. The damp wood fl oor contracts when it subsequently dries. A large excess of moisture will damage the fl oor permanently. Even natural seasonal variations can cause a certain amount of movement expansion and contraction in a wood fl oor as well as minor cross-sectional changes. These changes are not normally permanent. For example, during the summer and autumn multi-layer boards have a slightly convex cross-section as a result of expansion. The boards then contract in winter when the heating is on and acquire a slightly concave cross-section. Kährs Linnea can even exhibit the opposite behaviour when it gets damp. Gaps can appear between the boards, but these will disappear as the RH increases. The ideal RH for wood is 30 60%. This is also advantagenous for other reasons. The table Sunda hus (Healthy buildings) from BFR report R113:1989 shows that at higher or lower RH, problems such as mould, bacterial growth, asthma, etc., are created or aggravated in indoor air. There is therefore good reason to try to maintain the RH of indoor air at 30 60%. Moisture compass for relating the air s relative humidity (RH) to a fl oor s moisture content (MC). Example of interpretation of moisture compass: The levels of RH and MC on opposite sides of the diagram correspond to each other. When delivered, our fl oors have been dried to approximately 7% MC, which corresponds to a centrally heated room with a constant climate at approx. 40% RH. In a new building (e.g. a timber house), the building material normally used is only air-dry, which corresponds to outdoors under cover. If, for example, the fl oor battens are not suffi ciently dry, the parquet fl oor may become damagingly damp, and gaps will form when the wood fl oor subsequently dries. When damp battens contract, it results in a fl oor that rattles or creaks. Moisture content, %, in fl oor material at 20 C. Relative humidity (RH) Moisture content of air relative to that of saturated air. Moisture content (MC) Percentage of moisture by weight relative to the material in dry state. The diagram shows the importance of air humidity indoors. 2 3 Bacteria Virus Mould Mites 4a 0% RH 1 4b 100% RH Air passage infections Hay fever Asthma Emissions from building materials Dust 20% MC a 5 0% MC Ozone The heigth of each coloured sector is directly proportional to the occurrence of the respective contamination or risk factor Relative humidity (RH) in % The diagram is taken from BFR report R113: b 6 1. Extremely dry climate 2. Centrally-heated room with constant climate 3. None centrally-heated room with varying climate 4a. Outdoors under shelter 4b. Outdoors not covered 5. Extremely dry wood 6. Furniture-dry 7a. Joinery-dry 7b. Planing-dry 8. Storage-dry 9. Air-dry 10. Danger of mould 11. Construction timber
Wooden floors over underfloor heating
Published by the Swedish Flooring Trade Association, GBR (Edition 1:2005) Wooden floors over underfloor heating BASIC INFORMATION TRADE GUIDELINES TERMINOLOGY This guide to good practice provides basic
How to Install Hardwood Flooring Over a Sub Floor
How to Install Hardwood Flooring Over a Sub Floor Installation Preparation Instructions Read the entire instructions before starting your project. 1) INSPECT EACH PLANK (see fig. a) Wood is a natural product
How To Install Hardwood Flooring
phone: 1.855.Ludaire e-mail: [email protected] Solid Flooring Installation Instructions These Instructions and Guidelines are for the typical installation of ¾ Pre-finished Solid Hardwood Flooring manufactured
Please calculate with around 5% more square meters than needed because you will have material loss due to cutting and sorting.
