Alternative Project Delivery Methods (APDM) Valley Schools Management Group
|
|
|
- Lisa Crawford
- 9 years ago
- Views:
Transcription
1 Alternative Project Delivery Methods (APDM) Valley Schools Management Group
2 Introduction Bill Munch Tim O Brien Ken Carter David Cantelme Skip Brown [email protected] (602) [email protected] (602) [email protected] (866) [email protected] (602) [email protected] (602)
3 Alternate Procurement Delivery Methods (APDM) Harder to find resources Ever increasing accountability Unexpected latitude in contracting Design Build CM at Risk Job Order Contracting Pre-qualified Contractors New design services selection rules Advertising requirements 3
4 Class Agenda Project Management and Alternative Project Delivery Methods 1. Identify the project 2. Acquire design professionals 3. Determine the most effective procurement process 4. The Request for Qualifications 5. Selection Process 6. Award 7. Control 8. Reporting 9. Case Study 4
5 Determine Process APDM Process Project Need Identified Funding Identified Capital Improvement Plan Emerging Ideas Legal/Emergency Bond/Override SFB Adjacent Ways Acquire Design Professional RFQ Publish and Award GC Architects Other Professionals Pre Construction Services develop GMP Award if in budget Bid if not in budget 5
6 APDM Choices Are Like Tools in Your Tool Chest (know how to use em) Size and scope of job Resources available Time Staff Funding Expertise available District Architect Firm PM 6
7 Procurement of Specified Professional Services (R ) Who are professionals? Single or multiple contracts Notice (R ) Amounts (R ) Procurement file requirements On-line help 7
8 Contracting Methods Design Bid Build Design Build Cooperative purchasing/state Contract Construction Manager at Risk Select Bidders List Job Order Contracting 8
9 Design Bid - Build Invitation for Bid Award to lowest responsive & responsible bidder Used in jobs with simple, easily measured specs PRO Well known and understood Emphasizes head-on competition CON Tight bid specs difficult to write/evaluate Low bidder may try to make money thru change orders Prone to protest 9
10 Design Build RFQ committee selects contractor by quality Selected contractor provides both design and construction services Award construction contract only if GC s bid fits within the district s budget PRO Qualification based selection Reduced finger pointing by the service provider, Single point of contact for project delivery Potential for continuous value engineering and feedback system CON Potential for ill-defined scope of the work. Potential for decreased accountability Potential that a less qualified owner may not have the expertise to evaluate the work the contractor has performed 10
11 Cooperative purchasing/state Contract Find appropriate services on a cooperative purchasing agreement Place your order (purchase order is the contract) PRO Reduced administration Faster response time CON Potential for increased cost Small number of contractors Lose the benefit of competition 11
12 Construction Manager at Risk Most prevalent method of construction contracting in schools today R Procurement of Construction Using Alternative Project Delivery Methods Very popular many districts have adopted this method as their standard Introduces quality up front, but behaves much like a typical design bid build project after award of GMP 12
13 Construction Manager at Risk RFQ committee selects pre-construction GC by quality Award construction contract only if GC s Guaranteed Maximum Price fits within the district s budget PRO Qualification based selection Encourages teamwork among owner, architect and GC Preconstruction services by GC and subcontractors reduce or eliminate change orders On-going value engineering helps contain costs and maximize build- ability CON May be more expensive than traditional procurement Owner must stay engaged 13
14 Construction Manager at Risk Pre Construction Services You pay for this (typically around 1% of projected construction costs) GC and subcontractor review design/approach Subcontractor list Continuous Value Engineering Develop alternatives Establish prior approvals Develop Guaranteed Maximum Price (GMP) Schedule of values Allowances Fees General Conditions 14
15 Qualified Select Bidders List RFQ committee reviews to determine short list Select 3-5 GC s by qualification based selection Invitation for Bid to pre-qualified bidders only Rest of the process similar to hard bid Award to lowest responsive & responsible bidder PRO Qualification based selection Bid process familiar and well understood Emphasizes head-on competition CON Fewer bidders may reduce competition Selected GC s may not feel the pressure to make lowest possible bid 15
16 Job Order Contracting Select a Job Order Contractor by quality Award construction contract based on an agreed unit price determination (e.g., RS Means and/or Unit Price Book) PRO Responsive to district needs Known quality contractor (depends on your good will for continued business) CON Unit price techniques may be more expensive than traditional bidding Need Board approval for project in excess of $1M 16
17 Paperwork Procurement File Contents (R ) If no interviews were held If interviews were held In what order should the contents of the file be? Debriefing unsuccessful responders Is it required? Is it smart? What are some effective techniques? 17
18 Once You Have Identified the Project Overview and scope of a project Funding Sources Choosing Delivery Method Control Points Notes and Discussion Review of Important Terms 18
19 Develop a Capital Plan Strategy (Vision) Funding Estimates Change in population Growth Decline New Construction Scheduled Maintenance Programs (life cycle) Boundary changes School Closings (gasp) Grade reconfiguration New programs (gifted, traditional, magnet) Community agreements 19
20 What is a Capital Plan? Forecast of capital needs (needs assessment) Search for and Identify All needs and wants Use multiple sources No filtering yet Prioritize needs Health/Safety Projects to avoid large, catastrophic losses Bond imperatives (pamphlet, promises) Essential projects Projects identified as valid need 20
21 What is a Capital Plan? Sort list by resources Funds Time Sort list by Facilities based on SFB PM areas Pupil Transportation Safety/Security Furniture Fixtures and Equipment Technology Curriculum 21
22 Phases of a Project Project initiation stage Project planning and design stage Project execution stage Project completion/closeout stage 22
23 Phases of a Project Project initiation stage Identify project CIP or Needs Assessment Emergency Emerging opportunities (good ideas) Identify a Funding source Procure a design professional Determine what project delivery method is best Description/Scope Purpose of the project Resources available Money Time Establish initial budget estimate 23
24 Overview of a Project Project planning and design stage Collaborate with stakeholders Procure Construction Services (Alt Proj Del Means) Develop specifications Wants Needs Sacred Cows Develop design documents Layouts Standards (e.g., flush valves, toilets, HVAC, sole source, etc.) Refine estimated project budget Request and receive permits Procure Construction Services (Traditional Means) 24
25 Overview of a Project Project execution stage Financial Control Measures Notice to proceed Pay applications Retainage Documentation Control Measures Meeting minutes/notes Measuring the ongoing project activities (where we are) Week in review and three week look ahead Documenting issues Monitoring the project cost against the project baseline (where we should be) Change Control Measures Request for information (RFI, DIR, etc.) Change Order Request ~> Change Order Allowance Use Request ~> Allowance Use Authorization 25
26 Overview of a Project Project completion/closeout stage Documentation Warranty work tracking 26
27 Funding Sources Bond Adjacent Ways Capital Override Capital SFB new construction Building Renewal Grant Other Grants Gifts & Donations 27
28 Adjacent Ways, ARS Adjacent ways is a special property tax assessment Funds from adjacent ways may be used to construct, maintain or improve any public way adjacent to land owned by the school district sidewalks sewers utility lines roadways and other related improvements A school district shall not use adjacent ways funds for construction, maintenance or other improvements to the school district's property except Improvements necessary to assure the safe ingress and egress for buses and fire equipment. 28
29 Okay, CMAR is our choice, now what? List reasons APDM selected (R ) Issue RFQ (R ) Do we have to advertise? (R ) Pre proposal conference Changes Committee evaluation Negotiations & Notifications Award Preconstruction Services Guaranteed Maximum Price (GMP) 29
30 Project Control Points Project initiation stage Project identification/scope/budget Procuring Design Professional Project planning and design stage Choosing a delivery method/gc Project execution stage Contract/PO/Notice to proceed Approval for Change Orders and Use of Allowance Payment Requests Project completion/closeout stage Substantial/Final Completion release of retention Punch List Establish warranty date 30
31 When Should the District Superintendent Get Involved? Ground Breaking and Ribbon Cutting Initial Planning Priority Resources (time, people and funding) Educational mandate/philosophy Before any issue or decision is brought before the Governing Board GMP/PO/Contract Change Orders Before any substantive change to the project is made Bad news, unlike fine wine, does not get better with age 31
32 Notes and Discussion Match talent with project bigger firms may not be better on smaller projects The team is like a three legged stool General Contractor Design Professional Owner Another three legged stool Cost Schedule Quality Procurement by the numbers. Short cuts cost money and time 32
33 Notes and Discussion Notice to Proceed Contract Bonds Insurance Absolutely no work, mobilization or supplies before Notice to Proceed Pre Lien Notices Public property cannot be liened Lien releases & pre-lien notices provide info of subcontract amount 33
34 Notes and Discussion Who Do You Deal With? Contract is with the GC not sub contractors Dealing directly with subs can encourage change orders, add cost and let GC off the hook Deal through the team (PM, Contract Administrator architect, Weekly meetings Meetings: Architects take notes Contractor updates master schedule and provides three week look ahead Review a pencil version of a payment request a week before submission Discuss AUR s, AUA s, RFI s, COR, etc. 34
35 Notes and Discussion Timely Payment essential Lien releases - Lien releases & pre-lien notices provide info of subcontract amount Withholding Payment the ultimate hammer Affect only sub/division responsible Adjust individual lines on schedule of values Notify GC via Architect of deficiency and that payment was reduced to compensate 35
36 Review of Important Terms VE Schedule of Values GMP General Conditions Allowance Over head and Profit Retention Buy out Adjacent Ways/off sites Pre Lien Notice Lien Release RFI & ASI AUR & AUA COR & CO PR CofO & Temp CofO Substantial Completion Final Completion Punch list 36
37 Forms Notice to Proceed Request information/documents Respond to requests Requests to change the contract time scope unforeseen conditions Pay Applications Close out documents Substantial Completion Final Completion 37