1. TEKA Soft Loc Installation Guide Thank you for having chosen TEKA Parquet. To guarantee a constant quality product TEKA engineered hardwood flooring is made out of selected wood species and runs only
Euro Oak Installation
STYLE TIMBER FLOOR Bring your life in style Euro Oak Installation Before Starting Installation Your floor has been manufactured with the best possible care. However we would still advise you to check the
CERTIFICATE NAME OF PRODUCT MANUFACTURER PRODUCT DESCRIPTION CERTIFICATION PROCEDURE. No VTT C-6044-10 Date of issue 11.10.2010, Updated July 1, 2011
CERTIFICATE NAME OF PRODUCT No VTT C-6044-10 Date of issue 11.10.2010, Updated July 1, 2011 H-CONTROL REFLEX+ reflective insulating vapour control layer for roof and wall applications MANUFACTURER ACTIS
WOOD FLOORING ADHESIVES
dispersion adhesive 2 component adhesive MS polymer adhesive WOOD FLOORING ADHESIVES PROFESSIONAL PRODUCTS SOUDAL, leading adhesive manufacturer WOOD FLOORING ADHESIVES Soudal NV, located in Turnhout (B)
Installation for Wood Flooring
Installation for Wood Flooring Tarkett wood flooring offers a beautiful variety of options from species and colour, to plank widths and finishes. We developed enhanced locking system, T-lock, and the best
INTERIOR WALLS AND BASEMENTS CHOOSING THE RIGHT MEMBRANE FOR INTERIOR WALLS. Multi-Layer Technology provides increased strength.
INTERIOR WALLS AND BASEMENTS CHOOSING THE RIGHT MEMBRANE FOR INTERIOR WALLS Multi-Layer Technology provides increased strength. Specifically designed for interior applications. Compatible with most internal
WOODLINE PARQUETRY 25 Year Warranty
WOODLINE PARQUETRY 25 Year Warranty LIFE TIME STRUCTURAL WARRANTY WOODLINE PARQUETRY offers you a Lifetime Structural Warranty. WOODLINE PARQUETRY warrants that, under normal residential conditions and
Water Underfloor Heating Kit
Water Underfloor Heating Kit INSTALLATION MANUAL For small & large rooms 50 year pipe warranty CE approved Easy to install SINGLE ROOM SYSTEM INSTALLATION MANUAL Manufactured in Europe! SINGLE ROOM SYSTEM
Herringbone Pattern Flooring
Herringbone Pattern Flooring If it s not marked NOFMA, it s not certified. Handling, Storage, Installation and Tips Herringbone is generally manufactured from 3/4 x 2 ¼ or ¾ x 1-1/2 standard tongue & groove
Rockwool Flexi Insulation Application Guide
Pitched roof Rafters InterMediate floors INTERNAL partitions external Framed walls separating floors Separating Walls Rockwool Flexi Insulation Application Guide Ground floor The perfect fit for any framed
Low viscosity, solvent free elastic adhesive for wood flooring
Product Data Sheet Edition 25/06/2012 Identification no: 01 05 02 01 250 0 000009 SikaBond -54 54 Wood Floor Low viscosity, solvent free elastic adhesive for wood flooring Construction Product Description
The Solid Wood Flooring Company Unit 1 Helena Court, Hampton Street, Tetbury, Gloucestershire GL8 8JN
The Solid Wood Flooring Company Unit 1 Helena Court, Hampton Street, Tetbury, Gloucestershire GL8 8JN London Office: The Building Centre, Store Street WC1E 7BT Tel: 01666 504015 Fax: 05603 146907 Mobile:
INSTALLATION RECOMMENDATIONS. Outdoor Rubber Tiles
INSTALLATION RECOMMENDATIONS Outdoor Rubber Tiles Prior to Installation: The Outdoor Rubber Tiles and accessory transition pieces intended for this installation have been shipped to you via a freight carrier
Installation instructions for all Egger floors with the glueless system JUST clic!