38 Close out continued Punch list Warranty Documents Manuals Final pay application As builts 38
39 Pay Applications Pencil Copy one week prior (no surprises) Copy signed and notarized verified by architects Retention required by law. 10% for first half May be reduced to 5% if project is progressing satisfactorily Retention may be satisfied with a substitute 1. An assignment of time certificates of deposit 2. Share certificate of a savings and loan institution or credit union 3. Security issued or guaranteed as to principal and interest by federal, state or local government 39
40 Things Important to Understand Vendors are in business to make a profit that s why they are call for profit organizations. A great vendor who goes out of business is an unsuccessful vendor and we are unsuccessful clients. How does money figure in? 40
41 Profit Motive v. Cost Avoidance Max P R O F I T $0 Jul Public Sector Private Sector Oct Jan Apr 41
42 Profit Motive v. Cost Avoidance Contractor has 3 opportunities for profit GMP/Bid/Quote Allowance Change Orders Public has 3 opportunities for cost avoidance Pre contract negotiations Unused allowance Constructive change orders 42
43 Will APDM save you money? Difficult to quantify Open book GC walks in with profit established Some fees difficult to see Selection of subs Detailed Schedule of Values Time = Money Change Order avoidance 43
44 Palomino Elementary Case Study Situation: Palomino Elementary School has over 1,200 K-6 students. The area is growing rapidly, but there is no land to build a new school. There is an undeveloped city park across the street from the school 44
45 Palomino Elementary Case Study Task: New Construction 77,486 sf 2 story (nonprototypical) design on active playground Renovate 62,500 sf existing building (over summer break) Build playground on city park site (IGA) Demolish and remove public roadway Open for school August
46 Time Lines Begin construction Summer 02 Renovation Spring/Summer 03 Close/Demolish 30th Street July 03 Open new schools August 03 46
47 Palomino Elementary Case Study The nature of the project made a good strategy Complexity required pre-construction services Time Design Coordination Operational limitations Budget constraints Unknown issues with renovation Unknown issues with city collaboration 47
48 Palomino Elementary Case Study The project was on time and dramatically under budget because: General Contractor selection based on proven ability Early collaboration Value engineering Very accurate Guaranteed Maximum Price Open book review and GMP Continuous Value Engineering Enhanced trust among team members Partnering reduced General Conditions 48
49 Palomino Elementary Case Study Category Pinnacle Liberty Palomino Procurement DBB DBB Square Ft 80,279 79,434 77,486 Project Bid/GMP $8,352,000 $7,341,560 $8,546,617 Less site work ($1,599,317) ($1,171,611) ($1,791,100) Inflation adj (3%) $ 202,580 $ 185,098 na Less 2d story cost na na ($ 200,000) Less renovation cost na na ($ 579,141) Adjusted const cost $6,955,263 $6,355,047 $5,976,376 Adjusted Cost sq ft $86.64 $80.00 $
50 Alternative Project Delivery Methods A Three legged stool Owner Design Professional Contractor The stool will fail if any leg is too short, wobbly or missing 50
51 Alternative Project Delivery Method What it is Contractor selection based on value Opportunity for reduction of errors Opportunity for time & cost savings What it is NOT A guarantee of success Insurance against fraud, waste or abuse For those who do not want to stay involved 51
52 Stuff you should remember It ain t new. Many school districts have used CMAR and Job Order Contracting successfully for years. Resources are available. The new procurement rules are out and pretty easy to use. Don t cut corners. It doesn t take any longer to do it right than to do it wrong. You are not alone. Help is only a phone call away. 52
53 Stuff You Should Remember All construction issues look pretty much the same once the contractor is selected No construction procurement method is fool proof you must stay involved Owners can help contain costs by: Good communications Comprehensive scope and specifications Clear vision no changes/good ideas 53
54 Keys to Success 1. Reduce/eliminate changes Clear scope of work Pre-construction involvement 2. Enhance team work Business partnership Develop team over time Establish trust 54
Building Capital Projects in Tough Times John Lynch, State of Washington
Building Capital Projects in Tough Times John Lynch, State of Washington Published as a joint effort of the National Association of State Facilities Administrators (NASFA) and the Associated General Contractors
REQUEST FOR PROPOSAL FOR CONSTRUCTION MANAGEMENT SERVICES. Part I: Proposal Information
REQUEST FOR PROPOSAL FOR CONSTRUCTION MANAGEMENT SERVICES Part I: Proposal Information A. General Information The Berwick Area School District is soliciting proposals for construction management services
Evaluating Project Delivery Options
Evaluating Project Delivery Options Scot A. Bini Vice President, URS August 24, 2004 Design-Bid-Build Overview Design Build Construction Management at Risk Owner Representation Terminology Project Manager
REQUEST FOR QUALIFICATIONS FOR CONSTRUCTION MANAGEMENT PROFESSIONAL SERVICES. Part I: Qualifications Information
REQUEST FOR QUALIFICATIONS FOR CONSTRUCTION MANAGEMENT PROFESSIONAL SERVICES A. General Information Part I: Qualifications Information The Tacoma School District is soliciting Qualifications for onsite
To be used in conjunction with the Invitation to Tender for Consultancy template.
GUIDANCE NOTE Tendering for, choosing and managing a consultant Using this guidance This information is not intended to be prescriptive, but for guidance only. Appointing consultants for relatively small
REQUEST FOR PROPOSALS (RFP) - Construction Management Services. Germantown School District Office
REQUEST FOR PROPOSALS (RFP) - Construction Management Services From: Germantown School District Project: Germantown School District Addition & Renovations to Rockfield Elementary School N132 W18473 Rockfield
REQUEST FOR QUALIFICATIONS FOR CONSTRUCTION MANAGER-AT-RISK (CMAR)
REQUEST FOR QUALIFICATIONS FOR CONSTRUCTION MANAGER-AT-RISK (CMAR) For the Project: CITY OF KATY NEW KATY FIRE STATION #2 Issued: August 13, 2015 Katy Fire Station #2 August 13, 2015 Page 1 of 17 Request
LESSONS LEARNED THROUGH SCHOOL CONSTRUCTION PROJECTS
LESSONS LEARNED THROUGH SCHOOL CONSTRUCTION PROJECTS RUSS KOCH, FREMONT PUBLIC SCHOOLS MIKE LUCAS, YORK PUBLIC SCHOOLS DAN ENDORF, NORTH BEND CENTRAL NBC AND YORK BOARD MEMBERS DESIGN BID BUILD CONSTRUCTION
The UW Capital Projects Office and NW Construction Consumer Council
The UW Capital Projects Office and NW Construction Consumer Council Present: Changing Project Delivery at the UW through Innovation, Integration, and Adoption of MC/CM and EC/CM PACCAR Hall, the Gordon
Owner s project control review. 2014 Baker Tilly Virchow Krause, LLP
Owner s project control review 2014 Baker Tilly Virchow Krause, LLP About Baker Tilly > Established in 1931 > One of the top 20 largest accounting and advisory firms in the United States according to Accounting
MONTGOMERY COLLEGE JOB CLASS SPECIFICATION
MONTGOMERY COLLEGE JOB CLASS SPECIFICATION Title: Project Manager I (Facilities) Grade: J FLSA: Nonexempt Financial Disclosure: No Job Class Level: This includes performance level positions in the Project
Construction Management vs. General Contractor Method of Contracting POINTS OF VALUE OF THE CONSTRUCTION MANAGEMENT METHOD
Construction Management vs. General Contractor Method of Contracting POINTS OF VALUE OF THE CONSTRUCTION MANAGEMENT METHOD In an effort to take advantage of our opportunity to discuss with the Owner the
ATTACHMENT A. Ozarks Technical Community College Pre-Established Criteria for Construction Management and Design Build Construction Projects
Ozarks Technical Community College Pre-Established Criteria for Construction Management and Design Build Construction Projects Pursuant to Revised Statute of Missouri Section 8.250(3), Ozarks Technical
New WMHS Construction Management Firm
New WMHS Construction Management Firm RFQ Schedule November 5, 2013 Board Meeting Approval to Advertise and use revised RFQ Week December 9, 2013 Ad runs in local papers (Thursday Dec. 12 th ) Week December
REQUEST FOR QUALIFICATIONS CONSTRUCTION MANAGER / GENERAL CONTRACTOR (CM/GC SERVICES)
REQUEST FOR QUALIFICATIONS CONSTRUCTION MANAGER / GENERAL CONTRACTOR (CM/GC SERVICES) Return Completed Qualifications To: Twin Falls School District No. 411 Administrative Office 201 Main Avenue West Twin
Request for Qualifications. Owner s Project Manager. Design and Construction of a New School Facility. K~8 Charter School
Request for Qualifications Owner s Project Manager Design and Construction of a New School Facility K~8 Charter School 26 Madeira Avenue New Bedford, MA 02746 REQUEST FOR QUALIFICATIONS (RFQ) Issued: 4/16/2014
Please note that the attached forms will be used to evaluate the proposals as well as the interview itself.
CITY OF RAPID CITY RAPID CITY, SOUTH DAKOTA 57701 Public Works Department Engineering Services Division 300 Sixth Street Telephone: (605) 394-4154 FAX: (605) 355-3083 Web: www.rcgov.org November 12, 2013
NOTICE TO CM/GC Companies
NOTICE TO CM/GC Companies Facilities and Construction Management Jefferson County School District R-1 (Jeffco) is pre-qualifying Construction Manager/General Contractors for CM/GC services for a new K-6
SUMMARY OF MECHANICS LIEN LAW FOR THE DISTRICT OF COLUMBIA
SUMMARY OF MECHANICS LIEN LAW FOR THE DISTRICT OF COLUMBIA Section Contents Pre-lien Notice(s) Introduction Section Contents Mechanic s Lien Who is Entitled to a Lien? When to File/Record Where to File/Record
Request for Qualifications (CM at Risk Contract) State of Ohio Standard Forms and Documents
Request for Qualifications (CM at Risk Contract) State of Ohio Standard Forms and Documents Administration of Project: Local Higher Education Project Name Shideler Hall Renovation Response Deadline 12/20/13
NEGOTIATING STRATEGIES
NEGOTIATING STRATEGIES Career Services GSU 309 768-4287 www.hartford.edu/career An aspect of the job search process that people tend to have the most questions about is negotiating; how does one go about
REQUEST FOR PROPOSAL TO PROVIDE CONSTRUCTION MANAGEMENT AND GENERAL CONTRACTOR SERVICES SPRINGVILLE CITY NEW AQUATICS AND ACTIVITIES CENTER
RFP #2016-02 REQUEST FOR PROPOSAL TO PROVIDE CONSTRUCTION MANAGEMENT AND GENERAL CONTRACTOR SERVICES FOR SPRINGVILLE CITY NEW AQUATICS AND ACTIVITIES CENTER RELEASE DATE: January 29, 2016 DUE DATE: February
Request for Qualifications (CM at Risk Contract) State of Ohio Standard Forms and Documents
Request for Qualifications (CM at Risk Contract) State of Ohio Standard Forms and Documents Administration of Project: School District Board + OFCC Project Name Wellington New K-8 EM/MS Response Deadline