Installation instructions for all Egger floors with the glueless system JUST clic! OBLIGATORY TESTING AND EXERCISE OF DUE CARE/SUB-FLOORS 1. OBLIGATORY TESTING AND EXERCISE OF DUE CARE Laminate flooring
Guide to Assessment and Repair of Flood Damaged Timber and Timber Framed Houses
Technical Guide Guide to Assessment and Repair of Flood Damaged Timber and Timber Framed Houses ASSESSMENT OF DAMAGE Prior to any assessments or repairs being commenced, a licensed electrician must undertake
Knauf Aquapanel Interior. Tile Backing. Cement board for wet areas. Will not deteriorate in water. Easy to score and snap
Tile Backing Will not deteriorate in water Easy to score and snap Resistant to mould and mildew Knauf Aquapanel Interior Cement board for wet areas Knauf Aquapanel Interior Cement Board Drywall for Wet
FLOOR MAINTENANCE GUIDE EXPECTATIONS AVOIDING PROBLEMS
No. 8 Brands Hatch Close Kyalami Business Park Kyalami Tel: 011 466 0701 Fax: 011 466 2919 Email: [email protected] FLOOR MAINTENANCE GUIDE EXPECTATIONS AVOIDING PROBLEMS Please keep this folder
Guide Specifications for Maple Flooring Systems
Guide Specifications for Maple Flooring Systems MFMA Guide Specification for Resilient Pre-Engineered Fixed Panel System Purpose This Guide Specification is designed to assist in the production of actual
ENGLISH Installation guidelines for 10mm Engineered LOC flooring
ENGLISH Installation guidelines for 10mm Engineered LOC flooring A. INTRODUCTION General statement Congratulations with your new floor. Store the boards in the room where they will be installed for at
How To Level A Subfloor
Skill Level: INTERMEDIATE Give these projects a try if you're a confident DIYer with a good working knowledge of a variety of tools. They can take a day or more to complete. If you can build a birdhouse
Bella Cera Engineered Hardwood Flooring Installation Instructions. Check for Proper Color Selection Prior to Installation
Bella Cera Engineered Hardwood Flooring Installation Instructions Check for Proper Color Selection Prior to Installation 1 Important Information before You Begin 1.1 Installer/Owner Responsibility Carefully
Laminate Flooring T-Lock Angle-Drop Installation Instructions
TECHNICAL SERVICE Laminate Flooring T-Lock Angle-Drop Installation Instructions March 23, 2012 Read all instructions carefully before beginning installation. Make sure that the instructions are the most
Renovating Your Basement
building science.com 2006 Building Science Press All rights of reproduction in any form reserved. Renovating Your Building America Report - 0309 2003 (revised 2007) Building Science Corporation Abstract:
Mold Preventing I nterior System
interior insulation and renovation boards A system of components that have been designed to work perfectly together to repair damage caused by mold. The system consists of boards, insulation wedges, reveal
Neopor. Impact-sound Insulation. BASF Plastics key to your success. Expandable Polystyrene (EPS)
Neopor Expandable Polystyrene (EPS) BASF Plastics key to your success Impact-sound Insulation The problem: noise Impact-sound insulation with Neopor Peace and quiet equals quality of life Noise causes
Section 4.3. Separating Floors. Timber frame floor with I-Beams. Upgrading existing timber floor with new ceiling. Timber frame floor with
Section Separating Floors Timber frame floor with I-Beams Product: Earthwool Acoustic Roll and Floorfoam Easy Edge Strip Timber frame floor with solid timber joists Product: Earthwool Acoustic Roll and
We care about. Environmentally-Friendly Building Products from Renewable Resources. natural building products. Product range overview
http://upload.wikimedia.org/wikipedia/commons/a/ae/flag_of_the_united_kingdom.svg.0.0 :8 Seite von Environmentally-Friendly Building Products from Renewable Resources Product range overview We care about
Guide to Assessment and Repair of Flood Damaged Timber and Timber Framed Houses (Revised 19 th Jan 2011)
Technical Guide Guide to Assessment and Repair of Flood Damaged Timber and Timber Framed Houses (Revised 19 th Jan 2011) ASSESSMENT OF DAMAGE Prior to any assessments or repairs being commenced, a licensed
Installation guide. ENGINEERED and LOC. 1/2 in and 3/4 in (13 mm and 19 mm) INNOVATION TRADITION PERFECTION
Installation guide ENGINEERED and LOC 1/2 in and 3/4 in (13 mm and 19 mm) INNOVATION TRADITION PERFECTION It is important to read the installation instructions, maintenance guide and warranty document
Multi-layer Insulation Blanket for Roofs
Multilayer Insulation Blanket for Roofs Thermal Insulation in a 40mm thin, flexible, multilayer membrane Meets requirements of L1A, L1B 2010 In accordance with BR443 NHBC Acceptance Pitched & Flat roof
Guide to Assessment and Repair of Flood Damaged Timber and Timber Framed Houses (Revised 2 nd Feb 2013)
Technical Guide Guide to Assessment and Repair of Flood Damaged Timber and Timber Framed Houses (Revised 2 nd Feb 2013) ASSESSMENT OF DAMAGE Prior to any assessments or repairs being commenced, a licensed
STANDARD REQUIREMENTS FOR BONDING OR MECHANICAL ATTACHMENT OF INSULATION PANELS AND MECHANICAL ATTACHMENT OF ANCHOR AND/OR BASE SHEETS TO SUBSTRATES
ROOFING APPLICATION STANDARD (RAS) No. 117 STANDARD REQUIREMENTS FOR BONDING OR MECHANICAL ATTACHMENT OF INSULATION PANELS AND MECHANICAL ATTACHMENT OF ANCHOR AND/OR BASE SHEETS TO SUBSTRATES Scope 1.1.