Tel: (617) 727-4050 Fax: (617) 727-5363. OWNER S PROJECT MANAGER GUIDELINES M.G.L. c. 149, 44A1/2
The Commonwealth of Massachusetts Executive Office for Administration and Finance Division of Capital Asset Management One Ashburton Place Boston, Massachusetts 02108 Tel: (617) 727-4050 Fax: (617) 727-5363
Notes. Score. 1 Basic Services 1.1. A few instances; could have been more proactive
Jacobs Contract performance Tracking spreadsheet = Excellent 2 = Meets performance standards 1 = Improvement needed 0= Unsatisfactory Report for the time period: Annual report 210 Total average score 2.86
IDALIA SCHOOL DISTRICT RJ-3 REQUEST FOR QUALIFICATIONS (RFQ) CONSTRUCTION MANAGEMENT/GENERAL CONTRACTING (CM/GC) SERVICES DECEMBER 14, 2011
IDALIA SCHOOL DISTRICT RJ-3 REQUEST FOR QUALIFICATIONS (RFQ) CONSTRUCTION MANAGEMENT/GENERAL CONTRACTING (CM/GC) SERVICES DECEMBER 14, 2011 PROJECT: New PK-12 School Facility Idalia, Colorado Idalia School
Facility Services PROJECT MANAGEMENT METHODOLOGY FRAMEWORK
Facility Services PROJECT MANAGEMENT METHODOLOGY FRAMEWORK Facility Services Project Management Methodology Framework 1 - Executive Summary The purpose of this document is to introduce the University community
How to Write the Construction Management RFQ/RFP
2011-06-07 How to Write the Construction Management RFQ/RFP Setting Up a Project for Success Today's Objectives The Art of RFQ/RFP writing First things first Determining the optimum Project Delivery Method
Fundamentals of a Construction Audit. August 7, 2014
Fundamentals of a Construction Audit August 7, 2014 Agenda Definitions Risk Based Approach What Determines Risk Fraud Construction Risks What to Audit Red Flags Why Audit Prevention Wrap-up 1 Definitions
PROJECT MANAGEMENT BASICS
PROJECT MANAGEMENT BASICS Rick Panos AIA, CCM Director of Construction Management Totum Consulting Gary Cardamone, P.E., FCMAA Principal, G J Cardamone Consulting, LLC Program Management Is.... In the
Covance Construction Management Staffing Plan Chandler, Arizona
INTRODUCTION: This Construction Management (CM) Staffing Plan has been prepared for Covance to identify the critical organizational structure necessary to successfully complete the Chandler project according
Volume II- Project Development Processes
Volume II- Project Development Processes This section outlines the procedures that are expected of capital projects at The University of Chicago. These requirements supplement the planning procedures required
Guidelines. for. Construction and Renovation. Parish Facilities
Guidelines for Construction and Renovation of Parish Facilities Building Commission Diocese of Des Moines 2014 Table of Contents Introduction.. 1 Pastoral Planning. 2 Approval of Bishop. 2 Needs Assessment
Recommended Best Practices for the Use of Construction Management/General Contractor on Highway and Transportation Projects in the Public Sector
Recommended Best Practices for the Use of Construction Management/General Contractor on Highway and Transportation Projects in the Public Sector Approved March 23, 2011 Purpose: While the traditional Design-Bid-Build
CONSTRUCTION MANAGEMENT AT RISK A NEW CONSTRUCTION DELIVERY METHOD For PUBLIC SCHOOLS
CONSTRUCTION MANAGEMENT AT RISK A NEW CONSTRUCTION DELIVERY METHOD For PUBLIC SCHOOLS Senate Bill 914, ratified by the General Assembly December 6, 2001, made more changes to the public bidding and construction
Distributed Generation: Frequently Asked Questions
Distributed Generation: Frequently Asked Questions 1) What is distributed generation (DG)? Generating technologies located close to where the electricity is being used that are connected to the electric
Corrected Form: Revised Attachment 7B Cost Proposal Distribution Exhibits A1 and A2 Attached
ADDENDUM #1 RFP: 500 16 Design Build Maintenance & Operations Complex The following changes to the Request for Proposal and clarifications are provided based on questions received and must be added/considered
Eanes Independent School District
EANES INDEPENDENT SCHOOL DISTRICT 601 Camp Craft Road Austin, Texas 78746 Request for Qualifications Construction Manager at Risk Services Eanes Independent School District Construct a District Operations
Puget Sound Regional Council
Puget Sound Regional Council PSRC Request for Qualifications for Legal Services Consultant Services Solicited by the Puget Sound Regional Council Released: November 12, 2009 Submissions Due: 4:30pm, November
GENERAL CONTRACTOR PRE-QUALIFICATION 2014 - FOR PERIOD ENDING DEC 2017
APPLICATION for PRE QUALIFICATION GENERAL CONSTRUCTION CONTRACTORS Construction Projects up to $3,000,000 Prequalified General Contractors will be invited to submit bids for various Renovation and Construction
Assistant Project Management - Training Program A 3-year Program Beginning strategy places the new employee into a three-year program that provides
Assistant Project Management - Training Program A 3-year Program Beginning strategy places the new employee into a three-year program that provides for experience in the Construction Company's three areas
INSTRUCTIONS AND APPLICATION FOR CONTRACT BONDING
Melwain Enterprises, Inc. 181 South Franklyn Avenue - Suite 603 Valley Stream, New York 11581 (516) 295-6081 Fax: (516) 569-1516 Email Address: [email protected] INSTRUCTIONS AND APPLICATION FOR CONTRACT
REQUEST FOR PROPOSALS CONSTRUCTION MANAGEMENT SERVICES. PASSENGER SCREENING CHECKPOINT CONSOLIDATION PROJECT PROJECT No.
REQUEST FOR PROPOSALS CONSTRUCTION MANAGEMENT SERVICES PASSENGER SCREENING CHECKPOINT CONSOLIDATION PROJECT PROJECT No. FY15-805-67 Manchester-Boston Regional Airport is soliciting Proposals from qualified
How to best position your construction company to a surety in 2013
How to best position your construction company to a surety in 2013 Table of Contents Surety 2013 market forecast... 3 Criteria used by construction surety underwriters... 3 Five key areas for best construction
REQUEST FOR PROPOSAL CONSTRUCTION MANAGEMENT SERVICES PINE TRAIL ELEMENTARY HVAC, CEILING & LIGHTING PROJECT NO. 164514
REQUEST FOR PROPOSAL CONSTRUCTION MANAGEMENT SERVICES FOR PINE TRAIL ELEMENTARY HVAC, CEILING & LIGHTING PROJECT NO. 164514 Contact: Mr. Tom Brown, Senior Construction Project Manager Facilities Services,
Design-Bid-Build v. Guaranteed Maximum Price Contracting: The Basics for Owner's Counsel
Page 1 of 6 ALM Properties, Inc. Page printed from: New York Law Journal Back to Article Design-Bid-Build v. Guaranteed Maximum Price Contracting: The Basics for Owner's Counsel James E. Hughes New York
BOND MEASURE E CONTRACTOR OUTREACH
FREMONT UNIFIED SCHOOL DISTRICT BOND MEASURE E CONTRACTOR OUTREACH May 4, 2015 INTRODUCTIONS Therese Gain, Director of Facilities, Fremont Unified School District Carol Lemos, Administrative Assistant
Nebraska Public Schools: Statutes Related to the Construction of Improvements to Real Property
Nebraska Public Schools: Statutes Related to the Construction of Improvements to Real Property 73-101. Public lettings; how conducted. Whenever the State of Nebraska, or any department or any agency thereof,
REQUEST FOR QUALIFICATIONS (RFQ) FOR CONSTRUCTION MANAGEMENT SERVICES
REQUEST FOR QUALIFICATIONS (RFQ) FOR CONSTRUCTION MANAGEMENT SERVICES (Construction Manager At-Risk) FOR PROJECTS IN THE CENTER UNIFIED SCHOOL DISTRICT April 7, 2005 The ( District ) is seeking Statements
Dancing Willows Condominium HOA, Inc.
Dancing Willows Condominium HOA, Inc. October 28, 2013 C/O Stillwater Community Management 15400 W 64 th Ave Suite 9E53 Arvada, CO 80007 p. (303) 872-9224 f. (303) 309-0468 [email protected] RE:
What s so Progressive about Progressive Design-Build? Mark Alpert, PE, DBIA CH2MHill & Peter Tunnicliffe, PE, DBIA CDM
What s so Progressive about Progressive Design-Build? Mark Alpert, PE, DBIA CH2MHill & Peter Tunnicliffe, PE, DBIA CDM Progressive design-build: A better way? Discussion topics: What is progressive design-build?
MANAGING THE PROJECT RECORD
MANAGING THE PROJECT RECORD Project Record Filing System 2 Agency Submittals 2 Site Acquisition 3 Planning 3 Pre-Qualification of Bidders 3 Bidding 4 Construction 4 Inspection 4 Legal 5 Contracts 5 Accounting
Los Angeles Community College District PROGRAM MANAGEMENT SERVICES. Terri Mestas Program Director
Los Angeles Community College District PROGRAM MANAGEMENT SERVICES Terri Mestas Program Director CMAA Southern California Chapter February 13, 2015 1 LACCD Overview Established in 1969 Governed by seven-member
Doniphan-Trumbull Public School BP 902.05 Page 1 of 6 CONSTRUCTION MANAGEMENT AT RISK SCHOOL CONSTRUCTION ALTERNATIVE
Page 1 of 6 CONSTRUCTION MANAGEMENT AT RISK SCHOOL CONSTRUCTION ALTERNATIVE The school district adopts this policy in the event it resolves to use the construction management at risk (CM at risk) construction
Mechanical Contractor Pre-Qualification Packet. SPSC N180 Computer Data Room Phase II. Project No. CP 159313. Notice No. Notice 13-11.