INSTALLATION THE SIMPLIFIED VERSION
Fo Subfloor has to be flat, permanently dry, solid and clean. ng INSTALLATION THE SIMPLIFIED VERSION Floori rbo Adhésif Modul up pr é c o n is e Trim off over lengths leaving 1mm gap all around the walls.
INSTALLATION INSTRUCTIONS
INSTALLER/OWNER RESPONSIBILITIES Hardwood flooring is a product of nature and its inherent beauty stems from the fact that each piece is unique with no two pieces the same. Due to the fact that this flooring
INSTALLATION INSTRUCTION
Table of contents and general rules The backing is an important part of a carpet; both during daily use and when the carpet has to be fitted. These installation instructions are based on the backing types
Mezzanine. Technical manual
TechNICAL MANUAL 1 Mezzanine Technical manual 2 Varnished (optional) Product class P6 Melamined (optional) Tongue and groove Structural applications STANDARD FEATURE additional options - Chipboard - Varnished
BEST PRACTICE GUIDE. Fibrelime Premixed Universal Plaster and Render
BEST PRACTICE GUIDE Fibrelime Premixed Universal Plaster and Render Contents: Fibrelime description Fibrelime suitability Preparation before application Application Aftercare Painting General Recommended
Interior Walls below and above ground OLDROYD THE ULTIMATE WATERPROOF MEMBRANE SYSTEM
P r o d u c t a p p l i c a t i o n s a n d t e c h n i c a l i n f o r m a t i o n 2 below and above ground V OLDROYD THE ULTIMATE WATERPROOF MEMBRANE SYSTEM V The flexible, fast and cost-effective answer
Question: Can a gymnasium floor be restored after being exposed to water damage?
Question: Can a gymnasium floor be restored after being exposed to water damage? Several techniques are used in order to dry hardwood flooring. The most popular of these techniques is tenting the area
Sika Membran System For Sealing and Waterproofing Construction Gaps in Building Façades
Construction Sika For Sealing and Waterproofing Construction Gaps in Building Façades Waterproof and Airtight Flexible Seal Controlled Vapour Diffusion Bonds to any Building Substrate Prevents Interstitial
SolidfloorTM. - Installation instructions - Maintenance instructions - Heating and cooling - Guarantee provisions. www.solidfloor.