Mechanical Contractor Pre-Qualification Packet SPSC N180 Computer Data Room Phase II Project No. CP 159313 Notice No. Notice 13-11 Issued by Department of Facilities Management Delivery address: Research
Independent School District No. 1 Strive Achieve Succeed Go Beyond Lewiston, Idaho
Independent School District No. 1 Strive Achieve Succeed Go Beyond Lewiston, Idaho REQUEST FOR QUALIFICATIONS Independent School District No. 1, Lewiston, Idaho ( District ) is seeking responses from individuals
Request of Qualification Proposal for Construction Management Services
Request of Qualification Proposal for Construction Management Services Dated June 10, 2014 Table of Contents Overview 3 Introduction 4 Scope of Construction Managers Services 4 Submission of Qualifications
proactive contract management
TM proactive contract management Six Reasons Why Contract Management Matters Table of Contents Why Contract Management Matters 2 How Contracts Impact Your Business 2 Contract Data Determines Revenue and
Introduction/Background. Competitive Bidding- Statutory Requirements. Competitive Bidding- Charter/Code Requirements
Public Works Contracts in Missouri Presented September 8, 2008 by Joe Lauber 2008 Missouri Municipal League Annual Conference Introduction/Background Bidding the project New construction safety training
10 Steps to Building a More Profitable Construction Business. Leslie Shiner, MBA Sage Certified Consultant
10 Steps to Building a More Profitable Construction Business Leslie Shiner, MBA Sage Certified Consultant Introduction is a pragmatic approach to developing business practices that result in greater profitability.
The purpose of the policy is to establish guidelines for the administration of the School Planning and the School Construction programs.
SCHOOL PLANNING/SCHOOL CONSTRUCTION PROGRAMS Effective: August 14, 2014 I. Policy Statement The Board of Education is responsible for providing safe, engaging and supportive educational and work environments
GREENFIELD MIDDLE SCHOOL ROOF PROJECT
CITY OF GREENFIELD GREENFIELD, MASSACHUSETTS RFQ TITLE: GREENFIELD MIDDLE SCHOOL ROOF PROJECT RFQ #: 12-03 Date of Issuance: June 22, 2011 9:00 a.m. Deadline for Receipt Of Bids: July 8, 2011 2:00 p.m.
CHAPTER 48-01.2 PUBLIC IMPROVEMENT BIDS AND CONTRACTS
CHAPTER 48-01.2 PUBLIC IMPROVEMENT BIDS AND CONTRACTS 48-01.2-01. Definitions. In this chapter, unless the context otherwise requires: 1. "Agency construction management" means a public improvement delivery
GORDON COUNTY BOARD OF COMMISSIONERS REQUEST FOR QUALIFICATIONS FOR AN ARCHITECT FAMILIAR WITH COMMUNITY DEVELOPMENT BLOCK GRANT APPLICATIONS
GORDON COUNTY BOARD OF COMMISSIONERS REQUEST FOR QUALIFICATIONS FOR AN ARCHITECT FAMILIAR WITH COMMUNITY DEVELOPMENT BLOCK GRANT APPLICATIONS DATE RFQ RELEASED July 13, 2013 1 PURPOSE OF THIS REQUEST FOR
Marketing Subcontractor Services
Marketing Subcontractor Services Part I Winning That Big Contract is More Than Just Low Bid Today By Greg Hoyle, Consultant Fails Management Institute Often subcontractors come to our consultants and say,
Step 1 Getting Pre-Qualified
Step 1 Getting Pre-Qualified Now that you ve made the decision to purchase a home, the next step is to get pre-qualified from a lending institution, like Michigan Mortgage Solutions, to determine how much
DGS Prolog Manager & Prolog Converge User Manual
DGS Prolog Manager & Prolog Converge User Manual Table of Contents Prolog Overview Flowchart 1 Entering a New Project 2 Solicitations 7 Contracts Module 14 Change Orders 21 Change Order Workflow Diagram
What You Need to Know Before Your Business Insurance Renews
What You Need to Know Before Your Business Insurance Renews by Scott Kirby Shopping for commercial insurance is easy when prices are falling. Need to save money? Need broader coverage? Get another quote.