SolidfloorTM - Installation instructions - Maintenance instructions - Heating and cooling - Guarantee provisions Earth & Fire, Bretagne, Art. 11157362 www.solidfloor.com INSTALLATION INSTRUCTIONS Carefully
Armstrong Do-It-Yourself Tile Installation System
Armstrong Do-It-Yourself Tile Installation System What tools will I need to install my tile floor? You'll need just the basics: - floor tile (make sure you have enough tile to finish the job) - adhesive
Built-up roofing solutions with rigid insulation boards on concrete decks for new-build and refurbishment E-a5
Cl Sfb (27-9) Rn7 M2 December 2004 Built-up roofing solutions with rigid insulation boards on concrete decks for new-build and refurbishment E-a5 Fesco, Fesco S, Retrofit, Retrofit S, Fesco Fillet, PF,
Controlling the Transmission of Impact Sound through Floors
Construction Technology Update No. 35 Controlling the Transmission of Impact Sound through Floors by A.C.C. Warnock This Update presents guidelines for controlling the transmission of impact sound through
INSTALLATION GUIDE. Imago Installation Guide - January 2008 1
INSTALLATION GUIDE IMAGO Floors are very sensitive to ambient humidity conditions, since all wood flooring will expand and contract as relative humidity varies. In order to keep the flooring manufacturer
HOW-TO LAY HARDBOARD OR PLYWOOD FLOOR OVERLAY
HOW-TO HOW-TO LAY HARDBOARD OR PLYWOOD FLOOR OVERLAY Most floor coverings, if laid over uneven wooden floors, will wear unevenly and look unsightly. The answer is to cover the old boards with hardboard
Mapei systems for radiating floor heating with high thermal efficiency
Mapei systems for radiating floor heating with high thermal efficiency PRODUCTS FOR CERAMIC TILES AND STONE MATERIAL ADHESIVES SEALANTS CHEMICAL PRODUCTS FOR BUILDING III MAPEI systems for radiating floor
Division 9. SignaFlor Pad and Pour Flooring System
Division 9 SignaFlor Pad and Pour Flooring System SPECIFICATIONS Page 1. General... 2 1.1 Description 2 1.2 Quality Assurance 2 1.3 Submittals 2 1.4 Delivery and Storage 3 1.5 Warranty 3 1.6 Working Conditions
Section 5.0. Basements. Wall insulated externally. Wall insulated internally. Ba02. Product: Polyfoam ECO Floorboard Ba01.
Section 5.0 Basements Wall insulated externally Product: Polyfoam ECO Ba01 Wall insulated internally Product: Polyfoam ECO Ba02 Basements Basements Basement design Waterproofing BS 8102: 2009 Code of practice
If you hire a Professional Wood Fitter. If fitting the Wood Floor yourself (DIY)
WOOD FLOORING GUIDE WHILE A REASONABLY COMPETENT DIY ENTHUSIAST CAN SUCCESSFULLY FIT BOTH LAMINATED AND ENGINEERED CROSS-PLY FLOORING, TILE GIANT RECOMMEND THAT ONLY AN EXPERIENCED PROFESSIONAL WOOD FITTER
Best Practices for Crawl Space Insulation
Best Practices for Crawl Space Insulation Copyright 2011 Basement Systems Inc. All Rights Reserved Table of Contents I - Introduction II - Step By Step Guide 1 - Providing Adequate Drainage 2 - Controling
Construction. SikaProof A-08 Edge, A-12 Edge. Fully bonded FPO sheet membrane in L-shape for the SikaProof A waterproofing system. Product Description
Product Data Sheet Edition 15/10/2014 Identification no: 02 07 04 10 300 0 000002 SikaProof A Edge SikaProof A-08 Edge, A-12 Edge Fully bonded FPO sheet membrane in L-shape for the SikaProof A waterproofing
0800 30 50 90 www.bamboodirect.co.nz
Guide To Bamboo Flooring 1. Frequently Asked Questions 2. Installation Tips 3. Maintaining your Bamboo Floor 4. Why Bamboo Direct? COPYRIGHT 2009 BAMBOO DIRECT Frequently Asked Questions 1. Are Bamboo
Installation Instructions for Fletco Carpets
Table of Contents The backing is a very important part of a carpet, as well as the installation and the daily use are concerned, so therefore these installations instructions are based on the different
Asphalt Shingle Application Requirements
Alberta Allied Roofing Association Asphalt Shingle Application Requirements Section 1 Roof Decks 1.1 General Asphalt Shingles are not permitted to be installed directly over rigid insulation. When Asphalt
Improving the flood resistance of your home. Advice sheet 6: Flood-resilient floors
Improving the flood resistance of your home Advice sheet 6: Flood-resilient This sheet provides guidance on identifying different types of floor, assessing the routes floodwater may enter, and describes
ModuSec. Secure and efficient IT room solutions Composite Panel Systems Compared. Panel Systems are not all the same!
Secure and efficient IT room solutions Composite Panel Systems Compared Panel Systems are not all the same! When it comes to accommodating critical IT systems, the first issue to look at is the environment
Grand Mesa Plus LAMINATE - WIRE BRUSHED. GAGVGM81012A Prairie. GAGVGM80012NA Colorado. GAGVGM84012A Pecan Rustic. GAGVGM85012A Saddle Walnut
MARCH 2015 Grand Mesa Plus LAMINATE - WIRE BRUSHED Specifications 12.3mm 6.5 wide x 47-13/16 long 19.42 sf/ctn 48 ctn/plt Triple Plate Embossing Wire Brushed Texture Micro-Bevel & Waxed Edges Warranty
Energy Company Obligation (ECO): Technical Monitoring Questions
Energy Company Obligation (ECO) Technical Monitoring Questions v1 30/05/2013 Energy Company Obligation (ECO): Technical Monitoring Questions Under ECO suppliers are required to instruct suitably qualified
Crawl space heat and moisture behaviour
Crawl space heat and moisture behaviour Miimu Airaksinen, Dr., Technical Research Centre of Finland, VTT [email protected], www.vtt.fi KEYWORDS: crawl space, moisture, evaporation from ground, ground
INSTALLATION IMPORTANT INSTALLER/OWNER RESPONSIBILITY TOOLS & EQUIPMENT NEEDED FOR INSTALLATION PRE-INSTALLATION PROCEDURES & JOBSITE CONDITIONS
IMPORTANT It is important that you read & understand the following information and instructions in their entirety before proceeding with installation. Please thoroughly inspect all Flooring products in
High Performance Building Materials SCREEDS REPAIR MORTARS LEVELLING & SMOOTHING WATERPROOFING TILE ADHESIVES & GROUTS PRIMERS & ADDITIVES
High Performance Building Materials SCREEDS REPAIR MORTARS LEVELLING & SMOOTHING WATERPROOFING TILE ADHESIVES & GROUTS PRIMERS & ADDITIVES ARDEX manufacture a complete range of high performance building
Schlüter -KERDI-BOARD Substrate, structural panel, bonded waterproofing
Substrate, structural panel, bonded waterproofing The universal substrate for tiles Perfect covering No matter whether you work with mosaics or large format tiles, an absolutely level substrate with straight
DELTA Premium Moisture Management Systems for Foundations.
DELTA protects property. Saves energy. Creates comfort. DELTA Premium Moisture Management Systems for Foundations. DELTA Premium Moisture Management Systems provide the best protection for foundations.
WATERPROOFING OF REINFORCED CONCRETE FLAT ROOF 12
WATERPROOFING OF REINFORCED CONCRETE FLAT ROOF 12 87 88 GOOD INDUSTRY PRACTICES 12 WATERPROOFING OF REINFORCED CONCRETE FLAT ROOF 12.1 BACKGROUND Most roofs in Singapore are constructed using reinforced
Uniclass L31:N14:P7111 C1/SfB (16.9) Rn7 (J4) February 2008. Foundation Heave Protection
Uniclass L31:N14:P7111 C1/SfB (16.9) Rn7 (J4) February 2008 Foundation Heave Protection The safe, sure way to provide foundation protection Clayshield is the proven solution to protecting foundations against
BETONYP building boards. The modern way of living.
BETONYP building boards The modern way of living. Tough for 30 years. Healthy, debarked pine wood and cement: the raw materials used to produce one of our most successful products for more than three decades.
CREATING EFFECTIVE WATERPROOFING & DRAINAGE FOR INTERIOR WALLS. Using Oldroyd Xv clear, Xv20 and Xp on interior walls
CREATING EFFECTIVE WATERPROOFING & DRAINAGE FOR INTERIOR WALLS Using Oldroyd Xv clear, Xv20 and Xp on interior walls Oldroyd cavity drainage membranes provide a simple and cost effective solution for dealing
Saint Gobain Gyproc India Ltd. (Formerly India Gypsum Ltd.)