REQUEST FOR QUALIFICATIONS ARCHTECTURAL SERVICE FEBRUARY 20, 2015 JACKSONVILLE PUBLIC SCHOOL DISTRICT 117
Introduction The Board of Education for Jacksonville School District 117 is soliciting Statements of Interest and Qualifications pursuant to 50 ILCS 510/0.01 from qualified firms to provide comprehensive
REQUEST FOR PROPOSALS For. Kelowna and Vernon Hospitals Project
REQUEST FOR PROPOSALS For The Kelowna and Vernon Hospitals Project VOLUME 2 of 4 Instructions to Proponents Closing Time: Delivery Address: 3:00 pm (local time) Thursday, March 6,2008 Kelowna and Vernon
C.A.S.H. WORKSHOP Planning for the Building Season: Exploring and Understanding Project Delivery Methods
C.A.S.H. WORKSHOP Planning for the Building Season: Exploring and Understanding Project Delivery Methods Friday, December 3, 2010 9:00 a.m. to 3:00 p.m. Ontario Airport Radisson 2200 East Holt Boulevard
T34 - PUBLIC WORK IN MASSACHUSETTS, UNDERSTANDING CHAPTER 149 AND CHAPTER 149A
T34 - PUBLIC WORK IN MASSACHUSETTS, UNDERSTANDING CHAPTER 149 AND CHAPTER 149A PANELISTS: Deborah Anderson, Esq. Office of the Attorney General Laura Wernick, FAIA, REFP, LEED AP HMFH Architects, Inc.
Members, Council of Presidents. Advertisements for Architect/Engineer and Construction Manager Services and Calls for Bid
July, 2003 MEMORANDUM UCF-05.01-07/03 TO: Members, Council of Presidents FROM: SUBJECT: Advertisements for Architect/Engineer and Construction Manager Services and Calls for Bid AUTHORITY: Sections 240.209(3)(p),
How to do Business with the Province of British Columbia
How to do Business with the Province of British Columbia Every year, the B.C. Government buys a wide range of goods and services from businesses of all sizes and types. Your business could be one of them.
Contracts, agreements and tendering
Contracts, agreements and tendering 1) Introduction This guidance note provides an overview of the types of contracts and other agreements you might need to use in setting up and running a local energy
Average producers can easily increase their production in a larger office with more market share.
The 10 Keys to Successfully Recruiting Experienced Agents by Judy LaDeur Understand whom you are hiring. Don t make the mistake of only wanting the best agents or those from offices above you in market
GENERAL CONTRACTOR / CONSTRUCTION MANAGER SERVICES
REQUEST FOR QUALIFICATIONS GENERAL CONTRACTOR / CONSTRUCTION MANAGER SERVICES NEW DINING HALL MONTANA STATE UNIVERSITY Bozeman, Montana PPA NO. 15-0103 Campus Planning, Design & Construction Plew Building
Request for Qualifications Construction Management at Risk Services. Bismarck Public Schools Bismarck, North Dakota
Request for Qualifications Construction Management at Risk Services Bismarck Public Schools Bismarck, North Dakota December 1, 2014 Request for Qualifications Construction Management at Risk Services Bismarck
Program Management for School Construction
Program Management for School Construction Presented to: Pasadena Unified School District Board of Education January 13, 2009 Project Delivery Options Design Bid Build Design/Build Construction Management
COMMISSIONING SUMMARY TEMPLATE
COMMISSIONING SUMMARY TEMPLATE The following template shall be completed and submitted for permit review. Provide additional attachments as appropriate. SECTION 1 PROJECT DESCRIPTION Name of Project Project
AUSTIN INDEPENDENT SCHOOL DISTRICT INTERNAL AUDIT DEPARTMENT CONSTRUCTION AUDIT PROGRAM
GENERAL: Some of the Districts largest capital expenditures are from new construction, facility upgrades, and renovations. A single project can run into the millions of dollars, involving engineering,
Joint Bidding Guide. 9. Opportunity Assessment. prepared for Leaders of Potential Consortia and Bid Managers
Joint Bidding Guide 9. Opportunity Assessment prepared for Leaders of Potential Consortia and Bid Managers Figure 1.1 The Joint Bidding Cycle Key Chapter for Both Sides 1. Introduction Chapter for Supply
The BASICS of CONSTRUCTION ACCOUNTING Workshop GLOSSARY
The BASICS of CONSTRUCTION ACCOUNTING Workshop GLOSSARY From Financial Management & Accounting for the Construction Industry, CFMA. 2014 Matthew Bender and Company, Inc., a member of the LexisNexis Group.
FOR USE WITH PPP PROJECTS 1 SAMPLE GUIDELINES FOR PRE-QUALIFICATION AND COMPETITIVE BIDDING PROCESS 2
FOR USE WITH PPP PROJECTS 1 SAMPLE GUIDELINES FOR PRE-QUALIFICATION AND COMPETITIVE BIDDING PROCESS 2 1. PRE-QUALIFICATION 1.1 The requirements for pre-qualifications will be reasonable and efficient and
San Diego Gas & Electric
San Diego Gas & Electric Diverse Business Enterprises Yan Fei, Supplier Diversity Advisor 2002 San Diego Gas and Electric Co. and Southern California Gas Company. All copyright and trademark rights reserved.
REQUEST FOR PROPOSALS FOR PINE GROVE ELEMENTARY SCHOOL PLAYGROUND REPLACEMENT PROJECT TOWN OF AVON, CONNECTICUT
REQUEST FOR PROPOSALS FOR PINE GROVE ELEMENTARY SCHOOL PLAYGROUND REPLACEMENT PROJECT TOWN OF AVON, CONNECTICUT The Town of Avon and Avon Board of Education are seeking written responses to a Request for
School Construction Projects
The process of educating young people seems to be continually developing. New insights regarding how students most effectively receive retain and gain understanding of information and principles affect