Saint Gobain Gyproc India Ltd. (Formerly India Gypsum Ltd.) Gyproc Plasters The cracks in cement sand plaster are an inherent feature which cannot be completely prevented but can only be controlled and
We have been working in an ideal climate for thirty years.
Underfloor cooling We have been working in an ideal climate for thirty years. A climate that has brought us to a position of leadership in Italy in the field of radiant heating and cooling. RDZ was the
about your house Before You Start Renovating Your Basement Moisture Problems Figure 1 Moisture problems to solve
about your house CE 28 c Before You Start Renovating Your Basement Moisture Problems Mold and decay on floor joists and sill plates Stuffy air, high humidity, poor air circulation Water draining in from
Cavity Drain R20 is manufactured from1.0mm thick black high density polyethylene with studs approximately 20mm high.
CI/SfB Tn6 L6813 September 2013 RIW CAVITY DRAIN R20 R20 is manufactured from1.0mm thick black high density polyethylene with studs approximately 20mm high. Other systems are available for specific uses,
12 POLYURETHANE ADHESIVE (PU 105)
12 POLYURETHANE ADHESIVE (PU 105) DISCLAIMER: Refer to page 5 of this document. 12.1 DESCRIPTION PU 105 is a high performance two-part polyurethane adhesive for both indoor installations of Mondo rubber
AND MEMBRANES ROOFING UNDERLAYS. www.fakro.com
AND MEMBRANES 010 ROOFING UNDERLAYS 1 HO DOES YOUR ROOF BREATHe? MEMBRANES THE WAY to A WARM AND DRY ROOF HO HO HO HO HO HO WATERTIGHTNESS The FAKRO Company offers a wide range of membranes and underlays
BENTLEY ELEMENTS COLLECTION LVT
This document refers to the following products: Product Size Installation direction Seams treatment Elements Tiles See specifications 90 None Elements Planks See specifications Stair Step None Note: This
Fire 2This Technical Bulletin has been commissioned by the UK SIP Association in
REV 1-12.12.11/TB002 Technical Bulletin Fire 2This Technical Bulletin has been commissioned by the UK SIP Association in conjunction with TRADA Technology and is intended to provide the reader with introductory
BUILDING CONTROL GUIDANCE SHEET USE OF BREATHABLE ROOFING FELTS.
Building Control Charnwood Borough Council Southfield Road Loughborough LE11 2TN BUILDING CONTROL GUIDANCE SHEET USE OF BREATHABLE ROOFING FELTS. Last updated 16/11/2010 Page 1 of 6 PURPOSE: This Guidance
B. Related categories: The following categories contain requirements that relate to this section:
ORIENTED STRAND BOARD PART I. - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of Contract, including General and Supplementary Conditions and Division 1 Specification Sections, apply
ENGINEERED FLOORING INSTALLATION
ENGINEERED FLOORING INSTALLATION ATTENTION! INSTALLER/OWNER RESPONSIBILITIES Beautiful hardwood floors are a product of nature and, therefore, they will show variations in color, grain, texture, and appearance.
10 Year Guarantee. 15 Year Guarantee LAMINATE FLOORING
LAMINATE FLOORING GOOD TO KNOW Can be laid on existing floors, except on wall-to-wall carpet. When laying floors, always use NIVÅ floor lining (sold separately). When laying floors on concrete or stone,
CEILING SYSTEMS. CI/SfB (35) Xy April 2006. [Between us, ideas become reality.] ULTIMA CANOPY. Data sheet. Acoustic performance meets High Design
CEILING SYSTEMS [Between us, ideas become reality.] CI/SfB (35) Xy April 2006 ULTIMA CANOPY Data sheet Acoustic performance meets High Design ULTIMA CANOPY Installation Instructions I. GENERAL 1. Product
DIY GUIDE 10 EASY STEPS FOR TREATMENT OF RISING DAMP
DIY GUIDE 10 EASY STEPS FOR TREATMENT OF RISING DAMP CONTENTS WHAT IS RISING DAMP STEP 1 SURVEY STEP 2 METER READINGS STEP 3 CONCLUSION STEP 4 PREPARATION FOR TREATMENT STEP 5 TYPE OF TREATMENT STEP 6
INSTALLATION GUIDELINES wood floors
INSTALLATION GUIDELINES wood floors INSTALLATION GUIDELINES - WOOD FLOORS SUBJECT PAGE GENERAL INFORMATION PRIOR TO INSTALLATION WHAT KIND OF INSTALLATION SHOULD YOU USE? 1 Floating Installations Glue-Down
Manual lifting and handling
Manual lifting and handling When installing British Gypsum products and systems care should be taken to ensure that appropriate methods of handling and lifting are adopted. The following guidance details
6.1 Schlüter -DITRA. Application and Function
INNOVATIVE PROFILES 6.1 Schlüter -DITRA U N D E R L A Y M E N T UNCOUPLING, WATERPROOFING, AND VAPOUR PRESSURE EQUALISATION Application and Function Schlüter -DITRA is a polyethylene membrane with a grid
Improving the flood resistance of your home. Advice sheet 4: Flood-resilient walls.
Improving the flood resistance of your home Advice sheet 4: Flood-resilient walls. This sheet provides guidance on identifying different types of wall, and reducing the flow of floodwater through them
Flocking of textiles. Flocked shirt 13. flocking drying cleaning. adhesive. application. creation
Flocking of textiles > The motif flocking is the high-class alternative to textile printing. One not only flocks sports wear for schools, sport clubs, associations etc., but also fabrics for garments,
CONDENSATION - THE BASICS
CONDENSATION - THE BASICS Condensation is the most common form of dampness in buildings. Indeed, it appears to be more of a problem in modern properties than our historic buildings due to the introduction
INSTALLATION INSTRUCTIONS SINGLE CIRCUIT
INSTALLATION INSTRUCTIONS SINGLE CIRCUIT Unit 1 79 Friar Street Worcester WR1 2NT Tel: 01905 354 791 Fax: 01905 352 100 E-mail: [email protected] Website: www.underfloorheatingsystems.co.uk
Engineered Hardwood Flooring Installation Instructions
Engineered Hardwood Flooring Installation Instructions Tip: Check for proper color selection and style prior to Installation. No claims will be accepted after installation Important Information before
Your guide to home maintenance. Flat Roofs
Your guide to home maintenance Flat Roofs Your guide to home maintenance is a series of information leaflets that gives you all the information you need to keep your home in tiptop condition. Flat Roofs
Care and Maintenance for Wood Flooring
Care and Maintenance for Wood Flooring The finishing technology used for Tarkett wood floorings makes them the best choice for easy maintenance. To preserve all the beauty of your Tarkett wood flooring,
Carpet Tile Installation Guidelines
NOTICE FAILURE TO FOLLOW THESE GUIDELINES CAN RESULT IN VOIDING THE CARPET WARRANTY. Installation Guidelines The following instructions should be reviewed prior to installation. Shaw Industries will not
ELASTOCEM. Technical features. Applications. Two-component flexible, waterproofing and protective cementitious grout.
Two-component flexible, waterproofing and protective cementitious grout. 1504-2 PI-MC-IR Technical features Two-component grout, based on cements, selected aggregates, special additives and synthetic polymers
INSTALLATION INSTRUCTIONS FOR LAMINATE FLOORING
INSTALLATION INSTRUCTIONS FOR LAMINATE FLOORING Introduction Laminate flooring is designed to be a floating floor that may be installed over virtually any type of sub floor. It is not nailed or glued to
SIP (STRUCTURAL INSULATED PANEL)
SIP (STRUCTURAL INSULATED PANEL) KINGSPAN TEK ACORN SIP ABSTRACT BUILDING SERVICES Ltd Kingspan TEK is the manufacturer and supplier of the panels and components. Acorn SIP are the Architects who individually